QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
LIBERTY MERCIAN LIMITED |
Claimant |
|
- and - |
||
DEAN & DYBALL CONSTRUCTION LIMITED |
Defendant |
____________________
Mr Simon Henderson (instructed by Clarke Willmott) for the Defendant
Hearing dates: 22nd October 2008
____________________
Crown Copyright ©
The Honourable Mr Justice Coulson:
A. INTRODUCTION
B. THE CONTRACT
DETAILS OF THE SECTIONAL COMPLETION ARRANGEMENTS | DETAILS OF THE SECTIONAL COMPLETION ARRANGEMENTS | DETAILS OF THE SECTIONAL COMPLETION ARRANGEMENTS | DETAILS OF THE SECTIONAL COMPLETION ARRANGEMENTS | DETAILS OF THE SECTIONAL COMPLETION ARRANGEMENTS | DETAILS OF THE SECTIONAL COMPLETION ARRANGEMENTS |
Section Number |
Phase title |
Content (refer to the accompanying text) |
Liquidated & Ascertained Damages per week or part thereof | Date of Possession |
Date of Completion |
1 |
1A |
Completion of the new retail units A, B, C and D to a stage to enable access for the tenants' fit-out (but this is not deemed to be practical completion) | £12,000.00 |
6 June 2005 |
10 February 2006 |
2 |
1B |
Completion of the remaining works to section 1 and completion of the external works and car park providing the initial 87 spaces, all to a stage of Practical Completion, | £1,500.00 in addition to the above |
Upon completion of Section 1, Phase 1A to the required stage. |
7 April 2006 |
3 |
1C |
To complete the extended car park providing a total of 195 spaces |
£2,000.00 |
Upon completion of Section 2, Phase 1B to the required stage. |
5 May 2006 |
4 |
2A |
Completion to the refurbished and extended existing retail unit to a stage to enable access for the tenant's fit-out (but this is not deemed to be practical completion) |
£7,000.00 |
After pc of section 3 phase 1C |
3 November 2006 |
5 |
2B |
Completion of the remaining works to Section 4 and completion of the external works, all to a stage of Practical Completion. |
£1,000 in addition to the above |
The date of possession as Section 4, Phase 2A |
3 November 2006 |
Notes Section 2 cannot achieve practical completion until 8 weeks after Section 1 achieves practical completion. |
Notes Section 2 cannot achieve practical completion until 8 weeks after Section 1 achieves practical completion. |
Notes Section 2 cannot achieve practical completion until 8 weeks after Section 1 achieves practical completion. |
Notes Section 2 cannot achieve practical completion until 8 weeks after Section 1 achieves practical completion. |
Notes Section 2 cannot achieve practical completion until 8 weeks after Section 1 achieves practical completion. |
"Save where clause 24.5.3 applies, the contractor shall not in any event be entitled to an extension of time to the extent that the delay in the progress of the Works is caused to by any negligence, breach of statutory duty, omission or default of the contractor, his servants or agents or of any person employed or engaged upon or in connection with the Works or any part thereof, his servants or agents other than the employer or a tenant or any person employed or engaged by any of them".
C. THE DISPUTE
a) The sectional completion schedule was void for uncertainty because there was no provision in the contract which addressed the impact of delayed completion upon the remaining sections of the works;
b) The sectional completion schedule was to be disregarded, and time was to be regarded as being at large, because the schedule failed to identify the date for completion in respect of each section, and instead referred to the date of completion, which was not a term defined in the contract.
c) The architect had been wrong to grant an extension of time of only 4 weeks in relation to sections 2-5. Since the date of possession for each of those sections was dependent upon practical completion of a preceding section, the defendant was entitled to a full extension of time of 8 weeks on each subsequent section.
d) The liquidated damages constituted a penalty because the defendant was repeatedly penalised for the same delay by the deduction of the liquidated damages in respect of each section and/or because the delay on section 1 was then the subject of liquidated damages in respect of the remaining sections. This became known as the 'cascade' argument.
D. THE LAW
E. DATES OF/FOR COMPLETION
F. PENALTY
G. THE PROPER OPERATION OF THE SECTIONAL COMPLETION AGREEMENT
H. CONCLUSIONS