QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
UNITED MARINE AGGREGATES LIMITED |
Claimant |
|
- and - |
||
G.M.WELDING & ENGINEERING LIMITED |
Defendant |
|
- and - |
||
NOVAE SYNDICATES LIMITED |
Part 20 Defendant |
____________________
Mr Stuart Hornett (instructed by Lefevre LLP) for the Defendant
Mr Philip Shepherd QC (instructed by Kennedys Law) for the Part 20 Defendant
Hearing dates: 13 – 21 February 2012 & 5 March 2012
____________________
Crown Copyright ©
Mr Justice Edwards-Stuart:
Introduction
(1) Whether the fire broke out in the location alleged by UMA (the screening house) or the location alleged by the Defendants (the scalping house)?(2) If the fire broke out in the screening house, whether it was caused by any breach of duty, whether in contract or tort, by the Defendants?
(3) If the fire was caused by any breach of duty by the Defendants, whether the Defendants are entitled to be indemnified under the policy?
The facts
The outbreak of the fire
The witnesses
Mr Farla
"I phoned Paul Burgess at approx 10H05 (sic) and informed him of the fire, which by now was burning fiercely and CV06 was now on fire.
The Fire Brigade was on their way and arrived within 20 minutes. I went to meet them and direct them to the fire. I had in the meantime phoned John Curtis who said he was off site having breakfast. I told him to return to site immediately, he arrived approx 15 minutes later. Mark Garnham had in the meantime contacted Phil Smith who was in charge of the weekends work on behalf of GM Welding. In the next half hour all staff except Ray Shaw had arrived back on site.
The Fire Brigade took charge and we were told to vacate site. By this time CV06 had fallen to the ground still burning fiercely. The fire had now spread to the scalping house."
"The normal procedure was to use running water to protect the underpan, but this was not cut and dried. There were places that could not be covered and so we would spray them with water. I would accept that the A side underpan was one such area.
UMA was aware of the practice of spraying the lining of the underpan with water instead of covering it and approved it."
When asked about the method statement he accepted there was no reference in it to covering combustible materials with metal sheeting or welding blankets and that it only provided for live water to be at hand at all times during the repairs. He said that overall he would have approved the arrangements as described in the risk assessment and the Permit to Work.
Mr Davies
"On Sat 2/2/08 and Sun 3/2/08 myself & Terry Clancy carried out repairs to Scalpens underpan. No hot work done on Sat. Started hot work on Sun morning 8 am - 8:30 am. Tack welding dead boxes into underpan. Both Alan and Terry doing this. Finished this approx 9:30 am. Measured up next pieces to be fitted. Left Scalpens House approx between 9;35-9:40 am.
Both in underpan.
No man outside. The burning gear in underpan hatch (did not use).
Cut rubber in underpan to fit dead boxes.
Standing on CV6 belt.
Fire hose in situ.
Did not wet down after completion.
Mats were not removed from Scalpens screen.
Went to breakfast approx 9:40 am."
Mr Clancy
"Arrived on site approx 5 to 7. Went into canteen got changed into work gear, went around to workshop/Scalpen House about 7.25. Measuring up and fabricating dead boxes in workshop. Went to tea about 9.45-9.50. . . "
Mr Smith
"Approx 7:30 am myself & Don & Ray left workshop to start work upstairs. I myself turned on fresh water pump,
Don went inside screen and underpan to clean pipework ready for weld repairs
Ray had one lifting lug to finish welding on A-side secondary.
I myself had to burn 20 bolt heads off of tube flanges. 12* drive side, 8 walkway side, I do this by placing a shovel under each bolt so as not to drop hot bolts inside underpan. I had done 16 this way and changed bolts, the last remaining 4 were on rosta bracket at walkway front, don't have use a shovel because of bracket shelf. 100% sure no hot bolt fell into the underpan, as I discarded every hot bolt onto mezzanine floor. I never left area for at least a approx 35-40 m after last bolt was removed, checked area turned off water, went to breakfast at 9:30 am."
(* Initially written as 8 and then changed to 12)
"9. I would estimate that we were at the primary screen ready to start work by about 7:30 am. Ray Shaw was working on the secondary screen which is adjacent to the primary screen. Ray was undertaking the final works to attach lifting eyes to the secondary screen.
10. I proceeded to remove the guards from the day side/drive side of the primary screen and instructed Don to clean up the central rail within the primary screen using an angle grinder and a wire brush, ready to be worked on later in the day.
