QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
L. BROWN & SONS LIMITED |
Claimant |
|
- and - |
||
CROSBY HOMES (NORTH WEST) LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
Nerys Jefford QC (instructed by Messrs Eversheds) for the Defendant
____________________
Crown Copyright ©
MR. JUSTICE AKENHEAD :
Introduction
The arbitration
"7.Both parties seek disclosure of documents by the other. For that purpose the parties are to make written application to the other and co-operate with one another.8. If either party wishes to apply for an order for disclosure, the application is to:
(a) be made by no later than 28 days after delivery of the Statement of Reply to Defence to Counterclaim; and(b) be accompanied by evidence of a written request for disclosure of the documents or class of documents in question."
A two day hearing was fixed for 9 and 10 July 2007. In fact, both parties did produce a list of documents, Crosby's being dated 23 May 2007.
The evidence and arguments in the First Arbitration
"By April 2004 all or most of the apartments at Redbank had been sold, that is to say, contracts for their sale had been exchanged. However, the Works had been delayed. Crosby was concerned that the Plastering Completion Date of 30 April 2004 and the Date for Completion would not be met. Crosby's accounts were required to be prepared in accordance with an accounting policy imposed by Berkeley. Under the terms of the Berkeley accounting policy, if the Plastering Completion Date was achieved, then providing that contracts for sale had been exchanged, the first 70% of the profit on the Redbank apartments could be included in Crosby's accounts for the year ending 30 April 2004. At paragraph 3 of DT1 Mr Teague explains that was important because the profits in question had been included in the budget for the year and a failure to achieve the budget was likely not only to impact on the Crosby group but also on Berkeley because it is publicly quoted. Crosby therefore considered how the delay to the Works might be recovered so that Plastering Completion Date and the Date Completion could be achieved." (Paragraph 18 of the award)
(a) In April 2004, Crosby offered to Brown a completion bonus on various conditions including completion by the contractual completion date of 17 August 2004. A deed was drawn up to this effect. Crosby contended that that offer was never accepted and the deed not executed and in any event the terms were not fulfilled. The arbitrator referred to this as "the April Agreement".
(b) In July 2004, Crosby made Brown a further written offer of a completion bonus (for apartments handed over in August and September) and a waiver of liquidated damages if a "notice to complete" was served for all flats by 15 October 2004. This offer was accepted in writing but its terms were not fulfilled. That was common ground in the arbitration between the parties. This was referred to as "the July Agreement".
(c) Crosby then made a further written offer dated 7 October 2004 of a completion bonus for apartments certified by the NHBC by 15 October 2004 and a waiver of liquidated damages for properties if Crosby was able to complete the sale of every apartment by the end of October 2004. Crosby's case was that this offer was never accepted whilst Brown contended that this was the confirmation of an agreement already reached. In any case its terms were not fulfilled and no claim was made, as such, under this alleged agreement. This was referred to as "the 7 October Agreement".
(d) It was then alleged by Brown that there was an agreement on 14 October 2004 to extend the dates in the earlier 7 October Agreement to 15 November and the end of November 2004 respectively ("the 14 October Agreement").
(e) Finally, there was said by Brown to be a further agreement ("the November Agreement") whereby the parties agreed orally to exclude levels 10 and 11 from the 7 and the 14 October Agreements with at least one result that liquidated damages were not to be payable for late completion of levels 10 and 11.
(a) The April Agreement
(b) The 7 October Agreement
(c) The 14 October Agreement
(ii) It is clear that the arbitrator carried out a thorough review of the evidence and argument in relation to this alleged agreement. He considered the different points: motivation, management buy-out implications, commercial sense, other offers in writing, the principal witnesses' recollections of the meeting, evidence of other witnesses, waiver of liquidated damages, reversal of burden of proof, working to 15 November, abatement of bonus and later correspondence in March 2005. The arbitrator apparently considered each carefully and thoroughly.(iii) In dealing with motivation, the arbitrator rejected the suggestion that a saving in interest could be a motivator for Crosby in agreeing to pay bonuses to secure completions of sales by the end of November because the amount of interest saved would have been far less than the completion bonuses. Similarly, the auditing rules imposed by Berkeley which allowed incomes from completion within the four-month period after the end of the financial year to be brought back into the earlier financial year did not explain or provide a motive. Flats which were complete by the end of November were seven months after the end of Crosby's financial year. The arbitrator considered the rules contained in an "Audit Clearance Report" which had been disclosed and agreed with Mr. Teague's understanding of the policy.
