QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
P4 Limited |
Claimant |
|
- and - |
||
Unite Integrated Solutions PLC |
Defendant |
____________________
Lucy Garrett (instructed by Walker Morris, Leeds) for the Defendant
Hearing dates: 10, 11, 13 and 14 July 2006
____________________
Crown Copyright ©
Mr Justice Ramsey:
Introduction
"The goods were supplied under the terms of the enclosed contract. As you can see, they were not Tudor's to supply until P4 had been paid for them and, until P4 had been paid, title vests in P4.
We ask therefore that all P4's goods should be held awaiting P4's collection along with any of our products that may still be in the Tudor compound. In particular, you should not fix or in any other way convert any of our goods which are not already fixed to your premises.
Be aware that all the emergency lighting within Orion's Point (with the exception of 1 No Interface Box & 8 No Collector Boxes) is the property of P4 and we reserve the right to repossess them."
(1) Did P4 contract with Tudor on terms which included a retention of title clause?
(2) Did P4 assign its right to immediate possession to Abbey National?
(3) If P4 did contract with Tudor on terms which included a retention of title clause:
(a) Is unite protected by s. 25(1) of the Sale of Goods Act 1979 (the "disposition" issue)?(b) Did property vest in Unite under Clause 21.4.5 of DOM/2?(c) What is the true construction and effect of the 17 September 2003 Agreement on the contract between Unite and Tudor (including the issue of whether the sub-contract works required Tudor to provide Emergency Lighting to comply with a requirement for summer lets)?
(4) The claim in respect of P4's 830 exit signs and whether they were converted by Unite.
(5) What goods belonging to P4 remained on site unfixed at 20 October 2003?
(1) That the agreement made between P4 and Tudor on 21 January 2003 was varied by P4's quotation of 8 August 2003 so that Tudor was bound by P4's standard terms.(2) That the order placed by Mr. Husband of Unite on 24 September 2003 gave rise to a direct liability for Unite to pay for the goods delivered as a result of that order.
Incorporation of Terms
"as per your quotation 7911-4 Revised on Date 8th August 03
Original Quote - £34,335.50
Revised Quote - £52,815.50
Additional Cost £18,480.00 +VAT"
"Applying the ticket cases, the question is whether reasonable notice was given of that condition. In my opinion it was not. It is settled law that a ticket on its face must say: "For conditions, see back." If it does not say it on the front, it is not sufficient to put a condition on the back. That was decided by the House of Lords in Henderson v. Stevenson (1875) L.R. 2 Sc. & Div. 470, and is so well settled that Anson's Law of Contract, 23rd ed. (1969), p. 146 says:
"It is the practice, for example, always to refer on the face of a ticket to the fact that there are conditions on the back. If this is not done, then following the case of Henderson v. Stevenson in 1875, the courts have consistently held that such a notification is defective." "
"The photocopies of that form give an inadequate and incomplete indication of its true appearance. When one sees the original it is apparent that the texture of the paper is such that, even after the relevant particulars have been typed on the face, it is clear that there is printing on the reverse. This document was received by a businessman, a director of the defendant company, whose own standard form had terms and conditions printed on the back, and who would have expected the print on the back to relate to any future contract between the parties. In the absence of any evidence to the contrary or some other significant circumstance pointing to the contrary, I should infer that he did acquaint himself with the print on the back, at least to the extent of discovering that it embodied contractual terms and conditions and, probably as to their purport."
Did P4 assign its right to immediate possession?
""Debt" the amount (or, where the context allows, a part of such amount) of any obligation or indebtedness, including any tax or duty payable, incurred by a Customer under a Supply Contract together with (where the context allows) any Related Rights pertaining to such obligation or indebtedness."
"Following our conversation regarding the old invoices for Tudor M/E services Ltd ("Tudor"), I can confirm that under the terms of your agreement any invoice beyond 123 days is reserved against and hence withheld from funding. Five Arrows Commercial Finance took over your Abbey Invoice Discounting facility on 1 July 2004 and continued holding this reserve so did not fund against the "Tudor" invoices.
Following your instruction we wrote off the sum of £73,933.36 in relation to the 'Tudor' debt on 18 April 2005, so removing it from your assigned ledger."
"We shall have the right by oral or written notice to have transferred to us by you the ownership of any other Goods (the subject of a Supply Contract) of which the ownership shall not have passed to the Customer."
