QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
CLEVELAND BRIDGE UK LIMITED |
Claimant |
|
- and - |
||
SEVERFIELD – ROWEN STRUCTURES LIMITED (formerly SEVERFIELD-REEVE STRUCTURES LIMITED) |
Defendant |
____________________
Alexander Hickey and George Woods (instructed by DAC Beachcroft LLP) for the Defendant
Hearing dates: 8-11, 15-18, 22-25 October, 1 November 2012
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Shard and its Construction
The Witnesses
A. CBUK
(i) Andrew Hall: he was at the relevant time the Operations Manager, well-educated and a chartered civil engineer. He was in charge of overseeing this project. There was a certain amount of opinion evidence in his written statement. I felt that he was fairly straight talking but that he was particularly unconvincing in his explanations about delays to CBUK and about the lack of complaint by CBUK about factors which were said to have delayed CBUK in its performance (for instance information and free issue material said to have been delivered late).
(ii) Ben Robinson: although he no longer works for CBUK, he was the project manager for the Shard steel fabrication contract with SRS. He came over in correspondence as straightforward and as one who was just trying to get on with the job as best he could. When giving oral evidence, his memory was not very good (which was not surprising given the lapse of time and his job move) and he was somewhat faltering.
(iii) Brian Rogan: he was the managing director of CBUK at the time of this project but unfortunately for much of the time he was having to deal with cancer and the accompanying treatment; for considerable periods he simply was not directly involved although he was generally kept informed from time to time. He could therefore give little relevant first-hand evidence. Although he was a decent, straight talking down-to-earth man with a sense of humour, most of his evidence was second-hand, involving retrospective reconstruction of what may or may not have been happening or was opinion evidence to which I can attach little weight. In so far as he commented on correspondence or other documentation, the Court can draw appropriate inferences as well as he could.
(iv) Don Underwood: he was the company commercial manager of CBUK who gave his evidence, so far as it went, reasonably satisfactorily. He was unconvincing in some respects particularly in connection with the claims for loss of fabrication and production and acceleration.
B. SRS
(i) David McBride: he was the Coatings Manager for SRS, in effect in charge of the paint shop at Thirsk. I was particularly impressed with him as being down-to-earth, sensible, experienced and patently honest.
(ii) Thomas Haughey: he was the Chief Executive Officer of SRS' holding company and a director of SRS who gave some evidence about his relatively limited and high-level involvement in various aspects of the history between these two parties. He gave his evidence confidently and was convincing about what he did know but he did not know much about the detail.
(iii) Douglas Willis: although I felt that he gave his evidence in a reasonably honest way, he sometimes in a rather laconic way would not initially answer the questions albeit would after some equivocation answer the questions directly and honestly. He was particularly vague and general about events after April 2010. I found him unconvincing in relation to the post April 2010 events, although that may have been down to a lack of detailed knowledge and analysis of such events.
(iv) Gerry Rennison: he was the site manager of Steelcraft, SRS' wholly owned steel erection company which carried out the steel erection on the Shard. I felt that he was essentially a decent person, albeit a little vague in some of his answers (albeit that was down to a lack of knowledge I suspect rather than anything else) but his evidence about what he actually knew was reasonably convincing.
(v) Martin Pyle: he was also employed by Steelcraft and was involved with "wrapping up" operations, which describes the follow-on operations after the principal steel erectors have fixed the steel pieces into position, such operations involving final adjustments or remedial work to the steelwork and its connections. I thought that he was a very good witness and indeed I wrote down "salt of the earth"; he was highly experienced, straightforward, decent and unruffled despite a stringent albeit polite cross-examination.
(vi) Charles Bogg: he was the quantity surveying director of SRS and, although he had limited knowledge of much of what was in issue, he was reasonably straightforward. What I found completely unconvincing, although it was not his direct fault, was his unbelievable evidence that there was no documentary record of the settlement made between Mace and SRS in about April 2012. It was not credible because a settlement which apparently addresses a multi-million pound final account must have been evidenced in writing even if it was only by way of e-mail or handwritten notes. This was a highly relevant area of dispute between the parties because it went at least in part to whether there had been a settlement between Mace and SRS which encompassed SRS paying or allowing a very substantial sum for tower crane use which is sought to be passed on by SRS to CBUK. It was not his direct fault because he was not involved in the settlement but he was the witness in effect put up to deal with the settlement and I would have expected him to have found out a lot more about it.
The History
"CBUK confirmed that the current model includes for the slab edge detail that is detailed on WSP latest drawings, with the inverted tee, decking, double edge trim etc, but have made no allowance for the halfen ski assembly or for any temporary edge protection sockets.
