QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
COMMUNITY GATEWAY ASSOCIATION LIMITED |
Claimant |
|
- and - |
||
BEHA WILLIAMS NORMAN LIMITED |
Defendant |
____________________
Andrew Onslow QC, Neil Hext and David Thomas (instructed by Kennedys) for the Defendant
Hearing dates: 30 June and 4-6, 13,14, 18 and 25 July 2011
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Transfer Mechanism
(a) The Options Appraisal. The local housing authority had to conduct an Options Appraisal to determine the appropriate and affordable option to deliver decent homes. This was conducted in consultation with the tenants. Where housing stock transfer was identified as the preferred route to deliver decent homes investment, the exercise would also involve the identification and selection of an appropriate RSL to take ownership of the housing and undertake an investment or regeneration programme. Options Appraisals were signed off by the Government Office for the Regions. Local authorities and their tenants could call on the Community Housing Task Force advisers, employed by the Department to provide support to authorities and tenants. Where transfer was the preferred option the Task Force subsequently worked with authorities, tenants and RSLs to support the development of good quality transfer proposals that would meet the national programme criteria and ultimately, after tenant consultation by the local housing authority and where the majority of tenants were in favour, would merit a recommendation to the Secretary of State that consent be granted. Often, as here, Stock Condition Surveys ("SCS") would be carried out to check on the quality of the housing stock, to recommend repairs and improvements and to provide costings therefor.
(b) Application for a place on the Department's Housing Transfer Disposals Programme. A transfer involving more than 499 properties would be considered a Large Scale Voluntary Transfer ("LSVT"). In the case of an LSVT, the local housing authority would have to obtain a place on the Department's Programme before it could proceed. As part of the process the Department would be required to assess the proposed transfer against all its published criteria. As part of the assessment the Department would also take into account the views of the Housing Corporation's Stock Transfer Registration Unit "STRU", the Government Office in the relevant region and the Task Force. A full application from the local authority would have comprised a transfer proposal summary sheet, other information and a completed Single Transfer Model ("STM"). This information included details of the condition of the stock to be transferred, the repairs and improvements work the new landlord would carry out, as well as an estimate of its costs over 30 years. The STM had to be based on an independent stock condition survey carried out by a surveyor and was described as:
"…an Excel spreadsheet which comprises two models the ODPM uses to assess transfer proposal:
? The Cost Generation Model (CGM);
? The Pricing, Rents and Public Sector Net Borrowing (PSNB) Effects Model.
The CGM provides a means of bringing together information, drawn from a recent stock condition survey on the housing an authority is proposing to transfer. This includes the repair and improvement work that needs to be carried out and the estimated cost over 30 years. As well as helping the authority and the prospective new landlord put together a proposed repair and improvement programme, the CGM generates the expenditure figures that feed into the Pricing Model to calculate the value of the housing. …
The PSNB effects model calculates the long-term public expenditure effect of a proposed transfer in terms of its impact on the public sector borrowing requirement. The analysis compares the impact on the PSNB of retention by the authority with that of the transfer".
Following the ODPM assessment of the application and supporting documentation, it would make recommendations to the Secretary of State as to whether the local authority should be given a place on the Disposals Programme, or have a place held open whilst it carried out more work. Once the Secretary of State had made his decision, the Department informed the local housing authority and, where the decision was positive, issued a Direction placing them on the Disposals Programme. A place on the LSVT Disposals Programme signified the Department's agreement for the local housing authority and its tenants to develop the transfer proposal further, and to proceed to formal consultation. It did not at this stage confer the Secretary of State's consent to the transfer itself (which still had to be obtained).
(c) A formal and statutory consultation process. The local housing authority was then required to consult formally with the tenants and make them an offer in respect of the transfer ("the offer document"). A local housing authority was required under Section 106A of and Schedule 3A to the Housing Act 1985, and as covered in Section 11 of the Housing Transfer Manual, to consult all tenants whose homes would be transferred. An authority would be obliged to follow the ODPM good practice guidance in drawing up its consultation material and share drafts of the consultation document with others. Whilst not a legal requirement, it was usual for a ballot of tenants to be undertaken based on the offer document. Transfer would not be permitted to go ahead if the majority of tenants who voted were opposed to it.
(d) Transfer. Provided the majority of tenants were not opposed, the local authority could proceed to transfer. The transfer would be to a housing association, which would need to be registered with the Housing Corporation as an RSL. A transfer contract governing the sale of the stock and the relationship between the local housing authority and the RSL would also need to be drawn up. This would be a legally binding record of all agreements entered into between the local authority and the RSL. It would include an obligation on the RSL to abide by the promises made to the tenants in the offer document. The local housing authority would be obliged to submit a formal application (together with supporting information) to obtain the Secretary of State's Consent to transfer, before the contract could be completed and signed. Approval would only be given if the criteria at paragraph 17.2 of the Housing Transfer Manual 2003 had been met; these included the local housing authority's consultation exercise being adequate, that the majority of secure tenants affected by the proposed transfer were not opposed to it, that all houses transferred would meet the decent homes target by 31 December 2010 and that he estimated Exchequer and public expenditure costs represented value for money.
The Witnesses and the Documents
(a) Diane Bellinger: she has been the Chief Executive of the CGA since July 2005, albeit between then and late November 2005 she was employed by the Council. She was Chief Executive Designate from March 2005 to July 2005, albeit that she was still employed by her previous employers at East Manchester Housing Association. She has been in social housing since 1991. I formed the view that she was open, honest, enthusiastic and dedicated to what CGA stands for, in particular its commitment to tenant involvement. Some parts of her witness statement related to the period before she became involved and some relate to matters which are not the subject matter of complaint in these proceedings; for instance, she could give no useful evidence about what was promised to the tenants. It was surprising (albeit not her fault) that she seems to have been wholly unaware of the contents or even existence of Draft 1; she insisted, commendably, that promises to the tenants made in the period up to the Transfer should be honoured and, yet, she did not know and no-one within CGA told her that there was a list of detailed promises outside of the Offer. Either no-one within CGA knew of this list or they did know but did not tell her this or the list was not intended to record promises or work which was always intended to be carried out. Much of her witness statement broadly corroborates contemporaneous documents. However, her evidence, such as it was, about promises made to tenants not being kept is inconsistent with what was reported to the Board; she emphasised how important it was that promises to tenants were honoured and, yet, there is no minute in any Board Meeting or in any report to the Board that promises were not kept. It may of course be that this litigation is driven by other factors or indeed people.
(b) Paul Roberts: he is currently the Head of Business Improvement at CGA but had worked at the Council since 1990 primarily in the housing department in a management capacity. He was put in charge of a housing maintenance task force in early 2003 as Head of Corporate Performance. In December 2003 he was seconded onto the Council's Gateway team led by Mr Deacon whose job was to manage the transfer. Much of his written evidence was given by reference to contemporaneous documents and was in that context unexceptionable. Again, I found this witness to be broadly honest. However, there appeared to be a concerted effort by him to row away from the ramifications of his written evidence (Paragraph 71 of his statement) in effect that the improvements programme (which he had been involved with producing in 2005) reflected the consultation with CGA members and tenants since 2003 and had been "prioritised to what the tenants wanted where and when". This occurred because he seemed to be unable to remember in cross-examination what was involved in the programming work. It seemed clear to me that he had begun to appreciate that the way in which the programmes had been prepared and costed bore no relationship to the basis of the claim now advanced by CGA which is that no allowances were made in the budgets or indeed programmes for what CGA now say was promised to the tenants.
(c) Dennis Graham: he had worked for the Council from 1990 onwards and by 2003 was the Central Maintenance Unit Manager in relation to housing. He was, so the documents reveal, closely involved with maintenance programmes for the Council's housing stock before the Transfer to CGA as well as the creation and costing of programmes for the first five years and beyond in relation to CGA in the period leading up to the Transfer. He produced Draft 1 and was involved in regular meetings with tenant representatives before and after. I formed a somewhat poor impression of Mr Graham; although I do not consider that he was dishonest, I very strongly felt from the way that he gave his evidence that his memory was selective and there was some unreliable and after the event subconscious reconstruction of events. Some of his oral evidence bore little logical relationship with his witness statements. For instance, his first statement (Paragraph 21) suggests that he produced only one draft, Draft 1; there was no hint that there were other drafts or that Draft 1 represented some sort of final draft. In evidence, he suggested (Day 4, page 25) that Draft 1 was a first draft and there were a number of other drafts, the final one of which would have been saved by Karen Perry. It was slightly unclear from this exchange whether he was saying that all the versions of the draft were named as Draft 1 with the final one also called Draft 1 being the one saved by Karen Perry. He also said unconvincingly that Draft 1 was agreed by the Preston Homes Standard Group and the Capital Working Group, although there is not one verbal hint in any of the minutes or in any document that this occurred; if anything the minutes record that Mr Graham had not yet produced any draft before July 2004. He suggested that Draft 1 was a result of four months work with numerous tenants, Council employees, contracted staff and external agencies; that is belied by the minutes which, although they do record consultations and meetings, record no or virtually no agreements or promises at least in relation to the items of work which CGA now says were promised to the tenants or otherwise intended to be done. His oral evidence, not mentioned in his three witness statements, that he circulated Draft 1 to tenants, Council personnel, committee members or anyone else other than Ms Perry, and that he had "handed over" Draft 1 to the Gateway Team was not credible and was seriously undermined by the absence of any documentary record of it and the absence of any supportive evidence on this point from Mr Roberts and Ms Perry. His evidence that Draft 1 was "a collation of the work of others" (Day 3 Page 94) was belied and undermined by the absence of any supportive documentation and by the fact that he alone was tasked by the relevant committee with producing the document. His evidence both in writing and orally in relation to his involvement in 2005 up to the transfer in the programming and costing of the first five years post-transfer work was unconvincing. In spite of his written evidence that the programming work was to "cover a 5 year period post-transfer to meet the promises which had been made to tenants", he said, for instance, orally that he programmed and costed only the work required for the Decent Homes Standard; that is simply not credible as it would have been a complete waste of time, as he must have known. He had been the author of Draft 1 and therefore can not have believed that it necessarily or at all set out what might be described as work promised to the tenants. Irrespective of Draft 1, it would have been pointless programming and costing work to the Decent Homes Standard because he must have known, due to his earlier involvement, that the SCS surveys provided for works above the Decent Homes Standard, at least to the so-called industry standard. I can only and do assume that at least subconsciously Mr Graham had begun to appreciate before and when giving evidence that the minutes and other records in 2004 and the programmes and costings in 2005 with which he was associated were wholly inconsistent with Draft 1 recording promises made to tenants. Even Counsel for CGA had to accept that he was muddled and confused and, by way of masterly understatement, that he "was not the most impressive witness".
