QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
VGC CONSTRUCTION LIMITED |
Claimant |
|
- and - |
||
JACKSON CIVIL ENGINEERING LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000 Fax No: 020 7427 0093 DX: 410 LDE
Email: info@martenwalshcherer.com
MR ALEXANDER NISSEN QC (instructed by Messrs Fenwick Elliott) for the Defendant
____________________
Crown Copyright ©
MR. JUSTICE AKENHEAD:
Introduction
The History
"(1) Within 10 days, or such other period as may be agreed in writing, of receipt of the Contractor's written instructions so to do, the Sub-Contractor shall enter upon the Site and commence the execution of the Sub-Contract Works and shall thereafter proceed with the same with due diligence and without any delay, except such as may be expressly sanctioned or ordered by the Contractor or be wholly beyond the control of the Sub-Contractor. Subject to the provisions of this clause, the Sub-Contractor shall complete the Sub-Contract Works within the Period for Completion specified in the Third Schedule hereto.
(2) If the Sub-Contractor shall be delayed in the execution of the Sub-Contract Works:
(a) by any circumstances or occurrence (other than a breach of this Sub-Contract by the Sub-Contractor) entitling the Contractor to an extension of his time for completion of the Main Works under the Main Contract; or
(b) by the ordering of any variation of the Sub-Contract Works to which paragraph (a) of this sub-clause does not apply; or
(c) by any breach of this Sub-Contract by the Contractor;
then in any such event the Sub-Contractor shall be entitled to such extension of the Period for Completion as may in all the circumstances be fair and reasonable. "
"13.150 Delay and disruption £300,000.00"
"Pursuant to Clause 6 of our Sub-Contract we request an extension of time of 26 weeks, to extend the Contract Completion Date to 14 September 2007. This date relates to when the additional, varied works that are instructed by [Jackson] were completed.
The extension of time is justified by, but not limited to, the reasons listed on the attached Delay document."
The Delay document attached was a four-page document which comprised simply a number of heads of reasons for delay. The two-line "Overview" paragraph states:
"The purpose of this document is to describe the delays to the Contract between VGC and Jackson on the M3 NRTS Project."
Thus, for instance there is reference to delays attributable to Traffic Management. The "Delays" are simply headings such as "Delayed Start Traffic Management Fragmented Working Walk-out TM". There is no prose explanation of how or why any such delays occurred and how or why they justified an extension of time.
" for [Jackson] and [VGC] to establish why the measurement items listed in [Jackson's] letter date 10 October Notice of intention to withhold payment, were in dispute. [Jackson] were also to explain how their contra-charges listed in the above referenced letter were derived."
The bulk of the minutes address the measurement items and the contra-charges. It is clear that all the contra-charges relating to delay or disruption were not accepted by VGC.
"[Mr Exton] stated that VGC's claim for an extension of time and [Jackson's] over-run would be left in abeyance. [VGC] would like to agree the measurement items prior to their inclusion in the Final Account. VGC are currently preparing the Final Account. The Final Account will be submitted mid-January 2008 when the agreement to the measurement items has been reached. VGC will attempt to finalise the extension of time claim by the end of January 2008. [Jackson] confirmed agreement to the Final Account being submitted in January 2008 "
"At the conclusion of the meeting on 7 December 2007 it was agreed and as is recorded at Item 6 on page 9 of the minutes that VGC would now submit its final account in mid-January 2008 and its 'delay and disruption/extension of time' claim by the end of January 2008. I understood this to mean that in the interim VGC was not pressing its 'delay and disruption/extension of time' claim because it was finalising it. In the meantime, that claim and JCE's contra charge claim would continue to be held in abeyance It was not my decision to leave the claims in abeyance. VGC said they would be finalising the claims by the end of January "
"At paragraph 11 of his statement, Mr Brydon [of VGC] states that 'Mr Exton suggests that he understood that the Claimant was not pressing its claim for disruption and extension of time because it had agreed that it would attempt to provide further details of the claim by the end of January 2008'. I maintain that this was in fact the position as is clearly recorded in the minutes Whilst the minutes record that I stated that the 'delay and disruption/extension of time' claim and JCE's contra charges claim would be held in abeyance I wish to make it clear that this was the product of mutual agreement. This statement followed discussions wherein it was acknowledged that VGC was still not in a position to submit a formulated 'delay and disruption/extension of time' claim. Previously and during the meeting of 7 November 2007 Mr Mauldon [of VGC] had advised that this would take six months to prepare. However, at the meeting of 7 December 2007 he advised that this would now be submitted by the end of January 2008. It follows as a matter of common sense that until the claim is properly formulated and submitted it would be held in 'abeyance'."