SRS advise that it was their intention to incorporate all of the above into one composite member if at all possible. CBUK are to advise SRS of a 'last ditch drop dead' date for receipt of information to have the model updated to include these prior to fabrication."
The minutes record no discussion, let alone agreement, on a programme although there was some discussion about what was to happen over the next few days. There was however listed nine items of information required by CBUK. There was no discussion of any relevance about terms and conditions for any sub-contract although it was noted that payment was to be monthly.
"Hopefully it accurately reflects our discussions, however, please advise if there is anything we have missed or wrongly interpreted."
The e-mail does not suggest that it was agreed, let alone agreed in any way which was to be considered as binding or ultimately binding. There was no response to the e-mail.
"We have now received a formal complaint from our clients with regard to the quality of fabrication being produced.
We have in the last week had one column returned 15 mm out of square, a column rejected at site with the bearing area underground and two loads rejected yesterday for unacceptable welding.
It is difficult to argue that these occurrences are isolated and do not demonstrate a failing of our quality system as all items are allegedly inspected 100%, the requirements are clearly shown on the dimensional reports and the required weld finish on the drawings.
Please provide an explanation on how and why these failing[s] occurred and what measures have been put in place to prevent a re-occurrence…"
"The attached is totally unacceptable!
In general, our quality standards are dropping and it is concerning. We have well bedded systems in place that had been successful for years, so we have no excuses…
It is your responsibility to ensure we deliver a quality product, of which Cleveland Bridge has built its reputation on, so do not let us down and put the business at risk…"
At least some of the responses accepted that there were problems (for instance "contamination in tapped holes"). One response suggested that there was very little inspection on the nightshift work and that there had not been a corresponding increase in inspection personnel notwithstanding substantially increased recruitment. The problems had not been sorted out because, for instance, on 7 December 2009 internal e-mails within CBUK were reporting out of tolerance work.
"As you are aware the Works forward load has indicated an extraordinary overload since October 2009.
We have expressed concern over this, in particular the Shard programme and have requested that we sublet some of that work to reduce the load, of which to date we have not [been] able to achieve.
We understand that we have managed to have some movement in other programmes that has assisted, but the Shard programme has actually increased (due to changing priorities, late issue of drawings and generally not meeting the specified tonnage).
We have been trying to recruit, with little success and have been working excessive overtime.
The RRP suggests that we employ a further 135 men, but this is a period of 2 months of which, you can appreciate, is impossible/impractical.
I am looking at introducing 12 hour shifts, throughout the works, but this is at great expense and we will need to negotiate with the union.
Our best option is to move the Shard programme out, but I am unsure what our contractual arrangements are.
I suggest we review all of the programmes, as there has been further favourable movement on M74 and A46…"
"…I am concerned that we will have priorities 8, 9, 10 complete by 25th January with deliveries commencing w/c 18th starting with priority 8.
As discussed yesterday we are struggling to meet the overall programme, due to a number of factors. We have explored all the options in house to increase resources, coupled with working extensive overtime and we are still struggling to meet the programme. As you are aware we worked through the xmas break to pull things around but this was not as productive as we had hoped. The weather has played a significant part and we have lost a lot of labour over the past couple of weeks due to non-attendance.
We were expecting the site programme to drift out slightly due to the recent bad weather that will no doubt have hindered the core build. As this is not the case, we have to resolve the current programme position.
We had a meeting with our production team yesterday afternoon and the conclusion was that we need to sub-let or (return to yourselves) Phase 601 (approx 400Te). In the short term that would allow us to concentrate on the fabrication of 602/603. Depending on progress, we would then review Phases 801, 802, 803.
At present, if we continue at the current rate of progress then we would not complete the fabrication of 803 until the end of March. When we were fabricating the heavy box section columns we were achieving 200-250 Te or week comfortably, however, now we are fabricating a high number of beams were content per tonne has increased. The edge detail is far more labour-intensive than originally envisaged which is slowing productivity. We are currently only achieving 150-175 Te per week with no mechanism to increase this further without subletting.
We have approached Allerton who are keen to take some work should this be an option to go down.
…Please digest the above and I'll give you a ring this afternoon to discuss what the options are."
"Should this be allowed to continue we run the risk of being in a failing position at the front end of the job, with all the programme and cost implications that we are both fully aware of."
"You will also need to fully demonstrate any programme implications relating to this matter rather than simply states that three weeks have been added to the programme???"
No such demonstration was provided.
"…and you are still erecting levels 4 and 5 and no metal deck has been erected at the level 5. We need to work together can I suggest you urgently (say Monday) send us your detailed site erection programme and we can work together to meet your requirements.
