QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
EUROPEAN DYNAMICS SA |
Claimant |
|
- and - |
||
HM TREASURY (sued as Buying Solutions) |
Defendant |
____________________
Michael Bowsher QC and Elisa Holmes (instructed by The Treasury Solicitor) for the Defendant
Hearing date: 16 December 2009
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
The Background
The Statutory Framework
"(1) In these Regulations, an "economic operator" means a contractor, a supplier or a supplier or a services provider.
(2) When these Regulations apply, a contracting authority shall not treat a person who is not a national of a relevant State and established in a relevant State more favourably than one who is.
(3) A contracting authority shall (in accordance with Article 2 of the Public Sector Directive)—
(a) treat economic operators equally and in a non-discriminatory way; and
(b) act in a transparent way.
5 (1) Subject to paragraph (3), these Regulations apply whenever a contracting authority seeks offers in relation to a proposed public supply contract, public works contract, Part A services contract, framework agreement or dynamic purchasing system other than a contract, framework agreement or dynamic purchasing system excluded from the application of these Regulations by regulation 6 or 8.
19 (1) A contracting authority which intends to conclude a framework agreement shall comply with this regulation.
(2) Where the contracting authority intends to conclude a framework agreement, it shall—
(a) follow one of the procedures set out in regulation 15, 16, 17 or 18 up to (but not including) the beginning of the procedure for the award of any specific contract set out in this regulation; and
(b) select an economic operator to be party to a framework agreement by applying award criteria set in accordance with regulation 30.
30 (1) Subject to regulation 18(27) and to paragraphs (6) and (9) of this regulation, a contracting authority shall award a public contract on the basis of the offer which—
(a) is the most economically advantageous from the point of view of the contracting authority or
(b) offers the lowest price.
(2) A contracting authority shall use criteria linked to the subject matter of the contract to determine that an offer is the most economically advantageous including quality, price, technical merit, aesthetic and functional characteristics, environmental characteristics, running costs, cost effectiveness, after sales service, technical assistance, delivery date and delivery period and period of completion.
(3) Where a contracting authority intends to award a public contract on the basis of the offer which is the most economically advantageous it shall state the weighting which it gives to each of the criteria chosen in the contract notice or in the contract documents or, in the case of a competitive dialogue procedure, in the descriptive document.
(4) When stating the weightings referred to in paragraph (3), a contracting authority may give the weightings a range and specify a minimum and maximum weighting where it considers it appropriate in view of the subject matter of the contract.
47 (1) The obligation on—
(a) a contracting authority to comply with the provisions of these Regulations, other than regulations 14(2), 30(9), 32(14), 40 and 41(1), and with any enforceable Community obligation in respect of a public contract, framework agreement or design contest (other than one excluded from the application of these Regulations by regulation 6, 8 or 33); and
(b) a concessionaire to comply with the provisions of regulation 37(3);
Is a duty owed to an economic operator
(2) The duty owed to an economic operator in accordance with paragraph (1), except in relation to—
(a) a Part B services contract…
is a duty owed also to a GPA economic operator.
(3) The duty owed to a GPA economic operator referred to in paragraph (2) shall only be owed by the Secretary of State for Defence in relation to public supply contracts for the purchase or hire of goods specified in Schedule 5…
(5) In this regulation and notwithstanding regulation 4, references to an "economic operator" include, where the duty owed in accordance with paragraph (1) is the obligation on a concessionaire to comply with regulation 37(3), any person—
(a) who sought, who seeks or would have wished, to be the person to whom a contract to which regulation 37(3) applies is awarded; and
(b) who is a national of a relevant State and established in a relevant State.
(6) A breach of the duty owed in accordance with paragraph (1) or (2) is actionable by any economic operator which, in consequence, suffers, or risks suffering, loss or damage and those proceedings shall be brought in the High Court.
(7) Proceedings under this regulation must not be brought unless—
(a) the economic operator bringing the proceedings has informed the contracting authority or concessionaire, as the case may be, of the breach or apprehended breach of the duty owed to it in accordance with paragraph (1) or (2) by that contracting authority or concessionaire and of its intention to bring proceedings under this regulation in respect of it; and
(b) those proceedings are brought promptly and in any event within 3 months from the date when grounds for the bringing of the proceedings first arose unless the Court considers that there is good reason for extending the period within which proceedings may be brought.
(8) Subject to paragraph (9), but otherwise without prejudice to any other powers of the Court, in proceedings brought under this regulation the Court may—
(a) by interim order suspend the procedure leading to the award of the contract or the procedure leading to the determination of a design contest in relation to the award of which the breach of the duty owed in accordance with paragraph (1) or (2) is alleged, or suspend the implementation of any decision or action taken by the contracting authority or concessionaire, as the case may be, in the course of following such a procedure; and
(b) if satisfied that a decision or action taken by a contracting authority was in breach of the duty owed in accordance with paragraph (1) or (2)—
(i) order the setting aside of that decision or action or order the contracting authority to amend any document;
(ii) award damages to an economic operator which has suffered loss or damage as a consequence of the breach; or
(iii) do both of those things.