(iv) I will not go into all the other reasons why the arbitrator formed the view that Crosby's evidence was to be preferred to Brown's. However, Mr. Murphy apparently in oral evidence conceded that the alleged offer made in respect of the alleged 14 October Agreement was a "gift horse". The arbitrator, perhaps unsurprisingly, formed the view that there was no commercial reason for Crosby to have made an offer as alleged (Paragraph 137). Again the absence of any confirmation or record in writing influenced the arbitrator.
(d) The November Agreement
(ii) Because the arbitrator had found that there was no agreement on 14 October, the case had to fail in relation to the November Agreement. He found that it was not credible that Crosby would have made an agreement as alleged, there being no commercial reason for Crosby to do so. There was no written confirmation of the alleged agreement.(iii) He rejected the case that there was any agreement in November as alleged either by way of variation of an earlier agreement or by way of a fresh agreement.
The law
"(1) A party to arbitral proceedings may (upon notice to the other parties and to the tribunal) apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award. A party may lose the right to object (see section 73 and the right to apply subject to the restrictions in section 70(2) and (3)).
(2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant ... (g) the award being obtained by fraud or the award or the way in which it was procured being contrary to public policy ...".
"Where any provisions of this Part requires an application or appeal to be made to the court within the specified time, the rules of court relating to the reckoning of periods, the extending or abridging of periods, and the consequences of not taking a step within the period described by the rules apply in relation to that requirement ...".
"(1) the court may vary the period of 28 days fixed by section 70(3) of the 1996 Act for (a) challenging the award under s.67 or 68 of the Act ..."
"48. The effect of s.80(5) is to introduce the broad discretionary approach under this rule and for applications for the extension of the 28 days time limit under ss. 67, 68 and 69 of the 1996 Act.
49. It is therefore necessary to identify the criteria applicable to such applications under the Arbitration Act, for they may differ from those applicable under the CPR.
50. In determining the relative weight that should be attached to discretionary criteria the starting point must be to take into account the fact that the 1996 Act is founded on a philosophy which differs in important respects from that of the CPR.
51. Thus, the twin principles of party autonomy and finality of awards which pervade the Act tend to restrict the supervisory role of the Court and to minimize the occasion for the Court's intervention in the conduct of arbitrations. Nowhere is this more clearly demonstrated than in s.68 itself where there was superimposed upon the availability of a remedy for what used to be called 'misconduct' by the arbitrator and was redefined as 'serious irregularity' a requirement that it had caused or would cause substantial injustice to the applicant. No longer was it enough to demonstrate failure by the arbitrator scrupulously to adhere to the audi alterem partem rule.
52. ... Further, the relatively short period of time for making an application for relief under ss. 67, 68, 69 also reflects the principle of finality. Once an award has been made the parties have to live with it unless they move with great expedition. Were it otherwise, the old mischief of over long unenforceability of awards due to the pendency of supervisory proceedings would be encouraged.
53. At this point it is necessary to have in mind the general principle set out in s. 1 of the 1996 Act:
"(1) the provisions of this Part are founded on the following principles, and shall be construed accordingly –
(a) the object of arbitration is to obtain the fair resolution of disputes by an impartial tribunal without unnecessary delay or expense; ..."
54. The reference to unnecessary delay is pertinent to identifying the relevant discretionary criteria …
56. It is however also to be remembered that the threshold requirement set out in s. 79(3)(b) for extension of time limits to which s. 79 relates - 'that a substantial injustice would otherwise be done' is not expressed to be applicable to extension of time under s. 80 (5). In that respect therefore a lower unfairness threshold must be presumed to be intended.
