QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London. WC2A 2LL |
||
B e f o r e :
____________________
RIVERCOVE TRUSTEE LIMITED |
Claimant |
|
- and - |
||
JAN van WINKELEN t/a EURO RUBBER LINES |
Defendant |
____________________
Mr Ben Quiney (instructed by Clyde & Co LLP) for the Defendant
Hearing dates: 18th-21sl, 25th-29th June & 13th July
____________________
Crown Copyright ©
Mr Recorder Soole QC :
The Site
The parties and other players
The contract
'a) following payment of the money [ERL] may commence dismantling and removal of the Equipment.
b) [ERL] shall... use reasonable endeavours to remove at its cost the Equipment and all its equipment, tools, staff, agents and contractors from the Premises by 15 January 2008. Failing this... by 31 January 2008... Failing this... by 28 February 2008. Ownership of any equipment left on site after the 28 February 2008 will revert to Rivercove. No refund of the purchase price will be payable should [ERL] fail to remove the Equipment by the final deadline date of 28 February 2008 and ownership of the Equipment transfers to Rivercove.
c) [ERL] shall be responsible for the removal and disposal of waste material in connection with or arising from the said removal...
...e) [ERL] shall ensure that its staff agents and/or contractors shall comply with all relevant laws relating to health and safety when carrying out the said removal and shall be responsible for the safe operation of and for obtaining the necessary permits and licenses for the use of all equipment and tools (including, without limitation, cranes and lifting joists) whether they be the property of Rivercove or any other entity. Copies of method statements and risk assessments for removal of the equipment shall be submitted to [McBride] prior to commencing removal of the equipment.
...
f)...The Premises shall be left in a safe and tidy condition following removal of the Equipment, to the satisfaction of [McBride]..
...
Rivercove does not give any warranty, representation or undertaking as to any equipment, machinery, plant or power supply at the Premises used by [ERL] during the removal of the Equipment."
which was originally joined with the present action until settlement was achieved. In addition he continued to be responsible for the management of the southern section until Rivercove purchased that part in December 2007. This interim role also led to dispute with Rivercove, concerning oil contamination allegedly emanating from the northern section.
Standard of proof
Witnesses
The state of the Site and its causes
Before 31st July 2007
Conclusion on the period to 31.7.07
1st August - end-November 2007
Environment Agency
'With Mr Sullivan my colleague and I further inspected a number of buildings on site where we found varying quantities of oil, present in pits, tanks, barrels and numerous combinations of these plus in other containers as well as being spilled over some internal floors. In addition, the innumerable containers of inks/dyes/chemicals of varying states of condition were also found. Some of the spillages may have been deliberate but they do require urgent attention.'
ERL on Site
October/November 2007
'Made a further inspection today. Oil skimmer has been effective. XXXXX advised that BIFF A waste contractors will be attending on Wednesday to remove quantities of oil found in a number of sumps/channels. This process is likely to continue for some time until the demolition of the site is completed next year. NFA by DA except to monitor occasionally.'
'... whilst on site I inspected the oil water interceptor and found oil was still arriving at it from the site drainage. The whole site was therefore checked again to identify the source of this oil. Whilst a few buildings have pits and ducts with very minor traces of oil/oily water in them [the Calender Building] was found to have ducts, which despite having already been cleaned by ourselves, again contain significant amounts of free oil in them. This oil appears to be a type of hydraulic/gear box oil similar to that noted in the interceptor. It is in this building that [ERL] were present removing redundant machinery on my visit. The only sensible conclusion is that the machinery removal is the cause of the oil spillage/contamination and no measures were identified as being in place to prevent this.'
'... steps must be taken immediately to prevent any further oil from entering the ducts as from there it drains into the site's drainage system and eventually the open water. Furthermore, oil that has got into the ducts from the dismantling of the machinery must be removed as quickly as possible and removed off site under a hazardous waste consignment note. We have been advised that the works to remove this oil should the problem remain and get worse, could be very significant indeed, ie up to £30,000 - £35,000.'
'I have spoken to the engineers and drivers who have been removing the machinery and they are all puzzled about the allegation as they are unaware of any oil leakages. The only oil that could leak is when an oil pipe has been disconnected and a very small amount of oil would drip out and this would be soaked up with granules as it occurs. There has not been any leakage of oil that could warrant your allegations. Please be assured that due care will be exercised when the remaining machinery is dismantled.'
9th January 2008 meeting
'Jan,
further to our meeting yesterday I confirm the following:
The issues raised at the meeting were -
Oil spillage
Damage to floor plates
Damage to roller shutter doors
Following previous letters and discussions and negotiations on the day it was agreed that the following actions would be taken.
