QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE BOARD OF TRUSTEES OF NATIONAL MUSEUMS AND GALLERIES ON MERSEYSIDE |
Claimant |
|
- and - |
||
AEW ARCHITECTS AND DESIGNERS LIMITED |
Defendant |
|
- and - |
||
PIHL UK LIMITED and GALLIFORD TRY CONSTRUCTION LIMITED (trading together in partnership as a Joint venture "PIHL GALLIFORD TRY JV) |
Third Party |
____________________
Paul Reed QC & Brenna Conroy (instructed by Plexus Law) for the Defendant
Jonathan Lee (instructed by Pinsent Masons LLP) for the Third Party
Hearing dates: 22-25, 29-30 April, 1-2, 7-9 May and 10 June 2013
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
A Brief Description of the Elements of Work in Issue
The General Chronology
"The valley upstands have proved too difficult to design and [accordingly] it has now been agreed with the architect to cast the valley upstands in situ, and then clad this with Jura stone following the installation of the adjacent step units. This enables the geometry to be defined on site now, so that while the valley upstands are cast then the step units can be prefabricated."
"1 Manufacturing tolerances
The pre-cast units vary sufficiently in size to allow cumulative errors to occur and create different gaps between units. There are also tolerances in level to allow the trip hazards where they are marginally out of being truly flat. There are variations in the top and bottom line of step units, which gives varied gaps.
2 Workmanship issues
The precast units had been installed with significant variation in care and attention to detail. Some units have spaces between units and others do not. Some units sit exactly square and others do not. Units are tight against the 'wing wall' but then have large gaps across the width of the staircase…
3 Health and Safety issues
There are Health and Safety issues with the valley 'blocks' that over sail the landings, these protrude into the walkway and are dangerous. There are trip hazards with the intersection of the ramps and the terraced areas.
That heel trap issues with the upper steps cannot be overstated as a fall from the top of the flight of steps due to a high heel being trapped will be serious. The gaps are excessive.
4 Health and Safety issues with abuse of valley stones
The sloping top stone on the valley creates on its own a serious Health and Safety issue for children as it is an open invitation to use it as a slide. This is not something that can be redressed by including anti-skating metal strips.
5. Design issues with Valley Steps
The 'as built' valley varies from the original planning approved drawings. This will need a revised planning application as it is a significant variation from the approved drawings…
Conclusion
The whole terrace, ramp, step and amphitheatre seating area has widespread faults in design, manufacture, workmanship and installation. The cumulative effect of these is to make the whole area unacceptable; it will need significant remedial works to address all the above issues."
The Witnesses
(a) Sharon Granville: the Executive Director of the Museum who had been seconded into the project on a full-time basis since 2004, spent a considerable amount of time setting up the project and keeping a reasonably close eye on what was going on. She was astute and experienced in her job. For instance her descriptions relating to the actual and potential disruption to the work and exhibits of the Museum during the remedial works were extremely helpful in giving a very real insight into the major difficulties which the Museum suffered and will suffer when the remedial works were and will be carried out; that had the ring of absolute truth about it. She became even more involved when it began to emerge that there were problems with the steps and seats. She was a very impressive witness and one whose evidence I have no difficulty in accepting largely in its entirety. She was prepared to make concessions with regard to some of the quantum evidence which underlined her basic honesty and integrity. She was subjected to polite but firm cross-examination by Leading Counsel for AEW about quantum matters but she stood up extremely well to that and I found her immensely believable.
(b) Colin Matley: he was from August 2005 the Quantity Surveyor for the project employed by Turner and Townsend. He was originally called to give evidence primarily in relation to an issue raised on the pleadings by AEW, which was the extent to which the Client Change Control Procedure had been implemented, in particular in relation to CVI 340 and the construction of the plinth in late 2009. He explained that he had produced some of the details of quantum and indeed it was primarily about that area of the case about which he was cross-examined. I found him to be a decent and convincing witness.
(c) John Hewitt: he was from November 2008 the Contract Administrator who had 26 years' management experience on large-scale construction projects in the UK and abroad. Again his evidence was called to deal with the Change Control Procedure. Although initially somewhat nervous when he started to give evidence, he gained confidence as a witness. I formed the view that he had a good general recollection of what had happened, that he was a decent and positive witness and that he was broadly a credible witness. In particular his evidence about the leaks through the membrane in the steps and seats areas was clear and firm.
