BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY & CONSTRUCTION COURT
33 BULL STREET BIRMINGHAM B4 6DS |
||
Date of draft judgment: 21 February 2008 Date Of Judgment: 14 March 2008 |
B e f o r e :
____________________
J. S. BLOOR LIMITED | Claimant | |
and | ||
PAVILLION DEVELOPMENTS LIMITED | Defendant |
____________________
Mr Noel Dilworth of Counsel (instructed by Wayne Leighton) for the Defendant
____________________
Crown Copyright ©
Introduction
to Pavillion to build a care home;
(in about early 2005) to Miller Homes to build residential units; and
(in early 2006) to Bromford Housing Association.
The law
Background
Had the orange road been completed to base course tarmac level?
Did Bloor build the orange road by mistake? Was there any benefit to Bloor in having the orange road?
Good access to the adjacent plot which was to be sold for affordable housing, and which Bloor subsequently sold to Bromford Housing Association in February 2006. Pavillion's case is that a completed road would have been more attractive to potential purchasers of the affordable housing site than a situation where an adjacent developer had an obligation to construct a road. The constructed orange road gave easy access to the affordable housing site. In addition, the fact that the orange road was built with provision for foul drainage and incorporating service ducts was probably of benefit to the ultimate purchaser of the affordable housing land. Accordingly, the fact that there were such drainage and ducts, and a constructed road, is likely to have amounted to a benefit to Bloor. Mr Lusty accepted that, in an open market, these might well have been factors. Here, however, he said that the site was, in any event, attractive to housing associations generally, and there was unlikely to be any cost advantage to Bloor, as development of the site for affordable housing would have to be undertaken within the constraints imposed by Housing Corporation guidelines. I conclude that there was probably some non-pecuniary benefit to Bloor in having the road constructed at an early stage, with drainage and service ducts, as this is likely to have rendered the affordable homes site more attractive.
The orange road enabled access to adjacent sites for eg movement of plant. Bloor themselves used the orange road for a short time.
Bloor were to build a sub station south of the orange road. It is unrealistic for Bloor to suggest, as they do, that the contractor may not have used the orange road for access to construct the sub station: it is likely that the road was used for such access.
Benefit or disadvantage to Pavillion?
Pavillion were deprived of the opportunity to design and procure the work to their specification. Pavillion nevertheless remained liable (for example, pursuant to their obligations under occupiers' liability legislation) in relation to a road which had been designed and built by others.
Pavillion lost the opportunity to negotiate the cost of the road work and the terms on which it would let that contract. The sum which Bloor claim is considerably higher than the sum which Mr Baudet had budgeted to pay for the road construction.
Pavillion were deprived of the opportunity to enter into a contractual relationship with the contractor undertaking the road work. If a problem arises with the work undertaken, there are obvious advantages to a party to have the benefit of such a contractual relationship and obvious disadvantages absent such a relationship. For example, Pavillion lost the opportunity to have direct control over the road contractor if problems with work or materials had come to light when the road was to be adopted. (I note that no problems were encountered.)
As Mr Baudet explained, Pavillion would normally seek collateral warranties from contractors. He would have wished to do so in this case, as he was proposing to sell on the project. Pavillion lost the opportunity to obtain such warranties. (I note, however, that there is no evidence that the absence of such warranties in fact affected the price of any onward sale.)
Mr Baudet said that Bloor's action might have given Pavillion difficulty with funders, who sometimes wish to approve contractors. (Again, I note that there is no evidence that there was any such difficulty in this case.)
Mr Baudet confirmed that Pavillion would have been willing to pay for the road, had appropriate warranties been put in place and provided an acceptable sum could be agreed. So far as I am aware, Bloor have not volunteered any warranties or other device to give Pavillion a direct contractual relationship with CJL.
Conclusion
Pavillion's set off
Quantum
Frances Kirkham