QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ABB LIMITED |
Claimant |
|
- and - |
||
BAM NUTTALL LIMITED |
Defendant |
____________________
Marcus Taverner QC and Richard Coplin (instructed by Systech Solicitors) for the Defendant
Hearing date: 28 June 2013
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Law
"Before addressing those submissions the judge set out the legal principles which he was to apply. He examined a number of authorities, including five decisions of this Court – Bouygues (UK) Limited v Dahl-Jensen (UK) Limited [2001] All ER Comm 1041, [2000] BLR 522, C&B Scene Concept Design Limited v Isobars Limited [2002] BLR 93, Levolux AT Limited v Ferson Contractors Limited [2003]EWCA Civ 11, 86 Con LR 98, Pegram Shopfitters Limited v Tally Weijl (UK) Limited http://www.bailii.org/ew/cases/EWCA/Civ/2003/1750.html[2003] EWCA Civ 1750, http://www.bailii.org/ew/cases/EWCA/Civ/2003/1750.html[2004] 1 All ER 818 and Amec Capital Projects Limited v Whitefriars City Estates Limited http://www.bailii.org/ew/cases/EWCA/Civ/2004/1418.html[2004] EWCA Civ 1418, [2005] BLR 1. At paragraph 80 of his judgment he stated the general principles to be derived from those authorities and from two decisions in the Technology and Construction Court – Discain Project Services Limited v Opecprime Development Limited [2000] BLR 402 and Balfour Beatty Construction Limited v Lambeth London Borough Council http://www.bailii.org/ew/cases/EWHC/TCC/2002/597.html[2002] BLR 288:
"1. The adjudication procedure does not involve the final determination of anybody's rights (unless all the parties so wish).
2. The Court of Appeal has repeatedly emphasised that adjudicators' decisions must be enforced, even if they result from errors of procedure, fact or law: see Bouygues, C&B Scene and Levolux;
3. Where an adjudicator has acted in excess of his jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision: see Discain, Balfour Beatty and Pegram Shopfitters.
4. Judges must be astute to examine technical defences with a degree of scepticism consonant with the policy of the 1996 Act. Errors of law, fact or procedure by an adjudicator must be examined critically before the Court accepts that such errors constitute excess of jurisdiction or serious breaches of the rules of natural justice: see Pegram Shopfitters and Amec."
We do not understand there to be any challenge to those general principles. They are fully supported by the authorities, as the judge demonstrated in his judgment."
He went on later in his judgment to counsel caution in relation to challenges to the enforceability of adjudicators' decisions:
"85. The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator. The courts should give no encouragement to the approach adopted by DML in the present case; which (contrary to DML's outline submissions, to which we have referred in paragraph 66 of this judgment) may, indeed, aptly be described as "simply scrabbling around to find some argument, however tenuous, to resist payment".
86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator's reasons and identify points upon which to present a challenge under the labels "excess of jurisdiction" or "breach of natural justice". It must be kept in mind that the majority of adjudicators are not chosen for their expertise as lawyers. Their skills are as likely (if not more likely) to lie in other disciplines. The task of the adjudicator is not to act as arbitrator or judge. The time constraints within which he is expected to operate are proof of that. The task of the adjudicator is to find an interim solution which meets the needs of the case. Parliament may be taken to have recognised that, in the absence of an interim solution, the contractor (or sub-contractor) or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The statutory scheme provides a means of meeting the legitimate cash-flow requirements of contractors and their subcontractors. The need to have the "right" answer has been subordinated to the need to have an answer quickly. The scheme was not enacted in order to provide definitive answers to complex questions. Indeed, it may be open to doubt whether Parliament contemplated that disputes involving difficult questions of law would be referred to adjudication under the statutory scheme; or whether such disputes are suitable for adjudication under the scheme. We have every sympathy for an adjudicator faced with the need to reach a decision in a case like the present."
"57. From this and other cases, I conclude as follows in relation to breaches of natural justice in adjudication cases:
(a) It must first be established that the Adjudicator failed to apply the rules of natural justice;
(b) Any breach of the rules must be more than peripheral; they must be material breaches;
(c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant.
(d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this.
(e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto."
"33. In essence, and doubtless for what he believed were good and sensible reasons, the adjudicator has gone off "on a frolic of his own" in using a method of assessment which neither party argued and which he did not put to the parties. In some cases, this may not be sufficient to prevent enforcement of the decision where the "frolic" makes no material difference to the outcome of the decision. Thus, an adjudicator who refers to a legal authority which neither party relied upon, may have his or her decision enforced nonetheless if the application of that legal authority obviously makes no difference to the outcome. The breach of the rules of natural justice has to be material. Here, for the reasons indicated above, the breach is material and has or has apparently led to a very substantial financial difference in favour of HKM but necessarily against the interests of DHB."
The Facts
"10.1 The Contractor and the Subcontractor shall act as stated in the subcontract and in the spirit of mutual trust and cooperation but without prejudice to the respective rights and obligations of the parties.
11.1A No alterations or amendment may be made to this subcontract except where expressly recorded in writing by a document expressed to be supplemental to this subcontract and signed by the parties.
21.9 Notwithstanding the preceding provisions of this clause 21, the parties acknowledge that the Prices and the subcontract completion date have been agreed on the basis of the assumptions set out in this clause 21.9, and that if any such assumption is incorrect or invalid this may result in adjustments thereto. The parties shall each use their reasonable endeavours to check the accuracy of the assumption made in clause 21.9 (b) as soon as practicable and confirm in writing to each other as soon as the assumption has been checked and verified. If any of the assumptions made in this clause are incorrect or invalid and this requires or involves a change to the design or proposed design of the subcontract works and it is reasonable in all the circumstances that such change to the design or proposed design of the sub contract works should give rise to an adjustment to the Prices and/or the subcontract completion date, the Contractor notifies the Subcontractor that such change is to be treated as a compensation event, and clauses 60 to 65 then apply thereto as if the Contractor had instructed such change as a change to the Subcontract Works Information.
The following shall constitute assumptions for the purposes of this Clause 21.9…
(b) cables can be installed in accordance with the Conceptual Design Statements contained in the Subcontract Works Information, and space allocations have been granted in respect of each such cable route…
60.1 The following are compensation events, but only to the extent that they are not due to any negligence, default, unlawful act or omission or breach of or failure to comply with this subcontract by the Subcontractor…
61.1 For compensation events which arise from the Contractor giving an instruction or changing an earlier decision, the Contractor notifies the Subcontractor of the compensation event at the time of giving the instruction or changing the earlier decision. He also instructs the Subcontractor to submit quotations…The Subcontractor puts the instruction or change decision into effect and provides his quotation as soon as reasonably practicable and in any event within the period for reply [2 weeks] together with details of his assessment…
61.3 The Subcontractor notifies the Contractor of an event which has happened or which he expects to happen as a compensation event if
- the Subcontractor believes that the event is a compensation event and
- the Contractor has not notified the event to the Subcontractor.
If the Subcontractor does not notify a compensation event three (3) weeks of when he becomes aware, or ought reasonably to have become aware of the event, he is not entitled to a change in the Prices or the subcontract completion date. The Contractor may in his absolute discretion assess a change to the subcontract completion date (but not a change to the Prices) notwithstanding that the Subcontractor has failed to notify a compensation event within three (3) weeks of when he became aware, or ought reasonably to have become aware, of the event.
62.1 After discussing with the Subcontractor different ways of dealing with the compensation event which are practicable, the Contractor may instruct the Subcontractor to submit alternative quotations. The Subcontractor submits the required quotations to the Contractor and may submit quotations for other methods of dealing with the compensation event which he considers practicable…
62.3 The Subcontractor submits quotations within two weeks of being instructed to do so by the Contractor. The Contractor replies within five weeks of the submission. His reply is
- an instruction to submit a revised quotation,
- an acceptance of a quotation,
- a notification that a proposed instruction will not be given or a proposed change decision will not be made or
- a notification that he will be making his own assessment…
62.6 If the Contractor does not reply to a quotation within the time allowed, the Subcontractor may notify the Contractor to this effect. If the Subcontractor submitted more than one quotation for the compensation event, he states in his notification which quotation he proposes is to be accepted. If the Contractor does not reply to the notification within five weeks, unless the quotation is for a proposed instruction or a proposed change, the Subcontractor's notification is treated as acceptance of the quotation by the Contractor…
66 Failure by the Contractor to exercise his rights under this subcontract does not constitute a waiver of those rights or any of them, and nor does any such failure relieve the Subcontractor from any of his obligations under this subcontract. The waiver in one instance of any rights, condition or requirement does not constitute a continuing or general waiver of that or any other right, condition or requirement."
"We consider that the assumption that the cables works required by our subcontract could be installed in accordance with the conceptual design statements contained within the Subcontract Works Information has now proved to be invalid...we therefore notify ABB of a Compensation Event in accordance with Clause 63.1 of the subcontract".
(a) Mr Morrison and Bam said that the £1.5m was to relate only to all work done up to 31 January 2011 but that Bam was to be paid for any further work thereafter.