I can guarantee you that we are pulling out all the stops to produce the steel as quickly as possible actions taken are as follows…
The other big problem is SRS delivery of the folded plate for the edge detail. We are still receiving items for levels 6 and 7. We are [being] told minimum turn around from issuing detail is 2 weeks, this cannot be right, we have a shop full of beams waiting for folded plate to complete the. Could you please push your end.
Can you please send the site erection programme on Monday."
Priority | Phase | December Programme Delivery | Actual deliveries |
8 | 501 | 7 Jan 2010 | 15 Dec 2009 - 3 Feb 2010 |
9 | 502, 503 | 12 Jan 2010 | 4 - 8 Feb 2010 |
11 | 601 | 26 Jan 2010 | 15 - 24 Feb 2010 |
12 | 602, 603 | 5 Feb 2010 | 26 Feb - 11 March 2010 |
13 | 801 | 12 Feb 2010 | 5 - 29 March 2010 |
14 | 802 | 16 Feb 2010 | 24-31 March 2010 |
15 | 803 | 22 Feb 2010 | 30 March to 1 April 2010 |
Thus, delivery of Phase 803 steel was 38 days later than the December programme allowed for.
Phase | SRS' programmed erection- 2010 | Actual erection-2010 |
501 | 8-10 Feb | 8 – 17 Feb |
502 | 8-10 Feb | 11 - 17 Feb |
503 | 11-16 Feb | 16-23 Feb |
601 | 15 Feb – 2 March | 26 Feb – 21 Apr |
602 | 15 Feb- 2 March | 8 - 16 March |
603 | 23 Feb-5 March | 16-25 March |
801 | 3 – 16 March | 30 March – 30 Apr |
802 | 3 – 15 March | 6 Apr – 7 May |
803 | 19 – 30 March | 30 Apr to 13 May |
On 14 May 2010, erection of Phase 103 (Levels 10 and 11) commenced, it having been programmed to commence on 19 March 2010. Thus commencement of Phase 103 was 56 days later than programmed.
"(3) Our recovery was very much on track by the middle of June (as noted in my previous letter regarding crane times - we stated in the meeting of 22-06-10 that we were within 48 hours of the recovery programme) and one of the major factors contributing to the late handover of floors since this juncture is the large amount of crane downtime or disruption due to the operations involved in the timing of the cranes.
(4) Over a 12 week period we have recorded a 30% loss of total daytime craneage.
(5) We have continued to receive variations instructed by Mace, resulting in some instances of site works/disruption."
"Addition of day/night shift erections squads to mitigate the nine week delay…. £1,053.838.14
Addition of snaggers/wrap up squads to correct defects…as scheduled NCR's enclosed…£473,975.20
Additional site resources to manage the day/night shift and snagging works… £353,607.95
Senior Management deployed on-site… £111,333
Delay and disruption to metal decking installation… £500,000
Mace tower crane costs and site management costs the nightshift working as Mace valuation to end October 2010… £626,925.50
Delays to follow on trades and other third-party costs…TBA
SRS fabrication and paint shop costs rectifying fabrication/painting errors before delivery to site… £99,800"
The Sub-Contract
"Scope of Works:-
- All things necessary for the fabrication of all tower steelwork between the ground and ninth floor levels, including all connection details the temporary works and other trades…
- All 'black' steelwork necessary for the above works is deemed to have been procured under the terms of your previous agreement with Mace Ltd and is held at your works…
- Delivery of all fabricated steelwork to our works to suit a pre-agreed programme and sequence-details to follow…
Exclusions:-
- Procurement of any further 'black' steelwork (any additional requirements which may arise will be provided free issue by ourselves)…
Price:-
A final account value is to be determined partly by re-measurement and partly by the inclusion of lump-sum values, comprising the following six items:-
1) Fully fabricate and deliver approximately 3826 tonnes of structural steelwork up to level 9, including forming all service penetrations (remeasured at £617.00 per tonne nett)
2) Design and detailing to completion up to level 9 (£85,000.00 lump sum nett)
3) Blast and prime steelwork (remeasured at £6.00 per m2 nett)…
Programme:-
Programme details to follow…
Materials:-
…Any further main bar or plate materials required to levels 0-9 required by CBUK will be requisitioned through SRS. All fittings material required by CBUK…will be supplied by SRS. Listing of any CBUK materials requirements to be issued in good time without detriment to the programme dates.
Specifications and documents:-
…Structural Specification-Section G…
Movement and Tolerance Specification…"
"(1) Save where the provisions of the Sub-Contract otherwise requires, the Sub-Contractor shall carry out, complete and maintain the Sub-Contract Works such that no act or omission of his in relation thereto shall constitute, cause or contribute to any breach by the Contractor of any of his obligations under the Main Contract.
