QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
(1) LIBERTY SYNDICATE MANAGEMENT LIMITED (suing for and on behalf of itself and as agent for and on behalf of Lloyd's Syndicate 190 for the 2003 and 2004 years of account at Lloyd's and as agent for and on behalf of Lloyd's Syndicate 4472 for the 2005 and subsequent years of account at Lloyd's) (2) LIBERTY CORPORATE CAPITAL LIMITED (suing on its own behalf as the corporate member of Lloyd's Syndicate 190 for the 2003 and 2004 years of account at Lloyd's and as the corporate member of Lloyd's Syndicate 4472 for the 2005 and subsequent years of account at Lloyd's and as successor in title to Lloyd's syndicate 190) |
Claimant |
|
- and - |
||
(1) CAMPAGNA LTD (a Limited Company registered in England) (2) CAMPAGNA LIMITED (a Limited Company registered in Ireland) |
Defendant |
____________________
Ms Kim Franklin & Mr Crispin Winser (instructed by Berrymans Lace Mawer) for the Defendants
Hearing dates: 29th November 2010 – 20th December 2010
____________________
Crown Copyright ©
Mr Justice Edwards-Stuart:
The background
"From our point of view, one of the key things - and that was one of the important parts of why we set up the technical services department and why we changed firms of surveyors along the line - was actually to do with service and, by that - if somebody carried out an inspection, the house sale would depend on us being to issue the certificate of insurance. Now, provided that inspection was satisfactory for instance, then we would - we wanted to be able to receive the certificate of approval within a certain number of days otherwise the person may lose the sale. And the same with inspections and everything else. It was actually - the last thing a developer wanted was to be told somebody was coming to site or ask for somebody to come to site to look at a key stage and then they didn't turn up. So it was important for managing the service provided to the developer."
The engagement of Campagna
"LATENT DEFECTS INSURANCE - TECHNICAL AUDITS
"Contract"
Any contract where Campagna Ltd have been appointed by Syndicate 192 act as Latent Defects Technical Auditor.
"Standard"
The standard of skill and care expected of a reasonably competent Latent Defects Technical Auditor.
This letter is to confirm that Campagna Ltd agree to carry out their obligations in respect of any Contract to the Standard. Syndicate 190 agree that Campagna Ltd will be under no liability to Syndicate 190 whatsoever (whether in contract, tort (including negligence) or otherwise) for any injury or death (except where injury or death is caused by Campagna Ltd's negligence), damage or direct, indirect or consequential loss so long as the Standard is met."
"1. Definitions
1.1.3 "Certificate of Approval" means the certificate issued by the Site Audit Surveyor [Campagna] to Liberty confirming a satisfactory Survey of a Housing Unit
1.1.7 "Final Certificate" means the certificate issued by Liberty to signify acceptance of each Housing Unit for insurance following the issue of the Certificate of Approval by [Campagna]
1.1.9 "New Development" means a Housing Unit or a group of Housing Units located at the site noted on the Initial Certificate and for which an individual Final Certificate is issued for each Housing Unit
1.1.10 "Housing Unit" means the property described in the Final Certificate
1.1.12 "Technical Manual" means the functional requirements and performance standards issued by the Scheme Administrator and in force at the time when technical information relating to the New Development is first submitted to [Campagna]
1.1.16 "Survey" means checks and/or inspections carried out by [Campagna] at a Housing Unit
3. Survey
3.1 [Campagna] will carry out a Survey of a property as advised by the Scheme Administrator [MDIS] in order to establish whether the property has been designed and/or constructed in a manner to enable the Premier Guarantee policy to be issued by Liberty.
3.2 In carrying out its Survey, [Campagna] shall:
3.2.1 Comply with and adhere to the Council of Mortgage Lenders' Logic Test where applicable, a copy of which can be found at Appendix 1.