(d) Bill Shannon: he is a Liberal Democrat nominee on the CGA Board and a Council member for one of the wards in which some of the worst affected housing was located. He spent many years working for the Cooperative Group until retirement in 2002. Through his interest in the Community Gateway approach, he became a member of the CGA Shadow Board in mid-2004. I found him to be a particularly good witness, straightforward and honest. He clearly knew nothing about Draft 1 and he made clear that the tenants in his ward were very content with the work that had been done by CGA to the houses.
(e) Nigel Wilson: he is an independent non-executive Board director of CGA and has been from the Transfer; he was an independent member of the Shadow Board of CGA between mid-2004 and November 2005. He gave the impression that he was pragmatic, for instance in saying that one had to balance the demands of tenants against the available resources. He is clearly a decent and committed person and was an honest witness. Apart from what was in the Offer document, he clearly did not know about any or much of the detail of the work which was to be required to be done. I say that not in any way as a criticism.
(f) Andrew Upton: he is a non-executive director of CGA, having previously been appointed as an independent member of the Shadow Board in July 2004. He underlined that tenant involvement "was the vein running through the Transfer". He gave his evidence in an honest and straightforward way.
(g) Karen Perry: her witness statement went in as evidence because she was not required for cross-examination. It is difficult to form any view in her absence as to her competence and abilities. Most of her witness statement contains either general observations or evidence based on contemporaneous documents. Surprisingly, given her extensive housing experience with the Council, her detailed involvement with the Council's Gateway Transfer Team and her continued employment after the Transfer with CGA (she is now the Head of Community Empowerment), she says nothing about Draft 1 or indeed anything of relevance about any of the works which are the subject matter of these proceedings.
The Detailed History
(a) It had to meet the current statutory minimum standard for housing; this was effectively a negative standard.
(b) It had to be in "a reasonable state of repair". Dwellings which did not meet this criterion were those in which either "one or more key building components were old and, because of their condition needed replacing or major repair or two or more of other building components were old and because of their condition needed replacement or major repair.
(c) It had to have "reasonably modern facilities and services". Dwellings which failed to meet the criterion were those which lacked three or more of the following:
"- a reasonably modern kitchen (20 years old or less);
- a kitchen with adequate space layout;
- a reasonably modern bathroom (30 years old or less);
- an appropriately located bathroom and WC;
- adequate insulation against external noise (where external noise problem);
- adequate size and layout of common areas for blocks of flats."
(d) Finally it had to provide "a reasonable degree of thermal comfort"
The Decent Homes Standard was expressed to be a minimum standard but it was a standard that triggered action rather than set a standard to which work was to be carried out.
"Install double glazing windows
Install full gas central heating
Upgrade partial heating to full
Upgrade roof insulation
Install smoke detectors
Kitchen re-planning
Bathroom re-planning
Install mechanical extract fans
Security
Installation of entry phone systems for flats
Car parking
Solid wall Insulation
Environmental Improvements"
"(a) To produce the Preston Homes Standard that should apply to all properties and to
(b) Develop that standard to more detailed proposals about standards of fitments and design features taking into account costs and future repair."
This strongly suggests that, as happened, the intention was to produce a high level Standard and also to develop more detailed proposals about standards.
"The Group discussed what the standard should include (see notes attached) and Marlene is to produce a more concise version of the standard (see attached) in a draft format, to be circulated with the minutes. All Members agreed to check this for omissions and to respond to Marlene with amendments by 18th March 2004."
The attached notes summarise briefly the headings of the Decent Homes Standard, adding: "But we want better!" The notes went on setting out some general heads like "Structurally Safe-Smoke Alarms", "Insulation/Energy Efficient-Ventilation", "reasonably aesthetically pleasing to tenants", "Wiring-Sufficient to meet 21st Century Standards", "Bathrooms…Includes security aspects as appropriate-window locks, lighting, door alarms, identislot, magic eye…" and "Safety-exit in case of fire". There were two lists of "what do we want from" windows and doors. Windows would be required to be PVCU, double glazed, to be lockable and provide a fire exit as well as adequate vents. For the doors security was to be by "5 lever locks etc" and "identislots". An identislot is a domestic security device that allows householders to check callers' identification with an electronic card, before letting them in. Neither the minutes nor the evidence reveal the basis upon which the contents of these notes emerged other than they were discussed. For instance it is not minuted that these items of work were all agreed to or that the Council representatives in any way promised that these works would be done. It is also not clear whether the tenant representatives or others were simply tabling possible ideas or were in any way, representatively on behalf of other tenants or not, insisting on all or any of the items of work. The minutes record that there were detailed discussions about windows and doors.
"Preston Homes Standard Group. Scoped what tenants wanted for a standard which will be higher than [Decent Homes Standard] for [Community Gateway Model] proposals. [Preston Homes Standard] went to Task force on 18/3/4 and was accepted in principle. [D Graham] to expand on the 12 issues in the PHS. The group looked at standard of fittings eg doors, windows, boilers and the group will also need to consider future maintenance requirements."
It is reasonably inferable that the 12 bullet point standard document (see below) had been drafted by this stage.
(a) Paragraph 3 records that there was a fire safety presentation and concludes:
"All window designs for the PHS will comply with the standard determined by BS7950 as a minimum and will incorporate any requirements were possible for Secured By Design.
3.1 TC outlined the agreement:-
All downstairs windows are able to have key operated window locks provided not an inner room situation.
All 1st floor rooms should have at least 1 window that is a fire escape window and not obstructed with locks. These windows may have laminated glass fitted. If more than 1 window in a room then one of those windows can be fitted with a lock…"
Paragraph 4 records a Question and Answer session on fire safety.
(b) There was a discussion of "PHS Doors" recorded at Paragraph 5. It seems that nine door types were displayed with a range of door patterns said to be available made in a variety of different materials. There was a discussion and question and answer session, at the end of which the group voted for their top three choices.
(c) Paragraph 6 refers to a display of windows, currently in use or which had been used on recent housing schemes to designs and specifications previously agreed. It appears that there was a discussion but there was no final agreement. There was to be a discussion later about costs and specifications.
(d) Paragraph 7 records a discussion on heating and ventilation. Two gas condensing boiler types were discussed and Mr Fullalove of Nu-Aire said that with a "Nu-Aire drymaster there would be no need to open windows/fit trickle vents". Typical costs were identified ranging between £2600 for a flat on a first or ground floor to £3000 for a house. Although Mr Daynes of Emcor Drake and Scull strongly recommended a particular boiler, no agreement was recorded. It was said however that the next meeting would be arranged "once the heating & Window specifications have been confirmed".
"Dwellings and communal areas (when appropriate) should
1) Be free from structural defects that affect the soundness, safety and stability of the dwelling
2) Provide an effective barrier to the elements and normal patterns of weather with no penetrating or rising dampness
3) Provide affordable warmth through programmable, efficient heating and hot water systems, together with adequate ventilation.
4) Have a safe electrical installation conforming to the current IEE requirements with adequate provision of power outlets and lighting points
5) Provide an effective means of escape in case of fire and be resistant to the spread of fire, have appropriate fire detection and alarm systems fitted
6) Provide sanitary fittings with bathing and/or shower facilities together with hygienic services, a clean supply of drinking water and a satisfactory drainage system
7) Provide security measures to deter crime, both in the fabric of the property and in the surrounding environment
8) Provide an aesthetic appearance and design features to satisfy Tenants requirements
9) Provide rooms for sleeping that is separate from other habitable rooms to fulfil current and new Tenants' aspirations
10) Take into account people's disabilities in terms of design and access
11) Provide modern kitchen with satisfactory cupboard/storage space, worktop areas and hygienic services, with accommodation for a range of white goods wherever possible.
12) Wherever reasonable to provide in-curtilage garden areas with approach paths, parking, clothes drying, fencing and gates appropriate to the dwelling types"
This represents the high-level document which appears to have been drafted at some stage in April 2004 and been discussed. There is no suggestion that this was ever altered.
"…debate about the level of detail which should go in the offer document re improvement work. [Mr Deacon] suggested that it should be basic info plus details of the process of how tenants can be involved in making local decisions. Agreed [Mr Roberts] to ask Savills to look at the stock condition survey & break down work needed into the 10 [Local Community Areas]. PJD/NB/AJ/PR to discuss further."
There is an e-mail dated 14 June 2004 from Savills to Mr Johnson that the breakdown into Local Community Areas was underway.
"It is currently intended that all of these works (in homes that need them) would be carried out within the first five years of the Gateway…
It is currently anticipated that current work being done by [the Council] to examine tenant requirements for improvements will not significantly change the improvements required, but it may clarify the order in which improvements are carried out."
"1. AJ [Mr Johnson] set out the remit for the Group. Looking at specifics within the offer document. Need to ensure that document is 'Gatewayised'.
2. PH [Mr Heath, the Wright Hassall solicitor] advised not to go into great detail within the document. Advice notes & information material should underpin the document but not form part of the formal offer.
3. NB [Mr Bliss] advised the offer document is legally binding on the new landlord and contents feed into business plan.
4. AJ important to focus in the document on what is important to tenants…
6. NB concerned that content of document should reflect Community Gateway…
7. PH said it was important for Communications consultant [N Winn of Bridge & Co] to be involved in leading in writing the document.
11. GG advised that tenants needed to be involved via workshops.
12. GG said it was important that offer document is simple for all to understand. Also it shouldn't constrain future local decisions on how money should be spent.
