BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY & CONSTRUCTION COURT
33 BULL STREET BIRMINGHAM B4 6DS Date of hearing: 29 April 2008 Date of draft judgment: 7 May 2008 |
||
B e f o r e :
sitting as a deputy High Court Judge
____________________
OWEN PELL LIMITED | Claimant | |
and | ||
BINDI (LONDON) LIMITED | Defendant |
____________________
Mr Thomas Rochford of Counsel (instructed by Humfrys & Symonds) for the Defendant
____________________
Crown Copyright ©
Background
"The parties entered into a building contract for construction works to … Garenin Cottage, Holme Lacy…. Owen Pell was the Contractor and Bindi the Employer on the project. Owen Pell has submitted its final account to Bindi for payment. The parties are in dispute concerning the value of the works and wish to have the dispute settled by an independent expert appointed by RICS.
The proposed independent expert will be asked to determine the following:
1. The value of Owen Pell's work and therefore the sum due to Owen Pell pursuant to submission of its final account; alternatively the amount to be deducted from sums paid to Owen Pell under the contract; and2. The entitlement (or otherwise) of Bindi to contra charge Owen Pell in respect of work carried out on the project.
We would suggest that in carrying out his investigations and making his decision, the expert should have regard to Owen Pell's final account and all supporting documents including site diaries and Bindi's documentation concerning the project.
The independent expert should conduct the proceedings in any way that he sees fit but the parties suggest that it would be beneficial for him to conduct a site visit and hold a meeting between the parties.
The timescale for conducting the proceedings is in the hands of the independent expert. Nevertheless the parties agree that the process should take no longer than two months.
The parties agree that they should be bound by the decision of the independent expert and, following the decision, that they are not able to refer the dispute to a subsequent tribunal, including adjudication under the [1996 Act]."
The issues
(a) the expert failed to conduct himself in accordance with the principles of natural justice; or
(b) the expert conducted himself in such a way as either was biased or gave the appearance of bias; or
(c) in conducting himself and/or reaching his conclusions, the expert was guilty of gross or obvious error and/or was perverse in his conclusions.
The defendant contends that such term is to be implied as a matter of obvious inference (the officious bystander test) and to give business efficacy to the Agreement.
- He heard from the claimant in private at the site meeting on 4 September 2006.
- He gave the impression of being dismissive of the defendant's complaints throughout the meeting on 4 September 2006.
- He declined to consider Mr Jerrison's letter of 22 November 2006.
- He concluded that the parties had "effectively agreed a walk away situation" as at [the date when the claimant left site]; the defendant had not so agreed.
- He reached that conclusion without having given the defendant the opportunity to comment on it.
- He reached conclusions which contained gross and obvious error and which were perverse.
Authorities
"In former times (when it was thought that the valuer was not liable for negligence) the court used to look for some way of upsetting a valuation which was shown to be erroneous. They used to say that it could be upset, not only for fraud or collusion, but also on the ground of mistake: see for instance what I said in Dean v Prince. But those cases have to be reconsidered now. I did reconsider them in Arenson v Arenson [1973] 2 WLR 553. I stand by what I there said. It is simply the law of contract. If two persons agree that the price of property should be fixed by a valuer on whom they agree, and he gives a valuation honestly and in good faith, they are bound by it. Even if he has made a mistake they are still bound by it. The reason is because they have agreed to be bound by it. If there were fraud or collusion, of course, it would be very different. Fraud or collusion unravels everything. It may be that if a valuer gives a speaking valuation - if he gives his reasons or his calculations - and you can show on the face of them that they are wrong it might be upset."
The comment in the last sentence was obiter. It simply raised the possibility that the legal position might be different with a speaking determination.
"The binding effect, or otherwise, of an expert determination has been considered in a number of cases in recent years. Each case depends on the terms of the contract under which the determination is made, both as to what it is that the expert has to decide, and as to how far his decision is binding on the parties. In each case it is necessary to examine the determination, in order to see whether it lies within the scope of the expert's authority. If it does not, then it has no effect as between the parties. If on the other hand it does, then the contract also governs the question whether the determination is binding…."
At paragraph 24, he said: "The first question, therefore, is what the agreement has entrusted to the expert. The second is whether that is what he has decided. If so, the third is whether it can be shown that he has made a mistake which vitiates his decision."
Should the court imply the terms contended for by the defendant?
Mr Mouzer's report
Actual bias?
Apparent bias or appearance of bias?
Meetings and inspection on 4 September 2006:
Mr Cartwright was dismissive of the defendant's case
Mr Jerrison's letter dated 22 November 2006:
What was the scope of the dispute referred to Mr Cartwright? Did he answer the questions referred to him?
"(a) the basis of my evaluation
(i) The parties' agreement [ie to refer to expert determination] requires me to value Owen Pell's work in accordance with its final account which includes a reference to direct loss and expense in the form of preliminary and overheads recovery. As part of Owen Pell's submissions it says that it has made assessments without the need for contractual avenues. …… there are no references to determination provisions of the contract and no claims are made in that regard. However, Bindi has, subsequent to the agreement, included invoices for works executed after 20 October 2004 for the completion of the project. This completion work has not been included as part of the defect costs and is in addition to the omissions of works but again there is no reference to any contractual provisions.
(ii) Therefore, from the way the agreement is drafted, it seems that the parties have effectively agreed a walk away situation whereby Owen Pell are paid for the works properly carried out up to the date they left site, namely 20 October 2004. It follows on this basis that Owen Pell is entitled to payment less any defective works carried out whilst on site. I therefore take the view that Bindi can only abate any monies due to Owen Pell by the rectification costs of any defects…."
Errors
Conclusion
Frances Kirkham
19 May 2008