QUEEN'S BENCH DIVISION
BRISTOL DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
MELHUISH & SAUNDERS LIMITED |
Claimant |
|
- and - |
||
(1)EDWARD CHARLES HURDEN (2)ELIZABETH ANN HURDEN |
Defendants |
____________________
Andrew Kearney (instructed by Wards) appeared for the defendants
Judgment
____________________
Crown Copyright ©
Introduction
The history
51(1) Where an approved Inspector is satisfied that any work to which an initial notice given by him relates has been completed, he shall give to the local authority by whom the initial notice was accepted such certificate with respect to the completion of the work and the discharge of his functions as may be prescribed (called a "final certificate").
"Request that entrance door to comply with Part M Building Regulations. Following re-pointing of the building it is noted that weep holes are missing. These will need to be replaced.
Cavity tray vents at 450 centres and stop ends are required.
It is required that mastic is applied to a joint between conservatory and main building."
"… I can confirm that, in our opinion, the amount of mortar within the cavity is not acceptable and it would also appear that the cavity wall ties are sloping back towards the interior of the property, which contravenes good building practice.
During the inspection you sprayed water over the external wall and it became apparent, on the underside of the lintel in the kitchen, the water was entering the property. We were unable to ascertain the presence or condition of a cavity tray. However, cavity trays were present in other areas of the property where walls were exposed.
It was further noted that during the construction of the roof the gable blockwork has become dislodged and will require reconstruction."
"I can confirm that there are defects in the cavity wall, where inspected around the front door area, and where the full fill cavity insulation was removed. There is evidence of wall ties sloping towards the inner leaf of the building, poor mortar filling to the vertical joints, wall ties not properly bedded, and an excess of mortar within the cavity. The condition of the cavity wall (where inspected) is not in accordance with good building practice and contravenes the requirements of the Building Regulations. If the defects had been seen on site then advice would have been given to rectify the defective work. ... In my opinion the most practical way of ensuring that the external cavity wall performs its function throughout the life of the building is to demolish and rebuild the whole external leaf. This will allow the wall ties to be installed correctly, excess mortar in the cavity to be removed, defective lintels to be replaced over openings with adequate cavity trays, and for the external stonework to be properly bedded."
"I am unable to provide the final certificate as I am aware of inherent defects within the cavity wall which are very likely to allow water penetration into the building, which will be prejudicial to the health and safety of the occupants of the building."
The terms of the contract
Were the wall ties defective?
BS.5628 Part 3
"in cavity walls, some water will inevitably penetrate the outermost relief and prolonged periods of wind driven rain…"
BS.5628 Part 3 1985 section 32.11.4 wall ties
"... And have a slight fall to the outer leaf."
BRE Good Building Guide 41
"If ties slope the wrong way, if drips are off centre, or inverted, or if ties are fouled by mortar, rain can cross the cavity".
BS.5628 Part 3 2005 Section A5421
"... bed wall ties at least 62.5 mm or the desired embedment length into masonry walls and level or slope slightly downwards towards the outer leaf. Ensure the drips point downwards. It is important that proprietary wall ties are laid the correct way up".
"Resistance to Moisture
C2. The floors, walls and roof of the building should adequately protect the building and people who use the building from harmful effects caused by:
...
(b) precipitation and wind driven spray."
Cavity External Walls
5.12 Any external cavity wall will meet the requirement if the outer leaf is separate from the inner leaf by drained airspace, or in any other way which will prevent precipitation from being carried to the inner leaf.
Technical Solution
5.13 the construction of a cavity external wall could include:
a. outer leaf masonry (Brooks, blocks, stone or manufactured stone); and
b. cavity at least 50 mm wide. The cavity is to be bridged only by wall ties, cavity trays provided to prevent moisture being carried to the inner leaf, … and cavity barriers, fast stops and cavity closures, where appropriate; and
c. inner leaf masonry or frame with lining."