3.2.2 Comply with the technical audit procedures / standards for each type of property, which are provided by the Technical Services Department of the Scheme Administrator from time to time.
3.2.3 Comply with any Professional Code of Practice, statute, bye law, regulation, and/or such regulatory document which relates to [Campagna's] business and duties under this Agreement.
3.2.4 Ensure that any surveyor who carries out a Survey has at least five years' post qualification experience and is a member of the Association of Building Engineers or Royal Institution of Chartered Surveyors unless agreed otherwise with the Scheme Administrator.
3.3 Without prejudice to the above, [Campagna] shall use all reasonable skill and care to be expected of a competent surveyor when carrying out each Survey.
3.4 [Campagna] shall immediately notify the Scheme Administrator if [Campagna] is, or is about to, breach any of the conditions of Clause 3.2 and/or 3.3."
"This is a first party policy of indemnity for housing constructed in Ireland. In the event of a problem arising the householder will claim directly against the Insurer. The householder only needs to show that damage resulting from an insured event has occurred to recover under the policy. The Insurer will not then attempt to recover from the Builder."
"Upon receipt [of notification from the scheme administrator that a scheme has been accepted onto the Premier Guarantee for Ireland scheme] the Site Audit Surveyors should:
- Contact the person named on the form within 2 days of being notified to arrange for copies of the drawings and to ascertain when the foundation excavations will be ready for inspection.
- Two attempts to contact the proposer will be made if the surveyor is unable to make contact by telephone, a letter will be sent asking the proposer to contact the surveyor within 7 days. A copy of that letter will in all cases be copied to the scheme administrators. Should there be still no response after 14 days (the) scheme administrators must be informed.
- The plan check must address all items under the policy. The plan check will be restricted to those elements only. Plan appraisals, using the standard Plan Check Report format are to be issued within 10 days of receipt of the information. If external consultants are to be employed to check items such as structural calculations this may be extended, however, the scheme administrator must be informed of revised time-scales in such circumstances.
- Where the initial or additional design information is required this must be requested in writing from the applicant. Where repeated requests failed to illicit [sic] and the required information the technical services manager should be advised by e-mail in particular where works on site are reaching an advanced stage.
- During site inspections consideration should be given to all items covered by the policy and be undertaken at a frequency sufficient to allow a reasonable assessment of risk to the insurer to be provided. In general, and providing sufficient notice is given by the developer, inspections should be undertaken at foundation, pre-plaster and completion stages."
(1) "The necessary and reasonable costs incurred in repairing, replacing or rectifying any part of the waterproof envelope within the Housing Unit as a result of ingress of water caused by a defect in the design, workmanship, materials or components of the waterproofing elements of the new Housing Unit.
(2) The cost of repairing or making good any defects in the chimneys and flues of the new Housing Unit causing an imminent danger to the health and safety of occupants.
(3) The cost of complete or partial rebuilding or rectifying work to the new Housing Unit which has been affected by the Major Damage provided all its that the liability of the Insurer does not exceed the reasonable cost of rebuilding each New Housing Unit to its original specification."
(1) Tayleur's Point consists of 110 single (but with dormer bedrooms), two and three storey dwellings which were inspected by Campagna between January 2003 and October 2005 (although Mr Williams had been inspecting properties at Tayleur's Point since about June 2002). It is situated on the east coast of Ireland, to the north of Dublin in the town of Rush. It was built in three phases: the first phase commenced on 11 June 2002 and it consisted of 96 houses, the second phase commenced on 25 August 2004 and consisted of 12 houses and the third phase of 2 houses commenced on 30 March 2005. The sample properties at Tayleur's Point are:Nos 5, 13 - Type A chalet bungalowsNos 25, 25a - Type E detached dormer (similar to Type A)No 91 - Type A1 detached bungalow (similar to Type A)Nos 100, 101 and 106 - 2 storey terrace houses.(2) Mountgorry Wood is a development consisting of four blocks of 48 apartments which was inspected by Campagna between about February 2003 and March 2005. Block A is the largest block, with 18 apartments in a three storey building. Block B (10 apartments), Block C (12 apartments) and Block D (8 apartments) are all two storey buildings. The development is situated in north Dublin. It was accepted into the PGS on 13 February 2003. The sample properties at Mountgorry Wood are:
Apartment Nos 10 (Block A), 24 (Block B), 37, 39 and 40 (all Block C).(3) Derrycorris Drive consists of 56 two storey semi-detached houses which were inspected by Campagna between about May 2004 and December 2005. It is situated in County Offaly, approximately 50 km west of Dublin on the outskirts of Edenderry. It was accepted into the PGS on 11 May 2004. The sample properties at Derrycorris Drive are:
Nos 6, 11, 12, 24, 25 and 26.