13. AJ advised offer should have some specifics to make it attractive but not enough to tie up all the funding.
14. GG advised it should say in the offer that there is money for local choice…
16. Re improvement group AJ to take info from stock condition survey and produce discussion document re work needed at City wide level…
19. KP [Karen Perry] said important to link work with tenants on improvements to work already done with tenant reps on Preston Homes Standard (PHS)/partnering etc. KP to send list of names to NB and copy of PHS to all…
21. AJ to lead the improvement working group. First meeting to be arranged for PM on 15/7/04. AJ to produce short pre meeting discussion note…"
"1. Introduction
1.1 PR explained that the group had been set up to look at the content of the improvements section of the offer document.
1.2 KP outlined the work already done by several members of the group in putting partnering arrangements into place and drawing up the Preston Homes Standard.
1.3 CW [a tenant] explained more about partnering and gave an update on progress.
2. Offer Document
2.1 AJ explained what an offer document is & showed the group some examples of offer documents from other stock transfers.
2.2 AJ outlined that this group would be looking at what specific guarantees should be given to tenants in respect of investment in the condition of the stock.
3. Development of the Offer to Tenants
3.1 AJ presented a paper giving background material for discussion.
3.2 KS [a tenant] asked if there was enough money in the business plan to deliver Preston Homes Standard & not just Decent Homes Standard (DHS). AJ said the stock survey had been done to an aspirational standard & there was more money in the plan than needed to deliver DHS.
3.3 KS asked is there also money to pay for upgrades to previous improvements. CW thought surveyor had said this was covered by the AJ will check.
3.4 Discussion followed re level of detail needed in the offer document. AJ said offer document would need to give 'headline' information. NB agreed - too much detail at this stage would tie the Gateway Association to the figures & reduce future local flexibility. CW said promise should be that each area would get something at the start of the works programme.
4. Priority of Work
4.1 Discussion followed re priority of work.
4.2 P H-S [a tenant] said it was also important to have guarantees re quality. CW said some people at this meeting had already looked at this when drawing up the Preston Homes Standard & selecting good quality standards for doors and windows. PR said plan was to have a show trailer so people can see examples of the quality of e.g. doors/windows/[kitchen] units etc that Gateway could afford to fit.
4.3 BS [a tenant] said that re priorities it was important to concentrate on doing work to make properties wind & watertight first plus central heating should be fitted. There was general agreement to this…
4.5 NB said it was important to remember that everything couldn't be done in year 1…
7…AJ to produce a draft for offer document."
"Given the huge shortfall in resources it is difficult to be precise on exactly which parts of the investment programme would actually be carried out.
The offer document could however guarantee that the full investment programme of £… million would be carried out by the new landlord and that this is approximately £50 million more than the Council could afford.
Specific Guarantees
It is usual for the offer document to include specific guarantees in respect of individual components within the programme. The attached spreadsheet shows the number of replacement components for key elements covered by the survey, (e.g. the offer could gurantee that 5100 kitchens and 5100 bathrooms would be replaced in the first five years) In other areas it would be possible to gurantee a specified level of expenditure over the first 5 years (e.g. £3.6 million would be allocated to local communities for expenditure on environmental improvements of their own choosing).
Options for the Offer
Whilst the stock condition survey is based on a number of key assumptions there would be some flexibility to vary priorities if this would best meet tenant aspirations. For example it would be possible to bring forward some elements of expenditure provided that it would be acceptable to defer other elements of expenditure.
Therefore a key role of the Working Group will be to establish what are the most important elements of the investment programme from the tenants' perspective and how these can be addressed in the formal offer."
The attached spreadsheet identified that the analysis of the SCS showed that, in relation to "catch up/major repairs", £13.4 million could be spent on 5,100 replacement kitchens, £7.7 million on 5,100 replacement bathrooms, £4.7 million spent on heating works, £3.4 million on electrics for 2,500 properties, £2.2 million on external doors for 4400 properties and £11.2 million on double glazing to 3,500 properties amongst other expenditure. For improvements, for instance £11.2 million could be spent on double glazing to 3,500 properties, £1.9 million for providing full central heating to 1,000 properties and £4.5 million on upgrading central heating in 2,500 properties; £1.3 million could be spent on extractor fans for all properties.
"PRESTON HOMES STANDARD
Dwellings and communal areas (when appropriate) should be:-
Not the 12 disciples BUT the 12 disciplines!!
All the standards will comply with the appropriate BSI
Component/Location | Standard |
Free from structural defect that affects the soundness safety and stability of the dwelling |
Exterior walls of the dwelling must be in good condition to withstand the effects of weather. Air bricks for the purposes of ventilation to be clear to allow for flow of air… All curtain wall tiles to be securely fixed. All windows to be PVCU double glazed kite marked to secured by design standard… Windows to be lockable/push button operated… Identified escape in the event of fire. External doors (front/side/rear) to be PVCU/GRP secured by design with requirement for lock replacements if keys lost/stolen. Porches/canopies to shield visitors from weather etc. |
Provide an effective barrier to the elements and normal patterns of weather with no penetrating or rising dampness | All Damp Proof Courses (DPCs) are in good condition at ground floor levels and cavity walls are insulated. Where DPCs are not in situ to be installed. All internal floors are level and free from heave… |
Provide affordable warmth through programmable, efficient heating and hot water systems | All properties to have full house/flat heating with either gas/electric heating All gas heating installations to have a gas condensing boiler installed supplying heat to radiators in every habitable room, and a hot water supply. All radiators to be fitted with TRVs and heating controls/timers that are easy to use and maintain… All gas appliances to be serviced at least once a year or whenever the tenancy changes. Carbon monoxide detectors to be fitted where appropriate (i.e. medical need). Choice of gas fire with matching hearth and timber surround. |
Have a safe electrical installation conforming to BS7671 requirements with adequate provision of power outlets and lighting points. | All electrical work must conform to BS7671 and all materials should conform to BS. Provision for all installations to include the provision for (at a date in the future) wiring for an electrical shower, intruder alarm, security lighting, cooker extractor hood and smoke alarms. All rooms (except bathroom) to have adequate number of wall sockets and lighting switches. Suggested -… Lighting for kitchens? Fluorescent? ... Extractor fans and ventilation systems |
Provide effective means of escape in the case of fire and be resistant to the spread of fire, have fire detection and alarm systems fitted. | Internal doors to be at least half hour fire check, kitchen doors to be fitted with closers? ... Flashing alarms to be fitted for the elderly/disabled Identified windows for fire escape route |
Provide adequate sanitary fittings with bathing and/or shower facilities together with hygienic surfaces, a clean supply of drinking water and a satisfactory drainage system | …A minimum of one separate w/c and combined where space permits… All properties to have a limited choice of colour and matching wall/floor finishes for sanitary fittings. Thermostatically controlled overbath showers to be provided… Towel/drying rail Extractor fan |
Provide security measures to deter crime |
Identislot 5 lever mortice locks to front/external doors 3 lever mortice locks to shed/outhouse doors. Chubb bolts to front door All external doors to comply with secured by design specification and incorporate police recommendations where required for the more vulnerable (i.e. recently burgled). Spy holes/view finders. Sliding bolts to doors… Intruder alarms - PIN numbers amended when tenancies change. PIR security lights. CCTV where required eg sheltered schemes. |
Provide an aesthetic appearance and design features that satisfy tenant requirements | Incorporate provision of disabled adaptations during the course of works A recognised programme of external painting and maintenance… Internal doors which can be stained/varnished. |
To provide rooms for sleeping that are separate from other habitable rooms to fulfil current and new tenant requirements | Legislative guidance for children Separate bedrooms where a child under 10 shares a room with someone over 16, increasing problem for ethnic minority families. Building control/fire regulations to consider |
Take into account peoples disabilities in terms of design and access |
Adaptations to consider progressive nature of disability ie. ramp not required now but may be required at a later date. Adaptations built into overall scheme of works. Occupational Therapy service to fast track assessments for disabled applicants and incorporate into capital schemes of work |
Provide modern kitchens with satisfactory cupboard/storage space, worktop areas and hygienic surfaces with accommodation for a range of white goods wherever possible | Kitchens to be designed in consultation with occupiers using Auto-cad taking into account occupiers white goods… Work surfaces to be continuous and sufficient for use Adequate ventilation to avoid condensation from cooking Extractor hoods above cookers… |
Wherever reasonable to provide in-curtilage garden areas with approach paths, parking, clothes drying, fencing and gates appropriate to the dwelling type | Secure fencing to perimeter of properties with lockable side/front gates… Rotary clothes driers for all properties… Storage sheds for garden tools. Tenant choice improvements e.g. levelling of gardens, infilling of ponds, turfing of gardens, removal of debris. |
"Items needed to make wind and water tight-e.g. external doors double glazing, central heating, insulation…
extractor fans, specifically mentioning condensation issues
improvements relating to security
environmental works
that all homes should have some works done in year one and subsequently on a gradual basis…
the Preston Homes Standard-there was a discussion about inclusion of PHS clauses-translated into better English-it was mooted that there is a particular difficulty about including clauses relating to removal of bedsits. GG suggested the CGA Board could adopt a Gateway Homes Standard with the relevant clause removed. PD to give this further consideration…"
Tenant representation on the Tenant Steering Group had by August 2004 grown to 28 people.
"The costs of repairing, maintaining and improving the housing stock are based on the results of the stock condition survey carried out by, and subsequently updated by, FPD Savills in November 2003"
This was subject to some adjustments such as inflation, an allowance for fees and a reflection of the reduction in the number of properties being transferred.
"extractor fans would be provided to those homes that need them to tackle condensation"
This represents a change from the earlier suggestion that all properties should have an extractor fan.
"£80m in repairs and improvements in the first 5 years with enough £'s in the Business Plan to keep properties at this standard for next 30 years"
A Tenant Steering Group meeting attended by 14 tenants and Mr Bliss took place on 9 August 2004 at which there was a detailed discussion of the Offer document in its then current draft.
"I have made one further amendment to the Offer Document. I have added the words "when needed" in the first bullet point after the title "The Key Benefits of Transfer" (Section 1). It is essential that the document does not offer new kitchens/bathrooms/windows to all tenants as some tenants may recently have had such work carried out and as such these facilities are already 'new'. Without such wording, the RSL may potentially be promising to replace all windows etc where in some cases it may not be needed."
