QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
THE GOVERNING BODY OF CHARTERHOUSE SCHOOL |
Claimant |
|
- and - |
||
HANNAFORD UPRIGHT |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000 Fax No: 020 7427 0093 DX: 410 LDE
Email: info@martenwalshcherer.com Website: www.martenwalshcherer.com
appeared on behalf of the Claimant.
MISS JOANNA SMITH (instructed by Messrs Squire & Co, London EC1)
appeared on behalf of the Defendant
____________________
Crown Copyright ©
MR JUSTICE AKENHEAD:
"The request for an order to obtain quantity surveying evidence at the Case Management Conference on 8 March 2007" – I think it is 9 March, but anyway that does not matter – "was rejected by the Court at that time. I understand from my subsequent conversations with Counsel that His Honour Judge Thornton QC confirmed that it was not necessary for the Court to make an order at that stage but said that it was open to the parties to obtain expert evidence from a quantity surveyor if either party felt it was necessary to do so and that any reasonable decision to rely on such evidence could be reflected in an appropriate Court order subsequently. The Court certainly did not rule out the possibility of an application for permission to rely on quantity surveying evidence being made at a later stage in the proceedings."
"A further Case Management Conference took place before His Honour Judge Anthony Thornton QC on 9 March 2007. Again, as Mr Lewis records in his witness statement on behalf of the Defendant, the Defendant applied (this being its second application) for permission to adduce the expert evidence of a quantity surveyor. Again, that application was refused as is recorded in the directions made by the Judge," and he refers to various pages.
He continues:
'It is quite wrong to portray the learned Judge on that occasion as encouraging the Defendant to make a further application as Mr Lewis appears to suggest in Paragraph 14 of his witness statement. Mr Lewis has not been at either of the Case Management Conferences, but I have. The learned Judge again refused the application and made certain pertinent points to the Defendant's Counsel as to the correct approach to quantification and loss given the sizeable sum that had already been spent by the school in remedial works. The point made by him was not whether remedial works could have been done for less but, rather, were the works that were performed reasonable and were they caused as a result of actionable fault on the part of the Defendant? He did say that there was nothing to stop a party engaging a quantity surveyor if it wanted to, to provide assistance and that no permission was needed from the Court for a party to do so, but that was different from calling an expert as a witness. Mr Lewis seeks to portray this new application by the Defendant as, effectively, always being pending from March onwards. Quite apart from the obvious absurdity of one party stating that it was preparing for trial using an expert for whom no permission had been granted (and in fact twice refused by the Court) in actual fact since March of this year evidence from quantity surveying experts has effectively been a "dead" issue so far as the school has been concerned.'
The Applications
The Quantity Surveyor Expert
"The Defendant requires permission to adduce expert quantity surveying evidence to support its case as to the costs of the remedial work that the Defendant now acknowledges would have been necessary in order to remedy the inability of the few areas within each Boarding House to meet the required internal design temperature. In his report, Mr Welch [Hannaford's engineering expert] will identify the specific areas that require attention together with the works that he believes would have remedied the problem. The Defendant needs the evidence of a quantity surveyor to put a price on those remedial works."
(1) Permission to rely upon expert quantity surveying evidence is granted only upon the following terms:(a) It is limited to valuation of the remedial works attributable to the admissions of liability pleaded in the Amended Defence.(b) The Defendant serves, by 18 November 2007, all its expert evidence in respect of such valuation.(2) The Claimant is permitted to serve the report of any quantity surveying expert in respect of such valuation on or by 21 December 2007.
(3) The quantity surveying experts are to meet without prejudice and file statements in accordance with Rule 35.12(3) on such valuation by 10 January 2008.
(4) The Claimant has liberty to apply for a variation of these directions, including an adjournment of any issues relating to this valuation exercise, if it proves impossible or impracticable to comply with them.
"Further and in any event, the provision of stand-by pumps, new boiler flues, new control valves and modifications to the control system are all items of betterment over Hannaford Upright's original design and represent a revision and/or fundamental change in the Governing Body's [Charterhouse's] requirements. In the circumstances, the cost of the same is not properly recoverable from Hannaford Upright."
There were general denials in Paragraphs 71 and 72 relating to the loss and damage. No Particulars have ever been provided by Hannaford to support the plea in Paragraph 70 or to plead any other positive case with regard to loss and damage.