The relevant law
"As is well known, the architect is not permanently on the site but appears at intervals, it may be of a week or a fortnight, and he has, of course, to inspect the progress of the work. When he arrives on the site there may be very many important matters with which he has to deal: the work maybe getting behind-hand through labour troubles; some of the suppliers of materials or the sub-contractors may be lagging; there may be physical trouble on the site itself, such as, finding an unexpected amount of underground water. All these are matters which may call for important decisions by the architect. He may in such circumstances think that he knows the builder sufficiently well and can rely upon him to carry out a good job; that it is more important that he should deal with urgent matters on the site than that he should make a minute inspection on the site to see that the builder is complying with the specifications laid down by him.... It by no means follows that, in failing to discover a defect which a reasonable examination would have disclosed, in fact the architect was necessarily thereby in breach of his duty to the building owner so as to be liable in an action for negligence. It may well be that the omission of the architect to find the defect was due to no more than error of judgment, or was a deliberately calculated risk which, in all the circumstances of the case, was reasonable and proper."
[Campagna's emphasis]
"(a) The frequency and duration of inspections should be tailored to the nature of the works going on at the site from time to time: see Corfield v Grant 29 Con LR 58 and Jackson & Powell, at para 8–240. Thus it seems to me that it is not enough for the inspecting professional religiously to carry out an inspection of the work either before or after the fortnightly or monthly site meetings, and not otherwise. The dates of such site meetings may well have been arranged some time in advance, without any reference to the particular elements of work being progressed on site at the time. Moreover, if inspections are confined to the fortnightly or monthly site meetings, the contractor will know that, at all other times, his work will effectively remain safe from inspection.
(b) Depending on the importance of the particular element or stage of the works, the inspecting professional can instruct the contractor not to cover up the relevant elements of the work until they have been inspected: see Florida Hotels Pty Ltd v Mayo (1965) 113 CLR 588 and Jackson & Powell, at para 8–241. However, it seems to me that such a situation would be unlikely to arise in most cases because, if the inspecting officer is carrying out inspections which are tailored to the nature of the works proceeding on site at any particular time, he will have timed his inspections in such a manner as to avoid affecting the progress of those works.
(c) The mere fact that defective work is carried out and covered up between inspections will not, therefore, automatically amount to a defence to an alleged failure on the part of the architect to carry out proper inspections; that will depend on a variety of matters, including the inspecting officer's reasonable contemplation of what was being carried out on site at the time, the importance of the element of work in question, and the confidence that the architect may have in the contractor's overall competence: see Sutcliffe v Chippendale & Edmondson 18 BLR 149 and Jackson & Powell, para 8–242.
(d) If the element of the work is important because it is going to be repeated throughout one significant part of the building, such as the construction of a proprietary product or the achievement of a particular standard of finish to one element of the work common to every room, then the inspecting professional should ensure that he has seen that element of the work in the early course of construction/assembly so as to form a view as to the contractor's ability to carry out that particular task: see the George Fischer Holdings case 61 Con LR 85. That accords with Mr Jowett's evidence in the present case, with which Mr Salisbury agreed.
