QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
GREENORE PORT LTD. (formerly known as Greenore Ferry Services Ltd.) |
Claimant |
|
- and - |
||
TECHNICAL & GENERAL GUARANTEE COMPANY LTD. |
Defendant |
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
MR. MICHAEL DAVIE (instructed by Bayham Solicitors) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
MR. JUSTICE JACKSON:
"… if the Engineer shall certify in writing to the Employer that in his opinion the Contractor …
(d) despite previous warning by the Engineer in writing is failing to proceed with the Works with due diligence or is otherwise persistently or fundamentally in breach of his obligations under the Contract …
then the Employer may after giving 7 days notice in writing to the Contractor enter upon the Site and the Works and expel the Contractor therefrom without thereby avoiding the Contract or releasing the Contractor from any of his obligations or liabilities under the Contract or affecting the rights and powers conferred on the Employer or the Engineer by the Contract and may himself complete the Works or may employ any other contractor to complete the Works and the Employer or such other contractor may use for such completion so much of the Constructional Plant Temporary Works goods and materials which have been deemed to become the property of the Employer under Clauses 53 and 54 as he or they may think proper and the Employer may at any time sell any of the said Constructional Plant Temporary Works and unused goods and materials and apply the proceeds of sale in or towards the satisfaction of any sums or which may become due to him from the Contractor under the Contract."
(i) Reconstruction of sections A and B of the quay wall. This entailed sinking piles into the sea bed in front of the existing masonry quay wall and then constructing a new steel wall along the line of the piles.
(ii) Construction of a new concrete deck, together with crane rails, along sections A and B of the quay.
(iii) Construction of a new cattle access tunnel(iv) The installation of pipe work and other services.
(v) Dredging the harbour to specify depths, including the blasting and removal of rock. The specified depths were shown on drawing 4618.01\T\104.
(vi) Suction dredging of PCBs from an area delineated on a drawing marked "Figure 4-6", and depositing that material in the void between the old masonry quay wall and the new steel quay wall.
(vii) Shore protection works around Greenore Point.
References in the BQ to sections A and B are references to the eastern end of the quay. Section A extended westwards from Greenore Point for a distance of 98 metres. Section B extended westwards for a further 53 metres from the eastern end of section A. The remainder of the harbour renovation works which the claimant had in mind, namely sections C and D, formed no part of the contract and were deferred to a later date.
"Please note that concrete supply to site will be provided by the client, Greenore Ferry Services Ltd., commencing on 30th April 2001 as discussed and agreed. You will be required to liaise with the concrete supplier with regard to timing of supply and quantity required etc. The element of costs associated with the supply of concrete only as invoiced by the concrete supplier will be deducted from future valuations."
VO 4 stated:
"Please note that steel reinforcement supply to site will be provided by the client, Greenore Ferry Services Ltd., commencing on 30th April 2001. You will be required to liaise with the steel reinforcement supplier with regard to timing of supply and quantity required etc. The element of costs associated with the supply of reinforcement only as invoiced by the supplier will be deducted from future valuations."
"Following your recent conversation with one of our directors, Mr. Wilcox, I would confirm that monies received on site are in satisfaction of a contract sum for work currently being undertaken within the remit of the contract. We understand your concern but would assure you that this is the most efficient method of progressing the works."
"Present: Ms. R. de Pasquale, Greenore Ferry Services (GFS); Ms. V. Price, Greenore Ferry Services Limited (GFS); Mr. W. Wilcox, SAR Marine & General (SAR); Mr. R. McLeod, SAR Marine & General (SAR); Mr. D. O'Loan, Kirk McClure Morton (KMM); Miss R. Griffin, Kirk McClure Morton (KMM).
"1.0. SAR financial position. WW stated that SAR Marine and General Limited are about to go into liquidation and all insurances for the company were cancelled this morning.
"WW stated that SAR would be in court on Monday 23rd to start administration/liquidation proceedings.
"WW stated that due to the conditions of contract the plant which is on site at present would remain on site until sections A and B (up to pile 51) have been completed.
"WW stated that there would be two options available to GFS to complete the contract. Option 1, Mark Patterson would discuss with the administrator/liquidator today to try to purchase the SAR plant and start up a new company. GFS could then use the new SAR company to complete the works. Option 2, the administrator could run the contract on behalf of SAR in its present form.
"DOL noted that a third option was available to GFS following termination of the contract by SAR, then GFS could keep the equipment on site and finish the works with another contractor.
"RDP stated that she would prefer not to use the new SAR company as this would simply revert to a similar working arrangement as at present and would await the outcome of the administrator/liquidator meeting with MSP to review if Option 2 was viable.
"DOL stated that the contract with SAR was not terminated until official notice was received that SAR had gone into liquidation but that lack of insurance cover had effectively meant they had abandoned the contract.
"In addition, the previous six weeks' work on site had also demonstrated that SAR Marine & General, without the assistance of GFS to pay site administration, labour and material costs, would have abandoned the contract some considerable time ago.
"RDP requested a list from WW of the plant on site at present. WW agreed to forward a list.