(9) In proceedings under this regulation the Court does not have power to order any remedy other than an award of damages in respect of a breach of the duty owed in accordance with paragraph (1) or (2) if the contract in relation to which the breach occurred has been entered into.
(10) Notwithstanding sections 21 and 42 of the Crown Proceedings Act 1947, in proceedings brought under this regulation against the Crown the Court shall have power to grant an injunction."
"28…It would be strange if a complaint could not be brought until the process has been completed. It may be too late to challenge the process by then. A contract may have been concluded with the successful bidder. Even if that has not occurred, the longer the delay, the greater the cost of re-running the process and the greater the overall cost. There is every good reason why Parliament should have intended that challenges to the lawfulness of the process should be made as soon as possible. They can be made as soon as there has occurred a breach which may cause one of the bidders to suffer loss. There was no good reason for postponing the earliest date when proceedings can begin beyond that date. Mr. Lewis suggests that there is such a reason. He points out that if, in a case such as this, the limitation period runs from the date of publication of the tender documents, it will be possible for the contracting authority to rule out any real possibility of a challenge by issuing an invitation in breach of the regulations and then not taking any further steps in relation to tenders until after the three months period has expired. I confess that I find this an unlikely state of affairs, but I can see that it might conceivably happen. If it did, a service provider who wished to bring proceedings might have a good case for an extension of time: it would all depend on the facts. In my view, this cannot affect the plain meaning of regulation 32(2). I would therefore hold that the right of action which Jobsin asserts in the present case first arose on or about 14th August 2000. The essential complaint which lies at the heart of the proceedings is that there was a breach of regulation 21(3), in that the Briefing Document did not identify the criteria by which the DOH would assess the most economically advantageous bid."
"33. These arguments are formidable and were compellingly presented. But I am in no doubt that the judge was wrong to exercise his discretion to extend time in the circumstances of this case. First, I do not accept that it was unreasonable to expect Jobsin to start proceedings before they were excluded from the tender process. On or about 14th August they were aware of all the facts that they needed to know in order to start proceedings. The judge seems to have been influenced by two factors in deciding that there was a reasonable objective excuse for Jobsin's failure to start proceedings before they were excluded from the short list. These were that (a) they had no reason to believe that there had been any breach of the regulations and therefore no reason to consult solicitors to obtain advice as to the true legal position, and (b) even if they had known that there was a breach of the regulations, there were strong commercial reasons why it would have been reasonable for them to decide not to start proceedings until the tender process had been completed. I do not accept that either of these was a sufficient reason to extend time. As regards (a), in my view the lack of knowledge of the legal significance of facts of which a bidder is aware will not usually be a good reason for extending time. Although the maxim "ignorance of the law is no excuse" is not a universal truth, it should not in my view be lightly brushed aside. Regulation 32(4) specifies a short limitation period. That is no doubt for the good policy reason that it is in the public interest that challenges to the tender process of a public service contract should be made promptly so as to cause as little disruption and delay as possible. It is not merely because the interests of all those who have participated in the tender process have to be taken into account. It is also because there is a wider public interest in ensuring that tenders which public authorities have invited for a public project should be processed as quickly as possible. A balance has to be struck between two competing interests: the need to allow challenges to be made to an unlawful tender process, and the need to ensure that any such challenges are made expeditiously. Regulation 32(4)(b) is the result of that balancing exercise. It may often be the case that a service provider is not aware of the intricacies of regulations such as the 1992 regulations, and has little or no understanding of how they should be interpreted. If ignorance of such matters were routinely to be regarded as a good reason for extending the time for starting proceedings, the clear intent of regulation 32(4)(b), that proceedings should normally be started promptly and in any event not later than three months after the right of action first arose, would be frustrated."
The Law and Practice
"It is no part of the court's function at this stage of the litigation to try to resolve conflicts of evidence on affidavit as to facts on which the claims of either party may ultimately depend nor to decide difficult questions of law which call for detailed argument and mature considerations. These are matters to be dealt with at the trial."