(e) However, even then, reasonable examination of the works does not require the inspector to go into every matter in detail; indeed, it is almost inevitable that some defects will escape his notice: see East Ham Corpn v Bernard Sunley & Sons Ltd [1966] AC 406 and Jackson & Powell, at para 8–239.
(f) It can sometimes be the case that an employer with a claim for bad workmanship against a contractor makes the same claim automatically against the inspecting officer, on the assumption that, if there is a defect, then the inspector must have been negligent or in breach of contract for missing the defect during construction. That seems to me to be a misconceived approach. The architect does not guarantee that his inspection will reveal or prevent all defective work: see Corfield v Grant 29 Con LR 58. It is not appropriate to judge an architect's performance by the result achieved: see Jackson & Powell, at para 8–238."
"I think that the degree of supervision required of an architect must be governed to some extent by his confidence in the contractor. If and when something occurs which should indicate to him a lack of competence in the contractor, then, in the interest of his employer, the standard of his supervision should be higher. No one suggests that the architect is required to tell a contractor how his work is to be done, nor is the architect responsible for the manner in which the contractor does the work. What his supervisory duty does require of him is to follow the progress of the work and to take steps to see that those works comply with the general' requirements of the contract in specification and quality. If he should fail to exercise his professional care and skill in this respect, he would be liable to his employer for any damage attributable to that failure."
The standard of care
"Surveyors are engaged by The Premier Guarantee to manage insurance risk and to ensure that new housing units are constructed to recognised standards. This includes a combination of desktop appraisal of design proposals, combined with on-site inspection of work in progress and work completed. If information required ensuring compliance with standards is not provided, defects identified on site or works not completed, then The Premier Guarantee may withhold the insurance certificate for the new housing unit in question."
Mr Mulrooney, the expert instructed on the half of Campagna, was cross-examined at some length on this passage and, in his closing submissions, Mr Quiney made much of what he described as the "difficulty Mr Mulrooney experienced with this document, and particularly with the word "ensure"". I think that perhaps Mr Quiney's criticism here is a little harsh. Whilst the extract that I have quoted might suggest that Campagna's technical auditors were under a duty to ensure a particular result, the manual must be read in the context of Campagna's terms of engagement - which imposed an obligation to take reasonable care, not an obligation to achieve a particular result. So what the manual is really saying is that Campagna's technical auditors must exercise reasonable care when carrying out their plan checks and site inspections so as to ensure - consistently with the exercise of such care - that new housing units are constructed to recognised standards.
The relevance of the fee
(1) For the UK, if the technical auditors were paid £300 per visit and were limited to 50 visits per month they would each earn a maximum of £15,000 (when the limit was 60 visits per month, the maximum would be £18,000).(2) For Ireland Mr Devaney said that the amount received per visit was €210. If this figure were substantiated, 70 visits per month would produce €14,700. At the date of the MDIS contract (and Liberty's letter of 12 June 2003), the exchange rate was about 1.4. Thus this equated to £10,500.
(3) Accordingly, Ms Franklin submitted that on Liberty's figures the auditors were paid at the least 50% more for auditing in the UK (and she said that it could be up to 70% more). Further, as most of the auditors were UK based (as was known to MDIS and thus Liberty) they also incurred travel and accommodation costs when auditing in Ireland which would be greater than the travel and accommodation expenses incurred in the UK.
Practical guidance as to the standard of care given by Liberty
". . . in order [to] ensure that building works are suitably complete; The Premier Guarantee has set out a standard that can be readily interpreted by all interested parties and will provide a consistent approach to assessing the completeness of a new housing unit. It is also hoped that this will minimise the occurrence of abortive visits and ensure that any potential delays associated with rearranging inspections can be avoided."