(d) Ian Williams: he has worked for the Museum for some 13 years and had been involved in the Museum project since its inception. He was the Director of Estate Management with responsibility not only for the Museum but also a number of other museums and galleries run by the Claimant. He was a straightforward witness and ready to concede that an estimate of time spent by him in relation to the steps and seats works might be excessive. He was involved in the steps and seats problems as they emerged in early 2010 and again with the ceiling collapses and problems. He was asked questions that went to quantum and I found him to be impressive and believable.
(e) Martin Hemmings: he has been the Building Operations Manager within the Estate Management Department of the Museum since about 2002 and was resident on-site that this project from June 2008. He was the "eyes and ears on site" for the Museum. He was down-to-earth, sensible and honest. Again, he was asked questions which related to quantum and what he had to say was believable. He gave some practical evidence about how very complicated the process of lifting and placing the seats and seats actually had been. He gave practical and helpful evidence about likely access problems when remedial works are to be done
(f) Robert Batchelor: he was the Client Project Manager for Exhibition Projects Ltd which was retained by the Museum in connection with the exhibition fit out of the Museum. He gave evidence in connection with aspects of quantum in relation in particular to the work required to the SAS ceilings areas and in relation to other work yet to be done. He was sensible and a decent straightforward witness.
(g) Martin Lawton: he was the Project Manager for the new Museum project taking over that role in July 2009. He was employed by Mace Ltd which was in turn employed by the Museum he was called to give evidence about liability and was mostly cross-examined about quantum and in particular about his and his firm's involvement in the aftermath of the steps and seats issues arising. He was a reliable witness.
(a) Peter Bettridge: he was the Project Quantity Survey who was effectively the site representative for the Contractor. Although honest, I felt that he was somewhat careworn if not diffident in the giving of his evidence. He did not always answer relatively simple questions put to him. Much of his written evidence was not challenged but I am circumspect about the reliability of his evidence where it differs from contemporaneous documents.
(b) Torben Seemann: he was an engineer assigned to the Museum project in April 2009 primarily to monitor and promote quality assurance. Much of his evidence was related to the chronology and correspondence. He was a reasonably reliable witness.
Liability (Architect)
(a) AEW was responsible for the general layout of the geometry of the steps and seats.
(b) The Contractor's Technical Query, TQ 1676, identified what it believed was a "clash".
(c) Following discussions on site, it was AEW which proposed the "plinth" solution in CVI 340.
(d) (Although this had not been alleged as such by the Museum), AEW's original design was capable of being constructed by the Contractor and therefore it should have informed the Contractor that this was so in answer to TQ 1676. Accordingly, CVI 340 should not have been issued. It was accepted orally by Mr Reed QC on behalf of AEW that this was negligent of AEW.
(e) The Museum is not bound by any agreement in relation to be construction of the plinth and did not acquiesce in its construction.
(f) The SAS ceiling was not designed adequately by AEW in that the original specification in September 2006 specified that the lighting tracks and the ceilings within the museum were to be supported separately and AEW amended that design so that the ceilings were to be installed supportive by ERCO lighting track; the design should have been as per the original specification. Other aspects of the design set out in Paragraph 39 of the Particulars of Claim were accepted as being inappropriate. Mr Reed QC also confirmed orally that in this context AEW was negligent.
(g) It was accepted that the design was not adequate in relation to the Armstrong Ceilings in that additional perimeter clips were required to be installed. However this was a matter for the specialist subcontractor. Mr Reed QC did not accept that there was any liability in this context.
"3.1 The consultant shall provide those services included in Schedule 1 Part 2…
3.5.1 [AEW] warrants and undertakes to the Employer that he shall perform his duties such that the Project will comply with all planning…permissions and conditions…
3.5.3 [AEW] further warrants and undertakes to the Employer that in respect of the complete architectural services in relation to the Project as set out in this Deed he has exercised and will continue to exercise reasonable skill and care and diligence to be expected of a professional person acting in the capacity of a consultant experienced in carrying out such services for a development comparable in size, scope, complexity and purpose to the Project and within the scope of this Deed.
3.5.4 [AEW] further warrants and undertakes to the Employer that in respect of the Services he has carried out pursuant to the Sub-Appointment [when engaged by 3XN] he has exercised the reasonable skill and care and diligence which may reasonably be expected of a properly qualified and competent Architect/Contract Administrator experienced in carrying out such services as those specified in the Sub-Appointment."