(2) The Sub-Contractor shall carry out, perform and provide the Sub-Contract Works fit for purpose described in the Main Contract. Materials, goods and workmanship shall be the specified quality and to the satisfaction of the Contractor…
(4) The Sub-Contractor shall commence, carry out and complete the Sub-Contract Works in accordance with the Contractor's requirements in accordance with the Programme forming part of the Main Contract. Notwithstanding the foregoing, the Sub-Contract Works shall be performed at any time and/or in any sequence and with any degree of continuity of working as may be required from time to time by the Contractor and generally to suit the progress of the Works.
(5) The Sub-Contract works are to be completed within the period specified in the Programme subject to such fair and reasonable extensions of time as the Contractor shall allow where the Sub-contract works are delayed by causes which resulted in an extension of time under the Main Contract."
Responsibility for Delay in Fabrication and Delivery of CBUK Steel
CBUK's Money Claim
Item | CBUK | SRS |
1. Welding and fabrication | £245,537.95 | £80,679.56 |
2. Drafting | £82,132.31 | £12,636 |
3. Premium rate 20% of hours | £13,607.00 | Nil |
4. Project management | £9,292.32 | Nil |
5. Quantity surveyor | £2,599.20 | Nil |
6. Unloading/storage of free issue materials | £1,075.00 | £1,062.50 |
7. Uplifting steel for delivery | £1,075.00 | £1062.50 |
8. Rounding | £0.31 | Nil |
Sub-total | £355,319.09 | £95,440.56 |
9. Deduct measured work | £26,531.00 | £26,222.50 |
Total | £328,788.09 | £69,218.06 |
It is unnecessary to consider Items 3 and 8 which are not supported by Mr Davis.
Item | Sum allowed |
1. Welding and fabrication | £80,679.56 |
2. Drafting | £71,574.56 |
3. Premium rate 20% of hours | Nil |
4. Project management | Nil |
5. Quantity surveyor | Nil |
6. Unloading/storage of free issue materials | £1,073.25 |
7. Uplifting steel for delivery | £1,073.25 |
8. Rounding | Nil |
Sub-total | £154,400.62 |
9. Deduct measured work | £26,489.05 |
Total | £127,911.57 |
Measured work: £2,545,393.38
Other variations: £42,483.23
Edge Beam variation; £127,911.57
Gross sum due: £2,715,788.18
Less paid: £1,787,315.63
Net sum due: £928,472.55
The Counterclaim
Heads of claim | Sum Claimed |
Delay (prolongation costs 22.2.10 to 30.4.10) | £141,366.35 |
Disruption (8.2.10 to 13.5.10) | £122,547.33* |
Disruption to metal decking operation | £73,529.63 |
Acceleration: Day/night shift squads Management for such resources Senior management at site |
£1,682,011.76* £441,559.27* £252,417.41 |
Mace Tower Crane cost | £812,917.00 |
* higher than originally pleaded
Several claims for haulage, fabrication shop acceleration and third party claims are no longer pursued.
Phase | Crane | Weather | Climbing | Other | Misc | Total days |
1 | TC2 | 18.43 | 27.70 | 5.80 | 1.30 | 53.23 |
2 | TC4 | 14.58 | 20.08 | 4.45 | 2.60 | 41.70 |
3 | TC5 | 14.43 | 13.58 | 20.22 | 7.63 | 55.85 |
TC3 | 11.83 | 35.98 | 19.65 | 5.20 | 72.65 | |
Total | 59.25 | 27.33 | 50.12 | 16.73 | 223.42 |
He attached an Appendix 11 which provided a more detailed breakdown of the days on which the events happened. An example of the "other" category is claimed to be cranes being deployed to allow another contractor to use it. An example of "miscellaneous" would be a crane being taken out of service due to a need to inspect its base or grillage. "Climbing" relates to the operation, as the construction moves upwards, whereby the tower crane is moved or "climbs" upwards also. The "weather" downtime is self-explanatory albeit that the downtime is usually associated with excessive wind such that it is not safe to operate the crane; this is sometimes referred to as "winding".
"Where the sufferer from a breach of contact finds himself in consequence of that breach placed in the position of embarrassment the measures which he may be driven to adopt in order to extricate himself ought not be weighed in nice scales at the instance of the party whose breach of contract has occasioned the difficulty. It is often easy after an emergency has passed to criticise the steps which have been taken to meet it, but such criticism does not come well from those who themselves created the emergency. The law is satisfied if the party placed in a difficult situation by reason of the breach of a duty owed to him has acted reasonably in the adoption of remedial measures, and he will not be held disentitled to recover the costs of such measures merely because the party in breach can suggest that other measures less burdensome to him might have been taken."
