QUEENS BENCH DIVISION
LEEDS DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
Oxford Row Leeds LS1 3BG |
||
B e f o r e :
____________________
CLARK ELECTRICAL LIMITED |
Claimant |
|
- and - |
||
JMD DEVELOPMENTS (UK) LIMITED |
Defendant |
____________________
Riaz Hussain (instructed by Weightmans LLP) for the Defendant
Hearing dates: 6 September 2012
____________________
Crown Copyright ©
Judge Behrens :
1 Introduction
2 The facts
2.1 The Contract(s)
1. Provision and installation of 11 kv cabling
2. Distillery works and variations
3. Substation works
4. Substation earthing systems
5. Dry Mill works
6. Wet Mill works
7. Gluten Dryer Works
8. Dayworks with materials
2.2 The adjudication process
Dear Mr Lawless
We have now had an opportunity to review the attachments to your e-mails. … Thank-you also for your revised timetable.
We have also reviewed the HGCRA and in particular SI 1998 649 Scheme for Construction Contracts 1998, a document that we are unfamiliar with, unlike [CEL]. At this point we do not have representation and are not familiar with the adjudication protocols; accordingly we would appreciate your guidance on the procedures and our responsibilities.
If we have correctly understood the Scheme, clause 7 suggests that at the same time as sending you the Notice and supporting documents, [CEL] are to provide copies of those same documents to us. However, to date we have not received the documents referred to. Consequently we feel it is appropriate to put [CEL] and yourself on notice to this effect and request your guidance. We are sure it was simply an oversight on behalf of [CEL] that they failed to forward copies to us and therefore feel certain that [CEL] will see fit to agree to extend the timetable to take account of this and provide the correct documentation to enable us to proceed.
We would state that this is particularly important in this case, given that the last correspondence from [CEL] claimed the sum due to them was £220,266.87 plus a further £38,135.89 of unspecified works and the sum now claimed is £177,849.87 representing a 31% reduction in the claim, highlighting the ongoing discrepancies that we have continually stated since the first application from [CEL].This was the main reason we requested substantiation from [CEL] in January 2012 to resolve the issues. This detail has yet to be received, despite repeated requests.
I look forward to receiving your proposal for moving forward, and to receipt of [CEL]'s claim.
Yours sincerely
As to CEL's conclusion that you are not entitled to inquire into or decide the question of your own jurisdiction we agree with the position stated in your letter of 19th March 2012 … Our client maintains the site and operations fall under the exclusions set out in section 105(2)(c) … and consequently you have no jurisdiction.
Our client's position remains that should you make a non-binding conclusion that you have jurisdiction then [JMD]'s further participation in the purported adjudication is fully reserved. Its position remains that you do not have jurisdiction and for the avoidance of doubt [JMD] will not accept the validity of your decision, nor will it accept liability for any of your fees and expenses, which you may determine it is liable.
2.3 The adjudicator's decisions.
1. That there was no statutory jurisdiction. He held that the works were excluded under section 105(c)(ii). He also held that there was one contract comprising different work packages. Thus if the works had not been excluded under section 105(c)(ii) there would have been no jurisdictional bar to statutory adjudication.
2. That there was an ad hoc arbitration agreement arising out of the payment of the £6,000 by both parties. The agreement is contained in the letter of 5th March 2012 containing the terms of the adjudicator's contract which was accepted by the conduct of the parties in paying the appointment fee.
3 The Law
3.1 Ad hoc adjudication agreements
1. It is open to a defendant in enforcement proceedings to challenge the decision of the adjudicator on the grounds that he was not empowered by the Act to make the decision. [See paragraph 9 of the judgment of Dyson J].
2. If two people agree to submit a dispute to a third person, then the parties agree to accept the award of that person, or, putting it another way, they confer jurisdiction on that person to determine the dispute.
3. If one of the parties thinks that the dispute is outside the agreement that they have made, then he can protest against the jurisdiction of the adjudicator. [see paragraph 14 of the judgment of Dyson J and the citation from Devlin J's judgment].
4. Where the parties agree to be bound by the adjudicator's decision "in the full sense" they are agreeing to be bound by his decision on jurisdiction (subject to a later challenge – as provided in section 108 of HGCRA). [see paragraph 27 of the judgment of Simon Brown LJ].
5. It is a question of fact whether a party submits to the jurisdiction of a third party. [See paragraph 15 of the judgment of Dyson J].
