QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
KINGFISHER BUILDERS |
Claimant |
|
- and - |
||
CHRISTOPHER SEAR |
Defendant |
____________________
Mr Robin Neill (instructed by Morris Godard & Ward, Devizes) for the Defendant
____________________
Crown Copyright ©
The Hon. Mr. Justice Ramsey:
Introduction
Background
"Your job is going to cost £218,000 this includes everything we talked about, under floor heating, new central heating system, mega flow system, lighting as you wish, such things externally we would take off existing render and re render so the outside would be as one. What is not included is the new kitchen or sanitary wear (sic) as you would want to choose your own. An allowance has been made to fit all sanitary ware and an allowance for tiling in all bathrooms, painting and decorating is also allowed for, as a professional painter can enhance the finish very much, all other fittings as original house. If you do take us on of course a full specification will be supplied. The job will start as you wish on July 1st and you will be in for Christmas. A 2% retention will be left for maintenance for 6 months, a small works contract will be at your request."
"You continue to pay me on the basis that I am doing the original extension. Please, to rebuild is a completely different kettle of fish. A simple basis for a 3000 square foot house would be £600,000 at £200 a foot, but with the demolition on top of that £30,000, plus a double garage plus the spec you have now ordered, yes all this extra work will enhance the price of the house particularly the tile hanging. But what about the builder, I must now insist upon payment of the demolition payment and something towards all the other extra work you have ordered."
"You have ignored my requests for payment of the demolition and all the other payments but continue to order extra after extra. I am now going to consult a firm of surveyors to try to convince you that I am not building an extension for you but a 3000 foot new house, the cost of which is completely different to the original extension. You keep adding and adding extra work the cost of which is very substantial."
These Proceedings
All issues of liability save for any issue concerning which, if any, party repudiated the contractual or quasi-contractual relationship between the parties (in or about November or December 2008).
Any issue concerning sums paid by Mr Sear to the claimant or by Mr Sear on behalf of the claimant.
The agreed position
(1) The sum of £218,000 agreed by the parties for the original works in the written agreement dated 30 June 2008 was based upon the work to be carried out in accordance with the Original Planning and Building Regulation drawings (Bundle 5 pages 749-757, 762 to 778 and 779 to 788).
(2) To the extent any work has to be valued as a reasonable sum then that sum has to be evaluated based on an analysis of the sum of £218,000 for the original works and so as to represent the sum included within the £218,000 or which would have been included in the £218,000 had the work been included at that stage, calculated as follows:
(a) To the extent that work is within the scope of the original work, the sum derived from the analysis of £218,000 for that original work should be used.(b) To the extent that the work is not within the scope of the original work but there is similar work within that scope, then it should valued on the basis of a reasonable sum calculated by using the rates and/or prices for the similar work.(c) To the extent that the work is not within the scope of the original work and there is no similar work within that scope, then it should be valued using cost but using any applicable labour and plant rates or percentage uplifts in the analysis of the £218,000.
(1) The court would at this hearing determine the value of the original works in the written agreement with such necessary additions or omissions as would represent the works which were included in the revised scope of the works at 3 December 2008.(2) The court would not at this hearing determine the extent to which the revised scope of the works had actually been carried out by the claimant at 3 December 2008.
(3) The sums paid by the defendant to the claimant are £243,524.80 as set out in Schedule 1.
(4) There is a dispute as to whether the sums of £38,400 and £1,600 agreed in respect of the existing walls and the spine wall should have 10% added to them.
(1) In respect of work carried out prior to discovery that the existing walls were built from clay-pot tiles, the works have to be valued on the basis that they were included within the sum of £218,000 agreed by the parties for the original works in the written agreement dated 30 June 2008.(2) In respect of the work of demolition of the existing clay-pot tile walls, the claimant says that the work has to be valued as a reasonable sum because it was not included within the agreed sum of £38,400 (plus 10%). The defendant says that the work was included in the agreed sum of £38,400 or, if not included, it has to be valued as a reasonable sum.
(3) In respect of the rebuilding of the new walls to replace the demolished clay-pot tile walls, the parties agree that the costs of building the blockwork walls were agreed. The claimant says that the sum of £38,400 (plus 10%) represented this work; the defendant said that this work and other work was included in the agreed sum of £38,400.