(a) One needs to take account of the fact that the recovery programme was adopted to overcome not only the 42 days delay caused by CBUK's breaches but also the further 14 days delay which is not attributable to those breaches. Both parties' experts and indeed Counsel accepted that the appropriate way to proceed in this context was to determine the overall figure attributable to acceleration and then discount it, in the context of these findings, by 25%.
(b) There must have come a time between April and December 2010 when the acceleration measures (extended, night-time and weekend working), which continued throughout this period, were not in fact being deployed to overcome the 42 days delay caused by CBUK's breaches but were being deployed to prevent the delay becoming worse for other reasons not attributable to CBUK. There has been no direct evidence as such which identifies precisely when this "tipping point" was actually reached. However, in principle the costs of the acceleration after this point can not be said to be attributable to CBUK's breaches; rather, they were attributable to whatever other factors, such as crane downtime or Mace instructed variations, were actually operating to prevent the programme being recovered and in fact producing further delays.
Delay (prolongation costs 22.2.10 to 30.4.10)
(a) Steelcraft: £102,898.66
(b) SMD: £16,000
(c) Steelcraft supervision: £63,981.55
(d) Steelcraft overheads: £19,915.65
(e) Steelcraft profit: £10,917.95
Mr Gurnham has approached the quantum on this in a somewhat different manner, illustrated by a table in his main report:
Item | 22 Feb -1 Apr (38 days delay) | 1-19 Apr (4 days delay) | 19-30 Apr 10.5 days delay) |
Steelcraft prolongation costs | £67,237.40 | £8,053.29 | £20,695.63 |
Addition for weekly paid supervision for pension, life assurance and holiday & sick pay | £5,599.48 | £701.02 | £1,766.75 |
Steelcraft overhead supervision | £26,934.16 | £2,863.65 | £7,514.97 |
TOTAL | £99,771.04 | £11,617.96 | £29,977.35 |
He has not accepted that there should be anything for SMD or for Steelcraft profit under this head. CBUK's Counsel initially took a pleading point about Mr Gurnham's second and third heads but it seems to me that all that he has done largely has been to recast the pleaded supervision and overhead claims which are pleaded; in any event, this was regularised by permission to amend being granted on 1 November 2012 to enable SRS to bring its claim in line with what Mr Gurnham was promulgating. He and indeed Mr Davis inspected and analysed the Steelcraft books and indeed there was a large measure of agreement as to what those costs were. What Mr Gurnham discovered and this has not been effectively challenged is that Steelcraft kept records in such a way that basic labour and on site control costs were within records which covered the prolongation costs but the senior supervision, which was not necessarily wholly resident on site all the time were kept in a record which was so to speak labelled "overhead".
Disruption
ITEM | SUM |
Additional labour - additional shifts 515.43 (1145.43 -630) @ £217.84 | £112,371.55 |
Addition of 21.63% | £24,305.97 |
Addition for plant@ 5% of labour costs | £5,618.58 |
TOTAL | £142,296.10 |
From this he has deducted £19,748.77 as relating to factors which he would not attribute to CBUK. This leaves a balance for disruption of £122,547.33.
Holiday pay and sickness: 14.847%
Group life assurance: 0.222%
Travel cost: 3.00%
Total: 17.71%
SMD Disruption
SRS Acceleration
Item | Amount allowed [claimed] |
Day/night shift squads | £1,682,001.76 [£1,700,142.98] |
Management for resources | £441,559.27 [£406,937.72] |
Senior management on site | £252,417.41 [£419,549.70] |
NCR Management | Nil [£135,151.98] |
Total | £2,375,988.44 [£2,661,782.38] |
Mr Gurnham allocates £233,451.57 to the period up to 13 May 2010 and the completion of Level 9 and the balance, £2,142,526.87, to the period thereafter up to Christmas 2010 when Level 40 was completed. He excludes the NCR costs which he evaluates in fact at £193,249.96 on the basis that it is not to do with acceleration.
Item | Amount |
MCS day/night/weekend shifts | £1,182,688.68 |
K-Len dayshift | £279,921.55 |
Steelcraft overheads at 9% | £131,634.92 |
Steelcraft profit at 6% | £87,756.61 |
Total | £1,682,001.76 |
These figures are predicated upon the recovery essentially of all the main tower steel erection cost of acceleration measures provided by MCS and K-Len up to the completion of steel work at Level 40.