57. In approaching the identification the applicable criteria it is also important to take into account the fact that, at least in international arbitrations, English arbitration is probably the most widely chosen jurisdiction of all. It is chosen because of the ready availability of highly skilled and experienced arbitrators operating under a well-defined regime of legal and procedural principles in what is often a neutral forum. Supervisory intervention by the Courts is minimal and well-defined and the opportunities for a respondent with a weak case to delay the making of an award or to interfere with its status of finality are very restricted. Accordingly, much weight has to be attached to the avoidance of delay at all stages in an arbitration, both before and after an interim or final award. If the English Courts were seen by foreign commercial institutions to be over-indulgent in the face of unjustifiable non-compliance with time limits, those institutions might well be deterred from using references to English arbitration and their contracts. This is a distinct public policy factor which has to be given due weight in the discretionary balance.
58. On the other hand it has to be recognised that because of the extremely wide international nature of the market for English arbitration many of the parties may be located in remote jurisdictions and may have little or no previous experience of international or English arbitration. When these relatively unsophisticated parties find themselves involved in such an arbitration, it is only to be expected that they move somewhat more tentatively than would an international trading house well experienced in this field. It would therefore be wrong to fail to make at least some allowance for this factor in elevating the element of fault in failing to comply with time limits."
"(i) length of the delay;
(ii) whether, in permitting the time limit to expire and the subsequent delay to occur, the party was acting reasonably in all the circumstances;
(iii) whether the respondent to the application or the arbitrator caused or contributed to the delay;
(iv) whether the respondent to the application would by reason of the delay suffer irremediable prejudice in addition to the mere loss of time if the application were permitted to proceed;
(v) whether the arbitration has continued during the period of delay and, if so, what impact on the progress of the arbitration or the costs incurred in respect of the determination of the application by the Court might now;
(vi) the strength of the application;
(vii) whether in the broadest sense it would be unfair to the applicant for him to be denied the opportunity of having the application determined."
"As to (vi), it is right that Andrew Smith J did not explicitly refer to the strength, or indeed the weakness, of the claim. Perhaps this was not discussed before him. Mr. Hancock [Counsel] suggested that the present situation was, in any event, one where courts would not engage in any detailed way with the prospects, except perhaps in a clear case. In my judgment, this was, and is, clearly not a case where the owners' claim can be regarded as so strong that it would obviously be a hardship for them not to be able to pursue it; if anything, rather the contrary. On any view, the prospects here were clearly not such as to have affected what was otherwise the judge's view as to the right exercise of his discretion."
"Finally, as to factor (vii), general considerations of fairness, the judge must have had well in mind considerations of overall justice and fairness. They must, however, always be viewed in the particular context that Parliament and the courts have repeatedly emphasized the importance of finality and time limits for any court intervention in the arbitration process."
"Whilst the strength of the application is one, which the Court can take into account, it is self-evident in the present case that there are expensive conflicts of evidence between the parties. ... At all events, I am not in a position to evaluate the evidence as it appears on the statements in a way which enables me to take this into account as a factor one way or the other in the context of an extension of time."
It is perhaps of interest that in the Thyssen case the application for extension of time was, none the less, rejected.
(a) The time limits for any court intervention in the arbitration process (including by way of application under section 68) are important and reflect the policy expressed in section 1 of the 1996 Act.
(b) Factors (i) to (iii), that is the length of delay, its causation and the reasonableness of the parties' conduct as identified by Colman J in the Kalmneft case are the primary factors.
(c) The weight to be given to factor (vi) (the strength of the section 68 application) is not a primary factor. However, an intrinsically weak case will count against the application for extension whilst a strong case would positively assist the application. An application which is neither strong nor weak will not add significant weight to the application for extension of time.
"17. It would be unwise in my view to attempt to define the circumstances in which an award might be set aside or remitted on public policy grounds, but in the light of that comment and of the language of sub-s. (2)(g) as a whole I think that where the successful party is said to have procured the award in a way which is contrary to public policy it will normally be necessary to satisfy the Court that some form of reprehensible or unconscionable conduct on his part has contributed in a substantial way to obtaining an award in his favour. Moreover, I do not think that the Court should be quick to interfere under this section. ... the expressions 'serious irregularity' and 'substantial injustice' are intended to be reserved for only the most serious cases. ....
19. Where an important document which ought to have been disclosed is deliberately withheld and as a result the party withholding it has obtained an award in his favour the Court may well consider that he has procured that award in a manner contrary to public policy. After all, such conduct is not far removed from fraud. The position is more difficult, however, where there has been a failure to disclose a document as a result of negligence or a simple error of judgment. ...