"Delay, disruption and Prelims over-run: there are several items in relation to this. As these will be subject to a separate submission, we have removed them from our attached summary."
There was a "Schedule of disputed items in Measured Works" attached which against Item 13.15 "Delay and Disruption" it was indicated that these items are "elsewhere". I do not read this letter as indicating that the delay and disruption claim for £300,000 was being abandoned. The item was simply being removed from the physical schedule that was attached to this letter.
" Mr Butler advised that in his view adjudication was the only means of resolving the whole dispute particularly since the parties remained so far apart. I cautioned Mr Butler against taking this step because it was my view that most of the disputed items were capable of resolution without resort to adjudication. Adjudication would not have been appropriate in relation to the 'delay and disruption/extension of time' claim because it had still not been tabled and there was nothing to adjudicate on. I explained to Mr Butler that I could not undertake any assessment because the claim had yet to be formulated. I reminded him that the finalised claim was still outstanding. We could only consider the claim once it had been finalised."
"10. The parties have been, over a considerable period, negotiating the final account for the works. The basis of this has been application number 14 submitted by VGC.
11. During negotiations, the parties held several meetings to attempt to agree the value of the Final Account. These were unsuccessful.
12. VGC have prepared a Scott Schedule which they believe reflects the position of the parties at the date of the adjudication.
13. The gross value of works valued by VGC is £4,287,302.08, against which Jackson have valued £3,623,796.94.
14. Since Practical [Completion] has been reached, retention should be applied at 2.5% of the subcontract value.
15. Jackson are applying set-off charges to the value of £656,400. VGC dispute these charges.
16. To date Jackson have paid a net sum of £3,040,482.35."
The Adjudication
"Disputes or differences have arisen between the Parties under a Contract dated: on or around 9 November 2006 .
These disputes or differences have been referred to adjudication in accordance with The Institution of Civil Engineers' Adjudication Procedure (1997) and the Adjudicator has been requested to act."
It was agreed at Clause 1 that the rights and obligations of the Adjudicator and the Parties were to be as set out in that Procedure. By Clause 3 the parties jointly and severally undertook to pay for the provision of the Adjudicator's services. Rates were agreed in a Schedule.
"Extension of time: Appendix 29."
It was agreed that this was a mis-reference which should have been to Appendix 30. A Scott Schedule (Appendix 3) was also attached.
"1. It is apparent from the attached analysis [the Programme sent on 30 April 2008] that, as a result of numerous delays and additional works during the currency of the Sub-Contract Period, as defined in the Sub-Contract, together with additional works instructed after the Sub-Contract Period passed, that VGC suffered delays and consequently loss due to no fault of their own."
There is then set out over the following eight paragraphs some explanation or at least assertion that there were delays attributable to various factors such as their variations and Jackson's alleged "inability to organise the Traffic Management System".
" a meeting was arranged for 4 April 2008, where again it was apparent that VGC, notwithstanding the comments made by Jackson Civil Engineering at previous meetings, had still not provided proper supporting details of their claim and there remained a substantial amount of work required before a meaningful assessment of VGC's account could be undertaken. Clearly, this still remains the case, yet VGC have now launched a further adjudication to try and resolve its account without the substantive information usually required to back up any application for payment. Given the length of time that Jackson Civil Engineering have been requesting proper backup of the sums claimed, the only conclusion must be that such information does not exist. Without the proper proof, there can be no entitlement."
