QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137 Fetter Lane London, EC4A 1HD |
||
B e f o r e :
____________________
BARIS LTD |
Claimant |
|
- and - |
||
KAJIMA CONSTRUCTION EUROPE (UK) LTD |
Defendant |
____________________
Beachcroft Wansboroughs, Solicitors for the Defendant
____________________
Crown Copyright ©
His Honour Judge Peter Coulson QC:
a) the statement of Laura Harry dated 16 December 2005 and the three exhibits thereto;
b) the statement of Martin Gledhill, dated 9 January 2006 and the two exhibits attached thereto;
c) the statement of Terrance Damms, dated 12 January 2006 and the two exhibits attached thereto;
d) the claim form of 19.12.05 and the correspondence between the solicitors which they have copied to the court.
"Baris Ltd hereby offer to fully and finally settle their rights given by the adjudicator if Kajima Construction Europe (UK) Ltd pay the total sum in the decision, namely £181,895.60 only within 21 days of this letter, ie 3 January 2006, plus the costs to be taxed if not agreed on a simple basis incurred by Baris Ltd in issuing and serving proceedings in the High Court."
"We acknowledge receipt of your letter dated 13 December 2005, and confirm that funds will be in your account on or before 3 January 2006."
a) whether or not the offer letter of 13 January 2006 is admissible in these proceedings;
b) whether the offer of 13 December was fully accepted by the Defendant on 14 December so as to give rise to a defence of accord and satisfaction.
As noted above, it was agreed that I would provide a judgment on these issues in writing, without the need for the parties to incur the costs of the proposed hearing on 20th January. Accordingly, I set out below my decision on these issues.
Admissibility
Interest
"I find that Kajima shall pay to Baris due to the late payment, which up to the date of this Decision is the sum of £1,675.49 (excluding VAT) and thereafter at the rate of £62.06 (excluding VAT) per day until payment is made."
Costs
a) which were not commenced until after the parties had reached an agreement;
b) which therefore had no discernible purpose;
c) in which the Claimant has chosen not to explain why they were commenced without any reference to the relevant correspondence;
d) prior to the commencement of which, neither the Claimant, nor its solicitor, had thought it appropriate to raise expressly with the Defendant the only point which, even on their case, remained in issue, namely the question of interest.
Conclusions