"… some of the wall ties ... have a negative slope towards the inner leaf. My query is - if the wall ties are completely surrounded with Rockwool material containing a water repellent, then how can wind driven rain that might be forced through the 165 mm outer leaf track across the wall tie if it is prevented from doing so by the Rockwool?"
The answer he received was not entirely helpful. Rockwool said:
"The Rockwool Cavity consists of water repellent fibres which are randomly orientated which prevents water crossing the wall construction through the insulation batt. The product is designed so that any water penetrating the outer leaf will drain down the surface of the batt. The product is suitable for use in standard masonry constructions i.e. brick, block or dressed stone.
The construction should be designed to the appropriate local wind driven rain index, paying due regard to the design detailing, workmanship and materials to be used and relevant recommendations of BS 5390: section 3 (BBA certificate 94/3079)
The wall ties penetrate through the insulation and effectively act as a bridge which water could traverse.
Our installation recommendations are based on good building practice guidance set out in the British Standards and NHBC. As per the product datasheet, we recommend that wall ties should be installed sloping to the outside leaf to prevent or minimise the risk of water ingress into the inner leaf.
BS 8000: part 3:1989 paragraph 3.4.3.1 states: "Wall ties – bed ties at least 50 mm into masonry leaves, and sloping slightly downwards towards the outer leaf. Ensure that, with wire ties, the drip points downwards."
NHBC Good Craftsmanship Guide for brickwork and blockwork states – "wall ties should be level or slope into the outside" and "ensure drips wall ties face downwards in the centre of the cavity".
We would recommend that you seek the advice of the wall tie manufacturer so as to obtain their opinion as to the correct installation or recommendation for the wall ties used."
The remedy for the wall ties
"If the court takes the view that it would be unreasonable for the plaintiff to insist on reinstatement as where for example the expenses of the work involved would be out of all proportion to the benefit to be obtained, then the plaintiff will be confined to the difference in value."
Judge Toulmin also referred to the judgement of Clarke LJ (as he then was) in the Southampton Container Terminals Ltd v Schiffartsgesellschaft "Hansa Australia" [2001] 2 Lloyd's Rep 275 at para. 56, where he said:
"Ruxley also supports the proposition that, although what the claimant does with any damages he receives is irrelevant, his intention to reinstate or not to reinstate, while not conclusive, is relevant to the question whether it would be reasonable to reinstate the property – see Lord Jauncey at page 359C-D and Lord Lloyd at pages 372-373…"
The head stones and the lintels
(1) they were susceptible to sagging in the middle, unless supported adequately by lintels from behind, and any sagging would have the effect of bearing down on the frame of the opening below, and (2) the tendency to sag was aggravated by the fact that most of the head stones were installed with a central mortar joint wider than the maximum recommended width. Since the original lintels did not provide adequate support, divided head stones were a poor choice. As it turns out, any deficiency in the load bearing quality of the head stones is cured by the solution proposed by the experts for the lintels. That still leaves the issue of the central mortar joint in the divided head stones: but this will be of cosmetic rather than structural significance once the new lintels are installed. The defendants want the divided head stones replaced with single head stones (Item 7 in Part B of the Scott Schedule). Since I am not persuaded that installing divided headstones was a breach of contract per se, I do not find the claimant liable for this head of the counterclaim.
Liability for other defects and repairs
Who is to carry out the remedial works?
"Kindly note that this matter cannot be given any further consideration under the cover afforded in accordance with Section 2 or Section 3 of the Buildmark policy as court proceedings are currently in progress. Once a final adjudication has been made, please forward any further correspondence for consideration if applicable."
"The Experts are of the opinion that the Claimants are perfectly placed and competent to undertake all the remedial works, subject to the following: a) Appropriate and adequate supervision, b) NHBC and Building Regulation Certificates, c) Relevant access being granted."
The figures
Other counterclaims for damages
Conclusion