British
and Irish Legal Information Institute
Freely Available British and Irish Public Legal Information
[
Home]
[
Databases]
[
World Law]
[
Multidatabase Search]
[
Help]
[
Feedback]
England and Wales High Court (Technology and Construction Court) Decisions
You are here:
BAILII >>
Databases >>
England and Wales High Court (Technology and Construction Court) Decisions >>
L Brown & Sons Ltd v Crosby Homes (North West) Ltd [2005] EWHC 3503 (TCC) (05 December 2005)
URL: http://www.bailii.org/ew/cases/EWHC/TCC/2005/3503.html
Cite as:
[2005] EWHC 3503 (TCC)
[
New search]
[
Printable RTF version]
[
Help]
|
|
Neutral Citation Number: [2005] EWHC 3503
(TCC) |
|
|
Case No: HT 05
313 |
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH
DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
|
|
St Dunstan's House 133-137 Fetter
Lane London EC4A 1HD |
|
|
Monday, 5 December 2005 |
B e f o r e :
THE HONOURABLE MR JUSTICE
RAMSEY
____________________
|
L BROWN & SONS
LIMITED
|
Claimant
|
|
- and -
|
|
|
CROSBY HOMES (NORTH WEST)
LIMITED
|
Defendant
|
Tape Transcript of Smith Bernal Wordwave Limited
183 Clarence
Street Kingston-Upon-Thames Surrey KT1 1QT
Tel No: 020 8974
7300 Fax No: 020 8974 7301
Email Address: tape@wordwave.co.uk
____________________
MR HARGREAVES (Instructed by Messrs Walker Morris) appeared on behalf of the Claimant
MR NISSEN (Instructed by Messrs Eversheds) appeared on behalf of the Defendant
____________________
HTML VERSION OF JUDGMENT
____________________
Crown Copyright ©
Monday, 5 December 2005
MR JUSTICE RAMSEY:
- . These proceedings concern an adjudicator's
decision in respect of claims arising from the construction of 114 residential
apartments at the Green Quarter development at Redbank, Manchester. On 23 May
2003, L Brown & Sons Limited ("Brown"), entered into a construction
contract with Crosby Homes (North West) Limited ("Crosby") in the JCT 1988
standard form of building contract with contractor's design, incorporating
amendments ("the Contract").
- . By a referral notice dated 9 September 2005, Brown
sought payment of monies due under interim application 27 in respect of a
later side agreements in the sum of £228,000 alternatively £208,000, together
with reimbursement of wrongfully deducted liquidated damages in the sum of
£286,125.87.
- . On 14 September 2005 the Royal Institution of
Chartered Surveyors nominated Mr Alan W Wood as adjudicator and he accepted
appointment by a letter to the parties on the same date. The adjudicator made
his decision on 26 October 2005 in which he found that Crosby was not entitled
to deduct liquidated damages in the sum of £286,125.87 or at all; Brown was
entitled to payment of an agreed completion bonus of £208,000 pursuant to
interim application 27 and Brown was entitled to immediate payment of
£387,972.58 plus interest of £9,016.38 up to 26 October 2005 and continuing.
Challenges to the jurisdiction and the adjudication
- . During the course of the adjudication, Crosby
challenged the jurisdiction of the adjudicator. By letter dated 19 September
2005 and in the response, it took three points: (1) that there was no
jurisdiction under the "side agreements" as there was no agreement between the
parties; (2) that if there was an agreement it was not an agreement in
writing; and (3) if there was an agreement in writing, it was not a
construction contract. Brown responded to these matters on 27 September 2005
and the adjudicator held that he had jurisdiction.
- . On 3 October 2005, Crosby challenged the
jurisdiction of the arbitrator, writing in response to the submissions served
by Brown on 27 September 2005. Brown's case was that the adjudication was
brought under the contract, and that by clause 39A.1 the disputes arose
"under, out of or in connection with the contract". Crosby challenged this on
the basis that Article 5 which gave the right to adjudication, was limited to
disputes or differences which arose under the contract. It also contended that
the dispute could not in any event come within the words "arising out of or in
connection with the contract".
