QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ALSTOM POWER LIMITED |
Claimant |
|
- and - |
||
SOMI IMPIANTI S.R.L. |
Defendant |
____________________
The Defendant did not appear and was not represented
Hearing date: 21 December 2011
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Background and the Contract
"All Subcontractor's Equipment... and materials…. shall, when brought on to the Site, be deemed to be exclusively intended for the execution of the Works and the Subcontractor shall not remove the same or any part thereof, except for the purpose of moving it from one part of the Site to another, without the written consent of the Contractor".
The term "Subcontractor's Equipment" is defined by Clause 1.1 of the General Conditions of the Subcontract as meaning "all appliances and things of whatsoever nature, other than Temporary Works, required for the execution and completion of the Works excluding Plant, materials or other things intended to form or forming part of the Permanent Works".
"All Subcontractor's Equipment... and materials owned, leased or hired by the Subcontractor or any of its subcontractors, shall, when on the Site, be deemed to be the property of the Contractor".
Clause 54.9 deals with the vesting of goods and materials, to the effect that:
"Goods and materials to be supplied pursuant to the Subcontract shall become the property of the Contractor at whichever is the earlier of the following times: (i) when goods and materials are delivered to Site, or (ii) when the Subcontractor becomes entitled to payment of the value of the goods and materials".
Clause 54.14 deals with what is to happen when the employment of the Subcontractor ceases for any reason before the completion of the works, and it states that in those circumstances:
"…the Subcontractor shall deliver to the Contractor any goods and materials the property in which has vested in the Contractor. If it shall fail to do so, the Contractor may enter any premises of the Subcontractor or of any subcontractor and remove such goods and materials and recover the cost of so doing from the Subcontractor".
"If the Contractor takes possession of the Subcontractor's work under Sub-Clause 63.1, the Contractor may either by itself or by another contractor complete that work and the Contractor may without payment of compensation take possession of: (a) such of the Subcontractor's Equipment and Temporary Works and other things on or in the vicinity of the Site as are owned by the Subcontractor; and (b) the Subcontractor Provided Drawings and other documents, information and materials and the like produced by the Subcontractor".
"Subcontractor Provided Drawings" are also defined in Clause 1.1 as meaning "all drawings, calculations and technical information of a like nature provided or to be provided by the Subcontractor".
Findings
Contempt
Costs
Decision