"George congratulated everyone who had been involved in developing a good document. It contains a lot of commitments that are appropriate to set high standards in improvements and tenant involvement…"
"The final selection of the type of kitchens/bathrooms which will be installed by the Gateway Housing Association will be determined by a group of tenants who would like to get involved in the selection process.
Also on display will be a selection of doors and windows which are being fitted on some capital schemes this year."
That event took place and there are some photographs in the Court bundles which show what was displayed. So far as is material to this case, the kitchens did not show extractor fans or extractor hoods and the bathrooms did not show overhead showers. Approximately 300 tenants attended and some of them filled out a survey form which indicated preferences for particular design ranges. There was later to be arranged a smaller mobile exhibition on the back of a lorry which showed a bathroom and kitchen and which toured the areas where the housing to be transferred was located; the lorry trailer went out and about in the week commencing 11 October 2004.
"The cost of repairing, maintaining and improving the housing stock [is] based on the results of the stock condition survey carried out by, and subsequently updated by FPD Savills in November 2003"
The Board was given an update on the door to door consultation: of 1498 completed questionnaires, 1043 tenants were in favour of the transfer proposals. Mr Johnson was to repeat the above in a report to the Community Gateway Subcommittee on 11 November 2004.
"…indicating that the basis for the improvements programme was the stock condition survey that had been carried out, and what had been included in the offer document."
Various issues were raised that bore upon the prioritisation of the works and the minimisation of disruption to tenants. The view was expressed that the work on "wind & water tight issues" should come first.
"3.1 MB introduced a discussion on the improvements programme by suggesting that the overall aim of the programme was to "get the best out of the money that is available, delivering high quality improvements and involving tenants in the decisions about what is to be done and how these improvements should be carried out". The meeting agreed that this was a good definition of the aim of the improvements programme.
3.2 MB went on to discuss information available to inform the programme:
- the stock condition survey (SCS)-DG discussed the SCS. It was carried out on approx 3000 homes out of 6607 homes-a comparatively high percentage of homes surveyed. The SCS has informed the business plan in terms of how much money is needed to improve their homes. About £15 million is needed to bring the approx. 50% of homes that currently failed the Govt's Decent Homes Standard (DHS); and about £15 m is needed to ensure the other homes do not fail DHS in the future. The SCS also carried out an energy efficiency survey. PHS [a tenant] pointed out that there are some cases where previous improvements have not been done satisfactorily, but that the surveyors may not have picked this up.
- the asset management plan…
- the Offer Document-a "contract" with the tenants. The programme has to deliver what the offer document says about improvements
- the Preston Homes Standards Group-a group (that included tenants) that has defined some standards of improvements-most notably on doors and windows.
DG outlined that key issues regarding windows had been security, fire safety, lockability (using pushbuttons), being police approved….
- consultation at PNE [Preston North End] event-September 2004-where tenants were invited to view various potential improvements (kitchens, bathrooms, doors, windows etc). MB indicated that most people had been reasonably happy with the proposed level of improvements, but there had been some concerns on windows…PHS indicated that people have been particularly happy with the quality of door on offer…"
The meeting went on to discuss the programming of the improvements work. It would be fair to say that what was broadly resolved was that tenants would be involved and that the homes would be divided into their local community areas.
"The Preston Community Gateway Tenant Steering Group was formed to represent the views of Preston tenants on the proposals to transfer their homes to the new Community Gateway Association…
The Tenant Steering Group committee has been a leading player in the development of the offer document…
Having reviewed this offer, we believe that it is a good one… (page 2)
The housing transfer proposals
Key points:
- The Council cannot afford the amount of money that it needs to spend on tenants' homes
- The new Association would be able to spend £80 million on tenants' homes over the first five years but the Council can only afford to spend £22 million
- The Council believes that the only way to proceed is to transfer the homes to a new organisation-the new Community Gateway Association
- The new Association would make a firm promise to involve tenants in the running of the new organisation
- The improvement programme will only go ahead if tenants vote yes to transfer. (page 7)
4. Improvements and repairs
Key points:
- The Community Gateway Association would be able to spend £80 million on improvement work across the first five years; this compares to £22 million if the homes stay with the Council
- Homes will be brought up to the new 'Gateway Standard', making sure that all homes were fit for modern day living
- There would be massive programme of works including new kitchens, bathrooms, central heating and double glazing
- There would be a new role for tenants in influencing the improvement programme and making choices... (page 21)
1. How much work needs to be done?
Over the past five years the Council has carried out stock condition surveys, using independent qualified surveyors, to see what state of repair the homes are in and what work needs to be done. Almost five out of every 10 homes has been surveyed…
The stock condition surveys have shown that much more money needs to be spent to bring the homes up to modern day standards. The money required is far more than the Council is able to spend on the homes, as shown in the table below:
Time | Community Gateway | Preston City Council |
Years 1-5 | £80 million | £22 million |
Years 1-10 | £106 million | information not available |
30 years | £296 million | information not available |
Under the Council, it is not possible to say how much would be available to spend on the homes after the first five years. The amount the Community Gateway Association would have available is based on how much money the stock condition surveys have said is needed to bring the homes and environment up to a modern day standard.
2. What standards would apply under the Community Gateway Association?
The Government has said that all homes in the country should reach what it has called the 'Decent Homes Standard' by 2010. However, this is a minimum standard. The Community Gateway Association and tenant representatives have therefore worked together to define a higher 'Gateway Homes Standard' that fully reflects what most people would think should be in a 21st century home. The 'Gateway Homes Standard' is the equivalent to a modern day standard and is the standard to be pursued by the new Community Gateway Association.
The Gateway Homes Standard
Homes should:
1. Not have structural defects that affect their soundness, safety and stability.
2. Be wind and water tight, with no damp problems
3. Be easy and affordable to heat, with programmable and efficient heating and hot water systems, and be adequately ventilated to prevent condensation
4. Have electrical systems that conform to current accepted safety standards with adequate provision of plug sockets and light fittings
5. Have an effective means of escape in case of fire and be resistant to the spread of fire, with appropriate fire detection and alarm systems fitted
6. Have adequate sanitary fittings with bathing and/or shower facilities together with hygienic services, a clean supply of drinking water and a satisfactory drainage system
7. Have security measures to deter crime, both in the home and in the surrounding area
8. Look pleasing to the eye and have design features that satisfy tenants requirements
9. Take into account people's disabilities in terms of design and access
10. Have a modern kitchen with satisfactory cupboard/storage space, worktop areas and hygienic surfaces, with space for a range of white goods (eg. washing machine, fridge and freezer, cooker) wherever possible
11. Have garden areas appropriate to the type of home, with satisfactory approach paths, parking, clothes drying areas, fencing and gates.
The Community Gateway Association would aim to ensure that all homes reached the 'Gateway Homes Standard' if tenants vote for the transfer. This would also mean that all the homes would have reached and surpassed the Government's 'Decent Homes Standard' by 2010.
The stock condition survey has shown that £80 million would need to be spent over the first five years to bring their homes up to the 'Gateway Homes Standard' and at £57 million of this would be needed to reach the Government's 'Decent Homes Standard'..
3. What improvements would actually be done?
The following work would be done during the first five years after transfer:
- All homes would be made wind and watertight, with cost effective heating and insulation:
- 4,400 homes would have new external doors
- 2,000 homes would have new double glazed windows
- 500 homes would have new full central heating
- 1,500 homes would be upgraded to full central heating
- £5 million will be spent on roof repairs and replacements
- Roofing and the other installation would be provided and upgraded in many homes
- Improved ventilation would be provided to those homes that need it to tackle condensation
- The BISF steelhouses would be cladded to increase their warmth and installation.
- 5,100 homes would have replacement kitchens
- 5,100 homes would have replacement bathrooms
- 2,500 homes would have new electrics
- Various security improvements would be carried out (including £2 million to be spent on fences, walls and paths)
- £3.5 million would be spent on improvements to the environment around the homes.
Over the course of the 30 year business plan, all homes would have the above improvements, where needed. Funds will also be available for adaptations for people with disabilities.
4. When would improvements be carried out?
The Community Gateway Association would aim to ensure that all homes would have some work done in the first two years after transfer to ensure that everyone would share in the benefits of the transfer. Subsequently, the works would be carried out on a gradual basis, until all of the above commitments were met. The Community Gateway Association would particularly prioritise works needed to make homes wind and watertight… (pages 22-24)
11. Housing services for older people
Key points:
- Covers sheltered housing services which are provided to about 500 tenants and another 500 tenants linked to mobile wardens…
- Annual budget of £250,000 for adaptation work to homes occupied by people with disabilities…
What is the Community Gateway Association's commitment to people who live in sheltered housing?
…the Community Gateway Association would:
- …..
- Set aside a budget of £250,000 each year to ensure that adaptations are completed for people with disabilities…" (pages 52-3)
It was a substantial document running to 87 pages.
"In fact, I have never known the ODPM to be so hands off in the transfer process-I am used to the [Task Force] trawling through every single piece of literature and changing words line by line-I think this is in no small part due to my involvement-I think they know that I won't let anything past that the tenants would be unhappy with."
"Established the Preston Homes Standard Group whose membership included tenants, partners, officers (Housing and Community Safety), Police and Fire Safety Service. This Group has established the overall standard of the homes in Preston, and also developed a new specification for PVCU windows and doors."
"How business plan numbers are derived
- Figures from stock survey
- Plus fees allowance (8%)
- Plus VAT (17.5%)
- Above adjusted for VAT shelter (-4.5%)
- Adjusted for actual stock numbers
- Adjusted for inflation and growth in prices"
Under another heading "Other Issues", the following appeared:
"SCS set parameters
Programmes to be prepared within parameters…"
"…The CGA considered that burglar alarms should only be provided to vulnerable people, or to all the homes in particular area [sic] that have been identified as having particular problems. They should not be provided as a matter of course to anyone accepting a new home…"
The marketing strategy being commented on was dated 3 March 2005 and referred to there being "welcome packs for" the new tenants:
"A welcome pack, consisting of kitchen cleaning items, is given to all new tenants from Smart Move. The CGA would consider giving items such as white goods or burglar alarms as an incentive for people to accept properties in areas of low demand."
