QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
BUSINESS ENVIRONMENT BOW LANE LIMITED (formerly known as RAVENCAP (No.2) LIMITED |
Claimant |
|
- and - |
||
DEANWATER ESTATES LIMITED (formerly known as GOOCH WEBSTER LIMITED |
Defendant |
____________________
Mr Jonathan Ferris (instructed by Michael Conn Goldsobel) for the Defendant
Hearing dates: 9 & 10 June 2008
____________________
Crown Copyright ©
His Honour Judge Toulmin CMQ QC:
The Facts
"On behalf of our clients we require you to pay, by close of business on 28 April 2005, the sum set out in the Schedule of Dilapidations in order to settle your liability thereunder. Should our client not receive this sum by this time it reserves all its rights against you."
"We understand that your client has not carried out the work. Please advise as to whether [the claimant] has any intention of carrying out the work and if so when it intends to do the work and what steps it is taking to get the work done."
"Specifications for the work are currently being prepared and will be sent out to tender shortly. These tenders will be returned within three weeks of 27 June 2005… We look forward to receiving your comments relating to the Schedule of Dilapidations in accordance with the time limits laid down in the dilapidations protocol."
The tender period was subsequently extended to 23 July 2005.
"In those circumstances (my underlining) our clients do not regard themselves as being under any liability whatsoever in respect of the Schedule of Dilapidations and invite your clients to withdraw the same forthwith."
"However, it is clear that your clients are fully refurbishing the property (a point you openly acknowledged in our conversation and within your letter of 12 September). These actions clearly nullify the entirety of your claim for alleged internal breaches (toilets, circulation doors, light fittings, perimeter skirting, trunking and radiators etc. etc. have been stripped out)."
"The external condition must be similar to that at the commencement of the lease in 2002."
"8. By reason of the breaches [of covenant] the claimant has suffered damage and the value of its reversion has been diminished by an amount equal to the cost of repairing the premises in accordance with the covenants.
PARTICULARS
The cost of works £246,572.80
9. Further, the claimant has suffered damage that he was unable to re-let the premises, the annual value whereof is £300,000 from 25 December 2004 until 13 May 2005, the period during which the said repairs were executed. The claimant's loss of rent of the premises is accordingly £115,384.62.
Yet further, the claimant has suffered damage in that he has had to meet the professional costs incurred in connection with the preparation and service of the Schedule of Dilapidations and this claim. The value of this loss is currently £52,975.14."
"We have been advised by him (the Defendant's expert) that the Schedule of Dilapidations which has hitherto been relied on by your clients bears no relation to the work which appears to have been carried out in particular to the interior of the property. Indeed our expert's initial views are that the whole of the schedule has been superseded by the conversion of the property into a furnished office centre.
It therefore appears that in relation to the preparation of a Scott Schedule, your client's building surveyor will need to re-visit the Schedule of Dilapidations and ensure that the Scott schedule mirrors the works actually carried out by your clients."
"The sum claimed for the work was reduced to £83,802.63. To this was added a claim for £9,863.04 for loss of rent, fees for preparing the Schedule in the sum of £11,460. Together with a small item for VAT the total was reduced to £107,506.34."
It is suggested that the correct figure for mesne profits (loss of rent) to be extracted from the Scott Schedule was £69,230, i.e. twelve weeks and not twelve days.
"We understand that there may very well be very significant alterations made to the Schedule and indeed that it may be necessary for a further amended Schedule to be prepared and served by your client, which will have the effect of substantially reducing your client's claim yet further."
"We consider that the claim is worth more than this but we do not think that it is cost effective to argue the point at trial."
"Now your client accepts that its claim is minimal and should never have been pursued at the quantum level pleaded. It would thus appear more appropriate that your client should bear our client's costs of the dilapidations claim …"
"We don't accept that our client's claim is only worth £1,073.50."
"Our client's claim is less than it ought to be (having considered your client's schedule and the photographs belatedly produced by your expert)."
"The Defendant was so keen to pursue its collateral contract/estoppel argument that it clouded its judgment on the question of quantum and the overall commerciality of its position."
The Contentions of the Parties
"The arguments advanced on this appeal have demonstrated the real difficulties inherent in asking a judge to exercise his discretion in respect of the costs of an action which he has not tried. There are no doubt straightforward cases in which it is reasonably clear from the settlement that there is a winner and a loser in the litigation. In most cases of that description the parties will realistically recognise the result and the costs will be agreed. There will be no need to involve the judge in a decision on costs. If he becomes involved because the parties cannot agree and ask him to resolve the dispute, the decision is not usually a difficult one for him to make.
There are more complex cases (and this is such a case) in which it will be difficult for the judge to decide who is the winner and who is the loser without embarking on a course which comes close to conducting a trial of the action that the parties intend to avoid by their compromise."
"As the arguments on the present appeal demonstrated, it does the parties no service if the judge in a laudable attempt to assist them to resolve their dispute, makes an order about costs which he is in no position to make."
The Law
"(2)(a) the general rule is that the unsuccessful party will be ordered to pay the costs of the successful party, but
(b) the court may make a different order."
"(4) that in deciding what order to make the court must have regard to all the circumstances including
(a) the conduct of the parties
(b) whether a party has been successful on part of its case even if it has not been wholly successful …"
"(c) the manner in which a party has pursued or defended his case or a particular allegation or issue; and
(d) whether a claimant who has succeeded in his claim in whole or in part exaggerated his claim."
(a) the court must take fully into account the fact that the action has been compromised;
(b) it will normally not be possible to say in the light of the compromise that one or other party has been successful and in those cases the order will be no order as to costs;
(c) the court should not depart from the normal order unless it is in a clear position to do so on a proper basis of agreed or determined facts which enable the court to decide what other order should be made.
"I draw attention to the new Rules (Part 44(2) and (4) because while they make it clear that the general rule remains that the successful party will normally be entitled to costs, they at the same time indicate the wide range of considerations which would result in the court making different orders as to costs. From 26 April 1999 the 'follow the event' principle still plays a significant role but it will be a starting point from which a court can readily depart."