QUEEN'S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
Rolls Building |
||
B e f o r e :
____________________
(1) WHESSOE OIL & GAS LTD (2) CLEVELAND BRIDGE UK LTD |
Claimants |
|
- and - |
||
WILLIAM JON DALE |
Defendant |
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
info@beverleynunnery.com
MR. M. BOWDERY QC (instructed by Simons Muirhead & Burton) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
MR. JUSTICE AKENHEAD:
"By reason of the matters aforesaid [those are the breaches] WOGL and/or Cleveland have suffered loss and damage. The best particulars that they can provide prior to disclosure and/or the provision of any further information herein are as follows:
29.1 WOGL has suffered loss and damage of £50·6 million as a result of the cost overrun on the Dragon LNG project".
1 That gives them an extension of time which reflects at the outside the period of delay over which they had little or no control. It gives them 10 days which is capable of being met by dint of focussed and hard work; that will have given them 38 days to draft the requisite particulars, compared with the 28 days that only last month they were confident that they could do what was required; of the 38 days, no more than six days at the outside is arguably attributable to the hard drive glitches. In reality, there was work which the claimants could have gone on with in the meanwhile if they had used the other computer files available in this country;
2 The original date of 23 July, was fixed so as to enable the restored application for strike-out which had been brought by the defendant to come back before the court. It would come back before me, who was the judge who dealt with the initial strike-out application, so that:
(a) the particulars could be reviewed to see whether they were satisfactory and did provide the requisite amount of information; and if they did not that could lead to a strike-out. If they did, then appropriate directions should be given.
"Unless the first claimant complies with para.2 of the order of 25th June, by 3 pm on 2nd August, its Claim and Particulars of Claim should be struck out and there shall be judgment for the defendant".
(LATER)
MR. JUSTICE AKENHEAD