"… it is admitted that the provision of stand-by pumps and of new boiler flues are items of betterment over Hannaford Upright's original design and the Governing Body will give credit for those sums once they have been assessed. The Governing Body avers that these are modest sums totalling no more than approximately £35,000. Save as aforesaid, Paragraph 70 is denied."
The Reply was served on 15 January 2007.
"During the February 2007 data-acquisition exercise conducted at the Daviesites House by myself and Mr Child, I was shown the remedial works completed at Lockites Dormitory. The viewing was brief, but various items were pointed out or noted by myself as constituting an enhancement to the original heating scheme design completed by Hannaford Upright."
He then refers to some 10 areas or types of what he says are "enhancements", only some of which are reflected in Paragraph 70 of the Defence.
(a) The application is made much too late. It is clear from the applications made before His Honour Judge Thornton QC and from the pleading that Hannaford has been keen to advance arguments relating to betterment. It is also clear that Mr Welch has advised Hannaford, or been in a position to advise it, since at the latest February 2007 that there were a number of specific items of betterment (referred to in his Appendix 30). To wait until six working weeks before the trial to make this application is not acceptable. Little or no excuse or explanation has been given about the reasons for the delay.(b) It is clear that even now Hannaford is not in a position to produce a quantity surveying expert's report to support its case on quantum matters (other than those for which I am prepared to give limited leave, for which see above). It will be some weeks (whether before or after Christmas 2007) before Hannaford's quantity surveying expert is ready to produce a comprehensive and comprehensible report.
(c) There is thus at the very least a very significant risk that the trial date in January 2008 will be jeopardised. Indeed, it is an overwhelming probability that the trial date will have to be vacated or at the very least effectively the whole issue of quantum adjourned to a second trial.
(d) It is highly undesirable that the trial is adjourned in whole or in part. The trial date has been fixed for many months and the parties, and in particular Charterhouse, has doubtless made its dispositions accordingly. It is a charity, and the extended period of financial uncertainty is an unfair imposition for them to have to bear.
(e) There is also the factor of the availability of a suitable Judge to hear any adjourned case. I do know that the TCC High Court Judges are very heavily booked (including some double bookings) throughout 2008. Other TCC Judges are also heavily booked in 2008. Although I have not been in a position to check His Honour Judge Thornton QC's list in detail, I do know that he has a number of reserved bookings for matters next year. There is thus a very real risk that this case could not be brought on for a significant period of time in 2008. That is not a satisfactory state of affairs.
(f) I bear in mind also that Hannaford have already, in January and March 2007, made two unsuccessful applications on exactly the same basis. Both applications have been unsuccessful and, for reasons best known to itself, Hannaford did not even seek permission to appeal against those refusals. It is not obvious that factors have materially changed since those applications were made.
I consider that there is very real prejudice likely to be suffered by Charterhouse if I was to accede to this application. Save to the extent that I have allowed it (see above), the application is dismissed.
Hannaford's Application to Amend
(a) Those which are not opposed by Charterhouse. Permission to make these amendments will be allowed, subject to the usual terms as to costs and consequential amendments being made to the Reply, if so advised.(b) Amendments relating to the true construction of the Charterhouse Report as to the 30 year requirement.
(c) Amendments relating to the alleged requirement for compliance with the Education (School Premises) Regulations 1999 ("the 1999 Regulations"); and
(d) Amendments relating to the commissioning and the recommissioning works.
I will deal with the three disputed categories in that order.
Amendments Relating to the 30 Year Requirement
"It is further admitted that the design undertaken by Hannaford Upright for the Year 1 Works was to be suitable and sufficient for the buildings to enjoy a further 30 years' life after the Works had been performed."
Amendments Relating to the 1999 Regulations
"At the first Project Meeting, held on Thursday 8 March 2001, and attended by (amongst others), Mr Grant, Mr Szymanski and Mr Kingston on behalf of the Governing Body, Mr Grant was issued with a copy of … the 1999 Regulations. At some point, whether prior to, during, or shortly after the meeting, GTMS/GTCM instructed Hannaford Upright to comply with the 1999 Regulations. On a date that Mr Grant cannot recall, he confirmed that Hannaford Upright would comply."