(b) Ms Fletcher and ABB said that the £1.5m was to relate to all the survey and design work but that Bam was to be paid only for further such work after 31 January 2011 to the extent that it was required for reasons beyond Bam's control. This reflected concerns that some of the design work might have been necessary due to some default on the part of Bam.
Neither version of the agreement was recorded in writing or a least no such documentation was put before the adjudicator.
"In accordance with clause 64.1 we hereby notify you of our assessment of this event. The work under this CE includes for Survey Works, Detailed design, CE's for Frustrated Access (up to end of January 2011), and Space Allocation Engineer.
Background Information
The survey and detailed design changes have been developed during a process of site works and weekly meetings to validate the proposed routes and when necessary incorporate changes into the route and/or the enabling works. The work includes the preparation of SDS and CPS documents and the submission of space applications in addition to the changes to the work to be installed.
The work under this CE has been divided into four sections as follows
2.1 Survey Works
2.2 Detailed Design
2.3 Installation
2.4 Prolongation…
Cost Assessment
Following reviews of the cost submissions and detailed discussions carried out during the implementation of the works the cost has been agreed at £1,500,000…This is the direct cost for the cable service, SDS production, Space Allocations changes to the detailed design works, and the Frustrated Access up to the end of January 2011. It does not include any changes to the prices or Completion Date regarding Compensation Events covered by CE002.3 and CE002.4…"
"Please be advised that design work both at a concept and detail level has been required beyond January 2011 and this will require further discussions and dialogue, respecting ABB's current proposed cut off date for assessment of 31st January 2011."
"To formalise this process and in accordance with clause 62.3 we instruct a revised quotation for CE002 including sections 2.3, 2.4, 2.5, 2.6 and 2.7….
There has been a continual issue with Bam Nuttall not providing quotations within the period for reply as defined in the sub-contract, which is further demonstrated by the recent proposed schedule of planned submissions for CE002. In the interests of progressing the compensation event ABB will accept reasonable durations for resubmissions, and if extensions to the period for reply are required, we request that this is notified in accordance with the sub-contract."
"Compensation Event 2.2 was for additional design time to the end of January 2011 (including thickening)". Our quotation for 2.2B allows for additional design time from February 2011 to March 30th 2012…
Total Quotation based on Defined Costs for 2.2B
£977,088.88…"
There were other quotations given for other alleged events or sub-events.
"We are in receipt of your cost submission for the installation and enabling works for CE002 and are in the process of reviewing. This is taking longer than foreseen in the contract due to the format and timing of the submission from yourselves however we have noted some points that you need addressing…
We will revert to you with our comments assessment when our review is complete"
"Further to our letter of reference…dated 19 April 2012, the Contractor has not replied to the following Compensation Event Quotation in accordance with 62.3:
- Compensation Event Quotation 002
We hereby give notification in accordance with clause 62.6…"
"We acknowledge receipt of your quotation dated 12 [April] 2012, and in accordance with clause 62.3 hereby notify you that we will be making our own assessment in due course."
"ABB agree this item [CE2.2B] in principle, i.e. that the survey and design works carried post-Jan 11 are not covered by the £1.5m agreement and are to be fully reimbursed through CE2.2b where items for such reimbursement are demonstrated to be direct costs plus fee (appropriately incurred and expended) associated with this CE as agreed between both parties. Quantum using 'records' for the post-Jan 11 survey and design work to be established."
The Adjudication
"4.1.3 During 2011, the parties focused on attempting to agree other aspects of CE002 and in particular the revised installation and enabling work. During this period the design costs continued to be incurred.
4.1.4 However, no agreement was reached on the remaining parts of CE002 and it was decided, by both parties, to revert back to the contractual mechanism for dealing with quotations. As a consequence [Bam] was instructed to resubmit the quotation for CE002.
4.1.5 The consolidated CE002 quotation was issued in April 2012. The CE002.2B element of that quotation for design costs February 2011 to March 2012 amounted to £977,088.88.
4.1.6 Thereafter ABB was required to deal with the CE 002 quotation in accordance with the provisions of clause 62 and/or 64 but patently did not. Consequently, [Bam] contends that it is entitled to treat CE002 and/or its [constituent] parts (including CE002.2B), as accepted by operation of clause 62.6 and/or clause 64.4…
4.1.8 For the record ABB now purports [sic] that the sum due to [Bam] is £3,656.70. ABB also argues that [Bam] agreed to complete the design for the £1.5m already paid. This is evidently not the case which appears to have been acknowledged by ABB who now appear to have dropped this argument. However, for the avoidance of doubt [Bam] will seek a declaration on this point."