"A. The General Scope of Services
1.2.1 Design and document all architectural elements including advising on quality control during contract.
1.2.2 Lead the design team and coordinate the work of design team members including:
Acting as central point of contact for the design team
Overall coordination of the design…
Visit Site to prepare snagging lists prior to Practical Completion
6.1 The Consultant shall:-
… 6.1.2 As Design Team Leader the Consultant will liaise with the M&E, Structural, or consultants as well as other specialist subcontractors and consultants to ensure all elements of the Project are fully co-ordinated...
8.1 Ensure that proper and sufficient information, drawings, details, instructions, notices and the like are provided or given to the Contractor and Work/Sub-Contractors by the Professional Team in due time and in accordance with the Information Release Schedule and the Project Programme.
8.2 Ensure that the members of the Professional Team provide adequate supervision and regular site inspections in accordance with their terms of appointment, including the provision of resident site staff.
8.3 Ensure that the members of the Professional Team discharge their contractual responsibilities in respect of completion, defects and remedial works.
11.1 The Consultant shall:-
11.1.1 Provide such input, information, advice and assistance as necessary to enable each consultant's design leader in the Professional Team and the Museum Exhibition Designers to fulfil their duties and responsibilities and to ensure there is the interface between each design discipline.
12.1 The Consultant shall:-
12.1.3 Visit the site on a regular basis to inspect the progress and quality of the Works and to determine that they are being executed in accordance with the contract documents.
12.1.4 Direct and control the activities of the site staff
B. The Specific Scope of Services – Architect
6.1 Develop a co-ordinated detailed design from the approved scheme design in accordance with the project brief and cost estimate…
6.5 Prepare production information comprising the following:
… 6.5.2 fully detailed and coordinated dimensioned floor and reflected ceiling fans, sections and elevations showing all internal and external arrangements.
6.11 Participate in preparation of project wide definition of tolerances covering architectural elements and related interfaces.
11.1 Provide further production information as required in accordance with the programme of works and/or agreed information release schedules
11.2 Receive design, fabrication and installation drawings from contractors and check for adequacy, accuracy and adherence to the design concept and authorise for construction where applicable.
C. The Specific Scope of Services - Design Team Leader
At All Stages
5.10 Receive material from other participants and prepare a project wide definition of tolerances
6.4 Coordinate the preparation/checking as appropriate of operation and maintenance manuals prior to handover of each stage of the Project."
"Corrosion induced by chlorides other than from seawater (XD classes) (where concrete containing reinforcement…is subject to contact with water containing chlorides, including de-icing salts, from sources other than from seawater)
XD1 | Moderate humidity | Concrete surfaces exposed to airborne chlorides… Parts of structures exposed to occasional or slight chlorides condition |
XD2 | Wet, rarely dry | Reinforced and prestressed concrete surfaces totally immersed in water containing chlorides… |
XD3 | Cyclic wet and dry | Reinforced and prestressed concrete walls and structure supports… Reinforced pavements car park slabs |
Corrosion induced by chlorides from seawater (XS classes). (Where concrete containing reinforcement…is subject to contact with chlorides from seawater or air carrying salt originating from seawater)
XS1 | Exposed to airborne salt but not in direct contact with sea water | External reinforced and prestressed concrete surfaces in coastal areas |
XS2 | Permanently submerged | Reinforced and prestressed concrete surfaces completely submerged and remaining saturated; e.g. concrete below mid-tide level |
XS3 | Tidal, splash and spray zones | Reinforced and prestressed concrete surfaces in the upper tidal zones and the splash and spray zones [Note E: Exposure XS3 covers a range of conditions. The most extreme conditions are indeed spray zones. The least extreme is in the tidal zone where conditions can be similar to those in XS2. The recommendations given in this annex take into account the most extreme conditions within this class.] |
Freeze-thaw attack
Where concrete is exposed to significant attack by freeze-thaw cycles whilst wet)
XF1 | Moderate water saturation without de-icing agent | Vertical concrete surfaces such as facades and columns Non-vertical concrete surfaces not highly saturated, and to rain or water |