(a) MCS and K-Len were primarily deployed by Steelcraft with SRS' consent and knowledge to seek to overcome the delays to the steelwork erection which had started to be generated by the end of February 2010. By the time that the recovery programme was put in place in May 2010, that delay was 56 days or 8 weeks of which 6 weeks was attributable to the breaches of CBUK.
(b) As from May 2010, these resources were deployed and were initially effective; indeed in June 2010 some time had been recovered. However, by September 2010 other factors had probably combined to cause further delay and as from the end of August 2010 these other factors represented the dominant reason or cause for the need to continue to retain these additional accelerative resources. Therefore as from then it cannot be said that there is any or certainly any sufficient causative link between CBUK's breaches and the need to continue to deploy the accelerative resources.
(c) Mr Davis' approach based by reference to the recovery programme is a reasonable and realistic one, albeit that his exclusion of nightshift and his rates are unrealistic. It seems to me that, although the recovery programme only extended day shifts and Saturday working, SRS was always intending to and needed to deploy what it actually deployed which was full nightshifts and full weekend working as well to seek to recover the time which had been lost.
(d) Therefore the proper amount to allow to SRS and what it was liable to pay its sub-contractors is reflected in the following table:
Shift type | Month | Shift Nos | Rate | Sum |
Add day shift | ||||
May | 30 | £279.20 | £8,376.00 | |
June | 242 | £279.20 | £67,566.40 | |
July | 291 | £279.20 | £81,247.20 | |
August | 239 | £279.20 | £66,728.80 | |
W/e work | ||||
May | 0 | £356.07 | Nil | |
June | 35 | £356.07 | £12,462.45 | |
July | 15 | £356.07 | £5,341.05 | |
August | 42 | £356.07 | £14,954.94 | |
Night | ||||
May | 189 | £356.07 | £67,297.23 | |
June | 290 | £356.07 | £103,260.30 | |
July | 211 | £356.07 | £75,130.77 | |
August | 291 | £356.07 | £103,616.37 | |
TOTAL | £605,981.47 | |||
Less 25% | £151,495.38 | |||
Sum allowable | £454,486.13 |
Item | Amount |
Steelcraft supervisors/engineers dayshift | £155,852.53 |
Steelcraft supervisors/engineers nightshift | £52,979.35 |
Arthur Hudson Site Engineers Ltd | £51,435.10 |
Byrnes Construction Services Ltd | £46,580.00 |
Cotech Engineering Ltd | £54,269.00 |
Williamson Technical Services Ltd | £22,848.60 |
Sub-total | £383,964.58 |
Steelcraft overheads at 9% | £34,556.81 |
Steelcraft profit at 6% | £23,037.87 |
TOTAL | £441,559.27 |
Mr Gurnham has adjusted the first two items upwards and the overheads and profit has been adjusted down and up respectively, compared with the pleaded case. As I understood Counsel for CBUK, no pleading point is taken with regard to these adjustments.
Item | Amount |
Mr Ashton | £142,883.01 |
Mr Rennison | £76,610.39 |
Total | £219,493.40 |
Steelcraft overheads at 9% | £19,754.41 |
Steelcraft profit at 6% | £13,169.60 |
Total | £252,417.41 |
Mace Tower Crane Cost
(a) I disallow any usage of TC1 and TC6 over this period as the expert evidence reveals that it was essentially only TC2, TC3 TC4 and TC5 which were necessarily involved in the steel erection (see Paragraph 56 of Mr Barry's report). This equates to 388 hours of crane time and to a money sum of £23,280.
(b) In addition, I reduce the total crane hours for the weeks commencing 12, 19 and 26 August 2010 to a total of 228 hours, which allowing for the reductions made in the preceding sub-paragraph takes out an additional 48 hours at £63 per hour, nearly £3,024. The 228 hours allowance comes from the preceding two weeks and is not inconsistent with some of the other total hours in some of the preceding weeks.
(c) I exclude the hoist driver's costs because I can not see (and there is no evidence) why the hoist driver is required in circumstances where such evidence as there is suggests that the hoist was being used to enable materials other than steel to be lifted to higher parts of the building. This would remove four weeks worth of his time valued at £1,350 per week, that producing a deduction of £5,400.
(d) It is appropriate however to make a further more general reduction to reflect the absence of specific evidence as to what these cranes were actually doing and, for instance, whether opportunities were being taken to do work which was not in reality part of the accelerative effort. It is necessary, in the absence of such detailed evidence, to make a reduction which the Court can be confident adequately takes this into account. In my judgement, an adequate and safe further reduction is 50% of the balance.