(4) In respect of the plastering, electrical work, heating work/radiators, architraves and skirtings and other work necessary to put the rebuilt walls in the same state as the existing walls would have been, the claimant says that there was additional work which has to be valued as a reasonable sum because it was not included within the agreed sum of £38,400 (plus 10%). The defendant says that the work was included in the agreed sum of £38,400 or, if not included, it has to be valued as a reasonable sum.
(5) In respect of the demolition of the spine wall the claimant says that the work has to be valued as a reasonable sum because it was not included within the agreed sum of £1,600 (plus 10%). The defendant says that the work was included in the agreed sum of £1,600 or, if not included , it has to be valued as a reasonable sum.
(6) In respect of the rebuilding of the new walls to replace the demolished spine wall, the parties agree that the costs of re-building the spine wall was agreed. The claimant says that the sum of £1,600 (plus 10%) represented this work; the defendant says that this work and the demolition work was included in the agreed sum of £1,600.
(7) In respect of other work, the claimant says that the work has to be valued as a reasonable sum; the defendant says that it was either part of the original work scope or that the basis of valuation was agreed or if, it was additional work, it should be valued as a reasonable sum.
(1) What was agreed between the parties after the discovery of the clay-pot tiles in the wall as to the scope and cost of the work necessary because of the demolition and rebuilding of those walls and the spine wall?(2) Is Kingfisher Builders entitled to any further payment in respect of:
(a) Issues 1A and 1B: demolition and rebuilding of the clay-pot tile walls?Issue 14: Additional electrical works associated with the rebuilding of the external and spine walls?Issue 16: Plastering of the walls rebuilt following demolition?(b) Issue 2: The construction of blockwork walls at first floor level?Issue 11: Increasing the size of the RSJs at first floor level?(c) Issue 3: Building stud work for a flat TV?(d) Issue 4: Three sliding door frames?(e) Issue 5: Moving the bathroom at second floor level?Issue 6: Re-locating the SVP, drainage and manhole for the bathroom at second floor level?(f) Issue 7: Fibreglass insulation between ground floor and first floor and first floor and second floor.(g) Issue 12: Increasing the area of the crown roof?Issue 8: Constructing a Velux window in the crown roof?(h) Issue 9: Installing hanging tiles on the external faces of the Property?Issue 21: Changing roof tiles from clay tiles to concrete tiles?(i) Issue 19: Installing "scalloped" flashing under the windows?(j) Issue 10: Chasing pipework into walls?(k) Issue 13: Concrete oversite to the ground floor of the Property?(l) Issue 15: Additional carpentry to the bedroom wardrobes?(m) Issue 17: Renewing central heating radiators?(n) Issue 20: Installing vanity units?
The Evidence
The agreement
Additional Work
Items 1A, 1B, 14 and 16: Additional work to new walls under the agreement
Items 2 and 11 First floor blockwork and increased size RSJs
Item 3: Stud work for a flat TV.
Item 4: Three sliding door frames.
Items 5 and 6: Moving the bathroom at second floor level and re-locating the soil and vent pipe, drainage and manhole for that bathroom.
Item 7: Fibreglass insulation between ground floor and first floor and first floor and second floor.
Items 12 and 8: Increasing the area of the crown roof and constructing a Velux window in the crown roof.
Items 9 and 21: Installing hanging tiles on the external faces of the Property and changing the roof tiles from clay to concrete.
Item 19: Installing "scalloped" flashing under the windows.
Item 10: Chasing pipework into walls.
Item 13: Concrete oversite and underfloor heating to the ground floor of the Property.
"27 Ground Floor
75mm screed on 100mm Jablite 'SD' grade insulation or similar to incorporate underfloor heating if required on 150mm insitu concrete slab. 1200 gauge polythene dpm laid over insulation and lapped with dpc on minimum of 150mm sand blinded compacted hardcore."
Item 15: Additional carpentry to the bedroom wardrobes.
Item 17: Renewing central heating radiators.
Item 20: Supplying and installing vanity units.
Conclusion