'I have been shown the minutes of a meeting dated 8 March 2001 at which I was present and from which I can see that a copy of the … 1999 Regulations was provided to me "For information". I have a very clear recollection that Gardiner & Theobald had at some point, whether before or after this meeting, made it very clear to us that we had to comply with the requirements of those Regulations. I cannot recall whether this was done over the telephone or by way of email, but I had no doubt that Hannaford was asked to confirm that it would be complying with the Regulations in carrying out its design for the heating system. I am sure that I confirmed compliance in circumstances, whether requirements of the Regulations for internal temperatures were significantly lower than the room temperature requirement that had been specified to us by the school.'
Gardiner & Theobald were representing Charterhouse for the provision of management services in connection with the refurbishment work.
(a) There is no excuse proffered or obviously available as to why this point was not pleaded many months ago.(b) It is made much too late, with only six weeks left to go to trial.
(c) The lateness of the application brings about a significantly enhanced risk that Charterhouse will be unable to track down the one witness who might be able to challenge, in whole or in part, what Mr Grant says. If this pleading had been made in the original Defence or shortly thereafter, that would have left Charterhouse with a substantial period of time to seek to track Mr Szymanski down. Instead, it is left in the position of having to track him down, so far wholly unsuccessfully, in a period of time which, impendingly, includes Christmas and the New Year, when it is less likely that he will be tracked down. To allow this amendment at this stage would give Hannaford an unfair advantage.
(d) It was not unreasonable on the part of Charterhouse not to have sought to locate Mr Szymanski before any application to amend was made. There appear to be little or no issues arising out of the contracts between the parties which were not determinable on the face of the contractual documentation.
(e) It will still be open to Hannaford on its existing pleading to argue that different temperature considerations applied (contractually) to areas other than "rooms", although I make no comment about the efficacy or validity of those existing pleas.
Amendments Relating to Commissioning and Recommissioning
"(18) The replacement of the heating and hot water services at the Boarding Houses was completed in all material respects in accordance with the specifications and drawings produced by Hannaford Upright. The Year 1 Works were completed and commissioned during the School's summer holidays in 2001 by Aircool Engineering Ltd. The Year 2 Works were completed and commissioned during the School's summer holidays in 2002 by Dudley Bower Services Ltd (in respect of Lockites and Weekites), Aircool Engineering Ltd (in respect of Bodeites and Hodgsonites) and Kershall Mechanical Services Ltd (in respect of Pageites and Robinites).
(19) Commissioning was carried out by Russell Commissioning and Validation Services Ltd on completion of the Works. Recommissioning of the system was carried out by Barfield (Commissioning Services) Ltd in mid-2003. Yet further commissioning and also flushing of the system was carried out by Paul Banyard & Associates and Seaton Associates in late 2003. The Governing Body avers that Year 1 and Year 2 Works were commissioned and recommissioned as adequately as possible within the parameters of the system as designed and installed. Recommissioning was performed in an attempt by the Governing Body to improve the performance of the systems."
It can be seen that some seven different firms or companies were involved in the commissioning and the recommissioning.
"Save that:
(i) it is averred that no re-commissioning was either necessary, or undertaken in respect of the Year 1 Works; and
(ii) it is denied that commissioning by Russell … was carried out on completion of the Works, such commissioning having taken place in or around November 2002 at a time when the Boarding Houses were occupied
Paragraph 19 is admitted. For the avoidance of doubt, it is denied (if it is so alleged) that the re-commissioning and the flushing of the system referred to in Paragraph 19 was carried out with a view to resolving identified problems with the design criteria."
"It is denied that the Year 2 Works were commissioned as adequately as possible within the parameters of the system as designed and installed and further denied that the Year 2 Works were re-commissioned as adequately as possible within the parameters of the system as designed and installed."
Thus the admission of Paragraph 19 is to be further qualified. No particularisation is given as to any respects in which the commissioning of the Year 2 Works or the recommissioning was inadequate. A further plea is added at the end of Paragraph 26:
"It is further denied that such re-commissioning was carried out in accordance with the recommendations provided by Mr Grant of Hannaford Upright in July 2003. However, it is noted that in its report in relation to Lockites dated 7 July 2003, Barfield confirmed that: There seems to be no reason why the water cannot be distributed to allow all radiators to reach temperature …".
Again, there is no particularisation of any respects in which the recommissioning was not carried out in accordance with Mr Grant's recommendations.
"In the circumstances, I said that it remained our view that any reported performance problems with the heating circuit were likely to arise from inadequate commissioning procedures."