21. ...I do not think that proceeding with a reference following an innocent failure to disclose a document, even one of importance, can properly be described as acting contrary to public policy. If anything, the withholding of a document under these circumstances can more nearly be equated to what used in some cases to be described as 'procedural mishap' and its subsequent discovery to the discovery of fresh evidence. Under the Arbitration Act, 1950 the Court had a wide jurisdiction to set aside or remit an award and would sometimes do so, for example, where fresh evidence came to light or there had been some misunderstanding not amounting to misconduct. ...
22. The scheme embodied in s. 68 of the Arbitration Act, 1996 is quite different. An application to challenge the award may only be made on the grounds of serious irregularity which is itself carefully defined in sub-s. (2). The Court has no general jurisdiction to interfere with the working of the arbitral process and some of the grounds on which the Court would formally have acted find no place in s. 68. One such ground, which is particularly relevant for the present case, is the discovery of new evidence: the Court no longer has the power to remit an award simply on the grounds that new evidence has come to light. I agree with Lord Goldsmith [counsel for the respondent] that to allow a challenge to the award to be made on the grounds of an innocent failure to give proper disclosure would be contrary both to the spirit and to the wording of the Act."
"Whichever limb of section 68(2)(g) of the Act is relied on by the Claimants, they must establish that the Defendants acted in such a way as to obtain the award by fraud or to procure it in a way which was reprehensible or involved unconscionable conduct. .... The section 68 jurisdiction is a 'longstop' and, to some extent at least, the existence of lying witnesses must be considered, if not an ordinary incident of litigation/arbitration, at least one that is not uncommon. It is for the parties to prepare for hearings, whether in Court or arbitration and to adduce the evidence which they wish to establish the truth. If a decision is to be challenged on the basis of false evidence, this can only be done by an applicant where the Defendant can fairly be blamed for the adducing of that evidence and the deception of the Tribunal. In the present case, it can make no difference whether the application is made on the basis that the Award was obtained by fraud or procured in a manner that is contrary to public policy. In each case the Claimant must establish that the Defendant was responsible for the fabrication of perjured evidence, which has brought about a result which has caused them substantial injustice."
(i) The deliberate withholding of documents which had been ordered to be disclosed in the arbitration may in certain circumstances be considered to be reprehensible conduct and thus contrary to public policy under S.68(2)(g).
(ii) It must, at least, be less reprehensible (if reprehensible at all) for a party to withhold disclosure where disclosure has not as such been ordered by the arbitrator. Under some agreed or standard procedures for disclosure (for instance the IBA Rules) disclosure is voluntary unless specific documents are either agreed or ordered to be disclosed.
(iii) On balance, I consider that the withholding or non-disclosure of documents which have not been ordered to be disclosed by the Arbitrator or have not been agreed to be disclosed, cannot be described as reprehensible or fraudulent unless such non-disclosure is clearly part of some other fraud or reprehensible conduct on the part of the non-disclosing party.
(iv) Lying, being not uncommon in arbitration or in civil proceedings in general, can be a basis upon which an award is obtained by fraud or in a way which is contrary to public policy but where the credibility of the witness in question was a primary feature of the arbitration or the arbitration hearing it is less likely that it will be considered to be a serious irregularity.
(v) If there are grounds under Section 68(2)(g) based on lying or deception on the part of the respondent to the application, it is necessary to demonstrate that the award was dependent upon or was reached as a result of the lying or deception.
(vi) If the grounds under Section 68(2)(g) are established, it is still necessary to show that substantial injustice would be caused to the applicant as a result thereof. That may prove not to be very difficult to establish if the grounds under Section 68(2)(g) are established.
The delay
"Why was this not disclosed in Arbitration 1 as item 1.1 relates to progress in October and apartments signed-off by NHBC? It provides motive as to whether incentive agreements were extended. Please explain the serious omission from the disclosure in arbitration 1."
"The disclosure of documents which are clearly relevant to the issues that were decided by the arbitrator in the first arbitration between our clients, which were not disclosed in that arbitration."
Mr. Bate awaited Eversheds' urgent response to the issues raised.
"We will reply to that letter and attach schedule in detail when we have had an opportunity to go through the schedule ...
