TECHNOLOGY and CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
KEHR & TUCKER LIMITED |
Claimant |
|
- and - |
||
ASTRONOMICAL LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
MISS N. KLIER (instructed by Layard Horsfall Ltd.) appeared for the Defendant
____________________
Crown Copyright ©
Judge Wilcox:
"Following our telephone conversation of 24th May 2002 in connection with our fee submission for the design of the mechanical, electrical and public health services for the above project, I have attached a copy of section 5 of our fee proposal amended to reflect our discussion. This now confirms a lump sum fee of £15,000 for the design of the services and negotiations with the utilities. Post-tender supervision during the construction period to be reviewed at a later date is therefore currently excluded."
"It was apparent from my review of the time records submitted by the design team on the job that far more time was being recorded against the project than had been anticipated by the proposal. I discussed the matter with Neal Day who had the day to day control of the project. He informed me the Claimant had been required to redesign a number of areas of the design and had been instructed to undertake additional work. Mr. Day informed me that he raised the issue of additional costs with Mr. Ingham and that Mr. Ingham indicated that a detailed additional claim should be passed to him for consideration. At that time no such details had been passed to Mr. Ingham. I had a meeting with both Neal Day and Mr. Ingham in our office. The meeting took place on 16th April 2004. I am satisfied that Mr. Ingham had arranged the meeting to obtain drawings that he considered overdue. I am satisfied that he complained of delay to both KT directly and through Mr. Day."
(1) In respect of changed kitchen layouts one-third of the work varying the M & E drawings may be considered additional. I assess the costs of the additional charges at £203.(2) Additional work following the incorporation of the Jacuzzi into Mr. Ingham's unit, I assess the instruction charges at £340.
(3) The miscellaneous additions were works within the original scope of the services agreement.
(4) The changes in layout position of the showers warranted further time and revised drawings. £405 is the sum properly claimed additionally under this head.
(5) The design of the contents of the service ducts gave insufficient room for vacuum services. However, a centralised vacuum system was not specifically identified in the scope of services. I award an additional £740.
(6) Claims for services in relation to the so-called redesign of the linen cupboard in my judgment is misconceived. I am satisfied that KT were notified that instead of it being a bedroom as shown on the layout it was intended to use the room as a linen room, but nonetheless the M & E services should be provided for so that the room could revert to its original intended use at a later stage. The claim represents the cost of KT's failure to take account of the original instruction and is the cost of putting it right. It is not allowed.
(7) Drawing modifications in the sum of £2,060 are not proved by the Claimant to be other than part of the evolution of design within the original scope of services.
(8) Decisions consequent upon changed swimming pool regulations clearly fall within the exception to the schedule to the agreed proposal and the reasonable costs of the amended drawings are recoverable in the sum of £2,280.
(9) The claim in respect of the relocation of the core units is not reasonable. I am satisfied that it was part of the original design process within the original agreed scope of works.
(10) Drawings in respect of swimming pool ventilation would appear to be covered by the exception in the amended proposal. The reasonable cost of these is recoverable. This is agreed at £1200.
(11) The interstitial condensation prediction calculations were volunteered by Mr. Day. KT, it appears, had a copy of an unlicensed software programme which he was able to use. If it were incorrect he accepted that Mr. Ingham would have no come-back because KT were not entitled to use it for these third party purposes. In my judgment no charges are recoverable under this head.
(12) A charge for the review of the swimming pool quotation is not made out. In so far as it may give details of layout and requirement of M & E services it of course would have to be pursued and the information derived would be part of the exchange ventilation for the design work within the original services proposal. No sum is recoverable.
(13) Additional works arising out of architect's drawings. It has not been established by the Claimant on the evidence how the claim lies in relation to the (hours?) allocated. In my judgment it is simply part of the original design process included in the proposal for services to be provided within the fixed sum. It is evident that Mr. Day was not highly experienced, as he disarmingly admitted to me. A great deal of the uneconomic hours were at the risk of his employer and not of the client.
(14) Additional meetings. The sum of £3,750 is claimed here. This smacks of creative accounting following a realisation that a bad bargain had been struck by KT when allocating time and resources, and a consequence perhaps of putting an inexperienced and unsupervised designer in charge. I have no doubt that Mr. Ingham was not the easiest of clients and was demanding. The agreement should have taken this into account. This aspect of the claim is not made out.
(15) Above ground rain water drainage claimed in the sum of £810 in my judgment is made out.