Is Unite protected by s.25(1) of the Sale of Goods Act 1979
"The question raised by that case was whether or not the "other disposition" within section 25 has to be a sale, or of the nature of a sale, under which title has passed. In my view it does not and the word "disposition", as submitted by Miss Garrett, is of wide application and would be wide enough in this case to include an agreement of the nature contained in clauses 21.4.5.2 or 21.4.5.3. However, that does not mean that, when the "other disposition" is in the nature of an agreement, it has the same effect as if there had been a sale. In other words, if there is a sale there is the transfer of title but, in my judgment, if there is another form of disposition which does not transfer title then section 25 of the Sale of Goods Act does not give rise to a transfer of title merely because a "disposition" is in the same phrase as a sale."
(1) Lord Denning at 218 said that the word "disposition" was a very wide word and cited what Stirling J. had said in Carter v Carter [1896] 1 Ch 62 at 67, that a disposition extends "to all acts by which a new interest (legal or equitable) in the property is effectively created ".(2) Phillimore LJ at 219 said that "to constitute a disposition the dealing with the goods must go beyond the mere transfer or delivery of them: there must be some disposal which involved transfer of property"
(3) Megaw LJ at 230 said " "Disposition" must involve some transfer of an interest in property, in the technical sense of the word "property" as contrasted with mere possession."
Did property vest in Unite under DOM 21.4.5?
(1) Clause 21.3.1 states that each interim payment to the Sub-Contractor shall be the Contractor's gross valuation of the sums referred to in clause 21.4, less certain sums.(2) Clause 21.4 states that the gross valuation shall be made up of the amount referred to in clauses 21.4.1 and 21.4.2 less the total amount referred to in clause 21.4.3.
(3) Clause 21.4.1 contains three sub-clauses. Clause 21.4.1.1 concerns "the total value of the sub-contract work on site"; clause 21.4.1.2 concerns "the total value of the materials and goods delivered to or adjacent to the Works for incorporation therein by the Sub-Contractor but not so incorporated" and clause 21.4.1.3 concerns the "total value of any materials or goods other than those to which clause 21.4.1.2. refers where listed by the Employer under clause 15.2 of the Main Contract Conditions and where the conditions set out in clause 15.2 have been fulfilled."
(1) Clauses 21.3.1 and 21.4 oblige Unite to make interim payments which must include payment for work done and for certain goods and materials;(2) Clause 21.4.1 draws a distinction between goods and materials which have already been included in an Interim Payment under the Main Contract and paid for by the Employer, and those which have not;
(3) Clause 21.4.1.1 requires Unite to include payment for goods which have been installed whether or not those goods have already been paid for by the Employer;
(4) Clause 21.4.1.2 requires Unite to include payment for goods which are on site but unfixed whether or not those goods have already been paid for by the Employer;
(5) On the proper construction of clause 21.4.1.3 in conjunction with clauses 15.2 and 30.1.2 of the Main Contract, as amended, Unite must include payment for off-site goods only where such goods have already been paid for by the Employer;
(6) Unite is not prevented by the subcontract from making payments in excess of those which it is obliged to make pursuant to clause 21.3.1 and 21.4;
(7) On a proper construction of clauses 21.4.5.2 and 21.4.5.3, the phrase "any such materials or goods" must refer to both on site and off site goods. This is because:
(a) Both clause 21.4.5.2 and 21.4.5.3 refer to clauses 30.2A and 30.2B of the Main Contract which both expressly refer to payment for off-site goods.(b) The parties intended under Clause 21.4 that property in unfixed goods would pass on payment and it is unrealistic and uncommercial to suppose that the parties drew a distinction between on site and off-site unfixed goods which they did not then see fit specifically to identify in the contract;(c) The heading to Clause 21.4.5 in the JCT form, which it is accepted can only be indicative, reads "Property in unfixed materials and goods" and makes no distinction between on and off-site goods (such as is made elsewhere);(8) There is nothing in clause 21.4.5 to suggest that it does not apply where Unite makes a payment which is more than the payment which Unite was obliged to make pursuant to clause 21.3.1 and 21.4.1 to 21.4.3. Indeed, it would be odd if this were the case since the parties cannot have intended that if the Contractor pays the Sub-Contractor monies in advance this has the effect of disapplying the vesting provisions. The trigger for the operation of clauses 21.4.5.2 and 3 is either payment by the contractor or payment by the Employer respectively: nothing else;
(a) The September Agreement was an agreement by the parties as to what monies remained to be paid under the Sub-Contract. It followed a dispute in relation to what sum was due under application no. 8 and it was an agreement as to what would be paid in respect of that application and what would be paid in respect of the remainder of the Sub-Contract Works;
(b) The parties treated it as a payment made under the Sub-Contract in generating a certificate and self bill invoice in respect of it (as had been done in relation to previous applications);
"Tudor have been paid £1,754,901.77 less retention of £87,745.08 plus VAT for the sub-contracted mechanical and electrical works at Orion's Point the specification for which included the design and installation of the emergency lighting system for which P4 were the actual suppliers. I believe Unite has paid Tudor 100% of the lighting, small power and heating element of the works, into which P4's goods would fall."