The manual provided guidance as to what would or would not result in a satisfactory final inspection by setting out a sequential logic test. It said:
"If the answer to any of the standard questions is YES then that the item will be classified as CRITICAL and confirmation that a satisfactory final inspection has been carried out will be withheld until the relevant issue is resolved.
If the answer to the standard questions [sic] is NO then the item will be classified as NON-CRITICAL and confirmation of this would be provided to the house builder . . .
It is important to understand that the pre-hand over inspection performed by The Premier Guarantee's audit surveyors is concerned with the checking of warranty and associated items; it is not a snagging inspection."
The additional notes to the logic test include the following:
" If, following the pre-handover inspections, there are a number of NON--CRITICAL items amounting to remedial work that would involve significant disruption to the homeowner, the home will not be finalled (signed-off) and confirmation of satisfactory final inspection will not be provided. It is therefore in the interest of all parties that all CRITICAL and a sufficient number of NON-CRITICAL matters have been completed prior to the request for inspection being made under the Premier Guarantee."
Example 1
Small area of roof insulation missing.
Passes the logic test therefore classified as NON-CRITICAL. Note that a large expanse of missing installation might be classified as critical, for reasons of potential disruption to the building occupier.
Example 2
Mechanical extract fan from bathroom discharging into roof void.
Warm moisture laden air will quickly condense within the cooler roof void, potential claim and therefore fails the logic test - would be classified as CRITICAL.
Example 3
Stop end missing to roof gutter.
Passes logic test therefore classified as NON-CRITICAL.
Example 4
External threshold not complete.
Rectification would involve considerable disruption to the homeowner and possibility of rainwater ingress and therefore fails the logic test and hence would be classified as CRITICAL.
Example 5
Lead work not dressed over low-level chimney shoulder.
Passes the logic test and therefore classified as NON-CRITICAL.
As I have set out above, the additional notes to this section state that if there are a number of non-critical items requiring remedial work that would involve significant disruption to the homeowner, a Certificate of Approval will not be provided.
"Examples of items checked at final inspection stage included:
- Mastic around external door and window frames
- Weathering at thresholds
- General inspection inside including the uppermost floors in particular to ensure that there was no evidence of water ingress.
- A ground level check of chimney and abutment flashing where visible.
- General check that the unit was habitable. If kitchen units, sanitary ware was ex-contract and to be completed by the purchaser (as part of a PC sum) then Campagna would receive confirmation of this.
- A cursory look in the roof space to check that the roof insulation was in place.
- Check that adequate vents were in place in the external blockwork walls of timber frame construction
- Flue outlets were satisfactory.
By ensuring that the above items were completed satisfactorily, the requirements of the logic test (included in the site audit auditor's manual) would automatically be satisfied.
Campagna's auditors could not have seen the following at final inspections:
- Whether the roof coverings were watertight, unless there was evidence of water ingress.
- Whether the damp proof courses were correctly installed - unless there was evidence of water ingress or damp.
- The extent to which roof tiles were fixed unless they were missing.
- Whether the external elements were structurally supported - unless there was evidence of stress, deflection or failure.
An inspection of the roofspace would not normally have taken place. Defects in roofing felt and the connections of ducting to ceiling fans would not have been seen."
The inspections
3.2 The standard of care required to be exercised when undertaking the Desktop Study.
3.3 The standard of care required when inspecting each Development, including the number of inspections required and what level of inspection was required upon each visit.
3.4 What information was required from the Developers by Campagna.
The plan check
The inspection of the foundations
The pre-plaster inspection
The final inspection
General matters relating to inspections
The witnesses
Mr Evans
Mr Gray
Mr Turnick
Mr Devaney
Mr Byrne
Mr Gee
Mr O'Connell
Mr Holland
Mr Gillett
Mr Kerrigan
Mr Hilton
Mr Williams
". . . what I meant was outside the 4.5, the chimney height 4.5. I think it's a slight error there."
