QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
TSG BUILDING SERVICES PLC |
Claimant |
|
- and - |
||
SOUTH ANGLIA HOUSING LIMITED |
Defendant |
____________________
Marc Lixenberg (instructed by Trowers & Hamlins) for the Defendant in HT-13-85
Hearing date: 17 April 2013
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
Background
"1.1 The Partnering Team members shall work together and individually in the spirit of trust, fairness and mutual co-operation for the benefit of the Term Programme, within the scope of their agreed roles, expertise and responsibilities as stated in the Partnering Documents, and all their respective obligations under the Partnering Contract shall be construed within the scope of such roles, expertise and responsibilities, and in all matters governed by the Partnering Contract they shall act reasonably and without delay. [There was added as a bespoke term that the "roles, expertise and responsibilities of the Client and the Service Provider are further described in the Term Brief and the Term Proposals and the Service Provider shall be paid in accordance with the Partnering Terms and the Price Framework"].
"13.3 If stated in the Term Partnering Agreement that this clause 13.3 applies, the Client may terminate the appointment of all other Partnering Team members, and any other Partnering Team member stated in the Term Partnering Agreement may terminate its own appointment, at any time during the Term or as otherwise stated by the period(s) of notice to all other Partnering Team members stated in the Term Partnering Agreement. [A bespoke term confirmed that Clause 13.3 was to apply and identified that any "Partnering Team member may serve notice on the others, provided that at least three… months' notice is given.]"
"…Pursuant to clause 13.3 of the Agreement, South Anglia hereby gives TSG three months notice of its intention to terminate TSG's Appointment under the Agreement. In accordance with Clause 1.10 of the Agreement, the three month notice period is effective from the date of delivery of this letter to you. This letter is delivered to you by fax, as provided by clause 1.10, on 23rd of August 2010 and as such TSG's Appointment will terminate on 24th November 2010."
" . the additional costs which TSG has incurred during Year 1 as a result of poor maintenance, servicing or installation works undertaken by other parties (£548,086.73)
. the revenue TSG has lost as a result of [South Anglia] awarding contract works to other contractors (£67,235.47)
. the costs which have resulted from [South Anglia's] termination of the Agreement (£586,502.68)"
The latter figure was an amalgam of under recovery of overheads and profit, contract set-up and termination costs. The "redress" sought included decisions that TSG was entitled to payment of each of the sums claimed plus adjudicator's fees.
These Proceedings
"South Anglia having exercised its right to serve notice to terminate the Agreement under Clause 13.3 thereof, TSG has no entitlement, whether as damages for breach of contract, or as a sum due under the contract, to receive monies and/or compensation in respect of the overheads and profit it would have recovered over [the] balance of the Term (Post termination), had the agreement not been terminated"
It seeks a consequential declaration that the adjudicator was wrong in ordering South Anglia to pay £383,778.91 to TSG by way of compensation for termination and also in ordering payment of interest.
Jurisdiction of the Adjudicator
"33. It is important to bear in mind that construction contracts are commercial contracts and parties, at least almost invariably, can be taken to have agreed that a sensible interpretation will be given to what the meaning of a dispute is. It is conceivable that there may be a dispute on a construction contract which is simply: what is due to one or other of the parties? That could be a very broad dispute covering a large number of issues. For instance, there may be a dispute between the parties about an interim valuation with the contractor saying that it is entitled to payment for 50 variations but overall it is claiming £100,000; the Architect certifies £80,000 and disagrees with the contractor on each of the 50 variations (a) the amount of work done and (b) the rate or price. One could say that there were 100 disputes, namely 2 per variation. Alternatively and obviously sensibly, one could and should say that there was one dispute with 100 sub-issues. The parties can not sensibly have intended in these circumstances that each sub-issue for the purposes of adjudication and even arbitration gives rise to a separate dispute which must be referred to a separate adjudication or arbitration. The dispute in this example will be as to what sum the contractor was entitled to on the interim valuation. A particular dispute, somewhat like a snowball rolling downhill gathering snow as it goes, may attract more issues and nuances as time goes on; the typical example in a construction contract is the ever increasing dispute about what is due to the contractor as each monthly valuation and certificate is issued; a later certificate may accept amounts in issue previously not certified but then reject some more items of work. One may in the alternative have a dispute, like the proverbial rolling stone gathering no moss, which remains the same and unaffected by later events; an example might be disputed responsibility over an accident on site…
38. Drawing all these threads together, I draw the following conclusions:
(i) A dispute arises generally when and in circumstances in which a claim or assertion is made by one party and expressly or implicitly challenged or not accepted.
(ii) A dispute in existence at one time can in time metamorphose in to something different to that which it was originally.
(iii) A dispute can comprise a single issue or any number of issues within it. However, a dispute between parties does not necessarily comprise everything which is in issue between them at the time that one party initiates adjudication; put another way, everything in issue at that time does not necessarily comprise one dispute, although it may do so.
(iv) What a dispute in any given case is will be a question of fact albeit that the facts may require to be interpreted. Courts should not adopt an over legalistic analysis of what the dispute between the parties is, bearing in mind that almost every construction contract is a commercial transaction and parties can not broadly have contemplated that every issue between the parties would necessarily have to attract a separate reference to adjudication.
(v) The Notice of Adjudication and the Referral Notice are not necessarily determinative of what the true dispute is or as to whether there is more than one dispute. One looks at them but also at the background facts.
(vi) Where on a proper analysis, there are two separate and distinct disputes, only one can be referred to one adjudicator unless the parties agree otherwise. An adjudicator who has two disputes referred to him or her does not have jurisdiction to deal with the two disputes.
(vii) Whether there are one or more disputes again involves a consideration of the facts. It may well be that, if there is a clear link between two or more arguably separate claims or assertions, that may well point to there being one dispute. A useful if not invariable rule of thumb is that, if disputed claim No 1 can not be decided without deciding all or parts of disputed claim No 2, that establishes such a clear link and points to there being only one dispute."
"75. I have proceeded on the basis that Mr Hickey was correct and that s.108 precludes a party from referring more than a single dispute at the same time, as has been stated in a number of previous decisions. He however accepted that a party could refer multiple disputes to adjudication if the parties consent to that. Mr Lee was careful in his submissions to point out that under the Scheme, without the consent of the parties, it is not possible to refer more than one dispute to adjudication: see Bothma and Witney Town Council both of which involved adjudications under the Scheme. He did not accept that it went further. It is to be noted that the reasoning in Bothma at [4] was that as paragraph 8(1) of Part I of the Scheme provided that the adjudicator could, with the consent of the parties, adjudicate more than one dispute, that meant that absent such consent he could not. The decision was not based on a principle derived from the wording of s.108(1), which refers to a party having a right to refer "a dispute" to adjudication.
76. On analysis such an argument as to the meaning of "a dispute" in s.108(1) has difficulties. If s.108(1) limits a party to being able to refer a single dispute to adjudication by the reference to the phrase "a dispute" rather than the use of the word "disputes", then that causes problems for parties consenting to refer multiple disputes to a single adjudication. If a party agreed to a provision for multiple disputes to be referred to adjudication then that provision would not comply with s.108 (1). The effect of a provision of the construction contract not complying with s.108 (1) would be that s.108(5) would cause the adjudication provisions of the Scheme to apply. The effect would be that paragraph 8(1) of the Scheme would apply which allows multiple disputes to be referred if the parties consent and that would be what the parties had done and were free to do under the Scheme. On that basis the Scheme would not comply with s.108(1). This suggest that an argument based on the reference in s.108(1) to "a dispute" being "one dispute" may not be correct and that the reference to "a dispute" is more likely to be a generic reference to "a dispute", without seeking to limit it to a singular dispute.
77. In this case I have not needed to decide whether the references in rule 8 to "a dispute" or "the dispute" limited the parties in this case to referring one dispute. However, given the wording of rule 36 which refers to the Adjudicator being appointed "to determine the dispute or disputes between the Parties", I would have held that the reference to "a dispute" or "the dispute" in rule 8 was a generic reference which was not intended to limit the number of disputes which could be referred to adjudication by a Notice. Contrary to Mr Hickey's submission I do not consider that the reference to "disputes" in rule 36 cannot properly be construed as being limited to cases of joinder of third parties under rule 22. If it had been necessary, I would have based my decision on this."
