QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
1. Donne Place Investments Limited 2. Ives Street Investments Limited |
Claimant |
|
- and - |
||
1. Louise McDonnell 2. McDonnell Associates Limited |
Defendant |
____________________
Mr Marc Beaumont (instructed under the Bar Public Access Scheme) for the Defendants
Hearing dates: 30th November, 1st, 2nd, 6th-10th, 20th December 2010; 20th, 21st, 31st January 2011 & 1st February 2011.
____________________
Crown Copyright ©
Mr Recorder Soole QC :
"(1) The Employer wishes to have demolished an existing Structure and have designed and constructed a new house at 13/14 Donne Place, London, SW3 2NG in accordance with the list of Drawings…attached or any subsequent amended or additional Drawings or details…
(2) A Budget Cost of the Employers Proposals has been compiled and improved by the Employer (Document Marked "A" attached)…
(3) The Contractor has agreed to demolish the existing Structure and design and construct the new house previously referred to including any additional work required by the Employer."
(1) That the Contractor will carry out and complete the works shown on the Contract Drawings or on any subsequent amended or additional Drawings or details or in accordance with instructions issued by the Employer in relation to additional work.
(2) The Employer will pay to the Contractor the cost of carrying out the works plus a Contract Fee plus additional payments in accordance with Clause 4 (A) of the Contract Conditions.
'The Contractor will complete the Construction of the House within fifteen months of the Date of Possession. If the Contractor fails to complete the works within 15 months of the Date of Possession the Contractor will incur no penalty.'
Account : Donne Place
Background to the accounts
Issue 4 : Disputed expenditure – cost of goods not delivered directly to Donne Place
Issue 5 : Invalid invoices which have not been and may never be paid
Issue 6 : No or insufficient supporting information for items in the final account
Issue 7 : couriers transport and bank charges
Issue 8 : Costs included in the Final Account for which no invoice can be found
Issue 9 : No invoice or evidence of payments included in the Final Account
Issue 10 : Costs included in the Final Account for which no specific evidence of payment has been provided
Issue 11 : Disputed expenditure – classified as "Private, Incidentals and Other Associated Costs in the Final Account"
Issue 12 : Disputed expenditure – Amounts paid post termination of the contract
Issue 13 : Disputed expenditure – amounts paid pre-novation of the contract
Issue 14 : expenses mistakenly included twice in the Final Account
Issue 15 : Jetset
Issue 17 : New information not accepted
Issue 18 : VAT on pre-novation
Issue 28 : Fees due to MCD as Contractor on the Donne Place project
'Determination
The Employer shall be entitled to determine this Contract for any reason by giving the Contractor four weeks notice in writing.
The Employer shall in those circumstances pay to the Contractor on the Date of Determination or as soon as can be ascertained.
(1) The cost of the works to the Determination Date.
(2) A proportion of the Contract Fee, being the percentage of the fee that bears relation to the cost of the works to date in relation to the Budget Cost.
(3) Any other cost that the Contractor becomes liable for as a result of the determination.
(4) The Contractor shall be entitled to determine this Contract for any reason by giving the Employer four weeks notice in writing and the Contractor shall be entitled to payment in accordance with Clauses 1-3 above.'
'… (1) The Contract Fee to be paid by the Employer to the Contractor is a lump sum calculated as 15% of the Budget Cost described in the Articles.
(2) The 'Cost' which the Contractor will be paid is the cost of carrying out the works whether or not that figure is greater than or less than the Budget Cost.
(3) If the Final Cost is less than the Budget Cost them the Contractor will be paid 10% of the difference between the Budget Cost and the Final Cost as a bonus and this will be paid when the Final Cost is known.
If the Final Cost is greater than the Budget Cost them the Contractor will be paid no additional Contract Fee on the first £100,000 of additional cost above the Budget Cost but will be paid 5% of the additional cost over and above the Budget Cost plus £100,000 and this will be paid when the Final Cost is known.'
Issue 29 : Fees due to MCD as Architect on the Donne Place project
Issue 20 : Lack of details for couriers, transport and bank charges
Issue 21 : Missing invoices
Issue 22 : No invoice or payment evidence
Issue 23 : No payment evidence provided
Issue 26 : Private expenditure
Issue 27 : Duplicated expenses
Issue 30 : Ives Street Architects Percentage Fees
'5.7 Where for any reason the Architectural Designer provides only part of the Services specified in Schedule 2 the Architectural Designer shall be entitled to fees calculated as follows:
.1 for completed Services as described for those services in Schedule 3;
.2 for completed Work Stages as apportioned for those Work Stages in schedule 3;
.3 for Services or Work Stages not completed a fee proportionate to that described or apportioned in schedule 3 based on the Architectural Designer's estimate of the percentage of completion.