He was then compelled to accept that, since he had referred to the "properties" being outside the zone, his explanation that he meant that the chimney was outside the height to width ratio was unsustainable. He then said that it must have been something that he missed when he proof read the statement.
Mr Gough
The experts
The defects
Tayleur's Point: the inadequate fixing of the roof tiles to the single storey houses
"Yes, and you would see that as you were going round, and you could climb on them and test some of the tiles on some of the roofs. You wouldn't test every house."
Tayleur's Point: the roof overhang to the dormer houses
"Trusses OK, but additional info requested for cut roofs."
Tayleur's Point: the chimneys
"The proportions given in this paragraph are intended for general application. More slender chimneys may be built if they can be shown by calculation to be stable in the particular wind environment of the building."
"It was my experience. I'd seen the chimneys of that slenderness ratio, you know, higher than 4½, up to 6½ times the least width In my working life, which had been subject to building control in the UK. There are some chimneys around Taylor's Point which are still there, have been there for many years. . . . I was using my experience from what I'd seen in the UK. And I am convinced that what was there was satisfactory and if I'd asked for calculations to come in, they would have proven exactly what I was prepared to accept."
"Any defect in the design, workmanship, materials or components of the Structure that is first discovered during either the Defects Insurance Period or the Structural Insurance Period and which causes physical loss, destruction or damage or causes imminent instability to a New Housing Unit that requires complete or partial rebuilding or rectification work to the New Housing Unit."
Tayleur's Point: the defects in the external render
3 December 2004 (superstructure complete and ready for roofing)
3 March 2005 (roofs complete, external plastering in progress)
15 April 2005 (external plastering complete)
11 May 2005
8 June 2005 (houses complete)
8 June 2005
6 July 2005 (near competition)
16 August 2005 (work nearing completion)
Tayleur's Point: incorrect installation of coping stones
Mountgorry Wood: the roofing and the cause of the damage to it
"There would certainly have been an ingress of water, in my opinion, yes. Water, if you have significant rainfall, and we do, certainly in that area of Ireland, is quite close to the sea, there would have been, and I would have expected that there would have been an ingress of water, most definitely. Whether it would have manifested immediately internally within the apartment, that would definitely not be the case, but very shortly thereafter, yes."
Date | Progress |
29 September 2003 | Block C - First floor level Block D - Roofing in progress |
3 March 2004 | Block C - Plastering out Block D - Very close to completion, rainwater goods and weathering still to be completed |
2 April 2004 | Block B: Blockwork complete. Positioning of roof trusses in progress. Block C: Work nearing completion. Block D: Work complete |
3 August 2004 | Block B: second fix in progress Block C: Work almost completion [sic], weathering to front door and making good to external brickwork required. |
2 September 2004 | Block A: roofing in progress, trussed rafters in place Block B: nearing completion Block C: completed |
For the purpose of this exercise, I will ignore Block D because it is not clear whether or not that the roof of that building suffered any significant damage. However, I note that Mr Scott has said that Campagna's technical auditors had an opportunity to inspect the roof covering to at least one of the blocks in detail on 29 September 2003 (paragraph 7.18.4). This must refer to Block D, but there are two difficulties with this suggestion: first, it is not clear that there was any significant damage to Block D and, second, there is no way of knowing how far the roofing to Block D had progressed at the time of the inspection - if it had just started there would probably have been no damage to see. Accordingly, I do not think that there is anything in this point.
"Well, I think if I knew that I couldn't see the roof, having been to site on numerous occasions previously, then it may be something that might be worthwhile bringing with him, but I wouldn't necessarily say it formed part of their daily kit."