6. In three of the four cases there was held to be no submission to the jurisdiction. In the fourth – Nordot - the Defendant had written a letter, described as "clear and unequivocal" that it would abide by the adjudicator's decision. However I agree with Mr Beresford that it is not a prerequisite of submission that there be a clear and unequivocal statement such as occurred in that case. Where, as here, the agreement is said to derive from correspondence the Court must construe the correspondence in accordance with the ordinary canons of construction.
7. There is a concern that the salutary power to promote early payment in construction cases is emasculated by jurisdictional challenges. The solution to this concern is as Simon Brown LJ said:
"not in finding defendants too readily to have, in the full sense, submitted to the adjudicator's jurisdiction, which if properly advised they plainly would not do. Rather, as Dyson J observed in paragraph 8 of his judgment in the Project Consultancy Group case, it is for courts (and adjudicators) to be "vigilant to examine the arguments critically." It is only if the defendant had advanced a properly arguable jurisdictional objection with a realistic prospect of succeeding upon it that he could hope to resist the summary enforcement of an adjudicator's award against him."
The position can I think be summarised in the following two propositions. (1) If a defendant to a Part 24(2) application has submitted to the adjudicator's jurisdiction in the full sense of having agreed not only that the adjudicator should rule on the issue of jurisdiction but also that he would then be bound by that ruling, then he is liable to enforcement in the short term, even if the adjudicator was plainly wrong on the issue. (2) Even if the defendant has not submitted to the adjudicator's jurisdiction in that sense, then he is still liable to a Part 24(2) summary judgment upon the award if the adjudicator's ruling on the jurisdictional issue was plainly right.
3.2 Linnett v Halliwells [2009] EWHC 319
32. It is to be noted that, although adjudication is said to be "statutory adjudication" it is, on analysis, contractual. The adjudication process consists of two agreements. One agreement, the Adjudication Agreement, is that made between the parties to a construction contract either expressly or impliedly by the Scheme under s.108 of the 1996 Act. The second agreement, the Adjudicator's Agreement, is an agreement which may be made between the Adjudicator and one or both of the parties.
33. The adjudication provisions in s.108 of the 1996 Act are concerned only with the Adjudication Agreement. They require the parties to agree upon certain terms in their contract. These terms include provisions requiring the adjudicator to reach his decision within 28 days or such longer period as may be agreed (s.108(2)(c)); imposing a duty on the adjudicator to act impartially (s.108(2)(e)) and providing that the adjudicator is not liable to the parties unless there is bad faith (s.108(4)). Those provisions are essentially obligations or rights of the adjudicator which would be expected to be contained in the Adjudicator's Agreement or, like similar provisions in s.29(1) and 33 of the Arbitration Act 1996 in relation to the immunity and duties of an arbitrator, to be imposed upon the parties and the adjudicator as a matter of statute. In the absence of any other route, the necessary terms of the Adjudicator's Agreement would have to be implied into that agreement.
34. Similarly, in adjudication, the ability of an adjudicator to obtain fees depends on there being a contractual right to payment under the Adjudicator's Agreement with one or both of the parties. There is nothing in s.108 of the 1996 Act which gives the adjudicator a right to payment. It is to be noted that, in this case, under Clause 41A.2 of the Building Contract it was envisaged that the parties and the adjudicator would all execute the JCT Adjudication Agreement which would, amongst other things, provide the adjudicator with a direct route to payment of his fees from both the referring and the responding party. Although that provision was included in the JCT Standard Form, in this case no such adjudication agreement was entered into between both parties and the adjudicator.
In paragraphs 69 to 71 Ramsey J analysed the position where there is a jurisdictional challenge:
69. If there is a valid jurisdictional challenge and if a party has not participated in the adjudication then, on the basis of the view I have expressed above, that party can have no liability for the fees and expenses of the adjudicator.
70. If, however, a party has participated in the adjudication process, albeit without prejudice to its contention that the adjudicator did not have jurisdiction, then in principle by participating and thereby requesting the adjudicator to adjudicate on the dispute I consider that the party will generally be liable for the reasonable fees and expenses of the adjudicator on the same basis as set out above.
71. I emphasise that this is a matter of contract as between the adjudicator and the relevant party. If the adjudicator did not have jurisdiction then any decision made by the adjudicator will be null and void. This will preclude one party from recovering from the other party any sums based on the adjudicator's allocation of the fees and expenses contained in the invalid decision.
4 Submissions
1. The request for an extension of time in paragraph 3 of the e-mail.
2. The request for guidance on procedures and responsibilities in paragraph 2 of the e-mail.
3. The final paragraph where Mr Teale invites the proposal for moving forward.
5 Discussion and Conclusion
"Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonable have been available to the parties in the situation in which they were at the time of the contract."
6 Post Script