11. I placed the flexible hose in the underpan and turned the same on, leaving a continuous flow of water down approximately half of one side of the underpan. At the bottom of the underpan there was a bed of wet sand. I then proceeded to cut the nuts off eight bolts that hold the metal tube within the screen in situ using an oxy-propane torch. I placed a shovel under each bolt to catch the hot slugs before dropping them onto the metal floor out of harms way. I would estimate that it took me no longer than four or five minutes to cut all eight bolts on the drive side. WATER RUNNING IN UNDERPAN AT ALL TIMES. MOVED AROUND TO EACH AREA OF HOT WORK.
12. I then proceeded to undertake exactly the same task on the aisle/walkway side of the primary screen.
13. The only difference is that on the last four bolts it was not necessary to catch the slugs with the shovel as they were above a metal shelf known as a rosta hanger and so there was no risk of them falling into the underpan. I would estimate that all of the cutting works were completed by no later than 8 am. The oxy-propane torch was switched off immediately after use. I am 100% certain that none of the hot slugs fell into the underpan.
14. After checking the work that Ray Shaw was undertaking on the secondary screen I then proceeded to remove the remains of the bolt (sic) from the primary screen. Essentially I placed my hand through the gap between the primary screen and the underpan and attempted to catch each shank so as to prevent the same falling into the underpan.
15. I then proceeded to replace all eight bolts on the day side/drive side and tightened them hand tight. This took no more than five minutes per flange to complete. I then returned to the walkway/aisle side and replaced four bolts. Unfortunately, I had not taken sufficient bolts from the workshop to complete the task and so left the cut bolts in situ above the rosta hanger.
16. As it was approaching 9 am Don and I decided to leave the area to go for breakfast at a local cafe. Ray Shaw had left the area 10-15 minutes earlier for the same purpose.
17. Don left the area first, leaving me to undertake a final fire check of the primary screen. I undertook a routine inspection of both sides of the screen, including looking inside the underpan. I was also smelling the air as, if there had been any ignition of the rubber lining of the underpan, it produces an obvious odour. I then removed the hose from the underpan, opened the valve fully and sprayed the underpan and Don Percival's area of work to ensure there were no hot spots in the same. I would estimate that it took me approximately two minutes to undertake this task. I then switched the water off and left the area at approximately 9 am."
"11. In accordance with standard practice, the entire area was wetted thoroughly using pumped water from a 50 mm hose located in the primary screen tower.
. . .
13. . . . Don Percival went inside the primary screen and used a 4½ inch angle grinder and wire brush to prepare the central rail within the primary screen for welding work later that day.
14. I removed 20 bolt heads from the tube flanges using an oxy-propane torch: 12 bolt heads on the drive side and 8 on the walkway side.
15. Before commencing at this task, I placed the flexible hose in the underpan and directed towards the area we were working on. The hose was wedged between the top of the underpan and the screen. I turned the water on, giving a continuous flow of water down the underpan, hitting a central divide and then spraying the complete underpan.
16. A bed of wet sand was laid at the bottom of the underpan to extinguish any hot sparks or platter (sic) that dropped to the bottom.
17. I then proceeded to cut the necks off the 12 bolts on the drive side of the screen using an oxy-propane torch. I placed a shovel under each bolt and each one was caught. None dropped into the underpan. The task was repeated for 8 bolts on the walkway side, save that 4 of these bolts were above a steel shelf and so no shovel was required. I accounted for all 20 bolts and none fell into the underpan.
18. Throughout this process Don Percival and I exercised extreme care and vigilance to ensure none of the sparks from the welding equipment ignited anything. We also directed the hose in the underpan awards the side on which the burning* work was being undertaken. (* this was changed by correction from "welding")
19. After the hot work had finished, the torch was switched off. The area was again hosed down thoroughly and check for any fire, smoke or burning smells and none was found. The hose was relocated in the underpan as before.
20. The hot work finished at approximately 8 am. For approximately the next hour or more, I was in primary screen area. At no time was it left unattended. There was no sign at all of fire, smoke or burning smells. Absolutely nothing was found to indicate that any fire had started. I am very experienced in my job. I believe that I would have smelled or detected any sign of fire or smouldering over this hour period. There was none.
