QUEEN'S BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
BIRMINGHAM CIVIL JUSTICE CENTRE 33 BULL STREET BIRMINGHAM B4 6DS |
||
B e f o r e :
sitting as a High Court Judge
____________________
THOMAS VALE CONSTRUCTION plc | Claimant | |
and | ||
BROOKSIDE SYSTON LIMITED | Defendant |
____________________
Mr Simon Henderson of Counsel (instructed by HBJ Gateley Wareing LLP) for the Defendant
Dates of hearing: 10 October 2006
Date of draft judgment: 31 October 2006
____________________
HTML VERSION OF JUDGMENT
Crown Copyright ©
Background
Clause 1 provided that an expert would be appointed to determine whether the works were practically complete and to set out what snagging works remained. The parties agreed that the expert's determination would be temporarily binding on them.
Clause 2 provided that, once the expert had made his determination, TVC was to prepare and issue a programme to carry out remedial and snagging work and to use reasonable endeavours to comply with that programme.
Clause 3 noted that TVC's liability for late completion was agreed in the sum of £220,000, payable upon agreement or determination of the Final Account pursuant to the Building Contract.
By clause 6, TVC was required to submit its draft Final Account within 4 weeks of the date of the Supplemental Agreement, and, thereafter the parties were to attempt to agree the Final Account.
Clause 7 included the following: "Neither party shall be obliged to make any payment to the other, whether by way of payment for the Works, damages for late completion or the release of retention until such time as the Final Account is either agreed between the parties or determined pursuant to the Building Contract".
"...The obvious intention discussed at the settlement meeting, is that the payment at that time would be a balance, taking account of all the sums due. Why else would the Final Account be the "trigger mechanism"? The intention was that sums due to my client would be set off against the agreed liquidated damages amount.
Accordingly I invite you to:
1. confirm acceptance of Mr Riches' determination and that the retention may be set off against sums otherwise due to your client when the Final Account is agreed/determined;
2. confirm what, if any, values your client considers may be properly set off against the Final Account by reference to outstanding snags."
TVC's case
BSL's case
Relevant contract clauses
30.6.1 "Not later than 5 days after the Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 30.5.5, or after the Employer's Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 30.5.8, the Employer shall give a written notice to the Contractor which shall specify the amount of the payment proposed to be made in respect of any balance stated as due to the Contractor from the Employer in the Final Statement or in the Employer's Final Statement."
30.6.2 "The final date for payment of the said balance payable by the Employer to the Contractor or by the Contractor to the Employer as the case may be shall be 28 days from the date the Final Statement becomes conclusive as to the balance due between the Parties in accordance with clauses 30.5.5, or after the Employer's Final Statement becomes conclusive as to the balance due between the Parties in accordance with clause 30.5.8. Not later than 5 days before the final date for payment of any balance to the Contract the Employer may give a written notice to the Contractor which shall specify any amount proposed to be withheld and/or deducted from such balance due to the Contractor, the ground or grounds for such withholding and/or deduction and the amount of withholding and/or deduction attributable to each ground.
Discussion
Accordingly I invite you to:…. 2. confirm what, if any, values your client considers may be properly set off against the Final Account by reference to outstanding snags."
At that stage, the parties were awaiting Mr Ribbands' decision as to the Final Account sum and both knew that TVC still had work to do.
TVC's ground 1
TVC's ground 2
TVC's ground 3
TVC's ground 4
Conclusion
14 November 2006