QUEEN'S BENCH DIVISION
SALFORD DISTRICT REGISTRY
TECHNOLOGY & CONSTRUCTION COURT
Peel Cross Road Salford |
||
B e f o r e :
(Sitting as a Judge of the High Court)
____________________
DAVID McLEAN CONTRACTORS LIMITED | Claimant | |
-v- | ||
THE ALBANY BUILDING LIMITED | ||
Defendant |
____________________
Associated Verbatim Reporters
Dunscar Suite, Paragon Business Park, Chorley New Road, Horwich Bolton BL6 6HG
Telephone: 01204 693645 - Fax 01204 693669
Counsel for the Defendant: MR. A. SINGER
____________________
Crown Copyright ©
"McLean hereby give notice pursuant to clause 39 of the contract of its intention to refer the following dispute to adjudication; namely, (1) whether the withholding notice purportedly served by the respondent party and dated 19th June 2004 is valid and of no effect; (2) whether the deduction of liquidated and ascertained damages by Albany from McLean's certificate for payment number 20 is thereby invalid; (3) repayment of the sum of £664,893 due to McLean under certificate number 20."
It will be recalled that certificate number 20 was one of the matters which was dealt with in the second adjudication and Mr Hayes ordered payment of that sum of £664,000 and that is part of the 1.33 million pounds. There was then a claim for interest.
"By way of a further argument in the alternative, Albany suggests at paragraph 39 of the response that the claimant, McLean, is estopped from denying the validity and/or effectiveness of the notices intended as notices of non-completion. The basis upon which it is contended that estoppel arises is not particularised or evidenced. McLean says that no case has been made out that suggests either estoppel or waiver on the part of McLean. I would concur with McLean in that regard. If there are any grounds that gave rise to such an estoppel or waiver, Albany has not provided details to make out its case."
"Perhaps unsurprisingly, the issues, which at face value appear to be raised by this dispute, have resulted in not inextended argument about whether, on a proper construction of the contract or by reason of an estoppel by convention, the completion date for any given section is the Friday of the contract week stated in appendix to the conditions or the Sunday. In the event, I have concluded that in order to answer the principal question raised by this dispute – namely, whether the notices intended as notice of non-completion are valid notices complying with clause 24.1 – it is not necessary to decide which of those days the completion date is. The reason I have reached that conclusion is this. If (as Albany contends) the completion date is the Friday of the applicable contract week rather than Sunday, McLean's case is that they had until midnight of the Friday to complete the construction of any given section. Subject to that argument advanced by Albany about the meaning of the word "issue", which I will consider later, there is no suggestion that notices were raised after midnight of the applicable Friday."
Therefore, the adjudicator had, in fact, dealt with the matter which had been raised in the rejoinder; and his decision, it seems to me, cannot be criticised in that respect and certainly not on the grounds that he ignored a significant point raised by the defendant. He simply said it was not necessary to decide it for the reason he gave. That seems to me to be the end of the matter.
MR. SINGER: Yes, it has, my Lord. Mr Woolley, who appears today in the absence of Mr Darling, has calculated a total sum, including interest, of £2,192,168.58.
THE JUDGE: Yes. Are you content with that sum? Is it correctly calculated?
MR. SINGER: Yes.
THE JUDGE: Thank you, Mr Singer.
MR. SINGER: We have checked the calculations outside because Mr Woolley was kind enough to check them with me and they do appear correct.
MR. WOOLLEY: If they are not (inaudible).
THE JUDGE: Good. So there will be judgment for the claimant in the sum of £2,192,168.58 and that is including interest to date, I take it?
MR. SINGER: Yes.
THE JUDGE: Yes. Thank you.