21. At approximately 9 am Don Percival left the primary screen tower. I made a final fire check and then turned the hose to full and thoroughly doused the entire area in cold water for at least 2 full minutes.
22. At approximately 9:30 am Ray Shaw, Don Percival and I left site to go to breakfast. Mark Garnham remained in the our (sic) office on site. This was 1½ hours after the hot works had finished. There was absolutely no indication of any fire, smoke or burning smells on site."
Mr Garnham
Mr Gary Marshall
Mr Shaw
Mr Lynch
Miss Russell
Mr Heath
Mr Townsend
Where the fire started
"I ran round to the work shop and call (sic) Terry Clancy who was working on the under pan of the scalpen screen. After getting no reply I noticed No 6 belt had come down under the scalpen screen house. I grabbed two extinguishers and attempted to extinguish the fire on the belt but the pins would not come out of the extinguishers. By now the fire had taken hold of the belt and had spread up into the scalpen screen. I then retreated to the car park and waited for the Fire Brigade."
"5. I could see that the conveyor CV 06 between the main screen house and the scalpen house was on fire. The fire that I saw was at the top end of the conveyor only. I saw no evidence of fire or smoke at the bottom end of the conveyor or any fire or smoke near or coming from the scalpen house. I phoned Paul Burgess at approximately 10:05 am and informed him of the fire. By that time CV 06 was burning fiercely.
6. It was not long before CV 06 burnt through and dropped down to the scalpen house. I have marked the area where I believe the conveyor snapped on exhibit SF 2. The conveyor belt rolled down and collected that (sic) the bottom in the scalpen house."
(My emphasis)
"We agree that the fire did not significantly develop in the Scalping House until after the conveyor belt (CV6) had broken."
The contractual documents relating to fire precautions
"2.2 All sources of fuel within a (10 m radius) shall be removed where possible. Any, which cannot be removed, shall be adequately protected from heat and sparks.
2.3 Where it is not possible to remove sources of fuel, e.g. conveyor belt, wooden walkways, rubber decks or chute linings, etc, these should be protected by spreading non-flammable dust, fire blankets, covering with steel plates, etc, where possible the area should be damped down using water.
2.4 Where it is not possible to protect such items, extreme care and attention are required whilst carrying out hot work to prevent a fire occurring.
2.5 Pay particular attention to areas below the hot work where sparks, hot metal, etc can fall and create a fire later."
"2.2 All sources of fuel within a (10 m radius) shall be removed where possible. Any which cannot be removed shall be adequately protected from heat and sparks.
2.3 Where it is not possible to remove sources of fuel, eg conveyor belt, wooden walkways, rubber decks or chute linings, etc, these should be protected by spreading non-flammable dust, fire blankets, covering with steel plates, etc, where possible the area should be damped down using water.
2.4 Where it is not possible to protect such items, extreme care and attention are required whilst carrying out hot work to prevent a fire occurring.
2.5 Pay particular attention to areas below the hot work where sparks, hot metal, etc can fall and create a fire later."
Punctuation apart, these precautions are word for word the same as those set out in the note of the tool box talk on 16 January 2006. Section 5 of the document, headed "Carrying out the Work", contained the following additional provisions:
"5.3 A constant check of the area to be made for any signs of fire.
5.4 The working area shall be monitored after the hot work has been completed for signs of heating or fire. The period of time will vary according to circumstances and the degree of risk involved (30 minutes to 4 hours or longer).
5.5 In high-risk areas, such as around fuel tanks, rubber lined screens/shoots, buildings of a combustible nature, areas where they fuel is present, the area will need to be monitored until the area has cool and there are no signs of heat, i.e. services cool, no smell of combustion, etc. Pay particular attention to areas below the hot work where sparks, hot metal, etc can fall and create a fire later.
5.6 . . .
If in doubt, ask the Local Management for further advice"
These also reproduced, verbatim, similar provisions in the note of the tool box talk.
"Safe System of Work for rebuilding support frames, including heavy support tubes, centre rails, support flats and general fractured or worn parts on Primary, Secondary, Dewatering & scalping screens"
Under the heading "Other Safety Precautions":
"Dedicated person operating hose and for fire watching"
Under the heading "Work Procedure ":
"7. Any areas needing protection from fire, will be covered with welding blankets and sprayed with water, prior to any hot work.8. A dedicated person will remain on the hose for the duration of any hot work.