His logic was that references in Section 108 and the Scheme to the reference to adjudication of "a dispute" were generic and were not statutorily intended to restrict reference in one adjudication of more than one dispute and that it is open to the parties to agree in their contract that more than one dispute can be referred in a single adjudication; he found that the CIC Rules permitted more than one dispute so to be referred. I do not intend to add, obiter, to a debate on this topic which was only addressed by Mr Justice Ramsey himself on an obiter basis. I would say only that, absent specific agreement either in the original contract or on an ad hoc basis, authorities are sufficiently well established now to suggest that only one dispute can be referred to adjudication, albeit that the courts adopt a sensible and commercial approach in determining the relative width of any given dispute.
The Contract and the Part 8 Proceedings
"The Partnering Team members shall establish, develop and implement their partnering relationships, within their agreed roles, expertise and responsibilities and in accordance with the Partnering Documents, with the objectives of achieving for the benefit of the Term Programme and for the mutual benefit of Partnering Team members:-
(i) trust, fairness, mutual cooperation, dedication to agreed common goals and an understanding of each other's expectations and values;
(ii) satisfaction of the agreed pre-conditions to implementation of the Term Programme referred to in clause 6.1;
(iii) implementation of Tasks within the agreed time and price and to the agreed quality pursuant to Orders issued in accordance with clause 6;
(iv) innovation, improved efficiency, cost-effectiveness, lean production, improved Sustainability and other measurable continuous improvements by means of the Processes referred to in clause 2.2 and by reference to the agreed KPIs and Targets referred to in clause 2.5;
(v) commitments to people including staff and Users;
(vi) any additional objectives stated in the Term Partnering Agreement."
"Within…40 Working Days following the end of the Term, the Client Representative shall prepare and issue to the Client and the Service Provider a Final Account, which when agreed by them shall be conclusive evidence as to the balance due between them and, upon such agreement, the Client Representative shall issue a Final Account valuation. The Client shall pay in accordance with clause 7.6 the amount stated in the Final Account valuation…If agreement is not reached within…40 Working Days from the date of issue of the Final Account, either the Client or the Service Provider may implement the procedures described in clause 14 if appropriate."
"In the event that any Partnering Team member shall breach the Partnering Contract so as to have a demonstrable adverse effect on the implementation of the Term Programme or any Task and shall not remedy such breach within ten…Working Days from the date of notice from another Partnering Team member specifying the breach then, after notifying the Core Group and allowing a period of ten…Working Days from the date of such notification to receive and consider their recommendations, the notifying Partnering Team member (if it is not the Client) may terminate its own appointment under the Partnering Contract or, (if it is the Client) may terminate the appointment of the Partnering Team member in breach, in each case by notice with immediate effect."
Clause 13.8 provided:
"In the event of termination in accordance with clauses 13.2, 13.3 or 13.4 or by reason of Client bankruptcy or insolvency under clause 13.5 or by any Partnering Team member of its own appointment in accordance with clause 13.6, the relevant Partnering Team member(s) shall be entitled to payment in accordance with clause 7 of the total amount(s) properly due up to the date of termination."
Discussion
"[1] The Partnering Team members shall work together and individually in the spirit of trust, fairness and mutual co-operation for the benefit of the Term Programme, within the scope of their agreed roles, expertise and responsibilities as stated in the Partnering Documents, and [2] all their respective obligations under the Partnering Contract shall be construed within the scope of such roles, expertise and responsibilities, and [3] in all matters governed by the Partnering Contract they shall act reasonably and without delay."
(1) The first part of this clause is clearly and primarily calling upon the parties to "work together" and in that context jointly and separately to do so "in the spirit of trust, fairness and mutual co-operation", the object being towards "the benefit of the Term Programme"; the Term Programme has as its object the efficient and good quality performance of the gas related works in some 5500 dwellings. This is all to be "within the scope" of the "roles, expertise and responsibilities" called for in the Partnering Documents. This on its face and as a matter of commercial common sense does not obviously or at all impinge upon either party's right to terminate at will under Clause 13.3. Termination at will is not a "responsibility"; it does not give rise to a "role" or is not dependent upon any "expertise".
(2) The second part is in effect a corollary of the first part. The reference to the "respective obligations" does not obviously or at all relate to a negotiated right on either party to terminate at will. The second part in any event is simply calling for obligations on each or all of the parties to be construed in effect in the context of the specified roles expertise and responsibilities.
(3) It is in the third part of the clause on which TSG's Counsel has properly placed most emphasis. He argued that termination was a matter governed by the Contract and therefore that this last part of the clause requires each party to act reasonably, amongst other things, in effectively deciding whether to terminate under Clause 13.3. He points to other contracts referred to in other cases in which termination or other contractual requirements were subject to an express term that the party should not behave unreasonably or vexatiously, an example being John Jarvis v Rochdale Housing Association (1986) 36 BLR 10. In some of these cases of course, the termination provision is itself expressly qualified by a requirement that the terminating party shall not terminate unreasonably or vexatiously. I will return to this, which was TSG's strongest point on contract construction.
"The Trust and the Contractor will co-operate with each other in good faith and will take all reasonable action as is necessary for the efficient transmission of information and instructions and to enable the Trust or, as the case may be, any Beneficiary to derive the full benefit of the Contract. At all times in the performance of the Services, the Contractor will co-operate fully with any other contractors appointed by the Trust or any Beneficiary in connection with other services at the Location."
Clause 5.8 provided for deductions to be made from payments in certain circumstances:
"The Trust or any Beneficiary shall ascertain whether the Contractor's provision of the Services meets the performance criteria as specified in the Service Level Specification or, if the criteria are not so specified, meets the standards of a professional provider of the Services. Where such performance criteria or standards have not been met by the Contractor in the performance of the Services then the Trust shall be entitled to levy payment deductions against the monthly amount of the Contract Price payable to the Contractor in accordance with the terms of the Payment Mechanism. In addition, the Trust may by notice to the Contractor award Service Failure Points depending on the performance of the Services as measured in accordance with the Service Level Specification. Service Failure Points which are agreed or determined to have been awarded in circumstances where such award was not justified shall be deemed to have been cancelled."
"83. An important feature of the above line of authorities is that in each case the discretion did not involve a simple decision whether or not to exercise an absolute contractual right. The discretion involved making an assessment or choosing from a range of options, taking into account the interests of both parties. In any contract under which one party is permitted to exercise such a discretion, there is an implied term. The precise formulation of that term has been variously expressed in the authorities. In essence, however, it is that the relevant party will not exercise its discretion in an arbitrary, capricious or irrational manner. Such a term is extremely difficult to exclude, although I would not say it is utterly impossible to do so. Certainly clause 1.1.5 of the conditions in the present case is not effective to exclude such a term, if it is otherwise to be implied…
91. The discretion which is entrusted to the Trust in relation to service failure points and deductions in the present case is very different from the discretion which existed in the authorities discussed above. The Trust is a public authority delivering a vital service to vulnerable members of the public. It rightly demands high standards from all those with whom it contracts. There may, of course, be circumstances in which the Trust decides to award less than the full amount of service failure points or to deduct less than it is entitled to deduct from a monthly payment. Nevertheless the Trust could not be criticised if it awards the full number of service failure points or if it makes the full amount of any deduction which it is entitled to make. The discretion conferred by clause 5.8 simply permits the Trust to decide whether or not to exercise an absolute contractual right.
92. There is no justification for implying into clause 5.8 a term that the Trust will not act in an arbitrary, irrational or capricious manner. If the Trust awards more than the correct number of service failure points or deducts more than the correct amount from any monthly payment, then that is a breach of the express provisions of clause 5.8. There is no need for any implied term to regulate the operation of clause 5.8.
106...The obligation to co-operate in good faith is not a general one which qualifies or reinforces all of the obligations on the parties in all situations where they interact. The obligation to co-operate in good faith is specifically focused upon the two purposes stated in the second half of that sentence.
114. The substantial deductions which the Trust made in July and August 2009 fall into a different category. They were not agreed by Medirest and they exceeded the true amount which the Trust was entitled to deduct. In making these deductions the Trust was acting in breach of clauses 5.8, 6.3 and 6.5 of the conditions. The Trust was also acting contrary to the various provisions of the Payment Mechanism concerning deductions which I have set out in Part 2 above. On the other hand these unilateral deductions were not breaches of clause 3.5 of the conditions. I say this for two reasons:
i) There is no finding by the judge that the Trust was acting dishonestly, as opposed to mistakenly applying the provisions of a complicated contract.
ii) These deductions were irrelevant to the two stated purposes. They had nothing to do with the transmission of information or instructions between the parties. Nor were they relevant to the Trust or any beneficiary deriving the full benefit of the contract…
116…On the facts as found by the judge the Trust persisted in awarding an excessive number of service failure points throughout the period August 2008 to September 2009. This was a breach of the express provisions of clause 5.8 of the conditions. It was not, however, a breach of clause 3.5 of the conditions. I say this for two reasons:
i) There is no finding by the judge that the Trust was acting dishonestly, as opposed to mistakenly applying the provisions of a complicated contract.
ii) These deductions were irrelevant to the two stated purposes. In particular, an award of service failure points under clause 5.8 of the conditions was not "the transmission of information and instructions" within clause 3.5. The two clauses are directed towards different matters. There is no need for clause 3.5 and 5.8 to cover the same ground twice over and, as I read those two clauses, they do not do so… [per Jackson LJ]
141…In effect the judge has implied a term that makes it a breach of contract to misinterpret the contract. In my judgment it is not generally a breach of contract merely to assert rights which the contract does not confer…
146. It seems to me to be clear that whatever the scope of the duty it can be no more than a duty to co-operate in good faith. My difficulty is to see in what sense the unilateral decision by the Trust to award SFPs or to assert a right to levy Deductions (or even the actual levying of Deductions) is something that requires co-operation at all.
147. Mr Howe also argued that properly interpreted the second limb of clause 3.5 imposed on the Trust a duty not to act unreasonably in the exercise or purported exercise of its rights under the contract; and in particular imposed on the Trust an obligation not to make unreasonable claims. In my judgment, however, that is simply not what the clause says. First, it is concerned with taking action, not making claims. Second, the action concerned is action for limited purposes. Third, I do not consider that a positive obligation to take all reasonable action necessarily entails a negative obligation not to make unreasonable claims. [per Lewison LJ]
151. The scope of the obligation to co-operate in good faith in clause 3.5 must be assessed in the light of the provisions of that clause, the other provisions of the contract, and its overall context. As to the first of these factors, I respectfully agree with Jackson LJ (at paragraphs [106] – [108]) that the content of the obligations to co-operate in good faith is to be determined by reference to the two purposes specified in the clause. Those purposes are the efficient transmission of information and instructions and enabling the Trust or any beneficiary to derive the full benefit of the contract…
154. The contract in the present case is a detailed one which makes specific provision for a number of particular eventualities. The specific provisions include clauses 5.8, 6.3 and 6.5. In a situation where a contract makes such specific provision, in my judgment care must be taken not to construe a general and potentially open-ended obligation such as an obligation to "co-operate" or "to act in good faith" as covering the same ground as other, more specific, provisions, lest it cut across those more specific provisions and any limitations in them." [per Beatson LJ]
"Undertake during normal working hours the annual service, test and…gas safety certification, and maintain and repair in response to all breakdown callouts to any type of gas fired, oil or solid fuel appliance and the entire dwelling wet central heating radiator system, including provision and renewal of all unserviceable parts connected to the heating system and provision of service, maintenance and repair history records or as specified".
Implied Term of Good Faith
"16. Before discussing in greater detail the reasoning of the Court of Appeal, the Board will make some general observations about the process of implication. The court has no power to improve upon the instrument which it is called upon to construe, whether it be a contract, a statute or articles of association. It cannot introduce terms to make it fairer or more reasonable. It is concerned only to discover what the instrument means. However, that meaning is not necessarily or always what the authors or parties to the document would have intended. It is the meaning which the instrument would convey to a reasonable person having all the background knowledge which would reasonably be available to the audience to whom the instrument is addressed: see Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896, 912-913. It is this objective meaning which is conventionally called the intention of the parties, or the intention of Parliament, or the intention of whatever person or body was or is deemed to have been the author of the instrument.
17. The question of implication arises when the instrument does not expressly provide for what is to happen when some event occurs. The most usual inference in such a case is that nothing is to happen. If the parties had intended something to happen, the instrument would have said so. Otherwise, the express provisions of the instrument are to continue to operate undisturbed. If the event has caused loss to one or other of the parties, the loss lies where it falls.
18. In some cases, however, the reasonable addressee would understand the instrument to mean something else. He would consider that the only meaning consistent with the other provisions of the instrument, read against the relevant background, is that something is to happen. The event in question is to affect the rights of the parties. The instrument may not have expressly said so, but this is what it must mean. In such a case, it is said that the court implies a term as to what will happen if the event in question occurs. But the implication of the term is not an addition to the instrument. It only spells out what the instrument means.
19. The proposition that the implication of a term is an exercise in the construction of the instrument as a whole is not only a matter of logic (since a court has no power to alter what the instrument means) but also well supported by authority. In Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board [1973] 1 WLR 601, 609 Lord Pearson, with whom Lord Guest and Lord Diplock agreed, said:
"[T]he court does not make a contract for the parties. The court will not even improve the contract which the parties have made for themselves, however desirable the improvement might be. The court's function is to interpret and apply the contract which the parties have made for themselves. If the express terms are perfectly clear and free from ambiguity, there is no choice to be made between different possible meanings: the clear terms must be applied even if the court thinks some other terms would have been more suitable. An unexpressed term can be implied if and only if the court finds that the parties must have intended that term to form part of their contract: it is not enough for the court to find that such a term would have been adopted by the parties as reasonable men if it had been suggested to them: it must have been a term that went without saying, a term necessary to give business efficacy to the contract, a term which, though tacit, formed part of the contract which the parties made for themselves."
20. More recently, in Equitable Life Assurance Society v Hyman [2002] 1 AC 408, 459, Lord Steyn said:
"If a term is to be implied, it could only be a term implied from the language of [the instrument] read in its commercial setting."
21. It follows that in every case in which it is said that some provision ought to be implied in an instrument, the question for the court is whether such a provision would spell out in express words what the instrument, read against the relevant background, would reasonably be understood to mean. It will be noticed from Lord Pearson's speech that this question can be reformulated in various ways which a court may find helpful in providing an answer – the implied term must "go without saying", it must be "necessary to give business efficacy to the contract" and so on – but these are not in the Board's opinion to be treated as different or additional tests. There is only one question: is that what the instrument, read as a whole against the relevant background, would reasonably be understood to mean?
22. There are dangers in treating these alternative formulations of the question as if they had a life of their own. Take, for example, the question of whether the implied term is "necessary to give business efficacy" to the contract. That formulation serves to underline two important points. The first, conveyed by the use of the word "business", is that in considering what the instrument would have meant to a reasonable person who had knowledge of the relevant background, one assumes the notional reader will take into account the practical consequences of deciding that it means one thing or the other. In the case of an instrument such as a commercial contract, he will consider whether a different construction would frustrate the apparent business purpose of the parties. That was the basis upon which Equitable Life Assurance Society v Hyman [2002] 1 AC 408 was decided. The second, conveyed by the use of the word "necessary", is that it is not enough for a court to consider that the implied term expresses what it would have been reasonable for the parties to agree to. It must be satisfied that it is what the contract actually means.
23. The danger lies, however, in detaching the phrase "necessary to give business efficacy" from the basic process of construction of the instrument. It is frequently the case that a contract may work perfectly well in the sense that both parties can perform their express obligations, but the consequences would contradict what a reasonable person would understand the contract to mean. Lord Steyn made this point in the Equitable Life case (at p. 459) when he said that in that case an implication was necessary "to give effect to the reasonable expectations of the parties."
24. The same point had been made many years earlier by Bowen LJ in his well known formulation in The Moorcock (1889) 14 PD 64, 68:
"In business transactions such as this, what the law desires to effect by the implication is to give such business efficacy to the transaction as must have been intended at all events by both parties who are business men"
25. Likewise, the requirement that the implied term must "go without saying" is no more than another way of saying that, although the instrument does not expressly say so, that is what a reasonable person would understand it to mean. Any attempt to make more of this requirement runs the risk of diverting attention from the objectivity which informs the whole process of construction into speculation about what the actual parties to the contract or authors (or supposed authors) of the instrument would have thought about the proposed implication. The imaginary conversation with an officious bystander in Shirlaw v Southern Foundries (1926) Ltd [1939] 2 KB 206, 227 is celebrated throughout the common law world. Like the phrase "necessary to give business efficacy", it vividly emphasises the need for the court to be satisfied that the proposed implication spells out what the contact would reasonably be understood to mean. But it carries the danger of barren argument over how the actual parties would have reacted to the proposed amendment. That, in the Board's opinion, is irrelevant. Likewise, it is not necessary that the need for the implied term should be obvious in the sense of being immediately apparent, even upon a superficial consideration of the terms of the contract and the relevant background. The need for an implied term not infrequently arises when the draftsman of a complicated instrument has omitted to make express provision for some event because he has not fully thought through the contingencies which might arise, even though it is obvious after a careful consideration of the express terms and the background that only one answer would be consistent with the rest of the instrument. In such circumstances, the fact that the actual parties might have said to the officious bystander "Could you please explain that again?" does not matter.
26. In BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266, 282-283 Lord Simon of Glaisdale, giving the advice of the majority of the Board, said that it was "not … necessary to review exhaustively the authorities on the implication of a term in a contract" but that the following conditions ("which may overlap") must be satisfied:
"(1) it must be reasonable and equitable; (2) it must be necessary to give business efficacy to the contract, so that no term will be implied if the contract is effective without it; (3) it must be so obvious that 'it goes without saying' (4) it must be capable of clear expression; (5) it must not contradict any express term of the contract".
27. The Board considers that this list is best regarded, not as series of independent tests which must each be surmounted, but rather as a collection of different ways in which judges have tried to express the central idea that the proposed implied term must spell out what the contract actually means, or in which they have explained why they did not think that it did so. The Board has already discussed the significance of "necessary to give business efficacy" and "goes without saying". As for the other formulations, the fact that the proposed implied term would be inequitable or unreasonable, or contradict what the parties have expressly said, or is incapable of clear expression, are all good reasons for saying that a reasonable man would not have understood that to be what the instrument meant."
"120. The subject of whether English law does or should recognise a general duty to perform contracts in good faith is one on which a large body of academic literature exists. However, I not am aware of any decision of an English court, and none was cited to me, in which the question has been considered in any depth.
121. The general view among commentators appears to be that in English contract law there is no legal principle of good faith of general application: see Chitty on Contract Law (31st Ed), Vol 1, para 1-039. In this regard the following observations of Bingham LJ (as he then was) in Interfoto Picture Library Ltd v Stiletto Visual Programmes Ltd [1989] 1 QB 433 at 439 are often quoted:
"In many civil law systems, and perhaps in most legal systems outside the common law world, the law of obligations recognises and enforces an overriding principle that in making and carrying out contracts parties should act in good faith. This does not simply mean that they should not deceive each other, a principle which any legal system must recognise; its effect is perhaps most aptly conveyed by such metaphorical colloquialisms as 'playing fair', 'coming clean' or 'putting one's cards face upwards on the table.' It is in essence a principle of fair open dealing… English law has, characteristically, committed itself to no such overriding principle but has developed piecemeal solutions in response to demonstrated problems of unfairness."
122. Another case sometimes cited for the proposition that English contract law does not recognise a duty of good faith is Walford v Miles [1992] 2 AC 128, where the House of Lords considered that a duty to negotiate in good faith is "inherently repugnant to the adversarial position of the parties when involved in negotiations" and "unworkable in practice" (per Lord Ackner at p.138). That case was concerned, however, with the position of negotiating parties and not with the duties of parties who have entered into a contract and thereby undertaken obligations to each other.
123. Three main reasons have been given for what Professor McKendrick has called the "traditional English hostility" towards a doctrine of good faith: see McKendrick, Contract Law (9th Ed) pp.221-2. The first is the one referred to by Bingham LJ in the passage quoted above: that the preferred method of English law is to proceed incrementally by fashioning particular solutions in response to particular problems rather than by enforcing broad overarching principles. A second reason is that English law is said to embody an ethos of individualism, whereby the parties are free to pursue their own self-interest not only in negotiating but also in performing contracts provided they do not act in breach of a term of the contract. The third main reason given is a fear that recognising a general requirement of good faith in the performance of contracts would create too much uncertainty. There is concern that the content of the obligation would be vague and subjective and that its adoption would undermine the goal of contractual certainty to which English law has always attached great weight.