This was all considered at a Community Gateway Association Operations Working Group meeting on 17 March 2005, with a number of tenant members present.
"The costs of repairing, maintaining and improving the housing stock are based on the results of the stock condition survey carried out by, and subsequently updated by, FPD Savills in November 2003."
The attached "Valuation/Business plan assumptions" document identifies similar figures for repairs, improvements and maintenance as previously put forward, explaining them with a note:
"These figures are based on the stock condition survey figures (industry-standard) based on November 2003 stock numbers and prices."
At Paragraph 10 of the report, BWNL wrote:
"It is essential that the Association adopts a business plan that is based on realistic assumptions and demonstrates that the Association can operate viably while providing high quality services and honouring the promises that have been made to tenants."
This report was submitted on 15 April 2005 to the Community Gateway Shadow Board.
"Priority1-external features to buildings that would make homes wind and water tight was seen by all groups to be the most important priority. In particular, the following was seen as high priority by most groups:
- windows
- external doors
- external communal doors
- rainwater goods (e.g. guttering, fascias, soffits)
- roofs and chimneys
- roof and cavity wall insulation
- damp proofing
External wall finishes, external wooden items, balconies and soil vent pipes were also seen as important priorities probably because they could be done alongside some of the other works listed above. Health and safety items such as security lighting, smoke detectors and carbon monoxide detectors were seen by some groups as high priority
Other elements suggested as high priority by only some groups included:
- internal communal doors…
- central heating and partial central heating
- kitchens and bathrooms…
- re-wiring
- extractor fans…"
"stock condition survey
partnering with construction firms
set up local scheme panels
an asset management plan
tenant involvement in setting priorities
tenant involvement in specifying doors & windows
tenant consultation on kitchens & bathrooms
training sessions & site visits by Tenant Steering Group"
"Although the total provision in the Business Plan will be sufficient to carry out all the promised improvement work the cost of the actual work for individual improvements carried out may differ from that currently estimated (some may be higher and some lower)."
"STOCK SURVEY
- three separate surveys by FPD Savills…
- total numbers of stock surveyed now over 50%
- from the merged results of all surveys, whole stock reports can be produced…
- costs in the database are current actual costs
THE PROGRAMME
- The programme covers the first 5 years after transfer of October 2005-October 2010…
- It reflects members' priorities agreed in September 2003 and reconfirmed and further elaborated on at the Member Event on 22 April 2005
- All properties to have some work carried out to them within 2 years of transfer…
BUSINESS PLAN
- The programme is based on the latest version of the BP and cash flow projections. The total provision in the BP will be sufficient to carry out all the promised improvement work
- The money available to spend on improvements each year is limited to the total amount included in the BP for improvements for that year…
PROMISES
- Totals of improvements equal those in the offer document…
ELEMENTS OF WORK
- The programme groups improvements under headings that contain the detailed elements reported in the stock condition survey database
- Windows & doors-installation of PVCU double glazed windows and replacement of at least one external door
- External Doors-installation of one or more external doors (for properties that do not require new PVCU windows)
- Gas central heating-replacement of existing heating systems for Health & safety reasons, installing heating for the first time, upgrading partial heating to full or replacement of a gas heating boiler. Insulation and ventilation works are also included where required
- Roofs…
- Rainwater goods…
- Kitchens-replacement of kitchens to the Gateway Homes Standard (not like for like), incorporating…smoke alarms
- Bathrooms-replacement of existing sanitary fittings, improved layout, wiring for showers, ventilation and wall/floor finishes.
- Estate works…
- Sheltered accommodation Communal areas…
- BISF houses…
- Security works- e.g. security lights, fencing/gates, burglar alarms etc. to improve security/safety of properties/occupiers
- Curtain walls…"
This was a document which was intended to be looked at again because in his covering e-mail Mr Roberts said that it probably needed "another coat of looking at". There were some supporting notes which emphasised amongst other things that the costs in the database were "current actual costs for works being carried out and not Schedule costs used in the initial surveys in 2001 etc." These notes were prepared by Mr Graham.
"Difficulties on this and other unknowns, like IT and accommodation fit, making completion of financial projections a moving target. VAT shelter and additional gap funding looking increasingly necessary to deliver all the planned benefits of transfer."
Mr Johnson was charged with using his "best endeavours to get a credible Business Plan ready for Housing Corp." A Shadow Board meeting was held on the same date attended by the same people together with a number of tenant and independent board members which discussed these matters also. It seems likely that they had a report entitled "Organisational Assessment of Preston City Works" dated May 2005 which indicated on its ninth page that the forecasted year end total turnover on housing maintenance included the sum of £360,000 for "disabled adaptations". Mr Bliss also submitted a report entitled "Community Empowerment Strategy Progress" which incorporated as an appendix Mr Robert's Note of the CGA membership meeting held on 22 April 2005, originally dated 23 May 2005 (see above); he said that "the output from the meeting showed few surprises".
"…we were guilty of underestimating the CGA's management costs. This is linked with the number of changes that are outside the control of the CGA has resulted in a need for a very large increase in the need for Gap funding."
BWNL submitted a report dated 9 August 2005 to the Finance Working Group which indicated that the additional gap funding required was over £25 million. This was discussed at the group meeting on that date and it was confirmed that there would be a meeting with the ODPM.
"Our primary duty must be to keep the promises made to tenants and on which they base their decision to support transfer. That means that, from Day One, the Association's business plan needs to be robust and capable of delivering all of those promises."
On the same day, Council staff were briefed that the reasons were the need to allow for inflation, additional staffing, IT costs and allowances for voids and bad debt levels.
"I thank you for spending time with colleagues last month …when they came to see you, Sally and John about the financial difficulties that we were and still are, unfortunately, facing in relation to our stock transfer here in Preston.
…we have very reluctantly delayed the date of transfer from 10th October to 28th of November 2005. None-the-less, we are still committed to ensuring that this stock transfer goes ahead…
I can confirm that following a consultation with Tenants, the Board of Community Gateway Association have agreed to seek charitable status and arrangements are now well in hand to achieve this. On the other financial projection issues, over the last four weeks we have been assembling information regarding the items that we discussed. Our discussions with Community Gateway Association have been robust and searching…We believe that we have reached a "bottom line position" that will ensure that Community Gateway Association is able to run its business and deliver the promises made and we feel that the proposal that we are presenting to you represents the most realistic, economical and balanced way forward.
However, we do require further assistance from you, the Government and, in particular, the Housing Minister, if we are to realise our ambitions for the future. To ensure that Community Gateway Association is a financially viable organisation we would request that the amount of Gap Funding be increased from £31,291,882 by an additional amount of £16,706,874. We (the Council) and our Advisers are satisfied that this amount is needed and the justification is contained within the attached report.
We have also submitted a new Single Transfer Model and Cost Generation Model and would very much appreciate your assistance and advice…"
"There may also be replacement of some porches or canopies…"
"Ian [Lucas] introduced his report…He explained that in constructing the five-year programme he had looked to make it streamlined so as to achieve greater value for money. In this way the CGA would be able to carry out more and better improvements to the properties, with less disruption to tenants. However, he was keen to point out to the Board that such a streamlined programme would mean that he would not be able to guarantee that the CGA would be able to comply with the promise in the offer document that every tenant would have something in the investment programme done within two years…
John [Baptiste a tenant member] said that tenant Board Members will be the ones who will feel the effect of not fulfilling the promise in the offer document. Ian said he had spent a great amount of time on the programme and it would be possible to construct so that the promise was fulfilled but there is not enough in the budget to enable it. It might be possible to put a new door on all properties throughout the city but this would not be value for money and would be a severe disruption to the construction partners. He estimated that through the combined programmes CGA will hit over 90% of all properties within the two years.
Diane said that she and Ian had decided to put this in front of the Board now so that they were aware of the situation. What Ian was proposing in the programme is actually better than the promise in the offer document in that all properties will have benefited from a proper improvement within 2½ years rather than pepper-potted minor improvements within 2 years."
"As you will see we can live with most of the changes but are concerned with the increase in the management costs…"
On 21 October 2005, the Council prepared a Response seeking to justify its application sent it to the OPDM who responded on 28 October 2005 determining that subject to the issue of the formal gap funding agreement the ODPM was prepared to provide gap funding for a total of £47.9 million, reflecting an increase in the gap funding previously promised of £16.7 million sought.
"We have reviewed the stock condition survey to confirm that the promises as identified above have been incorporated within the survey and are scheduled to be carried out by the decent homes deadline of 2010. In carrying through the transfer promises the Board should be aware of the specification to which the stock condition survey has been costed in assessing the delivery of those promises at no greater than the costs projected within the Business Plan."
There is nothing in the disclosed documentation which suggests that this was challenged or came as any surprise to anyone involved on the CGA side.
"4. The letter we sent to the Council of 9 September 2004 indicated that the project had gained a place on the Disposals Programme 2004 and that ODPM intended to pay gap funding grant…up to a maximum of £31,291,883 for the grant recipient on the basis of a minimum valuation of £31,291,883. Since then the agreed minimum valuation has been revised to £47,998,756. As a result ODPM now intends to pay gap funding grant to the grant recipient as a contribution to eligible expenditure on the project up to a maximum of £47,998,756 over a period of ten years from 2005/06 to 2015/16 inclusive. Equal payments covering £31,291,883 will be made over the first five years and the remaining £16,706,874 will be made over the next five years. This is subject to the grant recipient meeting the agreed milestones set out in the attached Schedule A…
8. Eligible expenditure consists of payments made by the grant recipient to achieve the transfer and thereafter which contribute towards the costs of meeting milestones for the project…"
Schedule A sets out sums and the number of units projected to be spent and completed over the following five years against different heads of work: external doors, double glazed windows, full central heating, roof repairs, external insulation, new kitchens, new bathrooms, new electrics, partial central heating, cladding to BISFs, non traditional properties, environmental improvements, replacement central heating, new windows, sheltered improvements, conversions/structural works, garages, structural works and rendering/re-pointing.