The relief claimed included alternative declarations that the "parties agreed a lump sum in the amount of £1.5 million for additional survey, design and space allocation works, including frustrated access, up to end of January 2011 only" or that they "did not reach a binding agreement on the scope of the £1.5 million lump sum". On the basis of the deemed acceptance of the April 2012 quotation, £977,088.88 less the £3,656.70 previously paid was claimed.
"5. The dispute referred to me concerns [Bam's] claim for unpaid design costs and fees for the period February 2011 to March 2012 in relation to a compensation event under the Subcontract. The parties have referred to this as CE002.2B, which I decide is an element of an overreaching compensation event CE002. [Bam] claims the sum of £977,088.88 plus interest and vat. ABB has paid the sum of £3,656.70 plus vat.
8. [Bam] asks me to decide and declare as follows:
a. That the parties agreed a lump sum in the amount of £1.5 million for additional survey, design and space allocation works, including frustrated access, up to the end of January 2011 or that the parties did not reach a binding agreement on the scope of the £1.5 million lump sum…
[10-15 He sets out some of the history from March to November 2010]
16. The parties agree that a meeting took place on 3 December 2010 between John Morrison and Linda Fletcher of ABB at which agreement was reached as to the assessment of CE002.1 and CE002.2 in the sum of £1.5m. Mr Morrison's evidence is that the assessment was agreed to include for costs up to the end of January 2011 only. In her statement… Linda Fletcher gives evidence that the agreement of 3 December 2010 was "not a payment for the work [Bam] had only done up to the date of the agreement or the work [Bam] had done up to 31 January 2011, but a payment to cover all of the work done to the date of the agreement together with the work not yet done but required to complete those compensation events." Her evidence is that this agreement "closed out the additional detailed design work occasioned by the fact that the CDS had been flawed" and that an unforeseen requirement for further design work would require a new compensation event to be raised.
17. [The contents of the letter dated 10 March 2011 are set out]
18. Plainly ABB viewed works associated with Survey Works, Detail Design, Installation and Prolongation to be one compensation event numbered CE002…
Assessment of CE 002 at May 2011
20. Applying the Subcontract terms to the circumstances up to May 2011 is not straightforward. Both parties are bound by the terms they have agreed, subject to variation of the Subcontract (supported by consideration) or some other legal restraint such as estoppel. [Bam] suggests that the parties decided to "re-engage the contractual machinery for CE002" after January 2011 [footnote: Referral at 5.6.3] suggesting that a finding of a binding agreement for payment of CE002 at the end of January 2011 requires a finding of an extra-contractual arrangement or an estoppel by which the parties were "stepping outside the contractual machinery"[footnote: Referral at 5.5.2]. ABB states that "there has never been any agreement to vary or change the terms of the contract between ABB and [Bam] relating to notifications of compensation events" [footnote: Response 7.2].
21. However, ABB also contends for a binding agreement in the sum of £1.5 million for CE002.1 and CE002.2 to include for "all of the additional surveys and Detail Design work up to submission of the CPS together with any work arising out of the subsequent commenting and approval period."
22. Further, clauses 11.1A and 66 of the Subcontract provide that:
[Terms set out as above]
23. Given these provisions of the Subcontract, the fact that the Subcontract does not appear to provide a mechanism for the agreement alleged and the disagreement between the parties as to the facts of the alleged binding agreement suggesting that they were never "ad idem", I accept [Bam's] alternative submission that the parties did not reach a binding agreement on the scope of the £1.5 million lump sum. Such an agreement would be contrary to the provisions of clause 11.1A. I find that there was never more than an assessment by ABB under the terms of the Subcontract of CE002.1/002.1.1, 002.2, 008…and 059 in the sum of £1,500,000.
24. However, I am satisfied that the parties did waive certain requirements of the Subcontract in relation to submission/delivery of quotations and assessments…
26. On 4 October 2011 ABB wrote to [Bam] to formalise the process of completing the assessment of CE002 and "in accordance with clause 62.3" to instruct the submission of "a revised quotation for CE002 including sections 2.3, 2.4, 2.5, 2.6 and 2.7"…
28. I find that this instruction, stated expressly to be under clause 62.3, related to the entirety of CE002 and reject ABB's submission that CE002 is to be subdivided into a series of separate compensation events. This omission is not in accordance with the parties' actions and objective intentions…
31. Bam submitted its revised quotation in part on 12 April 2012… and for the remainder of CE002 on 19 April 2012. I have no conclusive evidence as to why the quotation was not submitted within two weeks as required by clause 62.3. There does not appear to have been an agreement to extend time under clause 62.6. However, the remedy for failure to submit a quotation in the time required is under clause 64.1 by which:
"The Contractor assesses a compensation event if the Subcontractor has not submitted a quotation… within the time allowed."