124. In refusing, however, if indeed it does refuse, to recognise any such general obligation of good faith, this jurisdiction would appear to be swimming against the tide…"
He then refers to cases in the USA, Canada, Australia and Scotland as well as to the law in New Zealand. He picks up the references to the Belize case above. He underlines the proposition that virtually all contracts will require honesty in their performance (Paragraph 137) and "fidelity to the parties' bargain" (Paragraph 139). He then goes on to say:
"140 The two aspects of good faith which I have identified are consistent with the way in which express contractual duties of good faith have been interpreted in several recent cases: see Berkeley Community Villages Ltd v Pullen [2007] EWHC 1330 (Ch) at [95]-[97]; CPC Group Ltd v Qatari Diar Real Estate Investment Co [2010] EWHC 1535 (Ch) at [246].
141. What good faith requires is sensitive to context. That includes the core value of honesty. In any situation it is dishonest to deceive another person by making a statement of fact intending that other person to rely on it while knowing the statement to be untrue. Frequently, however, the requirements of honesty go further. For example, if A gives information to B knowing that B is likely to rely on the information and A believes the information to be true at the time it is given but afterwards discovers that the information was, or has since become, false, it may be dishonest for A to keep silent and not to disclose the true position to B. Another example of conduct falling short of a lie which may, depending on the context, be dishonest is deliberately avoiding giving an answer, or giving an answer which is evasive, in response to a request for information."
"…based on the material that has been put before me, I feel I am able to construe paragraph 33 of the Third Schedule to the Agreement as imposing on the Defendants a contractual obligation to observe reasonable commercial standards of fair dealing in accordance with their actions which related to the Agreement and also requiring faithfulness is to the agreed common purpose and consistency with the justified expectations of the First Claimant."
"42. Under the terms of the appellants' contracts, therefore, Flag had an express contractual right, which it exercised, to bring the appellants' contracts of employment to an end at any time during the contract period without cause. Their Lordships agree with Flag that that is an end of the matter. As the Court of Appeal observed, "the very nature of such a power is that its exercise does not have to be justified".
43. The principal ground on which this was disputed by the appellants at trial was that the decision of Flag's Directors to bring their contracts to an end was vitiated by their "collateral purpose" in seeking to avoid having to grant the appellants stock options. But in the present context there is no such thing as a "collateral" or improper purpose; a power to dismiss without cause is a power to dismiss for any cause or none. The Directors of Flag were, of course, obliged to exercise their powers as directors in good faith and for the benefit of the company. As the Court of Appeal pointed out, however, this was a duty owed to the company and not to its employees…"
It can of course be said that employment contracts, given the nature of the relationship between employer and employee, fall into a somewhat different category to commercial contracts but these dicta at least provide a pointer which is germane. Their Lordships went on:
"45. Their Lordships accept that the appellants' contracts of employment contained an implied term that Flag would not without reasonable and proper cause destroy the relationship of trust and confidence which should exist between employer and employee. The existence of such a term is now well established on the authorities: see Imperial Group Pensions Trust Limited v Imperial Tobacco Ltd. [1991] 1 WLR 589 at pp. 597-9; Malik v Bank of Credit and Commerce International S.A. [1998] AC 20; Johnson v Unisys [2001] 2 All ER 801. But in common with other implied terms, it must yield to the express provisions of the contract. As Lord Millett observed in Johnson v Unisys it cannot sensibly be used to extend the relationship beyond its agreed duration; and, their Lordships would add, it cannot sensibly be used to circumscribe an express power of dismissal without cause. This would run counter to the general principle that an express and unrestricted power cannot in the ordinary way be circumscribed by an implied qualification: see Nelson v British Broadcasting Corporation [1977] IRLR 148 (where it was sought to imply a restriction of location into a contract which contained an unqualified mobility clause). Roskill LJ said at p. 151:
"... it is a basic principle of contract law that if a contract makes express provision ... in almost unrestricted language, it is impossible in the same breath to imply into that contract a restriction of the kind that the Industrial Tribunal sought to do.""
Conclusion