[ERL] will provide an environmental clean to the Calender roll building. This will include the removal of all material from the floors and within ducts. Any existing cables and pipes etc should be removed from the ducts prior to cleaning to ensure that all of the oil/contaminated material is removed.
All material arising from the environmental clean should be removed from the site by [ERL] and disposed of in line with current legislation.
Rivercove trustees will not charge [ERL] for the damage caused to the floor plates or the roller shutter doors and instead of demanding that [ERL] replace the damaged plates Rivercove will employ DSM to fill the ducts with concrete after they have been cleaned out by [ERL] so that the trip hazard is avoided.
We trust this is in line with our agreements reached yesterday and look forward to the works being carried out.
We would appreciate your confirmation and acceptance of the above by return so that we can close this matter.'
'I explained that the dirt and oil in the gullies had nothing to do with my employees or I and I denied having any responsibility for cleaning them, especially as my men have not even begun to remove the calenders. At this point Mr Kelly was being aggressive and hectoring, insisting that I clean the gullies. Despite denying responsibility for the cleaning of the gullies, I made an offer to Mr Kelly that if there was time after the removal of machines I would have my employees clean the gullies with a jet wash and tidy the area where they had been working. I did this as a gesture of goodwill for Rivercove, in order to ensure that I could complete the removal of the equipment I purchased. The area I said I would clean was approximately 3,000 square feet. At no time during this conversation did Mr Doody or I offer or agree to carry out an environmental clean, or admit that any of the oil in the area was there as a result of work which had been done by my employees. My employees had not even commenced work to the calender lines'.
'I refer to the above site where [ERL] are currently taking out machines purchased from [McBride], and confirm that we will ensure that any oil spillages caused by [ERL] in the removal of said machines will be cleaned up. This letter in no way admits acceptance of oil spillages prior to work commencing on 07/01/2008 as previously advised by email to [Mr McBride].'
'... although you and your son have verbally agreed that the content is correct we have received no confirmation in writing. I handed a further copy to your son last week when he was at our offices, he said he would return it signed as agreed in the next couple of days. This has not happened. We need your confirmation in writing by return. We also note that you have not commenced any of the works to clean out the ducts and pits as agreed. If we have not heard from you by Friday, 22nd February 2008 we will secure the site at 5.00 pm on this day and no access will be granted either to dismantle or remove any machinery from the site until these issues are resolved. If it is your intention to carry out the cleaning works after the machinery has been removed from site we will require a bond in the form of funds placed in an escrow account the sum of £30,000... which will be released upon satisfactory completion of the works'.
'... even though I do not accept liability for any oil spillages I did agree that [ERL] would attempt to clean the cable trenches in the calander building as agreed verbally during our meeting late last year. [He said that this must be a mistaken reference to the meeting of 9th January], It is difficult to start this work whilst the calenders are still being removed as we are still driving the area on a daily basis. I shall, however organise to start the cleaning process where we can next week, I shall do my utmost complete the work as soon as possible.'
'At no time did an oil spillage occur and the allegations from [Rivercove] are groundless. The former Wardle Storey factory is very old and there is a build up of oily substances which have happened over a number of decades. These have occurred in the cable trenches and calendar pits especially. The trenches and pits were subject to flooding due to high water table in the area... As a gesture of goodwill I was planning to have a go at cleaning the trenches, once the machinery had been removed, however emails subsequently arriving from Mr Rob Braid became ever more menacing.... I have no obligation to complete an environmental clean on a site which is being demolished as no contamination was caused by [ERL].'
Conclusions post-31st July 2007
The pits
The ducts
The floor
Quantum
'Further to your instruction to carry out the removal of spilt oils within the Calendar Building we would record the following points:
1. The oil contains additional chemicals and paints.
2. These substances have entered the outlets to the stream and lagoon...'.
Indemnity
Note 1 Wardle Storeys (Property) Limited [Back] Note 2 Storeys Industrial Products Limited ('SIP') [Back] Note 3 According to the Specifications for Calender Lines 2 and 5 : C/61,65 [Back] Note 4 Gerry Watson and Gary Head [Back] Note 5 Bernard Wardle & Company Ltd [Back] Note 6 Mr Mann's letter of 3rd August says that Mr Hawes was present, but this appears to be a mistake. Mr Hawes' employment terminated on 27th July and his presence is not supported by the statements of Messrs Cooke and Sullivan. [Back] Note 7 Letter wrongly dated 3rd August [Back] Note 8 There is a version without a job price at D/118. It seems that this was removed by Mr Jones before forwarding to Mr Evans : D/145 [Back] Note 9 This expert report is attached to the Particulars of Claim but is not relied on by Rivercove. [Back] Note 10 This included the water/oil removal works of 2007-8 [Back]