QUEEN'S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
B e f o r e :
____________________
R. C. PILLAR & SON |
Claimant | |
- and - |
||
THE CAMBER. |
Defendant |
____________________
Official Shorthand
Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane,
London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
____________________
Crown Copyright ©
HH Judge Thornton QC:
INTRODUCTION:
(1) The parties never entered into a contract at all so that there was no contract under which the adjudication could be started.
(2) If there was a contract, although it was a construction contract it was not sufficiently evidenced in writing, as required by section 107 of the Housing, Grants, Construction and Regeneration Act 1996 ("HGCRA") so that Pillar had no basis for requiring or starting an adjudication against Camber.
(3) If there was a construction contract which was sufficiently evidenced in writing, it was not a contract made on, or incorporating, the IFC standard form of contract. Since Pillar had applied to the RIBA, as a nominating body, to appoint an adjudicator in reliance on the adjudication clause contained in the IFC form of contract, it is contended that the adjudicator's appointment lacked jurisdiction since that clause was not part of the contract between the parties.
(4) The construction contract, if any, that had initially governed the work had been superseded by a fresh contract entered into in March 2004 which replaced the previous contract. It is necessary to determine whether that occurred, and, if it did, what the terms of the new contract were before it is possible to resolve the dispute as to the adjudicator's jurisdiction since he had been allegedly appointed under whatever contract had previously been in force which, according to Camber, had been superseded by the March 2004 contract. There should, therefore, be permission to defend this action so as to allow that issue to be tried out with oral evidence.
(5) There was no dispute in existence at the time the adjudicator was appointed.
BACKGROUND FACTS:
"Camber will only take part in this adjudication on the basis that such action will not prejudice its case [that the adjudicator has no jurisdiction]."
The response document then set out Camber's detailed defence to each item of monetary claim being advanced by Pillar both in relation to the originally contracted work and as to claims for varied and additional work.
"... Camber also seeks the following: ...
(b) Camber is entitled to compensation in the sum of £258,965.43",
which is the negative balance claimed after Camber has taken into account payments already made, ...
(e) All amounts that are found by the adjudicator to be due to Camber are be paid by Pillar to Camber within seven days."
"... never provided any notice for withholding in respect of its claims against Pillar as required by the contract or at all. Pillar intends to take no point about this, electing instead to deal head on with the claims made against it ...".
The pleading then set out a very detailed reply to Camber's cross-claims, running to many paragraphs and pages. Camber served a response document to this reply. Both Pillars claims and Camber's cross-claims were pleaded by reference to the IFC form of contract.
AD HOC SUBMISSION TO JURISDICTION:
OTHER ISSUES - PRELIMINARY PROCEDURAL ISSUE:
NO CONTRACT IN WRITING OR EVIDENCED IN WRITING:
FURTHER ORAL CONTRACT IN MARCH 2004:
NO DISPUTE:
CONCLUSION: