If you found BAILII useful today, could you please make a contribution?
Your donation will help us maintain and extend our databases of legal information. No contribution is too small. If every visitor this month donates, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand. London. WC2A 2LL |
||
B e f o r e :
____________________
Swindon Borough Council | Claimant | |
- and - | ||
Forefront Estates Limited | Defendant |
____________________
The Defendant did not appear and was not represented
Hearing date: 16 January 2012
____________________
Crown Copyright ©
Mr Justice Ramsey:
Introduction
Background
"The Theatre (FF02) roof structure is the main structural concern to date. It is not considered that the roof is likely to collapse imminently however in certain conditions it may be more prone to this. New temporary support should be provided as soon as possible and at no stage are any finishes to be removed until such support is provided unless under direct instruction from a Structural Engineer. Until this new support is in place it is recommended that in moderate wind and rain access is restricted. The condition of the roof at this stage doesn't prohibit further investigation and the 'clean up' both of which are likely to be required before temporary support is achievable
"3.1 The lateral movement of the eaves without visible distress to the wall suggests that the wall plate has deteriorated allowing it to move independently, whilst the truss bearing deterioration has allowed the trusses to drop. With the first truss over the theatre wedged against the stage it is considered that the risk of collapse of this truss is high. Due to the distress previously reported along the west side to the first four truss supports it is likely that if a collapse occurred at the south end it would pull and result in a failure of all four trusses. The roof is becoming more susceptible to distress and movement as the weatherproofing sheet deteriorates.
3.3. Due to the fact that a truss is taking support off the stage arch projection and the deteriorating nature, and overall condition of the theatre roof we are unable to classify this roof as safe."
"As a result of our investigations we are very concerned about the North Roof. Our conundrum is that we have reason to believe that one of the beams is failing resulting in the north roof being in danger of collapse. We would like to prop from the inside, drawing attached, but we can't as this would be putting people at risk whilst undertaking the propping. The other alternative is to take the load from an external structure but again we can't because this would mean putting people on the roof again putting people at risk. "
The Issues.
"(5) In proceedings to recover expenses under this section, the court shall inquire whether the local authority might reasonably have proceeded instead under section 77{1) above, and, if the court determines that the local authority might reasonably have proceeded instead under that subsection, the local authority shall not recover the expenses or any part of them. "
The evidence
The applicability of Sections 77 and 78 of the 1984 Act
Necessary work under section 78
The expenses reasonably incurred
Item 5.01. This item, in the total sum of £38,519.44, represents the cost of purchasing the internal shoring scaffolding and the roof sheets. I consider that from the drawing provided by Optima Scaffold Designs LLP showing the scaffold shoring and temporary roof to theatre an appropriate assessment would be some two-thirds for the support scaffolding to support the roof trusses and about one-third for the roofing. On that basis I consider that the sum recoverable for Item 5.01 is £25,679.62.Item 5.02. This is a claim for £20,000.00 for the labour to erect the shoring scaffolding and the roof sheets. Again, I consider that there should be a discount of one-third so that two-thirds or £13,333,33 is recoverable.
Item 5.03. This is related to the cost of dismantling the scaffolding. However, on Mr Thom's evidence, the Council took the decision that it was better to purchase the scaffolding than to pay continuing hire charges. This means that the Council have not incurred the cost of dismantling this scaffolding. Whilst at some stage the scaffolding will have to be dismantled when work is carried out at the Institute, I do not consider that the cost of dismantling the scaffolding can then form part of the expenses reasonably incurred in removing the danger. I therefore do not allow this item.
Item 5.04. This is a claim for the cost of inspecting the scaffolding. It is claimed at £50.00 per week for a period of 2 years, at a total of £5,200.00. On the evidence, I accept that these inspections are still being carried out on a weekly basis but, in my judgment, as Section 78(4) indicates in relation to fencing and watching, I do not consider that once the danger is removed the subsequent inspections can form part of the expenses reasonably incurred under Section 78 of the 1984 Act. I therefore allow the inspection fees for a total of 7 weeks at a total of £350.00.
Item 5.05. This is the cost of the support/shoring scaffolding for the North Gable which was erected on 6 August 2010. For the reasons set out above I do not consider the sum claimed of £5,041.00 is recoverable under section 78 of the 1984 Act.
Item 5.06. This is the supply of the further shoring scaffolding to the North Gable including its purchase. I consider that this item in the sum of £4,273.90 is recoverable as part of the expenses reasonably by incurred under section 78 of the 1984 Act.
Item 5.07. This is the cost of the design of the further scaffolding and I consider that the sum of £500.00 is recoverable.
Item 5.08. This is the cost for the supply of 55 Heras fencing panels and I allow the cost of £82.50.
Item 5.09. This is the labour for erecting the fencing panels and I allow the sum of £190.00.
Item 5.10. This is the cost of the independent support scaffolding to support the roof timbers once removed from the roof. For the reasons set out above, I do not consider that the sum of £890.00 is recoverable.
Item 5.11. This is the temporary shelter for the surveyors during the removal works and I consider that the sum claimed of £580 formed part of the expenses reasonably incurred under Section 78 of the 1984 Act.
Item 5.01 | £25,679.62 |
Item 5.02 | £13,333.33 |
Item 5.03 | Nil. |
Item 5.04 | £350.00. |
Item 5.05 | Nil. |
Item 5.06 | £4,273.90. |
Item 5.07 | £500.00. |
Item 5.08 | £82.50. |
Item 5.09 | £190.00. |
Item 5.10 | Nil. |
Item 5.11 | £580.00. |
£44.989.35 |
Summary of sums recoverable under s.78 of the 1984 Act
Preliminaries: | £30,513.50 |
Highways management: | £35,671.48 |
Security: | £11,318.40 |
Fees: | £30,931.20 |
Scaffolding: | £48,588.50 |
Roof removal works: | £105,145.42 |
Statutory Fees: | £167.40 |
Further fees: | £19.572.77 |
Total (excluding VAT): | £281.908.67 |
VAT at 17.5%: | £49.334.02 |
Total (including VAT): | £331.242.69 |
Costs
Solicitors' costs: | £28,168.30 |
Counsel's costs: | £26,600.00 |
Costs of Mr Green: | £1,500.00 |
Costs of Mr Bampfield: | £1,380.00 |
Court Fees: | £2,480.00 |
VAT: | £nil |
Total: | £60.128.30. |
Interest
A charge under section 107 of the 1984 Act.
"(2) A local authority, for the purpose of enforcing a charge under subsection (1) above, have all the same powers and remedies under the Law of Property Act 1925 and otherwise as if they were mortgagees by deed having powers of sale and lease, of accepting surrenders of leases and of appointing a receiver."
Summary