QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Aveat Heating Limited |
Claimant |
|
- and - |
||
Jerram Falkus Construction Limited |
Defendant |
____________________
Mr. Nigel Davies of Nigel Davies Associates) for the Defendant
Hearing date: 29th January 2007
____________________
Crown Copyright ©
Judge Richard Havery Q.C. :
The adjudicator shall notify its decision to the Contractor and the Sub-Contractor not earlier than 10 and not later than 28 Days from receipt of the notice of referral, or such longer period as is agreed by the Contactor and the Sub-Contractor after the dispute has been referred.
The adjudicator shall notify its decision to the Contractor and the Sub-Contractor not earlier than 10 and not later than 28 days from receipt of the notice of referral, or such longer period as is agreed by the Contractor and the Sub-Contractor after the dispute has been referred. The adjudicator may extend the period of 28 days by up to14 days, with the consent of the party by whom the dispute was referred. The adjudicator's decision shall nevertheless be valid if issued after the time allowed.....In Epping Electrical company Limited v. Briggs and Forrester (Plumbing Services) Limited [2007] EWHC 4 (TCC) I held a provision equivalent to the last sentence of that passage not to be compliant with the Act. Following the decision of the Inner House of the Court of Session in Ritchie Brothers (PWC) Ltd. v. David Philp (Commercials) Ltd. [2005] BLR 384, I held the provisions of section 108(2)(c) and (d) to be mandatory rather than directory, so that the adjudicator had no jurisdiction to reach his decision out of time. I went on to say in paragraph 19 of my judgment
The Scheme applies in place of the adjudication provisions of the contract. If it were otherwise, two competing adjudication provisions would simultaneously apply to the contract and many other contracts. That is a recipe for confusion and uncertainty and in my judgment cannot have been the intention of Parliament in passing section 108(5) of the Act.
Section 108(5) of the Act provides that if the contract does not comply with the requirements of section 108 subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts ("the Scheme") shall apply.
.....The Act does not render void a non-compliant procedure and a party to such a contract could adjudicate under that contractual arrangement, but is not bound by statute to do so. That party could still insist on adjudication under the Scheme.
It is not suggested that the defendant to the adjudication could insist on adjudicating under the Scheme. A footnote to the same paragraph, though not to the passage quoted, contradicts that passage. It says
.....The extent to which the contractual mechanism does not comply with the Act is irrelevant. If it does not comply the whole contractual mechanism is tainted and falls by the wayside to be replaced by the provisions of the Scheme, see John Mowlem Ltd. v. Hydra-Tight Ltd. (2002) 17 Const. L.J. 358.
John Mowlem was a decision of H.H. Judge John Toulmin C.M.G., Q.C. What he said (which appears at p.363) may suggest, but does not imply, the above proposition:
I have considered whether, if some parts of the sub-contract comply with the Act, they can be retained and the Act can be used in substitution for or to fill in those parts of the subcontract which are contrary to the Act. But the words of the Act are clear. Either a party complies in its own terms and conditions with the requirements of sections 108(1) to (4) of the Act or the provisions of the Scheme apply.
Judge Toulmin did not say whether, if the provisions of the Scheme apply, the contractual provisions of the adjudication can be used as they stand, in the alternative to the provisions of the Scheme.
The dispute concerns non payment of amounts considered due in an interim payment.
Mr. Davies submitted that it did not specify to which interim payment it referred contrary to paragraphs 1(3)(a) and (b) of the Scheme, not did it specify the nature of the relief claimed, contrary to paragraph 1(3)(c) of the Scheme. Paragraphs 1(3)(a), (b) and (c) of the Scheme require the notice of adjudication to set out briefly
(a) the nature and a brief description of the dispute.....(b) details of .....when the dispute has arisen
(c) the nature of the redress which is sought.
In my judgment, the notice did not comply with sub-paragraph (b) or (c). On the other hand, the nature of the redress sought in a dispute which concerns non-payment of amounts considered due is fairly obvious. I consider below whether sub-paragraph (a) was complied with.
The purposes of such a notice are first, to inform the other party of what the dispute is; secondly, to inform those who may be responsible for making the appointment of an adjudicator, so that the correct adjudicator can be selected; and finally, of course, to define the dispute of which the party is informed, to specify precisely the redress sought, and the party exercising the statutory right and the party against whom a decision may be made so that the adjudicator knows the ambit of his jurisdiction.I shall consider further the important question whether the dispute was sufficiently defined. But the other purposes mentioned in that passage were, in my judgment, sufficiently fulfilled. Judge LLoyd went on in paragraph 21 of his decision to say
The claimants were only entitled to exercise their right to call for adjudication if [they] first complied with paragraph 1(3) of the Scheme. They did not do so in part....
Judge LLoyd enforced the award only to the extent of the matters in dispute mentioned in the notice of adjudication. If Judge LLoyd was intending to say that compliance with all the requirements of paragraph 1(3) is a condition of enforcement of an award I respectfully disagree. The Scheme is more prescriptive than the Act in relation to the requirements of a notice of adjudication. In my judgment, those requirements must be regarded as directory rather than mandatory. The notice of adjudication was entirely sufficient for the purpose of selecting a suitable adjudicator, nor has the contrary been suggested.
Pursuant to clause 16.3.4 of the Sub-Contract Aveat Heating Ltd has ".....accepted [our valuation] notification under clause 16.3.3, and no further claim shall be made by [Aveat Heating Ltd] in respect of the Variation[s]" thereby a dispute does not and cannot exist.....Accordingly, in the absence of a dispute there is nothing to refer to Adjudication, and any third party that you may seek to be appointed will be without jurisdiction.