9. Steelwork will be cut into safe manageable pieces, using lifting gear to assist, as required
10. The old steelwork is then removed from the work area, so as not to create an abstraction in walkways etc.
11. The new steelwork is fabricated and prepared (unless this has already been done prior to the job)
12. The new steelwork is then installed, using lifting gear as required to enable the installation to be completed safely.
13. The steelwork is then rebolted or welded back in position, as appropriate.
14. When work is complete, there will be a thorough quenching with water, of all areas where hot work has taken place."
The Risk Assessment, method statement and Permit to Work
"whilst working and burning constant fire watch + live water at hand at all times during repair".
"fire watch and hoses to hand 2 people at all times (see risk ass)"
Apart from the reference back to the risk assessment, there was no reference to welding blankets.
- thoroughly damping down the area of work (principally the lining of the underpan) with water before the work, and
- having a bed of sand/ballast on the bottom of the underpan, and
- having one man on fire watch during the hot work, and
- having a high pressure hose in the relevant side of the underpan trained so as to provide a constant spray of water in the vicinity of the work whilst it was being carried out, and
- thoroughly hosing down the area of work with water after the work, and
- carrying out regular checks for fire for at least 30 minutes after the work in accordance with UMA's Hot Work Procedure and, if later, until the area had cooled and there were no signs of any remaining heat or smell of combustion.
The terms of SVB 9 - the Burning and Welding Warranty
"It is a condition precedent to liability that in respect of the use away from the Assured's own premises of an electric, oxy acetylene or similar welding or cutting equipment like blow lamps or blow torches, hot air guns or even hot air strippers and asphalt bitumen tar or pitch heaters, the following precautions will be complied at every occasion:1 Adequate and suitable portable fire extinguishers to British Standards 5423:1987 or its predecessors or successors in full working order will be kept at each area of work and used immediately if smoke or smoulder or flames are detected.
2 The area in the immediate vicinity of the work shall be cleared of all movable combustible material. The combustible materials which cannot be moved and (sic) must be covered and protected by over-lapping sheets or screens or non-combustible material.
3 A fire safety check of the working area to check for smoke, smouldering or flames (including spaces behind the walls and screens or partitions and above false ceilings) shall be made at regular intervals during work and between 30 and 60 minutes after completion of each period of work and immediate steps taken to extinguish any smouldering or flames when discovered.
. . ."
The internal investigation carried out by UMA
"Fuel
The ¼ turn open propane valve on the cutting torch is a potential source of fuel. The cutting was completed at 0900 hrs and the torch hung over the screen side. The bottle was not isolated until 09:25 hours (Verbal confirmation with P Smith) This would allow 25 minutes of gas to leak. Propane is a heavy gas that will gravitate to the bottom of the sump. The chutes will allow air flow which could supply the necessary mixture of oxygen to propane that will support combustion. The cutting torch might have been turned off on completion of works but the valve disturbed when the torch was hung over the screen side. This was discussed with the fire Station Officer reference noise (Explosion) I was advised that if the propane ignited in the open sump it would not cause an explosion as in a strictly vented container."
"Contractor completed the cutting of the final four nuts. The gas torch propane/oxygen was turned off and hung over the screen down side knocking the propane open. After checking the secondary screen works and washing the area down with fresh water he then turned the propane off and left the screen house. The mixture of propane and oxygen ignited due to the 110 volt splitter and created an immediate fire."
"Mr Percival entered the underpan of primary screen A at approximately 07:30 hours carrying two hand-held grinders, one fitted with a wire brush and the other with a grinding disc. He started to clean areas of the tubes in preparation for welding [PS2 paragraph 13]."
The reference quoted, PS2 paragraph 13, is to paragraph 13 of Mr Smith's witness statement in these proceedings which contains the passage that I have quoted above. It refers to the screen, and not to the underpan.
"Mr Smith sprayed some water into primary screen A underpan, being careful not to wet Mr Percival, who was still inside the underpan, and then he sprayed water into secondary screen B, where Mr Shaw had last been undertaking hot work."
"One person inside cleaning up welds with grinder.
