QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
CARILLION JM LIMITED |
Claimant |
|
- and - |
||
PHI GROUP LIMITED |
Defendant |
____________________
Krista Lee (instructed by Fishburns) for the Defendant
Ben Patten QC (instructed by Mills & Reeve LLP) for the proposed Part 20 Defendant
Hearing date: 10/03/2010
____________________
Crown Copyright ©
Mr Justice Edwards-Stuart:
Introduction
The facts relating to the dispute
The events leading up to the application
"We note that we have not yet received Robert West's Protocol Letter of Response (which is now overdue) and we will shortly be applying to join Robert West to the proceedings".
"Against the background of an increasingly imminent trial date, the importance in such circumstances of a proper and frank explanation of the reason for delay should not be under-estimated."
And, at paragraph 52:
"I would accept that there is a delicate line to be trod here between privilege and candour. But, if a party asks for a special dispensation to be shown to it, and there can be few dispensations more special than a litigant asking to join a new party to long existing proceedings on what is, relatively speaking, if not the eve of trial at any rate a short period before it, then such a party must carefully consider how candid it can be with the court. It is fully entitled to rest on its privilege. But then the court is not assisted with any explanation."
The relevant factors
"In exercising its case management powers, the court will be concerned, if possible, to maintain the timetable to which the existing parties are working. Any change of trial date may lead to a change of counsel, additional costs and all manner of problems for the existing parties. On the other hand, the court will also be concerned to protect new parties against injustice and to protect the procedural rights of weaker parties against the big battalions."
The application to amend the Defence
"Further and in any event, had the designs for the Sub-Contract Works been revised to take account of the existence of slip planes and/or higher water pressure then the original cost of the Sub-Contract Works would have been greater. This greater cost must be allowed for and deducted from any damages that are found to be due to the Claimant. The Claimant must also give credit for any betterment contained in any proposed future remedial works."
Consequential directions