As to balance of convenience, he went on to say:
"As to that, the governing principle is that the court should first consider
whether if the plaintiff were to succeed at the trial in establishing his right
to a permanent injunction he would be adequately compensated by an award of damages for the loss he would have sustained as a result of the defendant's continuing to do what was sought to be enjoined between the time of the application and the time of the trial. If damages in the measure recoverable at common law would be adequate remedy and the defendant would be in a financial position to pay them, no interlocutory injunction should normally be granted, however strong the plaintiff's claim appeared to be at that stage. If, on the other hand, damages would not provide an adequate remedy for the plaintiff in the event of his succeeding at the trial, the court should then consider whether, on the contrary hypothesis that the defendant were to succeed at the trial in establishing his right to do that which was sought to be enjoined, he would be adequately compensated under the plaintiff's under-taking as to damages for the loss he would have sustained by being prevented from doing so between the time of the application and the time of the trial. If damages in the measure recoverable under such an undertaking would be an adequate remedy and the plaintiff would be in a financial position to pay them, there would be no reason upon this ground to refuse an interlocutory injunction.
It is where there is doubt as to the adequacy of the respective remedies in
damages available to either party or to both, that the question of balance of convenience arises. It would be unwise to attempt even to list all the
various matters which may need to be taken into consideration in deciding where the balance lies, let alone to suggest the relative weight to be attached to them. These will vary from case to case."
So far as is material to this case, that remains the law and practice.
"16. The second feature is the basis upon which Jones J decided to refuse an interlocutory injunction and the Court of Appeal decided to grant one. It is often said that the purpose of an interlocutory injunction is to preserve the status quo, but it is of course impossible to stop the world pending trial. The court may order a defendant to do something or not to do something else, but such restrictions on the defendant's freedom of action will have consequences, for him and for others, which a court has to take into account. The purpose of such an injunction is to improve the chances of the court being able to do justice after a determination of the merits at the trial. At the interlocutory stage, the court must therefore assess whether granting or withholding an injunction is more likely to produce a just result. As the House of Lords pointed out in American Cyanamid Co v Ethicon Ltd [1975] AC 396, that means that if damages will be an adequate remedy for the plaintiff, there are no grounds for interference with the defendant's freedom of action by the grant of an injunction. Likewise, if there is a serious issue to be tried and the plaintiff could be prejudiced by the acts or omissions of the defendant pending trial and the cross-undertaking in damages would provide the defendant with an adequate remedy if it turns out that his freedom of action should not have been restrained, then an injunction should ordinarily be granted.
17.In practice, however, it is often hard to tell whether either damages or the cross-undertaking will be an adequate remedy and the court has to engage in trying to predict whether granting or withholding an injunction is more or less likely to cause irremediable prejudice (and to what extent) if it turns out that the injunction should not have been granted or withheld, as the case may be. The basic principle is that the court should take whichever course seems likely to cause the least irremediable prejudice to one party or the other. This is an assessment in which, as Lord Diplock said in the American Cyanamid case [1975] AC 396, 408:
"It would be unwise to attempt even to list all the various matters which may need to be taken into consideration in deciding where the balance lies, let alone to suggest the relative weight to be attached to them."
18.Among the matters which the court may take into account are the prejudice which the plaintiff may suffer if no injunction is granted or the defendant may suffer if it is; the likelihood of such prejudice actually occurring; the extent to which it may be compensated by an award of damages or enforcement of the cross-undertaking; the likelihood of either party being able to satisfy such an award; and the likelihood that the injunction will turn out to have been wrongly granted or withheld, that is to say, the court's opinion of the relative strength of the parties' cases.
19…What is required in each case is to examine what on the particular facts of the case the consequences of granting or withholding of the injunction is likely to be. If it appears that the injunction is likely to cause irremediable prejudice to the defendant, a court may be reluctant to grant it unless satisfied that the chances that it will turn out to have been wrongly granted are low; that is to say, that the court will feel, as Megarry J said in Shepherd Homes Ltd v Sandham [1971] Ch 340, 351, "a high degree of assurance that at the trial it will appear that at the trial the injunction was rightly granted." …
21…Factors which the court might have taken into account in this case if there had been a triable issue were, first, that the injunction required the bank to continue against its will to provide confidential services for the plaintiffs; secondly, that the injunction would require the bank to continue to incur reputational risks and possible exposure to legal action; thirdly, that it was by no means clear that the plaintiffs would be able to satisfy a claim under the cross-undertaking in damages; fourthly, that the plaintiffs' case was, even if not (as their Lordships think) hopeless, certainly very weak, and fifthly, that the plaintiffs could no doubt have obtained alternative banking services from any bank whom they could persuade that they were not running a fraudulent scheme. It is unnecessary to say what should have been the outcome of a weighing of these factors because that was a matter for the discretion of the judge but they suggest that, even if there had been a serious issue to be tried, it is by no means obvious that Jones J was wrong to refuse an injunction."
Serious Issues to be Tried
"Each requirement…in the ITT is subject to evaluation and will be assessed on a scale of 0 to 5 as specified below; all values within this range may be used by the evaluators.