(e) I therefore assess the amount attributable to CBUK as:
Cost for period: £286,884.50
Less (a): £23,280.00
(b): £3,024.00
(c) £5,400.00
Sub-total: £255,180.50
Less 50% £127,590.25
Total: £127,590.25
Defects and the NCRs
Item | Sum allowed |
Material sent to SRS in error/sent back to CBUK: 3 loads @ £258.20 (40 ft) | £774.60 |
Beams painted incorrectly: 904.5 hours @£17.10 + 20% for paint and plant | £18,560.34 |
Transfer beam returned for shot blast and paint:1 load @ £358.40 (60 ft) | £358.40 |
Corner columns with protruding welds on Wintergarden box beams: 100 hours @ £17.10 + 20% for materials and plant | £2,052.00 |
Make good external decorative columns delivered in a poor state: 494 hours @ £17.10 + 20% for paint and plant | £10,136.88 |
Total | £31,882.22 |
His "secondary valuation" contains an allowance on the second, fourth and fifth items above of a substantial mark-up for overheads and profit.
NCR 1: this has not been proved. The file does not really describe the defects in anything other than the most general detail. There was clearly confusion in categorising this defect and for some undisclosed reason it was "moved to NCR 001" after the event (see Daily Record Sheet).
NCR 48: this has been proved. The file identifies that no tolerance was allowed in the shear key connection which resulted in misaligned holes. There are photographs which illustrate this and a contemporaneous e-mail on 13 May 2010 which supports "this generic problem". The remedial work is consistent with what Mr Pyle has attested to.
NCR 61: this has not been proved. The defect description in the file does not match what Mr Pyle describes.
NCR 106: this has been proved. The file description is consistent with what Mr Pyle describes and the remedial works are consistent with the defects. There are helpful photographs and contemporaneous e-mails.
NCR 107: this has been proved on a similar basis to NCR 106.
NCR 167: this has been proved on a similar basis to NCR 106, albeit that there are no photographs or contemporaneous documents in the file.
NCR 168: this has been proved on a similar basis to NCR 167.
NCR 3a: this has been proved. Sufficient contemporaneous information has been provided in the file which identifies fabrication errors which prevented the placing of the incoming beam. The comments on the drawings indicate that the gap at the top of the cheek plates was less than the width of the incoming beam. In those circumstances there must have been a breach of the fabrication tolerance requirements in all probability.
NCR 26: this is proved. The file indicates that the gap between the plates was narrower than the beam width which strongly suggests that it must have been defectively welded in fabrication; that narrowness is inconsistent with anything other than welding the plates well out of tolerance. The documentation demonstrates a lack of perpendicularity within the fabrication which demonstrates shoddy workmanship.
NCR 30: this is not proved. All that the file shows is that the web cheek plates prevented the erection of beams. That does not, without more, prove that the fabrication was probably defective.
NCR 33: this is not proved for the same reasons as set out against NCR 30.
NCR 46: this is proved in relation to the cheek plates referred to on page 122 in Bundle N1 for the reasons given for NCR 26 but it is not proved for the remainder of the cheek plates for the reasons given for NCR 30.
NCR 53: this is proved in relation to the cheek plates referred to on pages 152 and 153 in Bundle N1 for the reasons given for NCR 26 but it is not proved for the remainder of the cheek plates for the reasons given for NCR 30.
NCR 124: this is not proved for the same reasons as set out against NCR 30.
NCR 127: this is proved in relation to the cheek plates referred to on pages 309, 310 and 311 in Bundle N1 for the reasons given for NCR 26 but it is not proved for the remainder of the cheek plates for the reasons given for NCR 30.
NCR 137: this is proved in relation to the cheek plates referred to on pages 331 and 332 in Bundle N1 for the reasons given for NCR 26 but it is not proved for the remainder of the cheek plates for the reasons given for NCR 30.
NCR 151: this is proved in relation to the cheek plates referred to on pages 384 in Bundle N2 for the reasons given for NCR 26 but it is not proved for the remainder of the cheek plates for the reasons given for NCR 30.
NCR 165: this is proved in relation to the cheek plates referred to on pages 405 and 406 in Bundle N1 for the reasons given for NCR 26 but it is not proved for the remainder of the cheek plates for the reasons given for NCR 30.
NCR 177: this is not proved for the same reasons as set out against NCR 30.
NCR 36: one fin plate was welded 180° out of position and therefore must have been bad workmanship (page 89 of Bundle N2, Beam 16131). This part of the claim is proved. The other complaint relating to the twin fin plate holes on Column 16103 being misaligned with Beam 16257 is also proved; if the misalignment was as bad as suggested, which I accept that it was, then there must have been poor workmanship in the fabrication.