"1. As identified by the framework and action plan of the asset management strategy… the lack of a comprehensive planned maintenance programme for many years, and the more recent replacement of key components only (e.g. Windows and doors), has left homes in a poor state of repair, with outstanding works in areas of wind and weather tight and structural defects. However, these areas have been prioritised by our tenants as very important to them. The existing gap funding targets do not acknowledge these areas of external wall remedial works, structural works, health and safety issues of balconies, staircases and railings, and it is the gap funding targets which have driven the first year (November 05 to March 06) of the investment programme, not sound asset management."
Essentially, the problem identified was in effect that the SCS reports did not identify a number of defects which then had to be addressed or that they contained inadequate allowances for work identified as being necessary. These do not now form part of any complaint against BWNL.
The BWNL Agreements
i) "formulating a detailed action plan and timetable to achieve" the Transfer;
ii) submitting an application in December 2003 for a place on the ODPM's list for 2004/2005 transfers;
iii) "confirming work on the initial valuation of the [Housing] [S]tock and subsequent amendments";
iv) providing "assistance in the appointment of other specialist consultants and advisers";
v) providing advice on the "preparation of the offer document";
vi) providing "ad hoc advice on any related issues which arise throughout the pre-ballot period"; and
vii) work in relation to the establishment of a new Registered Social Landlord if this option were chosen to facilitate the Transfer.
"Valuation of the Stock
The indicative valuation of the housing stock that has previously been produced will need to be refined in light of current circumstances to produce a Tenanted Market Value satisfies [sic] both parties, ODPM and funders.
Working closely with the relevant officers we will review all assumptions used in the valuation calculations, measure their sensitivity and incorporate the agreed offer to the tenants"
At paragraph 7(c) there appeared the statement that,
"the guarantees to tenants are likely to impact on the stock valuation and we therefore propose that we should demonstrate this effect to all parties before the formal offer design is finalised."
i) Using the "detailed financial assumptions" as a basis of "long term cash flow projections" which would form a key element of the new landlord's business plan (which BWNL would prepare).
ii) Advising on asset management and regeneration so as to improve the Housing Stock.
iii) Advising on and preparing a business plan for the new landlord which would cover "detail of the stock to be transferred", "cash flow and financial projections" and would be revised periodically to take account of, among other things, the stock valuation.
iv) Advising and assisting in relation to verifying the consultation material as the new landlord would need to be "satisfied" that commitments given to tenants were "both practical and reasonable".
i) Prepare a detailed work programme and action plan covering the steps required to enable CGA to complete the Transfer.
ii) Prepare terms of reference and instructions for any other consultants or professional advisers required to advise CGA in relation to the Transfer.
iii) Advise CGA as and when the assistance of any other consultants or professional advisers was required in relation to the Transfer.
iv) Advise CGA as to the issues which any other consultants or professional advisers should be instructed to consider and as to the terms of their instructions.
v) Advise upon, and lead, negotiations with PCC and its advisers as to the valuation of the Housing Stock.
vi) Prepare long-term financial models to calculate the valuation of the Housing Stock based upon recognised tenanted market principles.
vii) Prepare and advise upon operating costs budgets and long-term cash flow projections and plans in respect of the Housing Stock.
viii) Prepare and advise upon the business plan for the Housing Stock.
ix) Ensure that the Business Plan included and budgeted for meeting the promises made to tenants in the Formal Consultation.
x) Exercise the reasonable standard of skill and care to be expected of an ordinarily competent housing consultant and adviser in and about the performance of the terms of the CGA Lead Consultant Appointment.
Even if there was not an express term that BWNL should exercise reasonable care and skill, such a term would fall to be implied in any event
i) Preparing terms of reference for the appointment of any other consultants, including valuation surveyors.
ii) Advising on and leading negotiations with the Council on the valuation of the Housing Stock.
iii) Carrying out a critical review and then agreeing the base data and assumptions to be used and then preparing long term financial model to calculate the valuation of the Housing Stock based on the recognised tenanted market principles.
iv) Reviewing the stock condition survey and agreeing any adjustments as appropriate.
v) Assisting in preparing a stock investment programme.
vi) Preparing and reviewing a business plan, including long-term cash flow projections.
In addition, in its role as funding adviser it offered to assess the amount of funding required to support the business plan and test the sensitivity of the business plan.
The Complaints in These Proceedings
(a) Porches or canopies to shield visitors from weather (£276,250).
(b) Thermostatic radiator valves (£401,441).
(c) Carbon monoxide detectors to be fitted where appropriate (i.e. medical need) (Mr Stebbing's figure is £297,321 and Mr Whitehead's £35,612).
(d) Matching hearth and timber surround for gas fires (£586,864).
(e) Shower wiring (Mr Stebbing's figure is £513,490 and Mr Whitehead's £129,020).
(f) Extractor fans (Mr Stebbing's figure is £1,965,046 and Mr Whitehead's 0).
(g) Fire doors (Mr Stebbing's figure is £1,025,505 and Mr Whitehead's £64,107).
(h) Thermostatically controlled over bath showers to be provided (£2,420,913).
(i) Storage/wall cupboard (£312,992).
(j) Towel/drying rail (£210,105).
(k) 3 lever mortice locks to shed/outhouse doors (£120,298).
(l) Intruder alarms PIN numbers amended when tenancies change (£2,407,416).
(m) PIR (security) lights (£265,412).
(n) CCTV where required e.g. sheltered accommodation (£36,396).
(o) Kitchens to be designed in consultation with occupiers using Auto-cad taking into account occupiers of white goods (Mr Stebbing's figure is £158,700 and Mr Whitehead's 0).
(p) Extractor hoods above cookers (£1,622,549).
(q) Brick walls to front elevations where properties front a main bus route (£190,000).
(r) Rotary clothes dryers for all properties (£161,400).
(s) Storage sheds for garden tools (£300,000).
(t) Tenant choice improvements e.g. levelling of gardens, infilling of ponds, turfing of gardens, removal of debris (£750,000).
(u) Disabled adaptations (Mr Stebbing's figure is £2,250,000 and Mr Whitehead's 0).
There was one other item, flashing alarms, which I ignore as the experts agree that no quantum attaches to it.
Liability-Breach of Contract and Breach of Duty
"Adaptations to consider progressive nature of disability ie ramp not required now but may be required at a later date.
Adaptations built into overall scheme of works
Occupational Therapy service to fast track assessments for disabled applicants and incorporate into capital schemes of work."
This contained no indication of how much work of this sort would be done. Mr Stebbing, in his report, seems to have assumed that the work would be limited only by need, namely that CGA was promising to do all disabled adaptations that were required by tenants. Even without reference to the terms of the Offer Document, this text cannot be construed as making an open-ended promise in those terms.
"Homes should...Take into account people's disabilities in terms of design and access."
What ever this means, it is clear in context, even if one tries to avoid too legalistic an interpretation of the Offer, that the disability adaptation work was limited to £250,000's worth per year. I am by no means satisfied that this promised an open ended amount of disability adaptation work. These words are concerned simply with ensuring that such repair and improvement works as were carried out took into account the disabilities of the tenant. This might have involved, for example, ensuring that, where light switches were to be installed, they would be at a suitable height where the tenant was a wheelchair user. The words did not impose a wholesale promise upon CGA to fit disabled adaptations to all homes wherever they were required.
"20.1 The Council shall in accordance with the Chronically Sick and Disabled Persons Act 1970 and the Housing Grants Construction and Regeneration Act 1996 remain responsible for applications for disabled adaptations by way of Disabled Facilities Grant (or any such replacement grant).
"20.2 The Association has provision within its business plan for the funding of certain disabled adaptations and agrees that where a tenant of the Association request an adaptation, then PROVIDED THAT such adaptation has:
(i) been recommended by the Welfare Authority's occupational therapist; and
(ii) falls within the categories of permitted adaptations in the Council's Disabled Adaptations Policy or such other adaptations as the parties may from time to time agree;
then the Association shall incorporate the adaptations into its programmed maintenance repair modernisation or improvement works for such Dwelling.
20.3 In each Financial Year up to and ending on 31 March 2021 the Association shall meet the first £250k of the costs of any such adaptations, such sum to be increased on the 1st April of each year (the first increase to be on 1 April 2006) by the percentage increase in the RPI in the twelve months up to the September before the relevant 1 April date of increase. Any underspend in a Financial Year shall be carried forward and serve to increase the amount of the costs to be met by the Association in ensuing years.
20.4 The Association shall not be required to meet the costs of any disabled adaptations listed in paragraph 20.2 beyond the limit set out in paragraph 20.3."
The Status of the Draft 1 Document
(a) There is absolutely no and certainly no reliable evidence that prior to its production anyone from the Council or anyone else said anything to the tenants which was or could have been construed as a promise to them that the detailed list of work in Draft 1 represented what would be done by CGA. Indeed, Mr Graham accepted in evidence that the contents were not promised, albeit in the context that the promises could never be fulfilled "if the stock remained with" the Council. The evidence is that there was merely extensive consultation and discussion with some tenants. No-one from the Council or CGA was making what could be construed as promises prior to the Offer being made.
(b) The Draft 1 document itself was, as Mr Graham explicitly accepted, a list of the tenants' "aspirations"; put another way, it was a "wish-list" which had been culled from consultations with some tenants as to the sort of things which all or some of those consulted would liked to have seen done. There is no credible evidence that the detailed works in Draft 1 represented what the tenants as a whole wanted; put another way, that the detailed works were representative of what the tenants as a whole or their representatives wanted has not been established on a balance of probabilities. There is no reliable evidence that the majority of items which formed the subject matter of CGA's claims in these proceedings were in fact ever discussed in any detail or in some cases at all prior to Draft 1 being produced. Examples are overhead showers and clothes dryers. Even the list of items attached to the minutes of the first Preston Homes Standard Group meeting on 9 March 2004 are not set out as promises but as what those attending thought tenants might want.
(c) The fact that it was headed "Draft 1" suggests that it represented when drafted the first effort to list what might be thought to be tenants' aspirations. Mr Graham was particularly unbelievable in saying that this was the last of a number of drafts; that is contradicted by the fact that it was called "Draft 1" and was undermined by the fact that there were no copies retained by anyone apparently of any previous drafts. As the minutes of the earlier meetings suggest, there had been no drafting done by him before; no minutes or other documentation suggest that any draft had seen the light of day before 7 July 2004.
