QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
JAMES MARTIN SCOBIE and others |
Claimants |
|
- and - |
||
FAIRVIEW LAND LIMITED |
Defendant |
____________________
Paul Letman (instructed by Finers Stephens Innocent LLP) for the Defendant
Hearing dates: 22, 29 January, 1 February 2008
____________________
Crown Copyright ©
Mr. Justice AKENHEAD:
Introduction
(a) "inadequate insulation in partition" in bathrooms;(b) shower "plasterboard partitions" in bathrooms;
(c) "various earthing, wiring, isolation and earth leakage"
The application to amend
(a) NHBC Requirements;(b) Preliminaries;
(c) Electrical defects;
(d) Plasterboard defects;
(e) Room changes;
(f) Deviations from joint statements;
(g) Claim shifting from Second to First Claimants;
(h) Miscellaneous.
I will deal with each in turn. As indicated to the parties at the conclusion of the adjourned hearing on 29 January 2008, I am prepared to grant permission to amend on all aspects subject to certain constraints. I proceed upon the basic principle that amendments ought in general to be allowed to enable the real disputes between the parties to be adjudicated upon unless there is prejudice to the other party which can not be compensated for by a costs order or unless there is harm occasioned to the administration of justice (see notes to CPR 17.3.5).
(a) NHBC Requirements
(b) Preliminaries
(c) Electrical defects
"1. Ensuite fan not working.2. 230v fan in Zone 1.
3. Single socket in airing cupboard poorly terminated.
4. No earth fly leads to metal back boxes.
5. Kitchen ring circuit incorrectly wired spurs off of spurs.
6. Shower pull cord indicator not working
7. No fan isolators fitted.
8. Distribution not correctly identified or labelled, also requires an insulating back plate and fire barrier.9. CPC's not correctly terminated in plasterboard switches.10. Smoke alarm requires terminations checked and base fitted.11. Unknown condition of Hob outlet plate/Cooker fusing.12. Many cord grips have been removed or damaged.13. No ID on RCD CPC.14. No visual 4mm2 CPC around bathroom.15. Many electrical appliances/equipment in the wrong zones in bathrooms.16. CPC's twisted together throughout."
(a) The Claimants serve such expert evidence relating to electrical defects within a week, that is by 5 February 2008 4.30 pm.
(b) Reasonable requests by the Defendant and its experts for access to the flats should be acceded to promptly.
(c) At the special Pre-Trial review hearing which I have reserved on 14 February 2008, I will review progress on this aspect of the matter, with the option of adjourning the hearing of all or some of the electrical defects claims possibly at the expense of the Claimants. This is a justified approach given that the seven day period for the trial is in any event an ambitious one.
If reliance is to be placed upon Mr Wilcox or an MJW representative as expert, somewhat more may well be required to seek to demonstrate default than is simply contained in the test reports; I leave that however to the Claimants.
(d) Plasterboard defects/(e) Room changes
(f) Deviations from joint statements
"60 no Plasterboard partitions… Whilst the Claimants' costing of these works has significantly reduced (from £4,839 down to £1,421.58) the quantum of this claim has not been finally agreed, as the experts have not reached agreement over the duration…for each element of the works…
27 no Plasterboard/insulation to bathroom/shower… Whilst the Claimants' costing of these works has significantly reduced (from £8,899) down to £258.58 the quantum of this claim has not been finally agreed, as the experts have not reached agreement over the duration…for each element of the works…"
It all depends what "these works" mean in this context. It would be slightly surprising (if not unheard of) if an expert had agreed that the quantum was worth no more than £x and came along a few weeks later and asserted that it was £30x. I am not prepared to accept at this stage that, based on entries in a "not agreed" part of a joint statement, the Claimant's expert either did or intended to agree the lower figures for the work which he considers necessary to put right the alleged defects. If I am being insufficiently robust about this at this stage, it will of course be open to the Defendant's Counsel at trial to cross examine him as to his credibility on this topic. It would be wrong to cut out the Claimants from seeking to rely upon what they believe to be the bona fide evidence of their expert by reason of some possible inference that he (only) might be going back on something he signed up to in a joint statement.
(g) Claim shifting from Second to First Claimants
Miscellaneous
Claimants' application for leave to adduce in evidence a quantum report of their expert, Mr Easton
Strike-out
"Mr Easton has allowed 10 anchors @ £2000 each at one metre centres. The cost per anchor is taken form SPONS [a well known pricing publication].
No schedule of works is required, they are just rock anchors."
General