(1) At 537:
"My main reason for not following Banbury's case is that I am unable to accept the proposition that payments made with reference to the value of materials – materials being the external 'yardstick' used by the parties which, they hope, will soon be incorporated into the works – have the effect of creating any property interest in the paying owner. Payments have long been recognised as being merely agreed instalments in reduction of a lump sum price, made on that account to keep the building contractor on the job. The purpose of instalment payment is not to pay for the materials, in the sense that a purchaser of land or specific goods pays money for, or towards the purchase price. Instalment payments are made in contracts like this as a practical measure to enable the contractor to keep working under the contract; they are made also in reduction of the lump sum contract price. Such payments have been described as the lifeblood of the contract."
(2) Later at p 542:
"the progress payments were not allocated to, appropriated specifically for, or advanced against, the purchase of the materials …. Banbury … is not, or ought not to be, authority for the proposition that interim instalments or progress payments are in themselves evidence of payment for materials."
Emergency Lighting for Summer Letting
"The Subcontractor shall upon and subject to the Subcontract Documents and provisions of the Main Contract carry out and complete the Subcontract Works shown upon and described by or referenced to in those documents."
"A system of self test self contained emergency lighting shall be designed which shall incorporate a central addressable emergency lighting control distribution panel, providing for 3 hour support for illumination for safe exit from the building and for the illumination of exit signs. The battery life shall not be less than 5 years. The system shall be designed generally on the non-maintained principle. The emergency lighting specialist supplier shall also supply the emergency exit signs for Schedule of Emergency Lighting Luminaries."
"The Contractor shall be responsible for obtaining Building Regulations Approval, Building Notices and the Building Regulations Completion Certificate, the latter to be obtained prior to the Employer's issue of the Statement of Practical Completion.
Unite intend to directly let the accommodation outside of university term time. The Contractor will liaise with the relevant authorities to ensure that the building fully complies with building regulations and is fully complaint for its intended use.
Notwithstanding anything contained in the Articles of Agreement, Conditions or Appendices the contractor shall not be entitled to any extension of time or additional payment as a result of any delays or costs incurred in obtaining Building Regulation Approval."
Payment of £190,000 under the September Agreement
Extent of Incorporation at 20 October 2003
(1) Block B: Levels 8 and 9: 26 September 2003.(2) Block B: Levels 1 to 7: 28 September 2003.
(3) Block C: Levels 1 to 4: 4 October 2003.
(4) Block C: Levels 5 and 6: 11 October 2003.
Three Type 830 Light Fittings
Amendment of Pleadings
Summary
(1) P4 did not contract with Tudor on terms which included a retention of title clause.
(2) P4 did assign its right to immediate possession to Abbey National but P4 would still have had title to sue in respect of any claim for conversion based on a retention of title clause.
(3) If P4 had contracted with Tudor on terms which included a retention of title clause:
(a) Unite would have been protected by s. 25(1) of the Sale of Goods Act 1979 on the basis of the provisions of Clause 21.4.5 of the Sub-Contract(b) Property in the relevant materials and goods did vest in Unite under Clause 21.4.5.3 of the Sub-Contract to the extent that it had not vested in Hiremaxi under Clause 21.4.5.2.
(c) The September Agreement amended the method of payment but did not change the effect of payment under the Sub-Contract between Unite and Tudor.(d) The Sub-Contract Works required Tudor to provide Emergency Lighting to comply with a requirement for summer lets.
(4) P4 succeeds in its claim in respect of the three Type 830 Fittings which were converted by Unite.
(5) On 20 October 2003, there were 30 Klippa emergency lighting bulkhead units which remained on site unfixed.