- person inside fine
- hose was running over surface into underpan"
"Mr Percival then entered the underpan of primary screen A carrying two hand-held grinders, one fitted with a wire brush and the other with a grinding disc. He started to clean areas of the tubes in preparation for welding. Mr Smith started to remove 20 bolts, 12 on the drive side and 8 on the walkway side. I understand that he placed a shovel underneath each bolt and used an oxygen-propane cutting flame to remove the external portion of the bolts, catching the hot metal in the shovel. Mr Smith started on the driveside side of the primary screen, where he cut and replaced eight bolts. He then moved to the walkway side, where he cut and replaced four bolts. After removing the outer portions of the bolts he checked that the remaining lengths were cool before pushing them through to the underpan. Mr Smith then cut the outside sections from four further bolts but, since he did not have enough replacement bolts he did not remove the remaining lengths at that time. Mr Smith informed that he had a running water hose with which he played water over the rubber lining of the underpan in the area that he was cutting.
. . . Mr Smith sprayed some water into primary screen A, being careful not to wet Mr Percival, who was still inside the underpan, and then he sprayed water into a secondary screen A, where Mr Shaw had been last undertaking hot work. I understand that at approximately 09:15 hours Mr Percival completed the grinding work inside the underpan and then positioned a scaffolding board inside."
The work carried out by Mr Smith and Mr Percival on the morning of the fire, the associated fire risks and how the fire started
"The appellants, who are a public corporation, elected to call no witnesses, thus depriving the court of any positive evidence as to whether the condition of the fence and the adjacent terrain had been noticed by any particular servant of theirs or as to what he or any other of their servants either thought or did about it. This is a legitimate tactical move under our adversarial system of litigation. But a defendant who adopts it cannot complain if the court draws from the facts which have been disclosed all reasonable inferences as to what are the facts which the defendant has chosen to withhold."
"We have discussed this at great length with the Insured and believe the Insured have complied with Sections 1, 3 and 4. However, we do not believe that the Insured have complied with Section 2."
In the light of this, it is perhaps a little surprising that in their defence the insurers alleged, for the first time in unambiguous terms, that the Defendants were in breach of paragraphs 1 and 3 of the warranty (although the latter had been raised tentatively in a letter dated 10 October 2008), as well as paragraph 2. However, what is clear is that Mr Wookey was reasonably satisfied at the time that the Defendants had carried out a fire check (what he called Section 3), both during and after the hot work, in accordance with the warranty.
(1) A globule passes through the gap into the near side of the underpan and either lands on the base or hits the face of the divider at an angle and falls into the base. If such a globule was not extinguished as it passed through the water, then it would either end up on the sand and ballast at the base of the underpan or on the lining to the sloping part of the short sides. If the former, it would be harmless. If the latter, it might be capable of igniting the lining - but any such ignition would more likely be extinguished or prevented by the water. If, for some reason, it was out of the range of the water being played into the underpan during the hot cutting, it might cause the lining to smoulder but such a smouldering fire would be extinguished when the underpan was hosed down at the conclusion of the work or, alternatively, it should have been detected by sight or smell. I consider that the chances of a globule following this route into the underpan and causing an undetectable fire to be negligible. By "an undetectable fire" I mean one that could not be detected by reasonable checks of the area carried out during a 1 hour period following completion of the hot cutting work.(2) A globule does the same, but this time manages to cross the central divider and ends up in the far half of the underpan which is not being continuously sprayed with water. In this case, it might well cause a smouldering fire to the lining to one of the sloping short sides, but such a fire would either be detected in the subsequent check or extinguished when the underpan as a whole was hosed down after the work. Again, I consider that the chance of a globule following this route into the underpan and causing an undetectable fire to be negligible.
(3) A globule passes through the gap without being extinguished by the water and hits the lining on the face of the central divider at an angle that is close to normal to the plane of the lining so that it penetrates the skin of the lining and lodges within it at a point where the lining is not being continuously sprayed. This would be capable of causing a smouldering fire on the surface of, or possibly within, the lining, but I consider it a most unlikely that it would not be extinguished when the underpan was hosed down after the work. Although I regard this as a slightly stronger contender for the start of a fire, I consider that its likelihood of causing an undetectable fire is still fairly negligible.
(4) This scenario is the same as the previous one, except that this time the globule passes over the central divider and hits the lining on the far side at an angle that is close to normal to the plane of the lining so that, again, it penetrates the skin of the lining and lodges within it. My conclusions on this scenario are much the same as for the previous scenario.
(5) This is a variant of scenario (1), except that this time the globule travels over the side of the screen and falls into the near half of the underpan. My conclusion on the likelihood of this scenario causing a fire is exactly the same as my conclusion in relation to scenario (1).