"15. It should be noted, that within Application No 13 VGC submitted a claim for delay and disruption in the sum of £300,000.00 with no substantiation or prior notification. Formal notification of 'a claim' for an extension of time was issued under cover of VGC letter dated 25th October 2007 with only a 'table of contents'. There was no supportive information, justification or financial information appended During the meeting held with VGC on 7 November 2007, Jackson Civil Engineering requested when the basis for and the justification of the claim for delay and disruption/extension of time would be submitted and were informed that it would take them approximately 6 months to complete. Six months have passed and to date the 1½ page statement in the Referral remains the sole basis of their submission with no financial information at all. Clearly, on any view, this is insufficient for Jackson to assess its validity, and the Adjudicator should evaluate this claim as nil. The inclusion in Application No 13 by VGC of an, on paper, substantial claim for delay and disruption (and/or extension of time as requested under VGC letter dated 25 October 2007) when it is not supported by any substantiation or justifiable reasoning as to its validity cannot and does not show that Jackson were in breach of their rights under the sub-contract to dispute this item."
"For the reasons set out in paragraph 15 above, this claim lacks sufficient detail and substantiation for either Jackson Civil Engineering or the Adjudicator to assess its validity. Further, Jackson Civil Engineering will now demonstrate why VGC are not entitled to any time and/or money in respect of this claim and why VGC's submission, based on 1½ pages of unsupported statements, does not demonstrate entitlement as follows: "
There then follows some three and a half pages of prose which asserts why VGC is not entitled either to extension of time or indeed to any money. So far as the quantification is concerned the main argument was that payment of variations to the extent that variations caused delay would compensate VGC for any delay or disrupted related expenditure. It concludes with this:
"It can be seen that the substantiation of any claim for an extension of time/delay and disruption by VGC has not been made, and only emanates from the deduction by Jackson of its costs due to the extensive overrun on the Contract by VGC causing severe costs to be expended by Jackson ..."
"(i) that Jackson Civil Engineering has valued the Application No 14 correctly
(ii) that the set-off charges are applicable in the sum of £637,131.60 as contained in Appendices R and S
(iii) that VGC repay forthwith to Jackson any monies Jackson have overpaid VGC "
"VGC attach their calculation of the additional OHP [Overhead and Profit] costs required due to this overrun to their subcontract works."
"We are in receipt of a letter from VGC dated 29 May 2008 enclosing their Reply together with various attachments. Although most of these attachments are known and have been seen during the currency of the Contract, we would point out that the calculation of the VGC claim for extension of time is totally new. We therefore request the Adjudicator treat this as inadmissible in this Adjudication.
We await your instructions."
" It is Jackson Civil Engineering's opinion that VGC did not allow sufficient time for any meaningful discussions before launching into this Adjudication.
- Delay and disruption claim: Throughout the currency of the works on site, VGC never achieved their expected outputs. They only achieved them and slightly bettered them with substantially increased resources. In addition, VGC have for the first time submitted a form of calculation of their extension of time costs within their Reply. Jackson have already registered with the Adjudicator that this information is invalid and cannot be submitted at this late stage, and has no relevance to this Adjudication and should be ignored. Jackson reserves their position on this matter, subject to the decision of the Adjudicator on this Adjudication.
Conclusion
As clearly stated previously, the launching of this adjudication is premature as not sufficient time was given by VGC to see how discussions proceeded. The introduction by VGC of a substantial claim for delay and disruption/extension of time with no substantiation of any sort or a programme which showed clearly the entitlement of an extension of time is a case in point. It should be based upon the accepted programme of the 16 October 2006 with links showing the effects of the each and every one of the instructed variations. This must be the only way this could have been justified, not based on the 'balance of probabilities' It is for VGC to prove their case, not for Jackson to show how it attempts to give reasonable assessments against items with little or no information from VGC. Jackson clearly has given VGC every opportunity to provide additional information. VGC, equally, have failed in providing sufficient information, given within the period of negotiations from November 2007, to enable substantive discussions and agreements to proceed on their account.