- . In the letter of 3 October, Crosby submitted that,
on analysis, the dispute could be summarised as follows. First of all, did
Crosby and Brown agree that liquidated damages would not be levied? Secondly,
did Crosby and Brown agree that a completion bonus would be payable? Crosby
submitted that whilst the Contract contains provisions in relation to
liquidated damages, it does not contain any provisions which relate to the
payment of completion bonuses, and Crosby contend that it is stretching the
meaning of the words too far to conclude that the dispute as a whole arises
"out of or in connection with the contract".
- . In response, the adjudicator held that he had
jurisdiction and on 3 October 2005, he stated:
"I have further considered the submissions of the Parties and
would state as follows:
i) I note clause 39A.1 was amended by the Parties to include
the words "out of or in connection with," I am of the view that these
express words cannot now be separated from Article
5.
ii) I am of the view that the Responding Party's
representative's summarised questions relating to the dispute are not
exactly correct. The redress sought by the Referring Party in the
[adjudication] relates to an entitlement to payment of £407,672.58 (or
other sum), ie the Responding Party's entitlement to withhold
[liquidated damages] and the Referring Party's entitlement to a
completion bonus on the terms alleged.
I am of the view that both of these matters (however
paraphrased) arise " … out of or in connection with this Contract…"
and I remain of the view that I have jurisdiction to act as Adjudicator in
these proceedings..."
These proceedings before the court
- . On 2 November 2005 Crosby commenced Part 8
proceedings. In the Particulars of Claim at paragraphs 15 to 20, Crosby
pleaded as follows:
"15. Brown's case was that the adjudicator's jurisdiction to
determine the dispute derived from clause 39A of the JCT contract….
17. Brown's contention with regard to clause 39A is wrong. The
provision which contained the agreement to adjudicate was Article 5 of the
JCT Contract. Clause 39A merely contained the conditions applicable to any
dispute which is referred to adjudication pursuant to Article
5…
18. Accordingly, the parties only agreed to refer to
adjudication disputes or differences which arise under the JCT contract.
19. The dispute which Brown purported to refer to adjudication
did not arise under the JCT Contract. The claims for acceleration payments
and for release from liquidated damages derived from separate alleged oral
agreements, not the JCT Contract. Those agreements would not themselves be
susceptible to adjudication …
20. If, contrary to Crosby's primary case, the contract is to
be construed by reference to clause 39A, such that a dispute arising under
out of or in connection with the JCT Contract would fall within the scope
of a permissible adjudication, then Crosby also maintains that the dispute
referred was not one which fell within that ambit either. The claims
derived from separate alleged oral agreements reached after the parties
signed the JCT Contract and do not give rise to disputes arising out of or
in connection with the JCT Contract."
It therefore sought declarations that the adjudicator lacked
jurisdiction, and the decision of 26 October 2005 was of no legal force or
effect.
- . On 9 November 2005, Brown commenced Part 7
proceedings by which it sought to enforce the decision. At paragraph 30 of its
Particulars of Claim, it set out its case as follows:
"Browns case is that article 5 and clause 39A of the Contract
(as amended) must be read together and that the amendment to clause 39A of
the Conditions must also apply to Article 5."
It further stated at paragraph 37 that:
"It is patently obvious that the dispute referred must have
and did arise under out of or in connection with the Contract: the
variation to the Contract was an agreement as to how to deal with delays
to the Contract, did not relate to any other contract, waived LADs that
would otherwise have been levied under the Contract and related to the
project that was the subject matter of the
contract."
Continuing at paragraph 39:
"In other words even if the words "out of or in connection
with the Contract" do not apply, the Dispute arose under the Contract in
any event. The variations relied upon, oral or otherwise are variations to
specific parts of the Contract and must therefore have arisen under the
Contract."
The approach in these proceedings
- . During the course of argument, I raised the
issue of the basis on which I was determining the question which arose as to
the side agreements. In order to see whether the disputes under the side
agreements arise either out of or in connection with the contract, if the
wording in clause 39A.1 applied, or under the contract, if the wording in
Article 5 applied, I would have to consider these agreements. Whilst Mr
Alexander Nissen, who appeared for Crosby, submitted that I might need further
evidence to decide that question, he did not contend that I was not entitled
to base my decision on the findings of the adjudicator.
- . Mr Simon Hargreaves, who appeared for Browns,
submitted that in any event, it was not open to Crosby to contend otherwise.