"2.0. Completion of Phase 1. WW stated that he would be prepared to finish the contract under the same working conditions as present, i.e. GFS pay for the remaining labour and administration costs and materials but would be working under a different company, Norfolk Diving Company (NDC).
"VP stated that if NDC complete the contract that WW must supply a VAT number and a C2 certificate, otherwise GFS would have to withhold 35 per cent VAT.
"WW stated that he would provide insurance and would enquire what is required to obtain a C2 certificate.
"DOL stated that if GFS employed NDC the contract would be on a labour and administration basis with GFS supplying materials and that GFS may have to insure the SAR plant held on site. However, it would be desirable for NDC to cover all insurances if possible. WW to investigate insurance cover and revert.
"3.0. Requirements on site.
"WW stated that he required a construction drawing for the return wall capping beam. WW stated that there is approximately four to six weeks to complete the works as soon as the PCBs have been cleared.
"DOL confirmed that the chain connections from the sheet piles to the fender units were acceptable.
"WW requested the detail for the isolated mooring bollard behind the temporary offices.
"DOL confirmed that the ladders are to be shot-blasted and painted with zinc ridge paint.
"WW noted that the fender at chainage 110 metres has been moved one pile position eastwards as there had been difficulty installing at the proposed location."
"It is anticipated that a sale of the business will be effected soon to a new company owned by the current directors of SAR Marine & General. They will endeavour to minimise the disruption and loss to creditors of the company by completing outstanding contracts."
"MSP reports that SAR in 'Administration'. If management buy-out can't find finance within 6 weeks then automatically liquidated. Cost is approx. £1M to buy back (including 50K for goodwill – 'for whatever goodwill there is left'.)
"MSP reported that GFS has three options:
"1. To let administrator run the contract;
"2. To let SAR new company run the contract, both on similar basis as present, i.e. site admin, labour plus materials supply at cost;
"or 3. To determine the contract (by engineer).
"MSP noted that KMM had 'more than sufficient grounds to determine the contract.' DOL agreed. Discussion on reasons for lack of progress. No materials supply. MSP noted that insurances were now in place, thus not grounds to determine.
"MSP noted that Administrator had been in touch with Roisin de Pasquale and solicitor in Arthur Cox yesterday? (although he didn't sound confident on this).
"DOL checked with OMIS and no insurance in place for SAR or for SAR new company."
I should explain that the last two lines of that document are a note which Mr. O'Loan added after the end of the telephone conversation.
"GREENORE HARBOUR DEVELOPMENT
"CONTRACT WITH SAR MARINE & GENERAL LTD – CERTIFICATION UNDER CLAUSE 63.
"Following discussions on 18th July with the Contractor we note that the insurance cover for the contract has been rescinded (written confirmation received from SAR) and that the work on site therefore ceased completely.
"Given the recent history of direct payments from yourselves (GFS Ltd) to cover materials supply to site, site administration, labour charges on site and subsistence to the workforce, etc., since early May, we consider that the Contractor is failing to carry out his obligations with due diligence to the Contract.
"We remind you that had a direct intervention by yourselves not taken place to directly pay both the concrete and steel suppliers, that the vital supply of concrete and steel reinforcement would have been stopped in the first week of May 2001.
"Furthermore, the original date for completion of the contract was 14th January 2001 and we still await completion at this late stage (now in week 52 of a 24 week contract).
"We thus certify that in our opinion, the Contractor is persistently and fundamentally in breach of his Contractual obligations.
"You should note that under the terms of the contract in Clause 63(1), that the Employer may enter and expel the contractor from the site. Under Clause 63(3), we note that we shall determine and certify any amounts accruing to the Contractor in respect of work done and materials and plant on site. We would also point out that the constructional plant, temporary work, goods and materials on site shall be deemed to become the property of the Employer under Clause 53."
"I refer to the CONTRACT and I enclose a certification issued by the Engineer under the Contract which confirms that the Contractor is persistently and fundamentally in breach of his contractual obligations under clause 63 of the Contract.
"On behalf of Greenore Ferry Services, I hereby formally give seven days written notice to the Contractor of Greenore Ferry Services intention to enter upon the Site and the Works and to expel the Contractor from Site pursuant to the terms of Clause 63(1)(d) of the Contract.
"Greenore Ferry Services wishes to advise you that all constructional plant, temporary work, goods and materials on site are deemed to be the property of Greenore Ferry Services, under clause 53 of the Contract and therefore the Contractor has no entitlement to remove any such items from Site.
"Please note that I am also sending this formal notice to the Administrator of the Contractor."
The claimant did indeed send a letter in similar terms to the administrator on the same day.
"We understand that you have determined the contract on which Technical & General Guarantee Company Limited issued the above numbered Performance Bond.
"We advise that, as Guarantors, we will arrange to complete the Works as designated in the original contract for the original contract price, with no additional costs to yourselves other than as provided for in the original contract. We have appointed BME (Contracting) Limited as our contractors on the project, and would be grateful if you contact the writer at our Geneva office without delay to organise a start date for the works."