0 | Unanswered or inadequate response representing 0% of the stated Maximum Available Mark |
1 | Indicates a marginal response representing 10% of the stated Maximum Available Mark |
2 | Represents 30% of the stated Maximum Available Mark |
3 | Indicates a reasonable response representing 50% of the stated Maximum Available Mark |
4 | Represents 70% of the stated Maximum Available Mark |
5 | Indicates an excellent response representing 100% of the stated Maximum Available Mark |
Damages as an Adequate Remedy
(a) The main argument has been that damages would be difficult or nearly impossible to assess and given cases such as Letting International Ltd v London Borough of Newham [2007] EWCA Civ 1522 that is or may be sufficient to avoid or overcome the "damages as an adequate remedy" hurdle.
(b) I do not see however that damages are or should be difficult to assess. The fact that damages may not be a perfect remedy is not material (see Peaudouce SA v Kimberly Clark Ltd [1996] FSR 680).
(c) Although there may well be other ways of assessing damages in this case, at least a sensible way could well be:
(i) In English law, damages can always be and are often assessed on a loss of chance basis (see Chaplin v Hicks); the Court does the "best that it can" to assess damages when it is clear that there must have been some loss but it is difficult to assess.
(ii) One can assess on the basis of projections and previous framework type agreements entered into by the Defendant and indeed on the actual operation of the proposed new framework agreements (say, in 2010 before any damages are assessed) what the likely value or range of values of the work will be over the period of the new agreements. For instance there is evidence that some £84m's worth of work was let through the earlier Lots 1, 3 and 6 agreements in the last financial year.
(iii) Given that there are some 10 contractors who will be available under each framework agreement, it will be necessary to assess what the share of the Claimant (if successful on liability) would be over the period of the agreements. That can be done on a number of different bases; it may be that statistically the 7th or 10th or 1st in these types of agreements receive a particular percentage or range of the contracts and jobs which are going. It may be that based on say the first year of operation of the new framework agreements the contractor who is in the position in which the Claimant would have been if successful does attract, say, 5% or 15% of the work in value terms.
(iv) Once one has a figure or range of figures for the value of the overall work available over the lifetime of the framework agreements and one has a likely share available to the Claimant if it had been successful (or a range say between 5% and 10%), one then turns to assessing what the profit and possibly overhead share was or would have been. That is a relatively standard expert task; that percentage can be assessed by looking at the pricing actually adopted by the Claimant, other similar projects and its historic trading performance.
(v) One can then discount the figure to allow for the receipt of the damages before some of the return would have been earned.
(d) There may well be other ways of calculating damages and I do not say that the above is necessarily the right way in this case because I do not have all the facts. However judged at this very early stage, there is no obviously insuperable difficulty in assessing damages.
Balance of Convenience
(a) There would be substantial prejudice to the Defendant. The old framework agreements are said to have expired and there are customers who are waiting for the new framework agreements to be in place. Some of those customers would in all probability go elsewhere to acquire the services which they would have secured through the new framework agreements.
(b) The earliest in practice that there could be a court resolution of the disputes between the parties in relation to liability is about 6 months, assuming that the Court could find time in a very busy diary. A six month delay would or could result in irreparable harm being done to the Defendant's reputation.
(c) There is a general public interest in a central and common public procurement route for services such as are on offer under the framework arrangements in this case; that arises in terms of cost savings as well as the use of similar and compatible products and services. If that route is effectively suspended for 6 months or more, damage will be done. Some of that damage would be particularly difficult to identify and prove, such as whether a particular customer would have placed an order with or through the Defendant within the period of any injunction.
(d) There is no reliable evidence of reputational damage to the Claimant if it does not obtain an injunction. A statement from Mr Velentzas, the Managing Director, dated 16 December 2009 was belatedly handed in by the Claimant part way through the hearing on 16 December 2009 which says, without amplification, that the exclusion of the Claimant from these framework agreements "will defame the Company in the whole market and to its strategic partners which will impact its work all over Europe"; this is so vague that it does not assist the Court at this stage. The trial on liability will determine if the Claimant was rightly or wrongly excluded from the final lists of successful tenderers and that could be only 6 months away.
(e) There is no evidence that the Claimant will not be able to seek or obtain other works to replace what it might have secured if it had been successful here. There is no obvious or clear evidence that the Claimant will lose market share.
(f) If it succeeds on liability, damages will adequately compensate the Claimant for such loss as is established without any commercial risk other than having to prove its quantum case in court.
(g) There is an added difficulty that, if an injunction was granted for, say, 6 months, there must be real risk that the whole tender process would have to be re-run and, given the knowledge acquired by the Claimant, it might be necessary to exclude the Claimant and indeed others who tendered on the basis that there would not and could not be equality of opportunity in the new tender process. Having had a tender process that was presumably intended to produce the best qualified at least to tender, it would be unfortunate and probably contrary to the public interest if the second tendering exercise had to exclude the best tenderers.
Miscellaneous
Decision
Costs