(d) The terms of Draft 1 are provisional and tentative. The whole draft list of components and standards is prefaced with the words "when appropriate". A number of items have question marks against them. At least one item ("providing rooms for sleeping that are separate") apparently is dependent upon "building control/fire regulations" considering the matter. The final item, which deals with garden areas is itself prefaced with the words "wherever reasonable". Draft 1 is therefore in a number of important respects provisional and that suggests that further work remained to be done on it and that the scope of the works remained to be finalised. The 12 point Preston Homes Standard, as apparently eventually agreed, was itself qualified by its opening words to the effect that dwellings and communal areas "when appropriate" should have the 12 points applied; this itself suggests a perfectly legitimate and comprehensible qualification and a standard which itself is not of unconditional applicability.
(e) The fact that Draft 1 was not circulated within the Council, to the CGA shadow representatives, other than apparently to Ms Perry, or to any of the professionals retained suggests that it was not intended to represent promises or indeed intended to be something which the Council or anyone else believed was being offered to the tenants or was intending to undertake; it is simply unbelievable that it would not have received wider circulation. There would be no reason at all for it not to be provided to and discussed with those persons and committees dealing with the Offer document. The fact that it remained in Ms Perry's email but she gives literally no evidence about it at all suggests that she at least attached no importance to it at the time or at all. This is underscored by the fact that, only a few days before Draft 1 was said to have been e-mailed to her, at the meeting of 2 July 2004 she is minuted as saying it was "important to link work with tenants on improvements to work already done with tenant reps on Preston Homes Standard". It was not even discussed on 29 July 2004 at the Tenant Steering Group Committee meeting which appears to have concentrated on the high level Preston Homes Standard document, and at which there was discussion about the improvement section of the Offer document. It is surprising that there is no evidence that anyone showed Draft 1 to Mr Bliss, as effectively an independent professional who had the tenant's interests at heart. If Draft 1 was drawn up as a list of what was promised to the tenants or otherwise intended to be done, it is amazing that it was not given to Mr Bliss. The fact that it was not circulated strongly suggests that it was not such a list.
(f) The fact is that, if anyone on the CGA board, which included conscientious tenant representatives, was aware that there was a detailed list of what were believed to be promises or otherwise of work intended to be done, the list would have surfaced much earlier than 2009 when the lawyers were first involved. It would for instance have emerged in the period in which the Offer was being drafted. It is not credible that, if Draft 1 was supposed to represent a list of detailed promises which would have cost millions of pounds to implement, someone within CGA would not have said something to its Chief Executive or other senior representatives about it. She knew nothing about it until about the time that CGA's lawyers first floated the possibility of mounting a claim based upon it. The documented history of events in 2004 and 2005 positively suggests that a number of the items set out in Draft 1, such as burglar alarms, were positively not considered as having been promised orally or represented as something that it was mutually intended that tenants should have or should necessarily have. An example of this is the discussion in March 2005 about whether burglar alarms should be offered as part of a welcome pack to new tenants: if burglar alarms were always promised and intended to be installed in all homes, there would be no point in even considering them as part of a welcome pack because sooner or later they would have been installed in all homes in any event.
(g) The whole history of events after the Transfer, at least until about the time when these proceedings were instituted, strongly suggests that there was literally no-one within CGA who believed that promises were not being kept which in turn suggests that, from the Chief Executive level downwards, all honestly believed that the actual promises made were being honoured. This is important because by then CGA was almost four years into a five year programme in which the vast bulk of the promised work was to be done. I can not and do not infer that this is a lawyer-led claim because rightly I am unaware what the legal advice given to CGA is or was. However, given the absence of any hint in the evidence that, up to shortly before these proceedings were issued, anyone within CGA believed that material promises were not being kept, a proper inference is that all promises which had been made were being or had been honoured by then and that none of the items now said by CGA to have been promised or mutually understood to have been required were prior to the transfer promised or intended to be done. In the contemporaneous documentary evidence after proceedings were issued, there is no hint that promises were not being kept; that is surprising even though some of the CGA Board meeting minutes are redacted, because CGA is run for and on behalf of its tenants and I am confident that Ms Bellinger would not countenance the concealment from tenants of something as basic as key promises not being kept.
(h) The fact that not one of out of some 6,500 tenants has so much as hinted let alone complained that promises were not kept suggests that, in so far as Draft 1 listed work which has not been done, that work neither had been promised nor was understood to have been intended to be carried out. By all accounts, the opposite is the case: the tenants are delighted and believe that the promises actually made have been kept.
(i) No-one within the Council, least of all Mr Graham, or the shadow group in 2004, thought of doing even a rough costing on the contents of the Draft 1 list, which is surprising if not unbelievable if they believed that the list contained promises, commitments or resolutions.
(j) Mr Graham was also particularly unbelievable in suggesting that he did not try to price or cost or programme either the detailed Draft 1 list or indeed anything other than the Decent Homes Standard in 2005. If he was aware or believed that Draft 1 listed promises of work which would have to be done (and he was the one who drafted it), he would have secured or at least recommended that it was costed and programmed. The fact that neither he nor anyone else did so in the period between late November 2004 and the Transfer suggests that there was no appreciation that anyone within the Council or within the incipient CGA board and staff believed that there was a detailed list such as Draft 1 which listed promises to tenants.
(k) The Offer document itself was obviously and consciously drafted and presented to the tenants on the basis of what the Gateway Standard was and was to be considered to be, which was a list of high level points which were by and large non-specific; they essentially represented aims and standards to be achieved. It is clear that BWNL advised (and this is not as such said to have been negligent advice) that the Offer should not be too specific so that CGA would be left with some flexibility. If there was any thought that underlying the Offer was a list of detailed promises not as such reflected in the Offer, it would have been politically and otherwise dishonest for the Council and the incipient CGA not at least to have hinted that there was such a list; it would not have been difficult to say something like: "a detailed list of specific works to be done is on a list which can be inspected". For no obvious good reason, the ninth item ("provide rooms for sleeping that are separate") was dropped; if this had been promised to the tenants or mutually intended to be carried out, there seems to have been no compunction against dropping it and, indeed, no complaint from a person, let alone any tenants, about its omission.
(l) The terms of the Offer itself suggest that the only promises being made were those set out in it. As far as one can tell from the contemporaneous documents, everyone including the tenants representatives were content with the terms of the Offer and it is unbelievable that, if the contents of Draft 1 (over and above what was expressly being offered in the Offer) had been promised or in some way acceded to by the Council or CGA, there would not have been some reflection of it in the Offer document itself or in the contemporaneous and circulated and discussed documentation leading up to its presentation to the tenants for balloting. The tone of that documentation is clearly that everyone was proceeding on the basis that it would be the Offer which would contain the promises to the tenants. Indeed, the post-Offer history is confirmatory of this.
(m) It is and remains a mystery as to how Draft 1 was eventually found. Ms Bellinger, who would be expected to know, had no idea who found it or indeed who first showed it to her or where it was found. She had certainly never seen the document until well into 2009 or possibly later.
(n) Draft 1 also has to be put in context of it having been the Preston Homes Standard Group's remit as set out in the minutes of its first meeting of being one of producing such a standard applicable to all properties and then develop that standard to more detailed proposals about standards of "fitment and design taking into account costs and future repair". This suggests that the standard was always to be a high level one, in fact of the type set out in first the 12 point Preston Homes Standard and later in the Offer in the Gateway Homes Standard, with the development of the standard being one which would fall short of commitment to the tenants, being subject to constraints of costs and other necessary repairs.
(o) It is clear that Draft 1 was not and was never intended by anyone to be the document which, as CGA asserts, "lay behind" the Preston Homes Standards, describing the work promised to tenants or otherwise intended to be done. If it was such a document, everyone who had any real responsibility for setting up and facilitating the Offer and transfer, including Ms Perry, Mr Roberts, Mr Bliss, the tenant representatives and later senior executives of CGA would have known and would have had to know about it; they clearly did not know about it at any relevant time. They would all have been in the position to remember this and none of them apparently did. It is argued that there were commitments made through the Preston Homes Standard Group but the minutes and the stated objectives do not suggest that "commitments" were or were intended to be made by this process.
What if Draft 1 Had Emerged-Causation
(a) The negligence was Mr Johnson's failure initially at the meeting of 15 July 2004 and in the weeks which followed to ask what the Preston Homes Standard really was before saying that there was enough in the budget to fulfil it; the failure continued for several months thereafter until the Offer was finalised. If he had asked, it is obvious that he would have been provided with a copy of the Standard and it is equally clear that he would have said something to the effect that, unless the tenants were looking for something more than was in and budgeted within the SCS reports, the Standard was unexceptionable. What I can not say as a matter of probability is that at any stage Draft 1 would have emerged or the 22 items which are now the subject matter of CGA's claim would have been identified.
(b) As set out above, Draft 1 did not contain any promises as such at all. It was not and was not apparently intended to be circulated to anyone other than Ms Perry who did nothing with it. Mr Graham certainly seems to have forgotten it and done nothing with it after 7 July 2004.
(c) Draft 1 was at best work in progress and it is not possible to say what if any of the detailed work in Draft 1 would have been analysed and accepted as having been promised to or agreed with the tenants or otherwise thought necessary or desirable to be done.
(d) The Council, tenant representatives and Shadow CGA board had been advised by Mr Johnson and others that the Offer, in terms of offering to do work, should not be too specific, albeit that some specific promises could be made. They accepted this advice and were happy with the content of the Offer on which the tenants voted. This was sound and certainly not negligent advice because, with building works in ageing housing stock, it would be very difficult to predict the full scope of the work with any certainty or precision, let alone the cost. Any number of unforeseen contingencies might arise. For instance, because the SCS reports were prepared by surveying only a proportion of the dwellings and the number of dwellings needing specific types of work was extrapolated from that, it might be found that more dwellings than anticipated might need works carried out to them.
(e) There is no reason to assume or infer that any different decision would have been made than was made with regard to the Offer or the funding being sought from the OPDM. It is arguably an extraordinary and certainly an unfortunate fact that there is no evidence from anyone from CGA or the Council who actually has given evidence as to what would have been done if Draft 1 had emerged before funding was obtained. In my judgment, it would be wrong for the Court, in this case at least, to infer that further funding would have been sought or that particular items would have been accepted as necessary or desirable to be done. If neither Council nor CGA witnesses are produced to say what either would have done in these circumstances, then one can not readily find that either would have sought extra funding prior to the Transfer or have insisted that funding for any of the 22 items which are the subject matter for CGA's claim in these proceedings should be sought.