"Further to our recent discussions and review of the works to be completed at Greenore Port we are pleased to confirm that Norfolk Marine Limited ('Norfolk') has been appointed to complete the quay all works, as described below, at Greenore Port which were to be completed by SAR Marine under the terms of the contract entered into between Greenore Ferry Services and SAR Marine dated 4 September 2000 ('the Works').
"We are cognisant that you are aware of the extent of the outstanding Works (as described and referenced by Parts 1 to 4 of the original SAR Marine contract documents) which include:
"* Concreting of the capping beam/crane rail beam at Chainage 0m to approx Ch 38m and return end.
"* Suction dredging of berth spoil and placement behind quay wall but excluding final dredging.
"* Placement of third crane rail beam between cattle tunnel and return end of quay.
"* Concreting of deck area behind capping beam.
"* Fenders, bollards, water supply, moving cranes, ducts, electrics, ladders, etc.
"* All other associated works necessary for completion as described or implied in the original contract documents as varied together with ensuing site instruction and variations to the original works.
"Norfolk's contractual obligation is to provide labour and necessary site administration to complete the Works as the bulk materials and equipment will be supplied through Greenore Ferry Services Limited. This contract award shall therefore cover insurance, labour and site administration costs of Norfolk necessary for the completion of the Works. Norfolk hereby agrees that it will commence, undertake and complete the Works with due diligence and will use its best endeavours to complete the Works with minimum possible period.
"The precise reimbursement payable to Norfolk for completing the Works (as referred to above) shall be determined by reference to the agreed rates listed in the Kirk McClure Morton fax of 15 August 2001 which shall be deemed to form part of this agreement. The estimated cost is in the order of IR£14,000 - £16,000 per week.
"Please note that should the progress on site be deemed by the Engineer to be inadequate given the hours worked, then the Engineer can, at his sole discretion, proportionately reduce any monies which would otherwise be due given the inadequate progress of Norfolk in completing the Works.
"Please sign the enclosed copy of this letter to confirm your acceptance of your appointment on the above terms."
(i) How did SAR's contract come to an end? Was it repudiated by the claimant or repudiated by SAR or terminated under clause 63?
(ii) Is the claimant precluded from recovering its losses because it unreasonably rejected the defendant's offer to complete the renovation works at no additional cost?
(iii) Is the claimant in principle entitled to recover the difference between (a) actual costs incurred on the works and (b) the amount of the notional final account prepared by Mr. O'Loan? If so, what is the proper quantification of that difference?
(iv) What damages for delay is the claimant entitled to recover?
(v) In respect of the rock dredging which was not carried out, what is the claimant entitled to recover (a) in respect of the costs of that exercise, and (b) in respect of loss of profits?
(i) The new wall consisted of sheets of steel placed between tubular piles. The piles were pinned to rock at the base. Tie rods attached to the tops of piles were anchored into another wall behind.
(ii) The dredging works were of two types. First, excavation of a contaminant known as "PCB", using Toyo pumps; secondly, the main dredging works of the berth pocket to allow a deeper draught for ships. The main dredging works needed to come after the construction of the new quay wall, since the old quay wall would collapse if deep dredging was carried out close to it.
notes that one item of work which SAR priced in the BQ was a survey to ascertain the location of the rock head.
(i) SAR repudiated the contract on 18th July 2001 and the claimant accepted that repudiation by engaging Norfolk to take over the works.
(ii) The claimant repudiated the contract by engaging Norfolk to take over the works and SAR accepted that repudiation.
(iii) The claimant terminated the contract pursuant to clause 63 of the conditions.
(i) The basis of SAR's contract changed before repudiation in two important respects: (a) main dredging was excluded; (b) the basis of SAR's contract changed so that the claimant assumed responsibility for paying wages and purchasing materials.
(ii) The claimant did not complete the works in a reasonable manner, in that it engaged Norfolk under a contract which was unrestricted in terms of time and cost.
(iii) The engineer failed to measure the works either when SAR left site or when Norfolk completed. The evidence available to establish the additional completion costs is (through the claimant's default) so exiguous that this head of damages cannot properly be assessed at all.
"On completion of the main deck works there is also a dredging contract to complete which shall be profitable but has been excluded as these works will be to the discretion of the administrator."
In my view, when that note is read in context, it is not saying that dredging works had been excluded from SAR's contract. It is saying that dredging works have been excluded from the financial analysis set out in the spreadsheet.
(i) It is unlikely in the extreme that any new contractor would have been willing to tender for the remaining works at Greenore on a lump sum basis.
(ii) If a new contractor had been brought in, this would have generated additional delay which would have been highly damaging to the claimant's business.
(iii) The use of Mr. Wilcox and his team, who were familiar with the Greenore project, was the optimum solution to the problems created by SAR's repudiation.
(iv) Norfolk did not have the abilities or experience to enter into a lump sum fixed term contract, essentially for the reasons given by Ms. Price.
(v) Mr. Wilcox was in a strong bargaining position. The claimant was in a weak bargaining position. The contract which was negotiated during August 2001 fairly reflected the parties' bargaining strengths.