Jackson would reiterate its statement that, the submission of new information, for example, the basis of an extension of time claim in VGC's Reply is inadmissible, and all Jackson's rights are accordingly reserved."
The Adjudicator's Decision
"The dispute between the Parties involves their failure to agree the value of the Final Account for work done by VGC under a sub contract to JCE in respect of duct laying, cable installation and associated works on the M3 Motorway during 2006 and 2007."
He referred to his appointment, the date of referral and the time period for his decision and set out what submissions he had received; these included Jackson's letter dated 2 June 2008 and their Closing Submissions. He said also in relation to the dispute or difference:
"Having examined all of the documents provided by the Parties I am satisfied and therefore find that a crystallised dispute or difference exists between the Parties in respect of the valuation of the Final Account for the works, which includes the disputed application of Set Off Charges to the Final Account by [Jackson]."
"17.23 Extension of time."
These Proceedings
(a) It is argued that the only claim that had ever been made was in Applications 13 and 14 for a single lump sum of £300,000 with no breakdown or supporting information. That claim had been removed and separated, it is argued, from the remainder of the Final Account and was due to be the subject of a separate submission by VGC that never came. It is asserted that there can be no dispute in respect of the claim that was withdrawn. It is said that if there is a bona fide factual dispute between the parties as to whether or not it was withdrawn then that is a matter that cannot be resolved on a summary application.
(b) It is said that the claim for £300,000 was of such a nebulous nature that there could be no dispute in respect of it. It is said that it lacked contractual foundation in law, was unsupported by any form of detail or analysis and was nothing more than a single line demand for £300,000.
(c) The claim for £300,000 as it became during the course of the Adjudication was entirely or substantially new with the consequence that the Adjudicator had no jurisdiction to deal with it."
The Law
"85. The objective which underlies the Act and the statutory scheme requires the courts to respect and enforce the adjudicator's decision unless it is plain that the question which he has decided was not the question referred to him or the manner in which he has gone about his task is obviously unfair. It should be only in rare circumstances that the courts will interfere with the decision of an adjudicator. .
86. It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator's reasons and identify points upon which to present a challenge under the labels 'excess of jurisdiction' or 'breach of natural justice'. It must be kept in mind that the majority of adjudicators are not chosen for their expertise as lawyers. Their skills are as likely (if not more likely) to lie in other disciplines. The task of the adjudicator is not to act as arbitrator or judge. The time constraints within which he is expected to operate are proof of that. The task of the adjudicator is to find an interim solution which meets the needs of the case. Parliament may be taken to have recognised that, in the absence of an interim solution, the contractor (or sub-contractor) or his sub-contractors will be driven into insolvency through a wrongful withholding of payments properly due. The statutory scheme provides a means of meeting the legitimate cash-flow requirements of contractors and their subcontractors. The need to have the 'right' answer has been subordinated to the need to have an answer quickly.
87. In short, in the overwhelming majority of cases, the proper course for the party who is unsuccessful in an adjudication under the scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator's decision as correct (whether on the facts or in law), he can take legal or arbitration proceedings in order to establish the true position. To seek to challenge the adjudicator's decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead to a substantial waste of time and expense "
"1. The adjudication procedure does not involve the final determination of anybody's rights (unless all the parties so wish).
2. The Court of Appeal has repeatedly emphasised that adjudicators' decisions must be enforced, even if they result from errors of procedure, fact or law
3. Where an adjudicator has acted in excess of his jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision
4. Judges must be astute to examine technical defences with a degree of scepticism consonant with the policy of the 1996 Act. Errors of law, fact or procedure by an adjudicator must be examined critically before the Court accepts that such errors constitute excess of jurisdiction or serious breaches of the rules of natural justice."
"From his review of the authorities, the judge derived the following propositions:
'1. The word 'dispute' which occurs in many arbitration clauses and also in section 108 of the Housing Grants Act should be given its normal meaning. It does not have some special or unusual meaning conferred upon it by lawyers.