Mountgorry Wood: the curved roof parapets
Date | Progress |
3 March 2004 | Block C - Plastering out |
2 April 2004 | Block B: Blockwork complete. Positioning of roof trusses in progress. Block C: Work nearing completion. |
3 August 2004 | Block B: second fix in progress Block C: Work almost completion [sic], weathering to front door and making good to external brickwork required. |
2 September 2004 | Block A: roofing in progress, trussed rafters in place Block B: nearing completion Block C: completed |
Mountgorry Wood: the brick parapets on the front elevations
Mountgorry Wood: the defects in the roof spaces
Mountgorry Wood: the defects in the balconies
Mountgorry Wood: the unconnected ventilation outlet at roof level
Derrycorris Drive: the canopies
Derrycorris Drive: poor detailing of the felt in the roof space around the chimneys
"I am of the opinion based on the evidence following the joint site inspection that the installation of the sarking felt to this property (and other properties inspected by the TA at the same date namely no 6, 5, 11) all revealed:
- Omission of any timber trimmer arrangement to the chimney stack necessary to support the lead flashing/sarking felt interface
- Gaps to the party wall/chimney abutment
- Sagging and untidy installation of sarking felt
- Rips and tears to areas of sarking felt"
Derrycorris Drive: defective connection of the bathroom fan within the roof space
Derrycorris Drive: the junction of the lean-to and the rear of the houses
"I would like to see how far that upstand goes up behind the render for a start, yes, because those photographs don't show the upstand going to behind the render. You cannot tell that the flashing goes up behind the render, which I expect it does. The only bit that you are concerned about is the bit underneath the window sill."
Issue of Certificates of Approval
Conclusions and reflections
APPENDIX A - List of Issues
This is the list of issues annexed to the Order of 18 June 2010 to be determined by the Court at this hearing:
1. The Retainer of Campagna and which terms applied.
2. The role of Campagna with respect to the First Developments.
3. The standard of care required of Campagna both as a matter of contract and in tort, including:
3.1. The effect of the following matters on the content of Campagna's duties: the Scheme itself; the 2004 Retainer; the Site Audit Surveyor's Manuals; and the Technical Guides as issued by MDIS under the Scheme, for both Ireland and the UK.
3.2. The standard of care required to be exercised when undertaking the Desktop Study.
3.3. The standard of care required when inspecting each Development, including the number of inspections required and what level of inspection was required upon each visit.
3.4. What information was required from the Developers by Campagna.
3.5. How Campagna should make the decision as to whether or not to issue its Final Certificates of Approval.
3.6. When Campagna should advise Liberty as to the risks involved in issue the Final Certificate of Insurance under the Scheme for each Development and/or not to issue a Final Certificate of Approval.
4. Whether Campagna has breached that standard of care in respect to each of the First Developments; including whether:
4.1. It failed to properly carry out the Desktop Study for each of the First Developments.
4.2. It failed to inspect the Developments properly, with sufficient frequency, or at all.
4.3. It incorrectly issued Final Certificates.
4.4. It failed to advise Liberty properly or at all as to the risks arising from underwriting the Developments under the Scheme.