Such information is more historical than by way of particularisation of what inadequacies there were in commissioning procedures.
'• From the numerous and varied items of correspondence circulating after works completion and the witness statements of House Masters and Matrons, it appears that various of the heating systems were not or not adequately commissioned or handed over once installed.
• From Clause 4 of the "Site Refurbishment Meeting" dated 13 Nov 2002, the School confirmed their view "that no proper handover had been achieved". I take this to confirm that (as well as other issues of inadequate balancing; cleansing; and commissioning) no adequate operational "teach in" had been given to the School's Maintenance and Estate staff by GTMS.
• I am of the opinion that if a heating system as designed had been installed; commissioned; handed over; operated; and maintained adequately, then the remedial works required to comply with the School's brief would be minor in nature.'
"8.6 I note from documents scheduled at Appendix 22 that the individual heating systems were not adequately balanced, commissioned or handed over at practical completion …
8.9 In conclusion, I consider that the performance of the heating systems designed by Hannaford Upright was critically compromised by the lack of proper maintenance …; lack of adequate commissioning and water balances …"
"CPR Part 17 also requires me to apply the overriding objective (CPR Part 1) by considering whether the proposed amendments will enable the Court to deal justly with the claim in a way that is proportionate to the importance and complexity of the case and to the financial position of each party."
The learned Judge then goes on to deal with the extent to which one should consider whether the proposed amendment has realistic prospects of success. It is unnecessary for me to consider that aspect of the matter.
"The Court may allow a party to amend or withdraw an admission."
There is, therefore, a discretion upon the Court in considering whether to allow the withdrawal of admissions. In Sowerby v Charlton [2005] EWHC (Civ) 1610, the Court of Appeal approved a dictum of Mr Justice Sumner in Braybrook v Basildon Thurrock University NHS Trust [2004] EWHC 3352 (7 October 2004) in which that learned Judge said:
"45. From these cases and the CPR I draw the following principles:
1. In exercising its discretion the Court will consider all the circumstances of the case and seek to give effect to the overriding objective.
2. Amongst the matters to be considered will be:
(a) the reasons and justification for the application which must be made in good faith;
(b) the balance of prejudice to the parties;
(c) whether any party has been the author of any prejudice they may suffer;
(d) the prospects of success of any issue arising from the withdrawal of an admission;
(e) the public interest, in avoiding where possible satellite litigation, disproportionate use of Court resources and the impact of any strategic manoeuvring.
3. The nearer any application is to a final hearing, the less change of success it will have, even if the party making the application can establish clear prejudice. This may be decisive if the application is shortly before the hearing."
(a) The application is made far too late. There is no, and certainly no adequate, explanation as to why this application is being made only six working weeks away from the trial.(b) There is no adequate explanation why Mr Grant, having signed the Statement of Truth, in December 2006, now wishes to depart from the admissions previously made. Mr Grant has obviously been with Hannaford throughout and Hannaford's engineering expert, Mr Welch, has been involved also for a considerable period of time.
(c) If the application to amend was to be allowed, it would be inevitably the case that Charterhouse would have to consider calling representatives of up to seven companies or firms which were involved in the commissioning and recommissioning. The prospects of both finding the relative witnesses within these organisations and obtaining comprehensible witness statements from them in time before the January trial date is very low indeed. Thus there is a very real risk that the trial date would be jeopardised. For reasons given above, there is prejudice to Charterhouse if this trial date is adjourned.
(d) The lack of particularity of the amendments makes it impossible, or at the least very difficult, to ascertain what impact, if any, the suggested inadequacy in the commissioning or recommissioning had or would have had on the heating systems.
(e) Miss Smith says that the plea about inadequacy of the commissioning is simply a general one upon the basis that inadequate commissioning or recommissioning may have impacted on the deficiencies or poor performance of the heating systems. I understand by that she is saying that it will be impossible to particularise either the inadequacies or their impact. If that is the case, there seems little point in seeking leave to amend at all.
(f) With regard to the "signing off" point in Paragraph 25, signing off in a construction or engineering context does not necessarily mean that a piece of paper is signed by the relevant person. Signing off implies, usually, that there has been some approval by the person signing off. Miss Smith told me that in any event no complaints were being made by her clients in relation to the Year 1 commissioning. If that is so, the plea relating to signing off is, on that basis, immaterial, or at the very least less material one way or the other.
General