On 11th October Mr. Davies wrote to the Adjudicator at much greater length. The letter included the following passages:
.....Your appointment is defective and you do not have jurisdiction.....
.....it is not possible to bring an adjudication in respect of an agreement that has been settled.....
Clause 16.3.4 states
"If [Aveat Heating Ltd] disagrees with the whole or part of [Jerram Falkus Construction Ltd's] Valuation, it must, within 7 days of [Jerram Falkus Construction Ltd's] notification under clause 16.3.3, give its reasons for disagreement and [Aveat Heating Ltd's] own Valuation. In any other case [Aveat Heating Ltd] shall be treated as having accepted the notification under clause 16.3.3, and no further claim shall be made by it in respect of the variation"Neither Aveat Heating Ltd, or the Sharman Barton Partnership on its behalf, issued any such notice in accordance with clause 16.3.4. In accordance with the sub-contract Aveat Heating Ltd has accepted our valuation notification issued under cover of our letter dated 28 September 2006 and may not make any further claim in respect of the variations.
Given that the matter of the variation account is settled, a dispute does not and cannot exist.....
.....it is .....incumbent upon the party issuing the notice to describe the alleged dispute in sufficient detail to enable the other to understand what it is that it intends to refer to adjudication; such an ambiguous statement as ".....an interim payment" denies us the opportunity to understand what it is..... that is being attempted to be referred to adjudication.....
.....any information not previously disclosed within Aveat Heating Ltd's Final Account issued under cover of Sharman Barton Partnership's letter dated 22 August 2006 is information not previously relied upon by Aveat Heating Ltd and thereby cannot be the subject of dispute.....
Most of the propositions quoted above in this paragraph are matters of defence rather than matters showing the absence of a dispute. However, the penultimate passage ("it is..... incumbent...") is in a different category. And in the last extract the case of Edmund Nuttall Ltd. v. R.G.Carter Ltd. [2002] BLR 312 was referred to. Mr. Davies relied on the following passage in paragraph 36 of the judgment of His Honour Judge Richard Seymour, Q.C. in that case (ib., p.321):
No doubt, for the purposes of a reference to adjudication under the 1996 Act or equivalent contractual provision, a party can refine its arguments and abandon points not thought to be meritorious without altering fundamentally the nature of the "dispute" between them. However, what a party cannot do, in my judgment, is abandon wholesale facts previously relied upon or arguments previously advanced and contend that because the "claim" remains the same as that made previously, the "dispute" is the same.
.....it is [the claimant's] case that by virtue of its interim application for payment no.7 dated 18 April 2006 a further interim payment became due in the gross sum of £381,996.67* (cumulative, excl VAT)*[The claimant's] application for payment no.7 was actually in the amount of £385,631.35. Whilst this differs slightly from the gross sum referred [to] in this adjudication, the principle of the amounts claimed remain[s] unaltered.
By far the largest item in the claim is "Contract Works as attached schedule" £320,942.42. That sum, and the items and figures that compose it, appears in application number 7 and in appendix 10.4 to the notice of referral. The referral notice, in paragraph 6.02, states that the total value of £320,942.42 for contract works is arithmetically incorrect and should actually be £321,260.92, the difference being in respect of plot 5 sanitaryware in the sum of £318.50.
Item | Application no. 7 (£) | Referral notice (£) |
Contract works as attached schedule Plumbing & heating |
267,437.52 |
263,573.00 |
Sanitaryware | 24,524.50 | 24,639.54 |
Condensing boilers & associated works | 24,123.90 | 23,757.90 |
Washing machines | 2,212.50 | 2,183.00 |
Cookers | 2,962.50 | 2,923.00 |
Subtotal | 321,260.92 | 317,076.44 |
Alumasc rainwaters as schedule RW03 | 15,358.76 | 15,358.76 |
B.O.Q. rainwaters as schedule RW01+2+4 | 9,152.12 | 9,152.12 |
B.O.Q. rainwaters as schedule RW05 | 3,576.84 | 3,576.84 |
B.O.Q. rainwaters as schedule RW06 | 960.02 | 960.02 |
B.O.Q. rainwaters as schedule RW07 | 240.80 | 240.80 |
Subtotal | 29,288.54 | 29,288.54 |
Variations as schedule no. 1 | 10,855.98 | 11,087.28 |
Variations as schedule no. 2 | 5,488.23 | 5,488.23 |
Subtotal | 16,344.21 | 16,575.51 |
Prelims | 7,000.00 | 7,000.00 |
Design | 6,000.00 | 6,000.00 |
Increased cost 7000X77 of 89 flats | 6,056.18 | 6,056.18 |
Subtotal | 19,056.18 | 19,056.18 |
Gross value | 385,631.35 | 381,996.67 |
Thus the claim as referred to the adjudicator was substantially the same as that made on 18th April. Prima facie, one would expect the dispute to be the same, especially since the claimant had stated in its notice of referral that the principle of the amounts claimed remained unaltered.
It shall be a condition precedent to the appointment of an adjudicator that it [sc., the adjudicator] shall notify both parties that it will comply with this clause 38A and its time limits.The adjudicator gave no such notification. The only effect of that can be that he is not appointed under clause 38A (as I have found for other reasons). In my judgment, he is not deprived of his jurisdiction on that account.