XF2 | Moderate water saturation with de-icing agent | Concrete surfaces such as parts of bridges, which would otherwise be classified as XF1, but which are exposed to de-icing salt either directly or as spray or run-off |
XF3 | High water saturation, without de-icing agent | Horizontal concrete surfaces, such as parts of buildings, where water accumulates and which are exposed to freezing… |
XF4 | High water saturation, with de-icing agent or seawater | Horizontal concrete surfaces such as roads and pavements, exposed to freezing and to de-icing salt either directly or as spray or run-off Concrete surfaces subjected to frequent splashing with water containing de-icing agent and exposed to freezing |
"Corrosion induced by chlorides other than from seawater
Where concrete containing reinforcement…is subject to contact with water containing chlorides, including de-icing salts, from sources other than from seawater)
XD1 | Moderate humidity | Concrete surfaces exposed to airborne chlorides |
XD2 | Wet, rarely dry | Swimming pools. Concrete exposed to industrial waters containing chlorides … |
XD3 | Cyclic wet and dry | Pavements. Car park slabs |
Corrosion induced by chlorides from seawater
Where concrete containing reinforcement…is subject to contact with chlorides from seawater or air carrying salt originating from seawater)
XS1 | Exposed to airborne salt but not in direct contact with sea water | Structures near to or on the coast |
XS2 | Permanently submerged | Parts of marine structures |
XS3 | Tidal, splash and spray zones | Parts of marine structures |
Freeze-thaw attack (XS classes) (where concrete is exposed to significant attack from freeze-thaw cycles whilst wet)
XF1 | Moderate water saturation without de-icing agent | Vertical concrete surfaces…exposed to rain and freezing |
XF2 | Moderate water saturation with de-icing agent | Vertical concrete surfaces of road structures exposed to freezing and airborne de-icing agents |
XF3 | High water saturation without de-icing agent | Concrete surfaces subjected to frequent splashing with water and exposed to freezing Horizontal concrete surfaces exposed to rain and freezing |
XF4 | High water saturation with de-icing agent or seawater | …Concrete surfaces subjected to direct spray containing de-icing agents and freezing. Splash zones of marine structures exposed to freezing |
"1. Please advise specification for reinforcement for step units
2. Please advise level of cover to reinforcement…"
Given that AEW had done nothing itself beforehand either to provide an appropriate specification for the steps and seats in question or to secure that one was provided, this would have been a yet further opportunity for AEW to ensure that a proper design or at the least the basic criteria therefor were laid down.
"It is Rowecast/PGT/BWSS design so don't get into providing solutions. You will run out of time – v quickly."
The Rowecast drawings then appear to have been approved or at least not disapproved. There is not one jot of evidence that suggests anyone from AEW or Buro Happold applied their minds to what should be the appropriate cover to provide at least a 15 year life for these architecturally important steps and seats features.
(a) Paragraph 7.1 describes the Museum as including:
"Two arrangements of precast concrete steps and seats (the "Steps and Seats") leading up to an entrance situated at each end of the Museum Building. The Steps and Seats and the terrace areas are collectively referred to in some documents as "amphitheatre steps" but are hereafter collectively referred to as the "Steps and Terraces.""
(b) Paragraphs 8 to 30 appear under a general heading in capitals "The Steps and Terraces. They describe problems with the "Geometry" of the Steps and Seats, the Cover to Reinforcement and at Paragraphs 26 and 27 "The Gaps between the Step/Seat Units". Paragraph 28 then complains that "AEW designed the Steps and Terraces in a manner which was deflected, referring to 2 possible remedial solutions set out in Appendix 7A.
(c) Paragraph 49 identifies AEW's breaches which included;
"The Steps and Terraces: Gaps between Concrete Units
49.12 [AEW failed to] take proper care to avoid producing and/or approving a design which avoided finger and heel traps…"
(d) Paragraph 14 9.22 pleads quantum related to "estimated works" set out in Appendix 10. Appendix refers to remedial works to the "Steps/Terraces".
(e) When the Museum responded to the Contractor's Request the Further information relating to the gaps between concrete units or 19 October 2012, it is clear that the particulars indicated by mention of gaps not only between and in the step and seat units but also the terrace units.
(f) There was no doubt that once the expert quantity surveyor reports were exchanged that work to resolve the gaps to the terrace was being claimed for. The quantum experts have had no difficulty in addressing the point.