2. Despite the simple meaning of the word 'dispute', there has been much litigation over the years as to whether or not disputes existed in particular situations. This litigation has not generated any hard-edged legal rules as to what is or is not a dispute. However, the accumulating judicial decisions have produced helpful guidance.
3. The mere fact that one party (whom I shall call 'the claimant') notifies the other party (whom I shall call 'the respondent') of a claim does not automatically and immediately give rise to a dispute. It is clear, both as a matter of language and from judicial decisions, that a dispute does not arise unless and until it emerges that the claim is not admitted.
4. The circumstances from which it may emerge that a claim is not admitted are Protean. For example, there may be an express rejection of the claim. There may be discussions between the parties from which objectively it is to be inferred that the claim is not admitted. The respondent may prevaricate, thus giving rise to the inference that he does not admit the claim. The respondent may simply remain silent for a period of time, thus giving rise to the same inference.
7. If the claim as presented by the claimant is so nebulous and ill-defined that the respondent cannot sensibly respond to it, neither silence by the respondent nor even an express non-admission is likely to give rise to a dispute for the purposes of arbitration or adjudication."
"Secondly, however, like most words, 'dispute' takes its flavour from its context. Where arbitration clauses are concerned, the word has on the whole caused little trouble. If arbitration has been claimed and it emerges that there is after all no dispute because the claim is admitted, there is unlikely to be any dispute about the question of whether there had been any dispute to take to arbitration. And if the claim is disputed, any argument that the arbitration had not been justified because at the time it was invoked there had not been any dispute is, it seems to me, unlikely to find a receptive audience (although it appears that it did in Cruden Construction v Commission for the New Towns [1995] 2 Lloyd's Rep 37). So it is that in this arbitration context the real challenge to the existence of a 'dispute' has arisen where a party seeking summary judgment in the courts has been met by a request for a stay to arbitration and the claimant has wanted to argue that an unanswerable claim cannot be a real dispute.
67. It follows that in the arbitration context it is possible and sensible to give to the word 'dispute' a broad meaning in the sense that a dispute may readily be found or inferred in the absence of an acceptance of liability, a fortiori because the arbitration process itself is the best place to determine whether or not the claim is admitted or not.
68. Thirdly, and significantly, the problem over 'dispute' has only really arisen in recent years in the context of adjudication for the purposes of Part II of the Housing Grants Construction and Regeneration Act 1996. Jackson J referred below to some of the burgeoning jurisprudence to which the need for a 'dispute' in order to trigger adjudication has given rise. In this new context, where adjudication is an additional provisional layer of dispute resolution, pending final litigation or arbitration, there is, as it seems to me, a legitimate concern to ensure that the point at which this additional complexity has been properly reached should not be too readily anticipated. Unlike the arbitration context, adjudication is likely to occur at an early stage, when in any event there is no limitation problem, but there is the different concern that parties may be plunged into an expensive contest, the timing provisions of which are tightly drawn, before they, and particularly the respondent, are ready for it. In this context there has been an understandable concern that the respondent should have a reasonable time in which to respond to any claim."
" it cannot properly be said as a matter of ordinary English that the plaintiff and defendant were in dispute or that a dispute had arisen between them when the notice of arbitration was served" (page 394).
"The defendant did not identify which houses were alleged to be defective or what those defects were nor did it call upon the plaintiff to put the defects right or to pay compensation.
The letter of Oct. 7 was the first suggestion there might be something wrong with the houses which the plaintiff had built but beyond that the plaintiff knew nothing more than that the defendant was about to start arbitration proceedings. It is of course right that the plaintiff's solicitors in their letter of Oct. 11, did say that they were not acknowledging or admitting that the defendant had any basis for a claim against the plaintiff but it would in my judgment be wrong to treat that statement as in effect a non-admission by the defendant of the claim thereby putting the plaintiff to proof. A fair reading of the letter of Oct. 11, 1993 is that neither the plaintiff nor its solicitors knew what was going to be alleged against them in the arbitration proceedings and that the acceptance of service was not to be taken as an admission or acknowledgement that there were any matters which would give rise to a claim against the plaintiff. No such matters had been asserted by the defendant."