32. ABB did not make its own assessment at that time I decide that, on the assumption that there was no agreement to extend, ABB waived the two-week requirement of clause 62.3 by accepting the quotation…
34. …I also find that ABB's letter of 22 June 2012 [set out earlier in this judgment] was an effective response under clause 62.3 by which ABB accepted the quotation and, by such acceptance and by not rejecting the quotation, waived (in so far as it was necessary for it to do so) compliance with the first sentence of clause 62.3 and notified Bam that it would make its own assessment…
37. ABB accepts that under clause 64.3 the period for the Contractor to give the Subcontractor its assessment is two weeks on the day that the need for the Contractor's assessment becomes apparent. I accept ABB's submission that the start date is 22 June 2012 so that ABB's assessment was due on or by 7 July 2012.
38. Following [Bam's] notice of 27 July 2012 that…CE002 had not been assessed within the time allowed for by the Subcontract, under clause 64.4 ABB had four weeks to reply to the notice (i.e. until 25 August 2012) by notification of his assessment giving details of it (as required by clause 64.3).
39. ABB submits that its letter 31 July 2012 was the required reply under clause 64.4. I do not accept this submission. This letter is as follows…
40. I find that the letter does not constitute an assessment of CE002 (or indeed an assessment of any part of that compensation event) in response to the quotation delivered on 12 and 19 April 2012 and does not give details of such an assessment…
41. I am satisfied that at this stage both parties had stated that they required compliance with the terms of the [Subcontract]. Certainly there is no evidence that any waiver of those terms was contemplated or could be relied on by ABB…
43. I therefore decide that [Bam's] notification of 27 July 2012 is to be treated as acceptance by ABB of [Bam's] quotation of 12 and 19 April 2012 under clause 64.4 in relation to compensation event CE002.
44. I reject ABB's submission that there was an "un-written agreement" to the effect that ABB was not bound by the contract terms in relation to [Bam's] quotation. Such an agreement is contrary to clause 11.1A of the Subcontract and is not supported by the evidence, particularly the correspondence.
45. I am also not satisfied that there was a continuing waiver by [Bam] in response to ABB's waiver as claimed in paragraph 2.8 of the Response, particularly in relation to the quotation of 12 and 19 April 2012 in circumstances where [Bam] had given clear notice that it required compliance with the terms of the Subcontract.
46. In its evidence ABB has referred to the fact that it took [Bam] more than six months to reply to a request for a quotation when the subcontract allows two weeks. However, I am bound to make my decision in accordance with the terms of a Subcontract in circumstances where:
…b. The drafting of the NEC3 form of contract is intended to achieve certainty in certain circumstances by imposing time limits after which contractual rights may be lost both by Contractor and Sub-Contractor.
c. [Bam's] revised quotation for CE002 was instructed by ABB.
d. The quotation was requested for the entirety of CE002.
e. ABB did not make its own assessment under clause 64.1 when the quotation was late.
f. The quotation was not rejected as being out of time when it did arrive.
g. ABB notified that it would carry out its assessment.
h. ABB had more than 4 months in total to assess CE002 before it became treated as acceptance.
i. ABB's failure to assess CE002 was notified by [Bam] in writing in accordance with the Subcontract before it became treated as accepted.
47. I have considered the other evidence and documents to which I have been referred and have concluded that, in the light of this decision and my findings on the application of and effect of clause 64.4, much of the submissions and evidence submitted to me in this adjudication is not relevant to deciding the dispute referred to me. It is not therefore necessary for me to refer to all the matters I have considered including reasons.
48. In that regard I accept [Bam's] submission at A9 of the Reply that, following my decision that [Bam's] quotation for CE002 of 12 and 19 April 2012 is to be treated as accepted, the arguments put forward by ABB in the Response must fall away…
51. I therefore decide and declare as follows:
a. The parties did not reach a binding agreement on the scope of the £1.5 million lump sum (subject to my decision at 51d. below that [Bam's] quotation of 12 and 19 April 2012 including his sum is to be treated as accepted by ABB).
b. [Bam's] quotation of 12 and 19 April 2012 for CE002B is treated as accepted by ABB by operation of clause 64.4 of the Subcontract.
c. ABB has accepted the value of CE002B and £977,088.88 plus vat.
d. In accordance with clause 64.4 of the Subcontract, CE002B is treated as accepted by ABB as part of [Bam's] quotation of 12 and 19 April 2012 for CE002 that is itself treated as accepted by ABB…"
The Proceedings and the Argument
Discussion
Decision