Liability (Contractor)
"2.1.2 For the purpose of so carrying out and completing the Works, the Contractor shall, in accordance with the Contract Drawings and the Specification/Schedules of Work where and to the extent that the same are relevant, complete the design for the Contractor's Designed Portion including materials and goods and workmanship to be used in the construction of that Portion so far as not described or stated in the Employer's Requirements or Contractor's Proposals…
2.7.1 Insofar as the design of the Contractor's Designed Portion is comprised in the Contractor's Proposal and in what the Contractor is to complete under clause 2.1.2 and in accordance with the Employer's Requirements and the Conditions…the Contractor shall have in respect of any defect or insufficiency in such design the like liability of the Employer, whether under statute or otherwise, as with an architect or, as the case may be, other appropriate professional designer holding himself out as a competent to take on work for such design who, acting independently under a separate contract with the Employer, had supplied such design for or in connection with works to be carried out and completed by a building contractor not being the supplier of the design.
The Ceilings
Quantum (General)
Quantum (Steps, Seats and Terraces)
1. Remedial scheme - Basic Cost
(a) It is inevitable, based on what happened in 2009 when there were numerous leaks and punctures to the membrane as work was done on the membrane and units were manoeuvred into position onto the membrane, that, even if reasonable care is exercised by operatives, there will be further extensive damage to the existing membrane.
(b) Mr Jowett's scheme itself specifically involves cutting away membrane at the top of each inclined rib and in the area of a new concrete up stand at the valley junction.
(c) Although the units immediately around the valley were removed in 2010 or 2011 and no leaking has since been reported in the internal areas under the amphitheatres within the Museum, there is a very real risk, in my judgment based on the evidence, that this already much repaired existing membrane will be further damaged by the removal of the hundreds of remaining heavy units, by work people walking over the membrane when it is fully exposed and by the re-manoeuvring of the new units.
(d) A second membrane to be laid over the first and lower membrane will give reasonable added assurance that the Museum will not suffer leaks to the areas below. One reminds oneself that the Museum has only been put into the position of having to replace these very heavy units as a result of the negligence of AEW and it is not reasonable to expect the Museum to take the real risk of leaving the old single membrane in position which might well be further damaged by the indelicate operations involved in the remedial work. It is argued by AEW and the Contractor that the remedial work contractor would be responsible for not damaging the existing membrane and would be responsible for repairing further punctures and tears. The problem with this argument is that it does not take into account the real risks involved and the fact that the remedial works contractor would probably price in additional cost contingencies to the extent that it was asked to take the risk of being responsible for any further damage to the existing membrane; there is much less chance that it would price in such contingencies if there was to be a second and new membrane to be added.
(a) £542 reduction for disposing of less units: this reduction will not be allowed because all units need to be disposed off site.
(b) £1,473 for cutting membrane and forming new concrete upstand the valley junction: I accept Mr Jowett's evidence that this is required and I do not accept Dr Robert's view on this.
(c) £1,800 for testing the entire membrane electronically: in my judgement, this work is necessary and reasonable. It had to be done when the Contractor originally did the work and particularly after repairs.
(d) £1,500 for repairing any leaks: it is inevitable that there will be some leaks and punctures and repairs will be required to the membranes. £1,500 is a reasonable allowance which it is probable that any tendering contractors will build into their prices in any event.
(e) £20,481 for laying a second membrane layer: this should be allowed for the reasons given above.
(f) £5,728 for laying proprietary protective boards to entire membrane: this is a reasonable allowance because protective boarding will be required to prevent or limit damage to the lower and the new membrane layers.
(g) £19,080 for re-using some seat units: I do not consider that it is reasonable to expect any of the old seat units to be re-used.
(h) £30,922 for the use of stainless steel reinforcement: it has not been suggested that it was negligent or inappropriate to use ordinary (as opposed to stainless) steel reinforcement in the first place. I am not satisfied that using stainless steel is either reasonable or necessary. If an appropriate concrete mix is used with 35mm cover, that on the evidence should be an adequate remedial solution which should, all things being equal, produce a repair free life of 50 years. I would therefore not allow this.
(i) £750 for cleaning re-used units: there will be no re-used units.
(j) £13,300 for replacement handrail to the valley: as it was never intended for there to be such a handrail but simply a valley created by the junction between the steps and the seats, this should not be allowed.
It follows that the total sum of £369,002 should be reduced by £30,922 and £13,300, producing an allowable sum as damages of £324,780 for the actual construction works.
