QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane, London, EC4 |
||
B e f o r e :
____________________
MULTIPLEX CONSTRUCTION (UK) LIMITED |
Claimant |
|
- and - |
||
HONEYWELL CONTROL SYSTEMS LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG.
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
MR. MARTIN BOWDERY QC and MR. ROBERT CLAY (instructed by Messrs. Beale and Co., London, WC2) appeared for the Defendant
____________________
Crown Copyright ©
Mr. Justice Jackson:
Part 1. Introduction
Part 2. The Facts
Part 3. The Present Proceedings
Part 4. The Jurisdiction of This Court to Grant Permission to Appeal
"An application for permission to appeal may be made --
(a) To the lower court at the hearing at which the decision to be appealed was made; or
(b) to the appeal court in an appeal notice."
"Where no application for permission to appeal has been made in accordance with rule 52.3(2)(a) but a party requests further time to make such an application, the court may adjourn the hearing to give that party the opportunity to do so."
1. Apply for permission at the original hearing.
2. Apply at that hearing for more time in which to consider making such an application to the lower court.
3. Apply for permission to appeal to the appeal court.
"The first question to be addressed is whether the court has jurisdiction to accede to the defendants' present application. Mr. Mark Platts-Mills, who appears with Mr. Michael Tappin for the claimant, concedes that there is such jurisdiction. In my judgment, that concession is correct. There are a number of reported cases where it has been held that it is open to a judge who has given judgment to reconsider his conclusion and, in effect, to reverse his own decision, provided that the order recording his earlier decision has not been drawn up. Thus, in Preston Banking Co. v. William Allsup & Sons [1895] 1 Ch 141, 144-145, A.L. Smith L.J. said:
'so long as the order has not been perfected, the judge has a power of reviewing the matter, but once the order has been completed the jurisdiction of the judge over it has come to an end.'
The principle has been approved in subsequent decisions of the Court of Appeal: see, for instance, Millenstead v. Grosvenor House (Park Lane) Ltd. [1937] 1 K.B. 717, 722, 726 and In re Harrison's Share under a Settlement [1955] Ch. 260, 276-277, 283-284 per Jenkins L.J., giving the judgment of the Court of Appeal. In the last of those passages, one finds this:
'When a judge has pronounced judgment he retains control over the case until the order giving effect to his judgment is formally completed. This control must be used in accordance with his discretion exercised judicially and not capriciously.'
Two more recent cases where the principle was approved by the Court of Appeal are Reg. v. Cripps, Ex parte Muldoon [1984] Q.B. 686, 695F, and Pittalis v. Sherefettin [1986] Q.B. 868, 879A, 882C-D."
I gratefully adopt that summary of the law set out by Neuberger J. in Charlesworth.
Part 5. Decision
"1. On a true construction of the Sub-Contract between Multiplex and Honeywell dated 27th May 2004 clause 11 provided a mechanism for extending the period for completion of the Sub-Contract Works in respect of any delay to completion caused by an instruction issued under clause 4.2 of the Sub-Contract.
2. A direction issued by Multiplex to Honeywell under clause 4.2 of the Sub-Contract would not render time at large so as to relieve Honeywell of its obligation to complete the Sub-Contract Works within the period for completion set out in the Appendix, Part 4 as adjusted by clauses 4.6 and/or 11 and/or 38A and/or 38C.
3. The Sub-Contract mechanism for extending the period for completion of the Sub-Contract Works remains in full force so that a specific period for completion of the Sub-Contract Works remains ascertainable."
The declarations which Honeywell counterclaims for in its Re-Amended Defence and Counterclaim comprise certain declarations on the true construction of the Sub-Contract; alternatively, declarations that time is at large by reason of the breakdown of the Sub-Contract mechanism for extension of time.
"(a) whether or not the judgment or order is final;
(b) whether an appeal lies from the judgment or order and, if so, to which appeal court;
(c) whether the court gives permission to appeal; and
(d) if not, the appropriate appeal court to which any further application for permission may be made."