We have no reason to suspect that the affidavits sworn by Mr. Teague and Mr. Bridge during the course of the first arbitration between the parties were incorrect or insufficient in any way ..."
"Had your client disclosed these documents they would have opened up a further line of cross-examination for your client's witnesses but would have undoubtedly supported our client's case on motive. We are certain of this because of the references in the note at 10 November 2004 to the criticality of the NHBC issuing certificates on 10/11 and 12 November, e.g:
D T-critical to obtain search. But if outst. Worked to much and not completing 2 weeks to end.
Our client's counsel did not have the opportunity to cross-examine Mr. Teague on this cryptic but important note."
"Pursuant to CPR 31.23 our client can bring proceedings for contempt of court. CPR 31.23 provides the proceedings may be brought against the person if he makes, or causes to be made, a false disclosure statement without an honest belief in its truth. Pursuant to this our client is considering bringing proceedings for contempt of court against Mr. Bridge, Mr. Teague, Crosby Homes (North West) Limited.
In the alternative our client can bring proceedings for breach of contract or negligence against the same persons, in respect of the duty to disclose relevant documents further to the agreements made by the arbitration agreement as varied by the subsequent agreements of the parties.
Further or in the alternative, our client can apply to the court to challenge the arbitrator's decisions on the grounds of serious irregularity or that it offends against the interests of justice and principles of fairness enshrined in the Arbitration Act 1996.
In the light of the above, our client requires your confirmation by immediate return that your client will:
(I) Immediately repay to it the sum of £198,747.36 paid on Friday 2 November 2007 in respect of the Arbitrator's Award Number 01 ...
(III) enter into a settlement agreement confirming that the award in Arbitration 1 is invalid and that Arbitration 2 can proceed on the footing that your client is not entitled to levy liquidated and ascertain damages;
(IV) pay our client's costs at Arbitration 1 in their entirety (it follows that your client would also have to agree that it is not entitled to any costs of Arbitration 1) to be assessed if not agreed.
If your client does not provide this confirmation by immediate return or does not accept these conditions, then, given the serious nature of these issues and the fact that our client's time for applying to court to challenge the arbitrator's award is running out, our client will instruct us to:
1. as soon as reasonably practicable, issue proceedings in the Technology and Construction Court to claim the relief set out above ...
2. as soon as reasonably practicable issue proceedings for contempt of court against Mr. Bridge, Mr. Teague and Crosby Homes (North West) Limited and any other relevant person;
3. as soon as reasonably practicable, issue proceedings in the Technology and Construction Court to challenge the Arbitrator's Award and Arbitration 1."
(a) Mr. Bate had known for some five weeks that documents which he believed should have been disclosed in the First Arbitration had not been.
(b) He had had a full and sufficient opportunity to take instructions from his clients by 23 November 2007. Indeed I assume that he did have instructions to write the letter which he did write on 23 November 2007.
(c) He knew that the time for the lodging of an application under Section 68 was 23 November 2007.
(d) He believed on one ground or another that the alleged non-disclosure of documents in the First Arbitration in so far as it impacted on the evidence given by Mr. Teague and Mr. Bridge was such that it could found an application in effect to have the award in the First Arbitration set aside.
(e) He had by then had plenty of opportunity to examine the Missing Documents against the evidence and the award of the Arbitrator to determine whether or not there were properly arguable grounds to establish a viable argument under Section 68.
(f) He made no attempt to contact counsel with regard to the Section 68 application in November at all.
"We require a response immediately.
If we do not receive a response by 4 p.m. tomorrow, Friday 30 November 2007, our instructions are to commence proceedings without further recourse or notice to you."
(a) A consideration of the award shows that there were in essence substantive areas of disagreement in relation to the April agreement, the 7 October, 14 October and November agreements.
(b) There were transcripts of the evidence available together with the written opening and closing submissions and the witness statements or affidavits from the parties. There clearly was not a very large amount of relevant contemporaneous documentation going to the issues about these agreements.
(c) What was required was an analysis against the Arbitrator's award of the evidence given in writing and at the hearing by, primarily, Mr. Teague. That analysis needed to take into account the Missing Documents which in essence only comprised some six or seven new documents.
The "Missing Documents"
A. GTMS Weekly Status Report No 2
(i) Although the front page relates to October dates, the inside suggests that the report relates to 20-25 September 2004.
