QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE MAYOR AND BURGESSES OF THE LONDON BOROUGH OF CAMDEN |
Claimant |
|
- and - |
||
MAKERS UK LIMITED |
Defendant |
____________________
Karim Ghaly (instructed by Fenwick Elliott) for the Defendant
Hearing dates: 20 March 2009
____________________
Crown Copyright ©
Mr Justice Akenhead :
Introduction
The History
(a) Makers was failing to proceed regularly and diligently with the Works at the time of service of the Default Notice.
(b) Makers did not continue the default for 14 days from receipt of the Default Notice.
(c) Camden incorrectly served its Determination Notice on 27 July 2007. In serving the Determination Notice and requiring Makers to vacate the Site, Camden had repudiated the Contract.(d) Makers had not repudiated the Contract.
It was this decision which Makers successfully sought to enforce in July 2008, in so far as it required Camden to pay the Adjudicator's fees; the Adjudicator had not been required to address any matters of quantum. Camden had attempted to challenge this enforcement on jurisdictional and bias grounds.
The Financial Position of Makers
"On 20 August 2007, Keller group plc, the company's ultimate parent, announced its decision to withdraw from the Makers UK Limited business. As the directors do not believe the company will continue to trade once existing contracts have been completed, they have not prepared the financial statements on a going concern basis "
Year ending | [Loss]/Profit on ordinary activities before taxation* | [Loss] Profit for the financial year* | Total assets less current liabilities** | Net Assets/liabilities** |
31/12/07 | [£10,428,000] | [£8,541,000] | [£8,661,000] | [£10,268,000] |
31/12/06 | [£3,789,000] | [£2,957,000] | [£1,769,000] | [£1,831,000] |
31/12/05 | [£2,141,000] | [£1,356,000] | £2,081,000 | £1,081,000 |
31/12/04 | £413,000 | £437,000 | £1,709,000 | £1,474,000 |
31/12/03 | [£6,969,000] | [£6,598,000] | [£1,728,000] | [£4,728,000] |
31/12/01 | £2,289,000 | £1,588,000 | £1,898,000 | £1,898,000 |
* From Profit and Loss account
** From Balance Sheet
(a) based on the latest filed accounts, Makers is insolvent in that, without the support of its parent, Keller, which was effectively rescinded or removed in August 2007, its business is loss making and it has a substantial negative value. If anything up to £8m was paid over to it, it would be unable to repay it.
(b) based on the accounts (year ending 31 December 2004) available at the time that the Contract was entered into (September 2005), Makers was in profit from its trading activities and worth in capital terms a significant amount.
The Issues
(a) Makers does not institute any further adjudications covering issues addressed in these proceedings, and
(b) Makers gives Camden security for the costs likely to be incurred by Camden in defending Makers' intended Counterclaim herein.
a) What is the nature and scope of the jurisdiction to impose conditions upon setting aside a regular default judgment? ("The Jurisdiction Issue").
b) Is Makers insolvent and based on the evidence currently before the Court will it probably be unable to repay any sum awarded to it by an adjudicator upon a future adjudication in respect of its quantum claim against Camden and/or is there reason to believe that it will be unable to pay Camden's costs of defending the intended Counterclaim in this litigation if ordered to do so ("The Insolvency Issue").
c) Granted that that at this stage the Court is bound to conclude that Makers has a real prospect of successfully defending the claim, is there some other good reason why judgment in default should be set aside ("The Other Good Reason Issue").
d) Should the Court exercise its discretion to set aside the regular default judgment, upon conditions that:
i) Makers does not institute any further adjudications covering issues addressed in these proceedings, and
ii) Makers gives Camden security for the costs likely to be incurred by Camden in defending Makers' intended Counterclaim.
("The Conditions Issue")
The Jurisdiction Issue
"But it must be kept in mind that discretionary powers are not to be used to punish a party for incompetence - they must be exercised in order to further the overriding objective. In the present case, as the judge recognised, the essential question was whether the risk of injustice to the Governors (in denying them the opportunity to advance at trial a defence which as the judge himself said had a good prospect of success) outweighed the risk of injustice to the claimant and other defendants if the Governors were allowed (at this late stage) to participate in the proceedings."
(a) The court is not to impose conditions to punish the defendant;
(b) In considering whether to impose conditions, the court must have regard to the imperative to act justly as between the parties.