Stage E 30% Final Proposals
Stage F 30% Production Information
Stage G 5% Tender Documentation Stage
Stage H 5% Tender Action
Stage J 10% Mobilisation
Stage K 15% Construction to Practical Completion
Stage L 5% After Practical Completion
"E Final Proposals
Preparation of final proposals for the Project sufficient for co-ordination of all components and elements of the project.
F production information
F1 Preparation of production information in sufficient detail to enable a tender or tenders to be obtained. Application for statutory approvals.
F2 Preparation of further production information required under the building contract.
G Tender documentation
Preparation and collation of tender documentation in sufficient detail to enable a tender or tenders to be obtained for the construction of the Project.
H Tender action
Identification and evaluation of potential contractors and/or Specialists for the Construction of the Project. Obtaining and appraising tenders and submission of recommendations to the Client.'
Issue 31 : MCD Fees included in Final Account but still subject to agreement
'The Contractor will complete the Construction of the House within fifteen months of the Date of Possession. If the Contractor fails to complete the works within 15 months of the Date of Possession the Contractor will incur no penalty.'
Delay : Ives Street
'The Architectural Designer does not warrant:
1 that the services will be completed in accordance with the Timetable or the budget cost for construction works;
…'
Deceit
'We have sent all information to Metronet which was requested they are reviewing the final information and should be ready to give approval within the next 7 days.
They have requested and had been provided with Method Statements and Risk Assessments for: Construction, demolition, scaffolding and crane hire…'
'I have reviewed the MS for demolition. I have no further comments. I await the RA. Please send all MS/RA on two hard copies signed. I await a MS/RA for the scaffold and the relevant calculations and dwgs… I would request to send the required RA for the demolition and the MS/RA for scaffold as soon as possible in order to review it before my leave and I will deal with the rest of the MS depending upon my return.'
'Demolition: Jim I believe you assisted with this. Can you confirm we have both MS & RA for this element…
Scaffolding: – Jim I believe you assisted with this. Can you confirm we have both MS & RA for this element. I understand that I need to obtain contractor price if they are not willing to accept the generic. Thanks for this update."
The reference to 'the generic' was to MS/RA which were not site-specific. If the relevant intended subcontractor had not been appointed, or was not willing to provide the information prior to appointment, it would not be possible to provide more than generic MS/RA.
'Did you get my note on the scaffolding calcs they are asking for?
I can confirm that I sent the MS and RA for the demolition. You will need a RA for the scaffolding which I will do now and send over but you won't get a method statement or calcs for that until you get your subbie on-board.'
'On 17th January 2007 in an e-mail copied to [SC, LM] stated that the structure was 'designed in essence'… There was no basis on which [LM] could honestly have believed this to be true, since [MCD] were not close to having a final design at this stage."
'On 15 August 2007 in an e-mail copied to [SC, LM] stated that 'we need the Party Wall Award in place at the soonest possible time'…There was no basis on which [LM] could honestly have believed that the Party Wall Award was the key outstanding issue, since no material contact had been made with [LU] at this stage and no work could go ahead without the agreement of [LU]. Furthermore no quotes from demolition contractors had yet been obtained and no demolition sub-contractor appointed."
'On 13 February 2008, [LM] stated that: 'the negligence [insurance] is all good to go as soon as [LU] confirm that they are satisfied… This is the last piece of information required for Richard Birchall – the awards have been drafted and this letter will be enclosed and sent to the respective Surveyors…' There was no basis on which LM could honestly have believed that agreement from [LU] was all that was required for the Party Wall Awards to be sent out…' This was contained in an e-mail from LM to SC and others on that date.
"On 1 April 2008, [SV] sent an e-mail to [LM] asking why the [MS] had not been provided to London Underground.[ LM] responded on 2 April 2008 stating that the 'method statements have been submitted ages ago by the structural engineers'… There was no basis on which LM could honestly have believed that this was the case. On 31 March 2008, Amy Moss of MCD had informed LM that the method statements from KLH (i.e. in relation to the superstructure) had not been provided to London Underground. Furthermore, as shown by the extensive subsequent correspondence about method statements (including Metronet's e-mail of 28 April 2008) parental, no method statements for scaffolding or demolition had been provided either.'