(ii) Paragraph 9.4 forecasts completion in the week commencing 25 October 2004.
(iii) There is nothing obvious in this forecast which adds credence to Brown's case about the 7 October 2004 agreement.
(iv)The highest that Mr Bate can put it (Paragraph 9.30 (c) of his first statement) is that "Crosby might realistically have (and the Arbitrator might realistically have found) been pursuing internally at least an alternative target date later than 15 October 2004".
(v) However, the undisputed evidence was that Crosby had offered bonuses in writing for any dwellings completed by 15 October and a waiver of liquidated damages if all the dwellings were completed by the end of October 2004. Thus, the terms of the offer anticipated completion of some dwellings by mid October and the possibility of the rest being complete by the end of October.
(vi) I simply do not see that this Status report is obviously prejudicial to the case advanced by Crosby or that it should have been disclosed.
B. GTMS Weekly Status Reports No 4 and 5 (11-15 and 18-22 October)
(i) These explain in apparently uncontroversial terms the progress of the work to date and describe work remaining to be done. For instance there was concern that the external envelope work was falling behind.
(ii) There is some discussion about the NHBC inspector "signing off" flats or not doing so.
(iii) It is implied, if not stated, by Mr Bate (Paragraph 9.38) that in some way the contents of these status reports was such that they demonstrate that there would be motivation for Crosby to extend the incentive agreements until the end of November.
(iv) I do not see that these reports do that at all. Whilst the NHBC did have to sign off before the legal completions could be effected, there is no obvious hint let alone expression that the work had to be finished by the end of November. The reports do no more than indicate that completion of the work is being progressed as quickly as possible.
(v) Again, I simply do not see that these reports are obviously prejudicial to the case advanced by Crosby or that they should have been disclosed.
C. GTMS Weekly Status Report No 7 (1-5 November)
(i) This is said to have had Mr Teague's writing on it beside what is said to have been the key part of the report:
"1.1 Programme
The original brief from Crosby was to "serve notice" at the end of this week-15th Oct on 49 no. apartments across the two cores with purchasers possibly moving in at the end of October.
This did not happen. There were two key reasons; the scaffold was not dropped as planned which impacted on…completing the external areas…The second …was that Crosby's Construction Manager considered the apartment [sic] to be of a very low standard…
A set of revised dates was the agreed. The apartment signoff by NHBC and Building Control and issue of warranties/certificates had to be the 12th November 2004 3 pm. This is the last Crosby serving notice date in 2004-purchasers can occupy the apartments form 26th November 2004".
(ii) This is said to show that, because there was said to be a "last serving notice" date of 12 November 2004, this provides support for the proposition that Crosby had an incentive to complete work and get the NHBC in because there was evidence that legal completion could have been achieved by the end of November so that 30% of turnover and profit represented by such completions could be taken into possibly the previous company year's accounts (ending April 2004). This, it is said, supports the proposition that Mr Teague was lying about possibly the October and the November agreements.
(iii)Whilst that proposition is a possible one, the entry does not necessarily support it. Presumably, and indeed I was told without demur that dates of completion were provided during the arbitration. The entry may well mean no more than there was unlikely to be any more NHBC signing off after 12 November in 2004 for administrative reasons. This entry does not obviously impact on the evidence about the October agreements, from a historical perspective or at all.
(iv) If anything the document does not impact on the November agreement because that agreement relates to levels 10 and 11 which on Brown's case were not going to be completed by the end of November 2004 in any event.
(v)At its highest, this document, to borrow from the old Rules of the Supreme Court and the Peruvian Guano case, might have led to a possibly relevant line of enquiry in the arbitration. I do not see that it necessarily points to Mr Teague's evidence having been dishonest.
(vi)As to whether this document should have been disclosed even if formal standard disclosure had been ordered, I consider that this involved a judgement call as a result of which different solicitors might have disclosed or not.
D. Mr Myall's note of 8 November 2004
(i)This note recorded relatively informal notes of a meeting attended by Mr Murphy, Mr Teague, Mr Bridge and Mr Myall. This was the meeting at which the alleged November 2004 agreement was reached. Mr Murphy's version was that he was effectively instructed to suspend work on Levels 10 and 11 whilst Crosby's case was that it was Mr Murphy who suggested it so as to concentrate on completing levels 1 to 9.