NCR 57: this has not been proved. The NCR describes there being a clash with a connection fin plate on Beam 18277. Other documents such as the daily record sheet (page 157 of Bundle N1) suggest that the plates were welded too close together whilst the e-mail dated 18 May 2010 (page 161) suggests that the fins were too far apart. There is simply confusion here as to what the problem really was.
NCR 97: this has not been proved. The remedial work sheet (page 195 of Bundle N1) suggests that the work is "housekeeping". There is little or no description of there being any defect identified although page 202 talks about a "clash". There is insufficient evidence.
NCR 159: this has not been proved, save in one respect. It has been proved that the defect highlighted at page 384 of Bundle N2 namely a lack of perpendicularity and an inconsistent gap within the fabrication demonstrates shoddy workmanship. Otherwise the complaint about web cheek plates fouling a beam is insufficiently explained by the file or Mr Pyle.
NCR 161: this has not been proved. The file suggests that a top/bottom notch had to be enlarged but no explanation is given in the evidence, documentary or otherwise why this might be a tribute of all to pour fabrication.
NCR 173 and 174: although the Claimant's Counsel classified these as falling within this categorisation, they relate on their face to beams being supplied 15 mm over the required length. That, in my judgement, represents bad workmanship in the fabrication and can not simply be explained by reference to tolerances. This is proved.
NCR 178, 178a: this has been proved. Mr Pyle gave evidence that the defects present in two perimeter tray beams were that the bottom flanges were not fabricated with a notch to allow them to connect to the adjoining fin plate. I accept that evidence.
NCR 197: the file indicates two defects, one which is said to relate to NCR 186 which I have rejected (see below). The other annotation is "hold "holes in fin plates misaligned with connecting beam". No other detail is provided. I am not satisfied that this defect has been proved.
NCR 31: this was addressed in some detail by Mr Pyle who said that Beam 16214 was simply fabricated without allowing for any erection tolerance and that the beam end plates had been welded to the wrong ends of the beam and were upside down. I accept his evidence which is supported by the file of documents. This has been proved.
NCR 44: I am confused by the evidence which suggests that there was a setting out problem in relation to a particular beam. That is not obviously the fault of CBUK and it appears that the remedial works, albeit involving cutting a beam, evolved to overcome the setting out problem. The claim in this regard is not proved.
NCR 52: the file talks about web plates welded onto columns being "out of position" but little if any detail is provided. This claim has not been proved.
NCR 98: the complaint is that connection holes on twin fin plates were "misaligned" on a column and a beam. Little if any detail is provided. This claim has not been proved.
NCR 108: the complaint is based upon there being "a clash" between a column and the beam and, elsewhere, there is talk in the file about the misalignment. There is insufficient evidence. This claim has not been proved.
NCR 139: the complaint is that skirt beams had been fabricated without being preset and the quality of welding was not as specified. Nearly £22,000 is claimed for those which is one of the larger NCR claims. Mr Pyle repeats information received from Mr Adams of Steelcraft about the preset or camber not being to specification but does not speak to this personally. There is no evidence in the file about poor welding. This claim is therefore not proved.
NCR 179: Mr Pyle gave some detailed evidence in relation to this NCR. He said that there were two defects, the first being present in two columns with the splice plates on the lower columns being too far apart from one another, resulting in a clash between the splice plate on the lower columns and the upper columns shaft when the erectors tried to make the connection. This meant that the upper column would not fit over the splice plates on the lower column, so the connection could not be made. I accept his evidence to the effect that there was a workmanship defect in these respects in the fabrication. The second defect present on three remaining columns was that too much weld was present where the splice plates were welded to the lower column. This meant that when the upper column was lowered into position, it sat on the weld rather than sitting flush against the top of the lower column resulting in a misalignment between the connection holes. He said that there was a 6 mm discrepancy between the connection holes in the upper and lower column in these cases. I accept that evidence as demonstrating poor workmanship in the fabrication. This second defect is proved against CBUK.
NCR 186: this is similar to NCR 98 and for similar reasons this claim has not been proved.
Summary of Counterclaim Entitlement
Head of Counterclaim | Sum Allowed |
Prolongation – 22 Feb to 19 April | £105,088.50 |
Disruption –February to 18 April | £10,256.00 |
SMD disruption | Nil |
SRS Acceleration: A. Acceleration costs B. Additional site resources C. Senior Management |
£522,659.05 £29,305.82 £29,594.21 |
Mace Tower Crane cost | £95,692.69 |
Contra charges | £31,882.22 |
Total | £824,478.49 |
Conclusion and Decision