(f) The first questions which would in all probability have been asked (if Draft 1 had been produced in answer to Mr Johnson's presumed question) would have been (although not in these terms): what is the provenance of each of these items of work? Do they represent what the tenants as a whole wanted or just a few wanted? Have Council or incipient CGA staff agreed that the tenants should have them? Is it realistic just because the answer to these last two questions is "Yes", to put them forward to be costed and form the subject matter of the gap funding application? In my view the likely answers to these questions would have been that Mr Graham had simply listed what he thought the tenants might want; secondly, apart from the doors and windows and possibly heating, it could not be said that the tenants as a whole necessarily or at all wanted them and at best it could be said that some tenants might want them; thirdly neither Council nor CGA staff had agreed that the tenants should have them or had in any way promised them to the tenants. In those circumstances in relation to the answers to the final question, in the absence of any clear evidence from relevant people at the Council or CGA, I could not and would not find on a balance of probabilities that the Council or the incipient CGA would have required any work not covered by the SCS reports to be costed and the additional cost added to the gap funding application.
(g) I do give some weight to the contents of the Offer document itself which was clearly considered in detail by the Tenant Steering Group, together with the process by which the Offer document was debated and finalised. I have absolutely no reason to believe that the tenant representatives were anything other than sensible, decent and astute, certainly judging from the comments attributed to them in numerous meetings which they attended. For instance, Page 22 makes it absolutely clear that the £80 million, to be spent in the first five years, is derived from the stock condition surveys. I have no reason to assume that the tenants who contributed to the drafting of the Offer and the tenants who considered the Offer when they were balloted had any reason to believe other than that the primary source for describing the improvements was the SCS reports; indeed the offer expressly says this at Page 22. Additionally, without being too legalistic about the Offer, it is absolutely clear that the Offer document described the Gateway Homes Standard as the 11 high-level points set out on Page 23. I do not consider that anyone truly believed that the Gateway Homes Standard was anything other than those high-level points. This leads me to believe that, if the Draft 1 document had emerged, it would have led to nothing different than the Offer Document and its reference back to the SCS reports and the improvements which are there set out.
(h) A good example of this is the extractor fans which are one of the 22 items which are the subject matter of CGA's claim. As can be seen from the history of events above, the initial draft of the Offer called for extractor fans in all dwellings and this, with the full agreement of tenant representatives, went through a series of changes to end up in the Offer as "Improved ventilation would be provided to those homes that need it to tackle condensation." So, it is a fair inference that, if the universal installation of extractor fans was identified from Draft 1, the end result would have been the same as appeared in the Offer. Ventilation could be achieved by way of extractor fans and other means such as built-in ventilation within new windows but only on an "as necessary basis".
(i) The tenor of the advice recorded as given by Mr Johnson at the meeting on 15 July 2004 was to bring the parties back to the SCS. This reflects his advice over the next 12 months as well. His report to the meeting certainly identifies this as his advice and there is no particular reason to think that his advice would not have been followed even if Draft 1 had emerged. His advice, probably mirrored by that of Mr Bliss, was that the Offer could include specific guarantees in respect of individual components of work and indeed he identified in his report to the meeting exactly the sort of improvements that were ultimately contained in the Offer. For instance, Mr Bliss later advised on 19 October 2004 "that the basis for the improvements programme was the stock condition survey that had been carried out, and [which] had been included in the offer document"; there is no hint that this advice was considered unpalatable or wrong by the tenants or anyone else. There would possibly have been a debate if Draft 1 had emerged and if it seemed that tenants might want additional improvements such as burglar alarms and clothes dryers. There is no telling, at least on a balance of probabilities, where this debate would have got to. I can not be confident to the requisite degree of proof that such a debate would have led to additional items of work being identified as necessary and to an increased gap funding application being made.
(j) It is argued that several of the high level points in the Preston (and later Gateway) Homes Standard might or should have alerted BWNL to a probability that it encompassed more than may have been covered by the SCS reports, in particular "pleasing to the eye" (point 8) and "effective means of escape in case of fire and be resistant to the spread of fire" (point 5). It was argued for instance that porches or canopies might have made the dwellings more "pleasing to the eye"; that however would be subjectively contentious and there has been no evidence that the work done over the past 5-6 years has not provided something which is pleasing to the eye or at least more so than what was there before. Porches and canopies are more often provided to give added protection against water penetration in and around the doors in question and there has been no suggestion that the new external doors do not provide adequate protection in that regard. As for the fire protection, there really has not been any real evidence that Building and safety regulations have not been complied with following the provision of the measures actually implemented. There clearly was detailed consideration given to the windows on the ground floor being capable of being used as a means of escape in case of fire. In addition, it is clear that the SCS reports did consider and allow for fire safety issues. It is not in my judgment established on a balance of probabilities that, even if BWNL had been alerted to the possibility that the high level points in the Standard might have been underlain by something more, that it would have led to any conclusion other than the SCS made sufficient provision in any event.
Quantum
(a) I would broadly have accepted CGA's case that, if works promises had legitimately been made to tenants, which fell within a reasonably desirable or necessary category, it would have been more probable than not that the ODPM would have entertained and seriously considered further funding, either in an original or indeed pre-transfer later funding application; in that context I would have accepted the evidence of Ms Turner to that effect and indeed the expert funding evidence.
(b) As to carbon monoxide detectors, it is wholly unclear what Mr Graham meant or thought he meant in Draft 1 in this context (i.e. medical need"). I preferred Mr Whitehead's evidence on this that, if anything was intended, a universal installation of such detectors was not envisaged and that something significantly less than universal application was envisaged. I would have accepted his allowance of some £35,000.
(c) In relation to shower wiring, I very much doubt that anyone seriously expected electric shower wiring to be installed in every property including those where there was or was going to be a gas-fired shower; whilst I can see that having the facility of wiring for electrical showers in an ideal world, if money was no object, could be justified, I do not see that this would have been considered as necessary or even desirable. I would have preferred Mr Whitehead's view and quantum approach on this.
(d) In relation to extractor fans, there is no doubt that the SCS and indeed therefore the £80 million in the Business Plan allowed for a not inconsiderable amount of extractor fans and related work. I would not have been satisfied that it was necessary or desirable that extractor fans were put in every bathroom and every kitchen. The very fact that the need for extractor fans was very much reduced within the Offer from what was first drafted suggests that the considered view was that it was broadly accepted that such a universal installation was unnecessary. I would again have preferred Mr Whitehead on this aspect of the matter.
(e) For fire doors, I can not see that this would have been considered to be essential for all internal doors because the Building Regulations did not require this. However, Mr Whitehead convincingly said that, even under the relevant regulations, fire doors or closers would be required only in flats above two storeys. The Preston Homes Standard was prefaced with the words "when appropriate" and I do not see that the universal provision of 30 minute fire check internal doors with closers is or has been established to be appropriate. I would have preferred Mr Whitehead's views on this and allowed his figure of just under £75,000.
(f) If I had found liability and causation in relation to disability adaptations, I would have preferred the evidence of Mr Stebbing and allowed the sum of £2.25 million subject to net present value factoring.
(g) So far as kitchen design is concerned, I would have preferred the approach and logic of Mr Whitehead. I can not see that what might really have been promised was that each of the thousands of kitchens that were to be renovated would each need its own individual computer automated design process, although of course each would have to be fitted individually; the evidence strongly suggests that there were a large numbers of dwellings which were the same as each other and an Auto CAD approach for each kitchen would have been unnecessary and a waste of money. It is certainly wholly inappropriate for CAD designs to be provided for each individual kitchen.
(h) I would thus have preferred the evidence of Mr Whitehead on the six disputed items, which would have had the effect of reducing the quantum from £16.039m as pleaded to no more than £ 10,057,677.
(i) I would have upheld CGA's argument that loss based on what additional funding would have been obtained, as opposed to some valuation or capital diminution basis, was the proper measure of damages. This loss would have been foreseeable and of the type which the contract and relationship between CGA and BWNL was at least in part seeking to avoid; put another way, BWNL's job included giving sensible and careful advice to ensure that grant funding would be obtained in an appropriate amount and that the loss of grant funding represented the correct measure of recoverable loss.
(j) If I had found that probably the Council would have sought additional funding (and I have not so found), I would have classified this as a loss of opportunity case which would have been dependant primarily on the act of a third party, namely the OPDM. I would have found that, if additional funding was sought, there was a substantially better chance than evens of securing funding but I would have been unable to fix that at 100% due to the vagaries of Government and what was available and more importantly an element of likely cynicism within ODPM as to whether all the items were necessary and desirable, the main objects of such cynicism being clothes dryers, tool sheds, overhead showers and burglar alarms. Thus, whilst some items would attract a less than 50% chance of being funded, others would attract a much higher chance such as porches, radiator valves, cooker hoods, garden improvements and security lights. I would broadly have found there to be a weighted 66.67% (two thirds) chance of securing the overall funding. I would have had regard to the fact that OPDM's own guidance called for "a realistic and cost effective programme of works which will deliver the reasonable aspirations of tenants" and also talked about "value for money". Funding was also finite and subject to competing priorities from other organisations seeking funding. I would have found that there was no realistic chance of obtaining any additional funding from the Council.
(k) I would not have found any contributory negligence on the part of CGA. The active contributory negligence would primarily have had to have been in the July to October 2004 period which was a time when the incipient CGA was being guided by BWNL, which was in effect "holding their hands". I do not see that CGA can be criticised for failing to pick up something which Mr Johnson had not but should have addressed because the relevant personnel would not have known that there was anything amiss.
(l) The net figure would need to have been reduced to reflect the fact that CGA would have been receiving the damages as a sum now rather than staggered over a period.
(m) I would have withheld any judgement on a fixed sum for damages until I was satisfied that there was no duplication between the sum allowable and any sum secured by CGA from Countrywide by way of settlement, the contents of which the Court was not informed.
Conclusion