'On 3 April 2008,[ LM] stated in an e-mail to [SV] that 'this package of works (demolition) can happen as soon as: after the inspection of the tunnel: I can then pay for and put in place the insurance clause 21.2.1. This can then go to the Party Wall Surveyors who have the award ready – this will then be sent out… There was no basis on which the LM could honestly have believed that demolition could take place directly after the inspection of the tunnel since… she knew that method statements had not been provided to [LU], no demolition sub-contractor had been appointed and no final drawings were available for the superstructure party wall award.'
I have dealt with this above.
'On 25 July 2008, [LM] stated in an e-mail to [SC and SV] that: 'LUL/Metronet: Metronet have contacted us to ask for signed copies of all the paperwork that we sent before. This has been couriered to them. Party wall: Richard Birchall has copies of the insurance and we are just awaiting Metronet sign off and we will push the party wall awards to be signed… The implication of this statement… was that now signed documents had been provided, approval would follow. However, as set out above, key pieces of documentation were still missing, as LM knew.… In relation to the party wall awards… [LM] knew that in order to agree the superstructure party wall awards detailed drawings of superstructure were required and that no such drawings have been produced by [MCD]'.
'On 3 October 2008,[LM] stated in an e-mail to [SC] that: 'we have at last made amazing progress on Ives Street thanks to David Akera's persistence. it looks like we may have a sign off next week given the last bit of information. I will contact Richard Brichall (sic). We can do handover on the project with David Akera at your convenience although we will be happy to get the Party Wall awards signed off for you prior to MCD's handover… There was no basis on which [LM] could honestly have believed that the last bit of information had been provided to [LU] or that sign off could be expected with a week or that Party Wall Awards would be available directly upon such approval be given will. the method statement, drawings and calculations for scaffolding still not been provided to [LU], nor had satisfactory documents on demolition – see the e-mail of 3 October 2008 from Metronet which had been copied to LM by Mr Akera on the same day. Furthermore, the detailed drawings of the superstructure required structure party wall awards had still not been produced by [MCD]'.
'On 7 October 2008, LM stated in an e-mail to [SC] that: 'David [Akera] has sent everything once again to Melina at Metronet and hopefully by the end of next week we will get confirmation that we can progress and we will then get Richard Birchall to action the party wall award.… There was no basis on which LM could honestly have believed that this was the case. See above. That documentation was still missing is confirmed by Mr Akera's response to this e-mail of 9 October 2008.'
'On 27 October 2008,[LM] stated in an e-mail to [SC] that: 'We have now obtained the demolition quotes and LUL are now insisting that method statements and risk assessments are not generic as submitted by Jim Moss of Eldridge Moss – they now want them from the subcontractor who will work on the project – the subcontractor will only produce this once appointed. This was the latest request from 2 weeks ago – we immediately went out to tender with Akera Engineers scheme… There was no basis on which [LM] could honestly have believed the statements being made. [LM] had known throughout the dealings with [LU] that no method statement had been provided on scaffolding. In relation to demolition, Metronet's letter of 4 September 2008 (7 and a half weeks earlier and not 2 weeks earlier as stated) had made clear that site specific information was required. Despite this, no attempt had been made to obtain scaffolding or demolition quotes until shortly before this e-mail was written.'
'On 4th November 2008, LM stated in an e-mail copied to [SC] that: 'Bob [Warwick] will be able to appoint a Demolition Contractor and we can then ask for a MS and RA for the project to obtain LUL sign off for the project. Bob reported that the Party Wall Award had been sent out and we were not aware of this as we believe the Award had to [have] LUL approval for the party wall awards to be put in place; therefore Mr Birchall will have to carry out this service again"… There was no basis on which LM could honestly have believed the statements being made. LM knew that the appointment of a scaffolding sub-contractor as well as a demolition sub-contractor was necessary so that a method statement and risk assessment could be obtained from both sets of sub-contractors. LM was also well aware that the demolition Party Wall Award had been signed in August 2007, since Mr Birchall had informed her of this in his e-mail of 19 November 2007."
Dishonest assistance
Conclusion
Note 1 Comprised in (i) a design and build Contract between MCD and SC/SV dated 5.7.06 and (ii) a ‘Novation Agreement’ of the same date between MCD, SC/SV and DPIL. [Back] Note 2 More accurately, this means contributions made by SC/SV/expenditure incurred by MCD prior to the 5.7.06 novated contract, i.e. pursuant to the 2002 Agreement. However for convenience the expression will continue to be used. [Back]