2. Preliminaries
3. Site security
4. Design Reserve / 5. Contingency / 6. Design/local authority and building control fees
7. Inflation allowance
8. Abortive installation of plinth upstand
9. Removal of plinth
10. Security costs
(a) It is obviously in the interests of justice for there to be finality and the Court should, generally, strive to produce a final judgement which finally disposes of the matters is in issue, including the final assessment of all damages or other compensation payable.
(b) However, justice also demands that an innocent claimant which is clearly and obviously entitled to damages should be fully and adequately compensated, obviously within the legal rules and constraints in relation to the recovery of damages.
(c) There may be circumstances in which the Court must, to ensure justice to the innocent claimant, take appropriate steps to secure that it is adequately compensated.
(d) If the Court is of the view that there is a real likelihood that there will be heads of loss which can not be quantified by the Court at the stage at which the Court is being asked to fix compensation, the Court in effect has three options: make a very broad damages assessment in respect of those heads, postpone that assessment until further information is available or grant a declaration that the innocent claimant is entitled to be indemnified by the defendant which is liable against the losses in question.
11. Loss and expense incurred by the Contractor in relation to prolongation
12. Survey costs
13. Lawrence Bamber
14. Site hoarding (2011 onwards)
15. Adana Construction
16. Adjudicator's fees
17A. Legal fees in adjudication
Invoice date | Period of work | Amount (ex VAT) |
29 October 2010 | 13/9/10 - 25/10/10 | £15,531 |
30 November 2010 | Possibly 25/10/10 to invoice | £14,448.50 |
31 December 2010 | 2/12/10 -30/12/10 | £19,000 |
31 January 2011 | January 2011 | £40,000 |
16 March 2011 | 2/2/11 – 28/2/11 | £14,360 |
31 March 2011 | £3,151.50 | |
31 March 2011 | £12,739 | |
19 April 2011 | Couriers (12/10/10 and 17/11/11) | £301.32 |
Total | £119,531.31 |
(a) I exclude the first two invoices as being well before the actual adjudication and in the absence of evidence which makes it clear when adjudication was first threatened.
(b) I allow half of the invoice relating to work in December 2010 because by then the adjudication must have been intimated and indeed it was instituted. Substantial costs in adjudication do begin to be "racked up" at an early stage because it is such a short process and a defending party has very limited time to produce its responsive submissions.
(c) I allow 80% of the bill for work in January 2011, which was clearly a period of intense legal activity in the adjudication.
(d) Similarly I allow 80% of the bill for work in February 2011 for the same reason.
(e) In the absence of specific evidence as to the two bills dated 31 March 2011, I disallow them as not proven.
(f) I allow some £298.32 in relation to couriers for transmitting papers to the Contractor's solicitors and to the adjudicator on 17 January 2011.
(g) This produces a total of £53,286.32 (£9,500 + £ £32,000 + £11,488 + £298.32). I round this down to £53,000.
17B. T&T's time in adjudication
18. Professional Fees up to Practical Completion
T&T/Mace | Period | Calculation and Assessed amount |
T&T CM | Jan 10 | 90% for 13/31 days @£4,500: £1,698 |
T&T CM | Feb-March 10 | 90% of £9,000: £8,100 |
T&T CM | Apr 10 – June 11 | 30% of 4,500 x15: £20,250 |
Sub-total | £30,048 | |
T&T CA | Jan 10 | 50% of 13/31 @£4,800: £1,006 |
T&T CA | Feb-March 10 | 50% of £9,600: £4,800 |
T&T CA | Apr 10 – June 11 | 30% of £4,800 x 15: £21,600 |
Sub-total | £27,406 | |
Mace | January 2010 | 75% for 13/31 @£10,400: £3,270 |
Mace | Feb-March 10 | 75% of £20,000*; £15,000 |
Mace | Apr 10 – July 11 | 25% of £10,000* x 15: £37,500 |
Sub-total | £55,700 | |
Total | £113,154 |
* I have used a figure of £10,000 per month because there has been no explanation as to why what the time charges invoiced by Mace ran between £4,200 per month and £17,000. I have therefore used a rounded down median figure of £10,000 per month for assessment purposes on the basis particularly that Mr Lawton was obviously heavily involved in relation to the steps and seats in these periods and because there is no obvious reason for there to have been an increase over such a monthly charge specifically in relation to the steps and seats.