He referred me to correspondence exchanged between the parties leading up to
this hearing (file 1, pages 250-254) as showing that the parties had agreed to
proceed on the basis of the evidence in those files.
- . I am satisfied that the parties have approached
this matter on that basis and I therefore proceed to consider the
jurisdictional matters raised in these proceedings on that basis. Although Mr
Hargreaves produced some additional documents during the course of the hearing
to which Mr Nissen objected, I have not needed to have regard to those
documents in order to make my decision.
The jurisdictional challenges
- . There are essentially two main issues. The first
is this: under the contract, does the adjudicator only have jurisdiction in
respect of disputes or differences "under the contract", or does his
jurisdiction extend to disputes or differences "under, out of or in connection
with the contract"? Secondly, do the disputes referred to the adjudicator
arise "under" and/or "out of or in connection with" the contract?
Jurisdiction under the contract
- . Under the unamended standard form of building
contract used in this case, Article 5 of the Articles of Agreement provides as
follows:
"If any dispute or difference arises under this Contract
either Party may refer it to adjudication in accordance with clause 39A."
Clause 39A.1 of the conditions in turn, as unamended,
provides:
"Clause 39A applies where pursuant to Article 5 either Party
refers any dispute or difference arising under this Contract to
adjudication."
The use of the word "under" in these provisions, mirrors section
108(1) of the Housing Grants Construction and Regeneration Act 1996, and
paragraph 1(1) of the Scheme for Construction Contracts.
- . In this case there are amendments to the
Articles and conditions and in respect of clause 39A.1, the amendments
provided as follows:
"Insert after the word "under" the words "out of or in
connection with"."
In other words, clause 39A.1 of the condition now
reads:
"Clause 39A applies where pursuant to Article 5 either Party
refers any dispute or difference arising under out of or in connection
with this Contract to adjudication."
However, there was no amendment to Article 5. If there had been
the same amendment to Article 5, it is evident that there could be no
dispute that this would have permitted adjudication of disputes or
differences arising both "under" and "out of or in connection with" the
contract.
- . Mr Nissen submits that the amendments to clause
39A.1 alone do not achieve that purpose. He submits that Article 5 is the
provision that gives a party the right to adjudicate, and that clause 39A.1
deals with the details of the adjudication thereafter. He points to the fact
that Article 5 is expressly mentioned in clause 39A.1 as being the source of
the right and is clearly seen as having that role, even when clause 39A was
amended. He relies on clause 39A.4.1 which commences, both in the original and
in the amended version, with the words "when pursuant to Article 5 a party
requires a dispute or difference to be referred to adjudication".
- . In essence, he says, that if the right is
limited to disputes under the contract, the fact that the procedure may apply
to a wider group of disputes does not thereby give that right. If the gateway
in Article 5 is narrow, it does not, he says, matter that the procedural
gateway in clause 39A is wider, because there is no right to refer the wider
disputes to adjudication.
- . Mr Hargreaves contends that Crosby's approach is
too narrow. Article 5 and clause 39A have to be read together. He submits that
this court should apply principles of construction, including those enunciated
by Lord Hoffmann in ICS v West Bromwich [1998] 1 WLR 896
where he said:
"(4) The meaning which a document (or any other utterance)
would convey to a reasonable man is not the same thing as the meaning of
its words. The meaning of words is a matter of dictionaries and grammars;
the meaning of the document is what the parties using those words against
the relevant background would reasonably have been understood to mean. The
background may not merely enable the reasonable man to choose between the
possible meanings of words which are ambiguous but even (as occasionally
happens in ordinary life) to conclude that the parties must, for whatever
reason, have used the wrong words or syntax …
(5) The "rule" that words should be given their "natural and
ordinary meaning" reflects the common sense proposition that we do not
easily accept that people have made linguistic mistakes, particularly in
formal documents. On the other hand, if one would nevertheless conclude
from the background that something must have gone wrong with the language,
the law does not require judges to attribute to the parties an intention
which they plainly could not have had."
This second part was based on the well-known passage in the
speech of Lord Diplock in Antaios Compania Naviera SA v Salen Rederierna
AB [1985] AC 191, 201, where he said:
"I take this opportunity of re-stating that if detailed
semantic and syntactical analysis of words in a commercial contract is
going to lead to a conclusion that flouts business commonsense, it must be
made to yield to business commonsense."
