QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Biffa Waste Services Limited |
First Claimant |
|
-and- |
||
Biffa Leicester Limited |
Second Claimant |
|
-and- |
||
Maschinenfabrik Ernst Hese GMBH |
First Defendant |
|
-and- |
||
Outokumpu Technology Wenmec AB |
Second Defendant |
|
-and- |
||
Vanguard Industrial Limited (Trading as Pickfords Vanguard) (in voluntary liquidation) |
Third party |
|
-and- |
||
Hese Umwelt GMBH |
Fourth Party |
____________________
David Allen QC (instructed by Ince & Co) for the Second Defendant
____________________
Crown Copyright ©
The Hon Mr Justice Ramsey :
Introduction
(1) The value of Biffa's claim for lost electricity sales. OT contended that the loss was £102,025. Biffa claimed £176,223. The difference depended on two issues: the conversion factor from gas to electricity and whether Biffa should have produced some gas from compost available during the seven month delay period.(2) The value of Biffa's loss of income from sale of recycled materials. OT contended that the loss was £114,486; Biffa claimed £149,038.
(3) The value of savings made at Bursom and at Wanlip during the seven month delay. OT contended that savings of £490,605 had been made at Bursom and £522,715 at Wanlip. Biffa's figures were respectively £420,354 and £504,173. The difference related to internal hire costs, agency labour costs, sub-contracting costs and rent.
(4) The value of uninsured losses, being an MEH invoice for £26,429 and project management costs for Mr Nattrass of £6,956.
Evidence
Loss of Electricity sales
Gas to electricity conversion rate
Electricity Production July 2004 to January 2005
Summary
Loss of recycled metal
Savings at Bursom and Wanlip
Internal Hire
Agency Labour
Sub-Contracting
Rent
Summary
Additional uninsured costs
MEH invoice 009-88
"This invoice is for supervision costs that were not covered by our insurers is now part of out uninsured loss claim which was submitted on 6 January 2006. Should this claim be successful then we will have no problem settling this invoice in full."
(1) Hunt did not affect the principle that it is no defence to establish that the victim's liability to a third party has not been discharged.(2) Lord Bridge's concern with the reasoning of Megaw LJ was as to the question whether the source of the services to meet the needs of the victim was always irrelevant. Lord Bridge said at 361 that the source was relevant if the victim received free treatment.
(3) It is clear from Hunt at 361 to 362 that if services had been provided pursuant to an agreement rather than gratuitously then they would have been recoverable. Further the ratio in Hunt is that a claimant cannot recover from the tortfeasor for gratuitous services provided by the tortfeasor.
(1) A liability by a victim of a tort is sufficient to make that sum recoverable as damages even if that liability to a third party has not been discharged: see Randall v Raper EB&E 84 as applied in Total Liban SA v Vitol Energy SA at 652 to 656(2) Where a third party provides gratuitous services to a victim, the victim may recover a sum in respect of those services as a mechanism for re-imbursing that third party for those services. The mechanism is that the victim holds the damages on trust for the third party: see Hunt at 363
(3) Where a tortfeasor provides gratuitous services to a victim, the victim cannot recover a sum in respect of those services because an award of damages in tort is compensatory and the victim does not suffer a loss: see Hunt at 363.
Project Management costs
Summary
Overall Summary
Loss of electricity sales: | £176,223 |
Loss of sales of recycled metals: | £114,486 |
Landfill Tax Repayment: agreed | £342,295 |
Savings at Bursom: | (£420,354) |
Savings at Wanlip: | (£504,173) |
Onward Haulage: agreed | £138,317 |
Landfill Gate Costs: agreed | £169,230 |
Additional uninsured costs: | £124,225 |
Total | £140,249 |
Contribution