QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Monavon Construction Limited |
Claimant |
|
- and - |
||
(1) Mr Simon Davenport (2) Mrs Angelika Davenport |
Defendants |
____________________
WC1A 2LS, DX 134442 Bloomsbury, Ref: CJW/CBB/2812.1/1068_1) for the Claimant
Mr Paul Letman (instructed by Palmers, Solicitors, 19 Town Square, Basildon, Essex,
SS14 1BD, DX 53002 Basildon, Ref: APS/CC/Davenport) for the Defendants
Hearing dates: 8 June 2006 followed by further written submissions
No 2
____________________
Crown Copyright ©
HH Judge Thornton QC:
Introduction
(1) As to Monavon's claims, I found in its favour that there was no ceiling in relation to the sum that Monavon could charge for undertaking the work that was the subject of its claim and also in its favour in relation to some of the small items of claim still in dispute. The result was that Monavon was entitled, subject to abatement, set-off and cross-claim, to a sum of just under £100,000. Monavon's net claims had totalled about £116,000.
(2) As to the Davenports' claims, I found in their favour that they were entitled to just over £100,000 as damages representing the cost of repair of the many items of defective and incomplete work, subject also to Monavon's set-offs and cross-claims.
(3) The principle issues, in terms of their monetary consequences, were the issues arising from both parties' rival contentions that Monavon was, or was not, liable for any work carried out by the previous contractors or for any surviving defects or deficiencies in that work once Monavon had carried out its work, that there was, or was not, a cost ceiling or limit on Monavon's potential recovery, that the Davenports' principle defects claim relating to dampness in the basement was, or was not, caused by any breach by Monavon of its contractual obligations and that most of the remaining items of the Davenports' claims were, or were not, misconceived, subject to abatement or set off or greatly exaggerated.
(4) All these issues were closely inter-related. This was inevitable given the relationship between the claims based on the cost of the work and the cross-claims based on defects and deficiencies in that work which were, both in law and in fact, subject to defences of abatement and set-off in each direction.
(5) The total sum claim was about £115,000 and that being cross-claimed was originally about £230,000 but was increased by amendment just before the trial to about £365,000. Although these sums were, on paper, significantly different, they were closely inter-dependent and it would not have been possible to make a realistic offer of settlement or a payment into court that related solely to either the claim or the cross-claim, given the existence of the alleged cap and of the Davenports' entitlement to abate
(6) The end result of the litigation was that the Davenports ended up as succeeding by the marginal result of a judgment in their favour in a sum of just under £5,000.
Parties' Contentions
(1) The Davenports
(2) Monavon
(3) Indemnity Costs
Parties' Conduct
(1) Pre-action Conduct
(2) Delay and Late Development of Case
(3) Negotiation, Compromise and Offer to Settle
(4) Exaggerated or Unreasonable Pursuit of Issues and Claims
(5) Unreasonable Incurring of Costs
(6) Overall Conduct
Conclusion – Costs
Replacement Carpets and Damp Proofing Issues
Overall Conclusion
HH Judge Thornton QC
Technology and Construction Court