The Insolvency Issue
The Other Good Reason Issue
The Conditions Issue
"18. In my view, the principles deriving from the authorities to which I have referred have no application to adjudications. Section 108(2)(a) of the 1996 Act expressly states that a party may refer a dispute to an adjudicator "at any time". It is true that the words "at any time" do not appear in paragraph 1(1) of the Scheme. But it is plain from section 108(5) that it was intended that the relevant provisions of the Scheme should be consistent with the requirements of section 108(1) to (4) of the Act. I do not consider that the omission of the words "at any time" from paragraph 1(1) of the Scheme is of any significance. Nor did Mr Davies suggest that it was. Parliament had litigation and arbitration proceedings very much in mind when drafting the Act. As I said in Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] BLR 93, 97:
"The intention of Parliament in enacting the Act was plain. It was to introduce a speedy mechanism for settling disputes in construction contracts on a provisional interim basis, and requiring the decisions of adjudicators to be enforced pending the final determination of disputes by arbitration, litigation or agreement."
19. If Parliament had intended that a party should not be able to refer a dispute to adjudication once litigation or arbitration proceedings had been commenced, I would have expected this to be expressly stated. The relationship between adjudication on the one hand and litigation and arbitration on the other, was what informed the content of section 108(3) of the Act. The aggrieved claimant should not have to wait many months, if not years, before his dispute passed through the various hoops of a full blown action or arbitration.
20. In my view, there is no obvious reason why Parliament should have intended to draw a distinction between cases where litigation or arbitration proceedings have been started before a dispute is referred to an adjudicator, and those where the proceedings have been started only after an adjudication has been completed. The mischief at which the Act is aimed is the delays in achieving finality in arbitration or litigation. Why should a claimant have to wait until the adjudication process has been completed before he embarks on litigation or arbitration? If he is in a position to start proceedings, it is difficult to see why he should have to wait until a provisional decision has been made by an adjudicator. The normal rule that concurrent proceedings in respect of the same issue or cause of action will not be countenanced is justified on the grounds that (a) it is oppressive to require a party to defend the same claim before different tribunals, and (b) it is necessary to avoid the risk of inconsistent findings of fact. But it is inherent in the adjudication scheme that a defendant will or may have to defend the same claim first in an adjudication, and later in court or in an arbitration. It is not self-evident that it is more oppressive for a party to be faced with both proceedings at the same time, rather than sequentially. As for the risk of inconsistent findings of fact, on any view this is inherent in the adjudication scheme. The answer to Mr Davies' first submission has been provided clearly and unequivocally by section 108(2)(a). Parliament has decided that a reference to adjudication may be made "at any time". I see no reason not to give those words their plain and natural meaning."
"(1) These Rules are a new procedural code with the overriding objective of enabling the court to deal with cases justly.
(2) Dealing with cases justly includes, so far as is practicable-
(a) ensuring that the parties are on an equal footing;
(b) saving expense;
(c) dealing with the case in ways which are proportionate-
(i) to the amount of money involved;
(ii) to the importance of the case;
(iii) to the complexity of the case;
(iv) to the financial position of each party;
(d) ensuring that it is dealt with expeditiously and fairly; and
(e) allotting to it an appropriate share of the court's resources, while taking into account resources to other cases."
"(a) Adjudication (whether pursuant to the 1996 Act or the consequential amendments to the standard forms of building and engineering contracts) is designed to be a quick and inexpensive method of arriving at a temporary result in a construction dispute.
(b) In consequence, adjudicators' decisions are intended to be enforced summarily and the claimant (being the successful party in the adjudication) should not generally be kept out of its money.
(c) In an application to stay the execution of summary judgment arising out of an Adjudicator's decision, the Court must exercise its discretion under Order 47 with considerations (a) and (b) firmly in mind
(d) The probable inability of the claimant to repay the judgment sum (awarded by the Adjudicator and enforced by way of summary judgment) at the end of the substantive trial, or arbitration hearing, may constitute special circumstances within the meaning of Order 47 rule 1(1)(a) rendering it appropriate to grant a stay (see Herschell).
(e) If the claimant is in insolvent liquidation, or there is no dispute on the evidence that the claimant is insolvent, then a stay of execution will usually be granted (see Bouygues and Rainford House).
(f) Even if the evidence of the claimant's present financial position suggested that it is probable that it would be unable to repay the judgment sum when it fell due, that would not usually justify the grant of a stay if:
(i) the claimant's financial position is the same or similar to its financial position at the time that the relevant contract was made (see Herschell); or
(ii) the claimant's financial position is due, either wholly, or in significant part, to the defendant's failure to pay those sums which were awarded by the adjudicator (see Absolute Rentals)."
I followed and applied this approach in Air Design Kent Ltd v Deerglen (Jersey) Ltd [2008] EWHC 3047 (TCC).