19. The Museum's Internal Management and Staff Costs to Practical Completion
"I consider that the authorities establish the following propositions:
(a) The fact and, if so, the extent of the diversion of staff time have to be properly established and, if in that regard evidence which it would have been reasonable for the claimant to adduce is not adduced, he is at risk of a finding that they have not been established.
(b) The claimant also has to establish that the diversion caused significant disruption to its business.
(c) Even though it may well be that strictly the claim should be cast in terms of a loss of revenue attributable to the diversion of staff time, nevertheless in the ordinary case, and unless the defendant can establish the contrary, it is reasonable for the court to infer from the disruption that, had their time not been thus diverted, staff would have applied it to activities which would, directly or indirectly, have generated revenue for the claimant in an amount at least equal to the costs of employing them during that time."
"77. In my judgment, as a matter of principle, such head of loss (i.e. the cost of wasted staff time spent on the investigation and/or mitigation of the tort) is recoverable, notwithstanding that no additional expenditure "loss", or loss of revenue or profit can be shown. However, this is subject to the proviso that it has to be demonstrated with sufficient certainty that the wasted time was indeed spent on investigating and/or mitigating the relevant tort; i.e. that the expenditure was directly attributable to the tort … This is perhaps simply another way of putting what Potter L.J. said in Standard Chartered, namely that to be able to recover one has to show some significant disruption to the business; in other words that staff have been significantly diverted from their usual activities. Otherwise the alleged wasted expenditure on wages cannot be said to be "directly attributable" to the tort."
122. At exhibit PR 33 to his witness statement Mr Peter Ruck has set out a schedule of the time spent from 31 August 2002 to 30 April 2003. In the main part of his witness statement he deals with the claim at paragraphs 79 and 80. He says that he calculated that he was engaged for 128 hours in dealing with the problems caused by the Defendant. As he explained in evidence the hours were based on his assessment of the time he spent on various matters. That assessment was made retrospectively. He prepared it by looking through the various documents which record what happened.
123. Such a method of retrospective assessment is, I consider, a valid method of calculation. I have been referred to the judgment of His Honour Judge Peter Bowsher QC in Holman Group v. Sherwood (Unreported, 7 November 2001) where he indicated that in the absence of records, evidence in the form of a reconstruction from memory was acceptable. I respectfully agree. However, it must be borne in mind that such an assessment is an approximation of the hours spent and may over-estimate or under-estimate the actual time which would have been recorded at the time…
125. I accept that the appropriate approach to the question of recovery of such management time is that set out by Gloster J. in R+ V Verischerung…
126. In this case Mr Ruck states at paragraph 79 of his witness statement and I accept that the Claimant "suffered losses due to lost opportunities since I was the New Business Development Director at the time, and I was unable to leave the premises in order to attend to other responsibilities such as selling and marketing the Claimant's business."
128. As a result, I am therefore satisfied from Mr Ruck's evidence that he spent time dealing with, investigating and mitigating the effect of the problems caused by the Defendant. That time amounted to 100 hours. Mr Ruck would otherwise have been selling and marketing the Claimant's business during that time. On that basis the Claimant is entitled to recover for 100 hours of Mr Ruck's time.
129. In this case Mr Jarvis has produced a short statement in which he as stated that from the audited accounts of the Claimant he has calculated the annual income of Mr Ruck in the relevant period to be £100,074.84. When this is divided by 2080 hours (equivalent to 52 weeks at 40 hours a week), it gives a figure of £48.11 per hour. Mr Jarvis is a qualified Accountant and I accept his evidence as to the accuracy of the calculation of Mr Ruck's income. On this basis I am satisfied that the sum of £48/hr claimed by the Claimant is appropriate.
Ms Granville - 30 days @ £323.48: £9,704.40
Mr Williams – 30 days @£268.10: £8,043.00
Ms Green – 30 days @ £104.51:£3,135.30
Mr Hemmings - 90 days @ £162.61: £14,634.90
Total: £35,517.60
20. The Museum's Internal Management and staff costs for steps and seats remedial works
Ms Granville - 72 days @ £323.48: £23,290.56
Mr Williams – 100 days @£268.10: £26,810.00
Mr Hemmings - 130 days @ £162.61: £21,139.30
Total: £71,239.86
Legal costs
22. Remedial Works Contract/Project/Cost Management
Project Manager: 5 days (tender period) and 52 days (contract period)
Project Manager's assistant: 5 days (tender period) and 78 days (contract period)
Costs Manager: 10 days (tender period) and 52 days (contract period).