- . In the context of the amendments, Mr Hargreaves
relies on what Lord Bingham said in Homburg v Agrosin [2004] 1 AC 715 at
737:
"… it is common sense that greater weight should attach to
terms which the particular contracting parties have chosen to include in
the contract than to pre-printed terms probably devised to cover very many
situations to which the particular contracting parties have never
addressed their minds."
In essence, Mr Hargreaves submits that it is apparent that the
intention was to broaden the scope of the adjudication provisions and that I
should construe the provisions of Article 5 and clause 39A.1 so as to give
effect to that intention. He also relies on other provisions of the contract
in relation to construction and discrepancies.
- . He relies first on clause 1.2 which provides as
follows:
"The Articles of Agreement, the Conditions and the Appendices
are to be read as a whole and the effect or operation of any article or
clause in the Conditions or item in or entry in the Appendices must
therefore unless otherwise specifically stated be read subject to any
relevant qualification or modification in any other article or any of the
clauses in the Conditions or item in or entry in the Appendices."
He also refers to clause 2.4.4 which was added by the amendments
and which provides as follows:
"Where there is any discrepancy or conflict between or within
the Contract Documents the Amendments will prevail over all other Contract
Documents and the Articles of Agreement, the Conditions, the Supplementary
Provisions and the Appendices will prevail over all Contract Documents
other than the Amendments."
- . He also refers to dictionary definitions of
"discrepancy". Mr Nissen's position is that there is no discrepancy between
Article 5 and clause 39A.1 as one deals with the right and the other is
procedural.
- . In my judgment, the amendment to clause 39A.1
was intended to broaden the scope of the reference to "adjudication". The
wording of clause 39A.1 as amended, provides that "clause 39A applies where,
pursuant to Article 5, either party refers any dispute or difference arising
under, out of or connection with this contract to adjudication". I consider
that clause 39A was amended on the basis that those words "pursuant to Article
5" meant that a dispute or difference under, out of or connection with the
contract, could be referred to adjudication under Article 5.
- . However, as Mr Nissen states, Article 5 was not
amended. That is not, in my judgment, decisive. The plain intention of the
parties was to broaden the scope of adjudication, and applying the relevant
principles of construction, I consider that the court can give effect to that
intention, on the basis that the principles were referred to in ICS v West
Bromwich. Otherwise, the words added by the amendment to clause 39A.1
would be given, in effect, no effect. Whereas, as Lord Bingham pointed out in
Homburg, such words should be given greater weight.
- . This is not, in my judgment, a case where there
is surplusage or redundancy of language and where the court might decide that
it can ignore the words added by clause 39A.1. The words added by the
amendment were intended to have effect and unless they are construed in the
way I have found they should be, they would, as Mr Nissen accepts, have no
purpose. I therefore find that reading Article 5 with clause 39A.1, the
intention of the parties was that disputes arising under, out of or in
connection with the contract should be referable to adjudication.
- . I do not consider that clause 1.2 of the
contract is of much assistance in this case. It could be said that clause
39A.1 had to be read subject to Article 5, or that Article 5 had to be read
subject to clause 39A.1, and that on its own does not take the matter much
further. This clause does though, generally assume that a contract should be
read as a whole and effect be given to each provision, which is the effect of
the way I have construed the contract.
- . Clause 2.4.4 is, in my judgment, more directly
applicable. On my reading, there is a discrepancy between clause 39A.1 and
what it says is the effect of Article 5, and what Article 5 actually provides.
I consider that clause 2.4.4 applies in a case such as this where there is a
discrepancy. It provides that the amendments will prevail over all other
contract documents. That, in effect, in my judgment, puts the amendments to
the top of the order of precedence. As a result, this provision on its own
(the provision of clause 2.4.4) would, in my judgment, be sufficient to make
the wording of clause 39A.1 prevail over the unamended wording of Article 5,
even if I had not come to that conclusion as a matter of pure construction.
- . In my judgment, therefore, an adjudicator
appointed under the contract has jurisdiction over disputes or differences
arising under, out of or in connection with the contract.
- . I now turn to consider whether in this case, and
on that basis, the adjudicator had jurisdiction over the particular disputes.