(a) at the time that the relevant contract was made, that is in September 2005, the filed accounts showed Makers as solvent and trading profitably. Profits were some £400,000 and the capital value of the company was some £1.5m. That is to be compared with a trading loss of over £8m and a negative capital value of over £10m. The claimant's financial position is now wholly different to its financial position in 2005.
(ii) There can be no doubt that Makers' financial position is not on any count wholly attributable to Camden's failure to pay those sums which might be awarded by an adjudicator in the future. Makers' claims are for some £4m which in large part (over £3m) relate to uncertified or otherwise unpaid sums allegedly due for work done. Given the trading loss of over £8m and the capital liability of over £10m, even if Makers succeed in full before the adjudicator, the current insolvency is not wholly due to Camden's failure to pay other sums due to Makers. The reference in the Wimbledon judgment to the claimant's financial position being due "in significant part" to the defendant's failure to pay needs to be looked at in the context of it being a cause of the claimant's poor financial position, which is significant in all the circumstances. I would find it difficult to see that, where, as here, the bulk of Makers' financial problems must be attributable to factors other than to Camden's failure to pay, a "significant part" of those problems is attributable to Camden. The current insolvency of Makers would on any count still be present. It is difficult to express a final view unless and until one sees what an adjudicator decides and on what basis.
(a) The failure to serve a Defence within the permitted time, without securing an extension of time was an oversight on the part of Makers or its Solicitors. It was thus purely fortuitous that Camden was able to enter judgment in default. But for that, the Court would have had no power to prevent Makers from pursuing an adjudication concurrently with the Court proceedings.
(b) It will at best be an exceptional course for the Court on setting aside a judgment to prevent a party from pursuing a statutory right to adjudicate at any time.
(c) This is not an exceptional case. Although the evidence currently before the Court shows clearly that Makers is insolvent and would be in no position to pay back any money paid out by Camden pursuant to any future adjudication, it is at least possible that other information and circumstances may be applicable at that later stage.
(d) Parliament has altered the commercial balance as between employers and contractors by passing the 1996 Act. It has given parties the lever of adjudication. The threat to adjudicate might encourage settlement; an actual adjudication decision might induce a final settlement.
(e) If Makers or those financing Makers wish to take the risk of proceeding to adjudication, they will bear in mind the potential advantages in so doing and the very real risk that a Court could well stay any judgment to enforce any adjudication decision in Makers' favour by reason of insolvency and inability to repay. The Court should generally not interfere in the commercial relationship between the parties. The parties should be permitted to pursue such courses as are open to them.
(a) Unless grounds exist pursuant to CPR Part 25 upon which to order security for costs, the imposition of a security would in effect involve punishing the Defendant in this case. However, in an appropriate case, it is open to the Court to impose a condition requiring security for costs on setting aside a default judgment where the defendant is also a counter-claimant.(b) Although the evidence establishes in this case that Makers would be unable to pay Camden's costs if ordered to do so (within the meaning of CPR Part 25.13.1), this would be an inappropriate stage at which to order security.
(c) The court may make an order for security from costs in favour of a claimant such as Camden in respect of the counterclaim brought against it if the counterclaim raises issues which go beyond the defence of its claim (see Thistle Hotels Ltd v Gamma Four Ltd 2004 EWHC 322)
(d) Camden's claim against Makers is predicated upon the basis that it was entitled to terminate the contract. Makers' defence is that Camden was not entitled to terminate the contract and that Camden repudiated the contract
(e) As the parties have agreed and the court will order, there will be a trial on liability which will take place in November 2009. Directions will be given accordingly so that costs will not be incurred to any significant extent in relation to the counterclaim. If any order for security for costs was to be made, the most appropriate time to make it would be at the stage immediately after any judgement on liability when it becomes clear that the counterclaim will be pursued and that the parties will commence incurring expenditure in relation thereto.
(f) As security for costs will not be ordered against a defendant in relation to its defence of a claim against it, it should not be ordered at this stage when costs are only or primarily being incurred in relation to the pursuance of Camden's claim and Makers' defence of that claim.
Costs
(a) Makers has won its application; the need for such application however arose as a result of Makers' default in serving its Defence in time. Makers offered to pay its own and Camden's costs at an early stage.
(b) Makers contested a number of issues in the course of the occasion upon which it failed; some time and costs was therefore wasted.
(c) Given that it was necessary to consider the Insolvency Issue, my findings on that aspect should be of use to the parties in planning for the future conduct of this case and for the saving of expense.
(d) Camden acted reasonably in defending the application.
(e) Makers' cost bill if assesses by a cost judge would probably have been reduced somewhat in any event.
Conclusion