4.5. Whether the defects that Campagna failed to identify whether during the Desktop Study or the inspections were covered by the Scheme
APPENDIX B - Certificates of Approval
No | Date of completion | Date of Certificate of Approval | Date of Certificate of Insurance | Defects alleged | Comments |
Tayleur's Point | Tayleur's Point | Tayleur's Point | Tayleur's Point | Tayleur's Point | Tayleur's Point |
5 | 10 May 2004 | 13 May 2004 | 27 Oct 2006 | Overhang/chimneys/loose tiles | Overhang not checked. Chimney dimensions not checked. Certificate should not have been issued. (Campagna not liable for loose tiles) |
13 | 14 May 2003 | 16 May 2003 | 9 Sep 2009 | Overhang/chimneys/loose tiles | Preceded plan check. Overhang not checked. Chimney dimensions not checked. Certificate should not have been issued. (Campagna not liable for loose tiles) |
25 | 25 Oct 2005 | 27 Oct 2005 | Overhang/chimneys/loose tiles | Overhang not checked. Chimney dimensions not checked. Certificate should not have been issued (if it was). (Campagna not liable for loose tiles) |
|
25a | 11 Sep 2003 | 30 Aug 2006 | 30 Aug 2006 | Overhang/chimneys/loose tiles | Overhang not checked. Chimney dimensions not checked. Certificate should not have been issued. (Campagna not liable for loose tiles) |
91 | 20 Dec 2004 (VOK) | 23 Apr 2009 | Overhang/chimneys/loose tiles | Overhang not checked. Chimney dimensions not checked. Certificate should not have been verbally approved. (Campagna not liable for loose tiles) |
|
100 | 8 Jun 2005 | 15 Jul 2009 | Render applied out of sequence | Out of sequence work should have been noted. Certificate should not have been issued. | |
101 | 8 Jun 2005 | 15 Jun 2005 | 23 May 2008 | Render applied out of sequence | Out of sequence work should have been noted. Certificate should not have been issued. |
106 | 2 Sep 2005 (VOK) | 16 Jul 2009 | Render applied out of sequence | Out of sequence work should have been noted. Certificate should not have been verbally approved. | |
Mountgorry Wood | Mountgorry Wood | Mountgorry Wood | Mountgorry Wood | Mountgorry Wood | Mountgorry Wood |
10 | 23 Mar 2005 | 24 Mar 2005 | 4 Oct 2007 | Defective balcony details | Balcony defect not evident. Certificate properly issued. |
24 | 26 Oct 2004 | 13 Nov 2007 | Defective balcony details and absence of parapet DPC. Unconnected ventilation outlet | Absence of parapet DPC not noticed. Certificate should not have been issued (if it was). | |
37 | 2 Sep 2004 | 3 Sep 2004 | 30 Oct 2007 | Damaged roof | Damaged roof not noticed. Certificate should not have been issued. |
39 | 2 Sep 2004 | 3 Sep 2004 | 21 Nov 2007 | Damaged roof | Damaged roof not noticed. Certificate should not have been issued. |
40 | 2 Sep 2004 | 3 Sep 2004 | 17 Apr 2009 | Damaged roof. Absence of DPC in front parapet wall. | Damaged roof not noticed. Certificate should not have been issued. |
Derrycorris Drive | Derrycorris Drive | Derrycorris Drive | Derrycorris Drive | Derrycorris Drive | Derrycorris Drive |
6 | 9 Nov 2004 | 2 Mar 2005 | 30 Apr 2009 | Canopy not properly supported | Lack of suitable support for canopy not identified. Certificate should not have been issued. |
11 | 9 Nov 2004 | 4 Sep 2008 | Canopy not properly supported. Defectively installed valley gutter. | Lack of suitable support for canopy not identified. Valley gutter defect not noticed. Certificate should not have been issued (if it was). | |
12 | 9 Nov 2004 | 2 Mar 2005 | 31 Jul 2008 | Canopy not properly supported. Defectively installed valley gutter. | Lack of suitable support for canopy not identified. Poor detail of junction between lean-to and rear wall not noticed. Valley gutter defect not noticed. Certificate should not have been issued. |
24 | 1 Mar 2005 | 18 Jun 2009 | Canopy not properly supported. Poor detail of junction between lean-to and rear wall. | Lack of suitable support for canopy not identified. Poor detail of junction between lean-to and rear wall not noticed. Certificate should not have been issued (if it was). | |
25 | 1 Mar 2005 | 23 Dec 2008 | Canopy not properly supported. Poor detail of junction between lean-to and rear wall. | Lack of suitable support for canopy not identified. Poor detail of junction between lean-to and rear wall not noticed. Certificate should not have been issued (if it was). | |
26 | 1 Mar 2005 | 4 Feb 2009 | Canopy not properly supported. Poor detail of junction between lean-to and rear wall. | Lack of suitable support for canopy not identified. Poor detail of junction between lean-to and rear wall not noticed. Certificate should not have been issued (if it was). |