(ii) This note materially says:
"BM [Mr Murphy] feels ignore level eleven & reallocate resources to 9 and 10 [therefore] give Core A&B to 10 and 9"
(iii) On its face it does not support the Brown case at all and it does support the Crosby case. Indeed, it only relates to Level 11.
(iv) It was accepted that this document ought to have been disclosed albeit not prejudicial to Crosby's case. However, I do not see how this could support an argument that this document begins to support an argument that Mr Teague lied about the meeting on 8 November 2004, given that it supports if anything his evidence.
E. GTMS note of meeting on 10 November 2004
(i) This meeting was one attended by amongst others Mr Teague, the GTMS team ( including Mr Myall) and a Mr Flewker-Trattles of Brown. The latter was not called by Brown as a witness.(ii) The note contains the following noted by Mr Myall:
" NHBC attending site 10/11 & 12 Nov. assume obtain certificates what still needs to be completed & can it be done in 2 week time slot.
Levels 10/11 to be forgotten…
DT [Mr Teague]-critical to obtain cert. but if outst. work to [sic] much & not complete in 2 wks to end".
(iii) It was accepted also that this document should have been disclosed. It is on its face a relatively neutral document in that the reference to "Levels 10/11 to be forgotten" is neutral: it is not inconsistent with each side's version of the 8 November meeting. The other references relate to the same matters as Status Report 5.
(iv) Again, I find it difficult to see how this document shows necessarily that Mr Teague was lying.
"Perjury"
The strength of the Section 68 (2)(g) application
(a) Credibility was a major issue in the arbitration.(b) One can and should ignore all suggestions that Mr Teague was lying to the extent that the material for seeking to suggest it was available to Brown at the hearing.
(c) I do not consider it likely that any court would come to the view that the non-disclosure of the Missing Documents was reprehensible or unconscionable given the Arbitrator's limited orders about co-operative disclosure. Furthermore, I doubt that many of the Missing Documents would have been discloseable in the First Arbitration if some more standard disclosure had been ordered.
(d) I do not consider it likely that a court would do anything other than find that the non-disclosure, assuming disclosure was required, was anything more than inadvertent. If it had been, it is then most surprising that the Missing Documents were then disclosed at all in the Second Arbitration before the award in the First Arbitration was published. This does not suggest some conspiracy or plot to withhold key documents.
(e) I strongly suspect that Mr Bate and those for whom he acts have convinced themselves that there was some "dirty work at the crossroads". I very much doubt that the Missing Documents add very much to the issue as to whether Mr Teague was telling the truth, for the reasons indicated above.
(f) There were numerous other facets of the evidence and the facts which went to influence the Arbitrator of which the absence of any written corroboration or confirmation from Mr Murphy relating to the alleged agreements featured to a significant extent. That factor would always loom large in most tribunals' thinking on such topics, particularly when the alleged agreements were going to produce over £200,000 and save a six figure sum on liquidated damages for Brown.
(g) I have serious doubts as to whether the material produced by Mr Bate is such that any reasonable court would be persuaded that there had been any reprehensible or unconscionable conduct let alone fraud on the part of Crosby or that there had been substantial injustice, to enable any application under Section 68(2)(g) to succeed.
The decision
(a) An explanation of the disputes and background leading up to the award;(b) An analysis why each of the Missing Documents demonstrates individually or in combination that a witness is said to have lied;
(c) An explanation as to why this gives rise to a real possibility that the arbitrator would or might have reached a different overall view on any relevant dispute;
(d) The exhibiting of the Missing Documents (and possibly a few other contemporaneous documents), the award, the Arbitrator's orders, Crosby's list of documents, the affidavit of Mr Teague, relevant parts of the transcript of the evidence and, possibly, the opening and closing submissions of Counsel in the arbitration and possibly some selected correspondence between the solicitors in the arbitration.
If the response raised issues of fact which had not been addressed by the applicant, they could be addressed in a further witness statement. Whilst I accept that the supporting documentation needs to be (particularly) carefully prepared to support a charge of dishonesty, it remains unnecessary and indeed unhelpful for vast quantities of documentation and prose to be provided at least initially.