(6) This is a variant of scenario (5), only this time the globule travels over the side of the screen and falls into the far half of the underpan (where no water is being sprayed). My conclusion on the likelihood of this scenario causing a fire is exactly the same as my conclusion in relation to scenario (2).
(7) A globule passes through the gap and lands on the very narrow band of mastic just below the top of the side of the underpan (at the base of the metal strip welded to the top of the long side). The kinetic energy of the globule causes it to burn through the mastic and into the body of the lining below (because it is passing through a cross-section of the lining, it would not have to pass through any skin on the lining). There it is able to start a smouldering fire. Such a fire smouldering below the surface of the lining might not be extinguished when the underpan is hosed down because the line of the jet of the water would be roughly parallel to the line of the mastic, so that water might not readily penetrate downwards into the interior of the lining. Another possibility might be that some of the mastic melts into the hole and seals it sufficiently to prevent the necessary amount of water getting in - although there would have to be sufficient oxygen present to sustain combustion for the necessary length of time. This scenario seems to me to be the most likely one - in terms of its potential for causing a fire - that I can envisage. The chances of a globule having exactly the right trajectory to bring this about must be very, very small indeed. Nevertheless, I find that that is how this fire was probably caused.
(8) This is the same as scenario (7), except that the globule, by one means or another, lands on the corresponding narrow band of mastic on the far side of the underpan. In this case if the globule went over the top of the screen it would fall onto the mastic band on the far side of the underpan under gravity. If, on the other hand, it went through the gap and over the central divider it would strike the steel strip and then fall onto the horizontal band of mastic. Either way it would have very much less kinetic energy then the globule in scenario (7) and so would be unlikely to penetrate far into the lining. In these circumstances, I regard the chances of this causing an undetectable fire as being close to negligible.
"3.22 We agree that a competent fire watch would have noticed a flaming fire in the underpan and, on that basis, we consider that there was no flaming fire within the primary A underpan whilst the fire watch was present. Therefore, have a fire to have been related to the hot work then it must have started as a smouldering fire.3.23 We agree that the tests revealed that the mastic-type sealant between the sheets of rubber lining had a propensity to smoulder and produced very little outward sign of the smoulder in relation to smoke or odour.
3.24 We agree that it is possible that the smoulder continued to develop underneath the surface of the combustible material such that it could not have been reached by the quenching water. Alternatively, the area in which smouldering might have occurred was not quenched. The smoulder could then have progressed in longer than the fire watch and subsequently undergone transition to flaming.
3.26 We agree that this could explain why a fire initiated by hot work at the underpan might not have been extinguished or discovered by the steps taken following the hot work."
Were the Defendants in breach of their duty to take reasonable care?
The claim against the insurers
Conclusions
(1) The fire started in the A side primary screen underpan in the screening house. It then spread to the scalping house when the CV6 conveyor belt broke.(2) The fire was caused by a globule of molten steel from Mr Smith's oxy-propane cutting which penetrated the band of mastic above the lining which was just below the steel strip that had been welded to the top of the side of the underpan. This was not the result of any carelessness by Mr Smith: it was part of the spatter that is normally produced by cutting operations of this type however carefully carried out.
(3) The hot globule went through the mastic band and penetrated some way into the interior of the lining. There it started a smouldering fire.
(4) Neither the water being sprayed into the underpan whilst the hot cutting work was taking place nor the water used when the underpan was being hosed down by Mr Smith on completion of the work, as I find it was, penetrated into the lining sufficiently so as to quench the smouldering fire.
(5) The hosing down of the lining of the underpan by Mr Smith was carried out with reasonable care, as he had done it on many previous occasions.
(6) Mr Smith and Mr Percival remained in the area of the underpan for at least 1 hour after the hot cutting had finished, and one of them probably for about 1¼ hours, in order to check for any signs of a fire (which they did).
(7) By the time that Mr Smith and Mr Percival left the area of the underpan, which was probably shortly before 9:30 am, there was no visible fire in the underpan and there was no reasonably detectable smell of burning.
(8) It was not reasonably foreseeable that a fire might smoulder undetected within the lining of the underpan for a period in excess 1¼ hours. By remaining in the area and checking for any signs of fire for at least 1 hour after the completion of the hot cutting, Mr Smith complied with UMA's Hot Work Procedures and other generally recognised standards. He therefore acted with reasonable care.