Discussion
(a) Often, claims will include for expended preliminary costs on site, or "site on-costs"; thus the fact that the claiming contractor's foreman or site huttage has had to be on site for X weeks longer than anticipated will give rise to a claim for extended preliminaries.
(b) Disruption costs usually fall into the category of lost productivity or the diversion of personnel and resources away from productive work.
(c) Almost invariably, there will be claims for loss of head office overhead and profit usually calculated on a formula basis, the most common formula being the Hudson basis. There are other variants on the Hudson formula such as the Emden formula.
(a) The claim for £300,000 was merely one of 150 sub-claims within the Applications.
(b) The claim for delay and disruption was within that substantial part of the Applications which related to variations. Thus it was or should have been clear to all concerned that the primary basis for any claim for delay and disruption related to variations.
(c) A number of the items within the Variations part of the Applications identify factors which purportedly give rise to delay or disruption. Such items include items 003 (the later Works), 008 (provision of labour and plant on other contract), 2.015 (disruption due to moving sections), 3.020 (loss of shift due to issues with Traffic Management), 3.022 (late setting up of Traffic Management and stoppages due to TM changes), 3.028 (delay awaiting instruction) and 11.129, 11.130 and 11.131 (Traffic Management delay).
(d) There were specific claims at Paras 11.139, 12.142, and 13.152 for "Site Pre-lims Over-run". This would in all probability have identified to the recipient of the application that the general claim in 13.150 for delay and disruption (for £300,000) did not include for the Site Pre-lims. The fact that elsewhere (for instance at 2.015) there is reference to disruption costs would again suggest to the recipient that specific loss of productivity disruption was being claimed in other items.
(e) Thus, to the recipient or to any reasonable recipient in the circumstances, the assumption would or should have been made that the general £300,000 was for other aspects of delay and disruption, the most obvious being a head office overhead and profit type claim.
(f) It is not uncommon for claims for delay in interim applications to be very much by way of "on account" applications. That does not mean to say that they cannot be addressed by the recipient.
(g) It must have been obvious to Jackson that this general and unparticularised claim must relate at least by way of a maximum to the 26 weeks' delay in completion which had occurred.
(a) I do not consider that the evidence proffered by Jackson establishes even on a prima facie basis that there was some binding agreement whereby VGC abandoned or withdrew its claim for £300,000 for delay and disruption (item 13.150 in it Applications). On Mr Exton's evidence this could only have occurred at the meeting of 7 December 2007. He does not say in his first witness statement that there was any agreement. In essence, he says there that, because VGC was going to submit its delay and disruption/extension of time claim by the end of January 2008, he understood that VGC was not pressing "its delay and disruption/extension of time" (claim) because it was finalising it. For a party to withdraw its claim, there must be a clear agreement or expression (by words, conduct or otherwise) that it will not pursue a particular claim. A wholly reasonable inference from everything that was said (apparently) at this meeting, was that VGC was going to provide substantiation to support the claim for extension of time. The extension of time claim was relevant not only to the £300,000 and other claims such as the "site prelims claims" but also to whether all or part of the set-offs or contra charges were justified. The fact that Mr Exton was treating VGC's claim for an extension of time as being left in abeyance does not mean, by inference or otherwise, that VGC were withdrawing or abandoning their claim for £300,000 which it had made in its Applications 13 and 14.
(b) Of course, if VGC did not provide any further substantiation, it might well prove to be the case that any adjudicator would reject such a claim as, in practice, lacking substantiation. But that was always going to be VGC's risk.
(c) There would have to be very clear wording, which is not suggested here by Mr Exton, that in relation to any established dispute, VGC was in effect agreeing that it could not pursue adjudication (or later arbitration) in relation to such dispute. No such clear wording exists or is even said by Mr Exton to have been uttered.
(d) Mr. Exton in his second statement substantively says that it is the minutes of the 7 December 2007 meeting which clearly records what was the position. The minutes do not go anywhere near far enough to establish that the claim for £300,000, for what it was worth, was being withdrawn.
The Decision