Project Manager: 57 days @ £600: £34,200
Project Manager's assistant: 83 days @ £250: £20,750
Costs Manager: 62 days @ £550: £34,100
To this that should be added £2,500 for the CDM requirements. This produces a total of £91,550.
Summary of Damages and Relief in relation to the Steps and Seats
ITEM | AMOUNT ALLOWED AS DAMAGES |
1.Remedial scheme - Basic Cost | £324,780 |
2. Preliminaries | £94,550 |
3. Site security | £18,000 |
Sub-Total | £437,330 |
4. Allowance for Design Reserve @7½% of the above | £32,799.75 |
Sub-Total | £470,129.75 |
5. Allowance for Contingency @8% of the above | £37,610.38 |
Sub-Total | £507,740.13 |
6. Allowance for design/local authority and building control fees @ 15% of the above | £76,161.02 |
Sub-Total | £583,901.15 |
7. Inflation allowance@2.3% of the above | £13,429.73 |
Sub-Total | £597,300.88 |
8. Abortive installation of plinth upstand | £67,936.96 |
9. Removal of plinth | £12,948.27 |
10. Security costs | Indemnity |
11. Loss and expense incurred by the Contractor in relation to prolongation | Indemnity |
12. Survey costs | £6,655 |
13. Lawrence Bamber | Nil |
14. Site hoarding (2011 onwards) | £41,994.25 |
15. Adana Construction | £1,553.48 |
16. Adjudicator's fees | £19,830.66 |
17A. Legal fees in adjudication | £53,000 |
17B. T&T's time in adjudication | £5,160 |
18. Professional Fees up to Practical Completion | £113,154 |
19. The Museum's Internal Management and staff costs to practical completion | £35,517.60 |
20. The Museum's Internal Management and staff costs for steps and seats remedial works | £71,239.86 |
21. Legal costs | £10,000 |
22.Remedial Works Contract Project and Cost Management | £91,550 |
TOTAL | £1,127,870.40 |
Contribution
"…any person liable in respect of any damage suffered by another person may recover contribution from any other person liable in respect of the same damage (whether jointly with him or otherwise)".
Section 2(1) of that Act states:
"…the amount of the contribution recoverable from any person shall be such as may be found by the court to be just and equitable having regard to the extent of that person's responsibility for the damage in question."
(a) The responsibility for the inadequate concrete cover rests (in broad terms) equally between AEW and the Contractor. The responsibility for fixing cover was the Contractor's because it was part of its contractually assumed Designed Portion. However, AEW are equally to blame for failing to specify in the specifications what the criteria were or should be. It was the Contractor (or its sub-contractor for whom it was contractually responsible) which selected the 25 mm cover allowance and put it up for approval. It was AEW which negligently caused, allowed or permitted that allowance to be or to stand as approved.
(b) However, AEW is wholly responsible for the geometry problems and for the excessive gap allowance of 10 mm.
(c) If the only problem had been the gaps, wholesale replacement would not have been required and there would simply have had to have been substantial raising and refitting of the units. If the only problem had been the gaps and the geometry, it is likely that a significant number of units could have been re-used.
(d) The full remedial scheme would, largely, have been required by reason of the reinforcement cover problem because all the units would have to have been completely replaced to overcome that problem. However, on that assumption, the design would otherwise have been a tried and tested one which would have involved less design work and therefore cost.
(e) It is difficult in many cases, including this one, to adopt some mathematical method of fixing a just and equitable percentage to reflect responsibility of two separate parties. 25% reflects the above factors in circumstances where overall the primary responsibility rests with the architects in relation to whom there was a substantial abnegation of responsibility and continuing carelessness and the secondary responsibility rests with the Contractor which put forward carelessly and without any discernible forethought an inadequate precast concrete specification. I do not seek to underestimate the fault or responsibility of the Contractor but in the overall scheme of events in this case their responsibility overall was not insignificantly less than that of AEW.
There will therefore be a liability on the part of the Contractor to make contribution to AEW in the sum of 25% of £820,323.60, namely £205,080.90.
Decision