Those disputes arose not in relation to the terms of the original contract,
but to various side agreements made between the parties. The relevant side
agreements were as follows. The July agreement: this was made by the
acceptance by Brown by letter of 2 July 2004 of the terms of Crosby's letter
of 1 July. The adjudicator states that this agreement was not in dispute. He
refers to the terms of that agreement and states that it was not in dispute
that Brown did not achieve the dates set out in the July agreement, and the
agreement lapsed and was replaced by the October agreement (paragraphs 12 to
15 of his decision).
- . Secondly, the October agreement. This was
contained in Crosby's letter dated 7 October 2004, and was concluded and
became binding on the parties by Brown's conduct and implied acceptance of
Crosby's offer in that letter (paragraphs 16 to 22).
- . Thirdly, the second October agreement. The
contentions as to this were set out by the adjudicator in paragraph 24 of his
decision in these terms:
"The Second October Agreement … was alleged (by the Referring
Party) to have been made on 14 October 2004 in a private meeting between
Mr Murphy of the Referring Party and Mr Teage of the Responding Party. The
essence of the Second October Agreement was to vary the (first) October
Agreement such that the dates by which NHBC certification was required for
the Referring Party to qualify for the apartment bonus was changed from 15
October 2004 to 15 November 2004 and the waiver of LADs term/date was
similarly changed to the end of November 2004."
- . His findings were set out in paragraph 32 as
follows:
"I accepted on a balance of probabilities the Referring
Party's submissions that the first October Agreement was amended such that
the operative bonus dates for NHBC certification and the Responding
Party's ability to legally complete on apartments were amended to 15
November 2004 and the end of November 2004 respectively. I further decide
that the operative dates for those apartments on Levels 10 and 11 were
removed from the agreement and the time for certification essentially
became a matter of best endeavours."
- . He made further findings at paragraph 34. He
said:
"I preferred the Referring Party's evidence in this respect
and I decided that the Referring Party had met the terms of the agreement
to obtain NHBC certificates (on 104 No. apartments) by 15 November 2004
and that the Responding Party was able to legally complete on these
apartments by the end of November 2004 and the Referring Party was
entitled to receive bonus payments totalling £208,000 in respect of the
said 104 No. apartments."
And at paragraphs 39 and 41 he said:
"Second, to the extent that I did not have the power to decide
such discretionary matter then I decided that I preferred the Referring
Party's version of the agreement partially evidenced by the Responding
Party's letter dated 7 March 2005, such that there was a continuing
agreement to waive LADs and the Responding Party was bound by such
agreement.
…
41. I decided that these letters supported the Referring
Party's case that there was an on-going (post 14 October 2004) agreement
that the Respondent Party would waive LADs and I was of the view that such
agreement was linked to the Referring Party's completion of apartments by
the November 2004."
- . The question arises whether the disputes which
were decided by the adjudicator in relation to the side agreements were
disputes under, out of or in connection with the contract. Mr Nissen submits
that the disputes arise from the alleged side agreements and not from the JCT
contract and therefore are not disputes linked to the contract.
- . He submits that the disputes: (1) do not arise
out of or in connection with the contract, but relate to a claim made pursuant
to the side agreements and arise under a completely separately agreement; (2)
that the disputes cannot be disputes under the contract as they are disputes
about a totally discrete agreement. He relies on Shepherd Construction v
Mecright [2000] 1 BLR 489 at 493 to 494 and Fillite (Runcorn) v
Aqua-lift (1989) 45 BLR 27 at 41 and 44.
- . In addition, he says that the contention that
the side agreements constituted variations to the contract so as to give rise
to disputes under the contract, is not supportable. There is an absence of
reference to the terms of the contract and an agreement waiving liquidated
damages assumes that they are due under the contract and so does not vary the
contract.
- . Mr Hargreaves submits that the side agreements
varied the contract so that the disputes arise under, out of or connection
with the contract as varied. Further, even if the side agreements were
separate, he submits the disputes are nevertheless disputes arising out of or
in connection with the contract.
- . In relation to the words "arising out of", he
refers to Heyman v Darwin [1942] AC 356 at 360 where Viscount Simon
L-C, was dealing with a case where the particular clause provided for
"disputes arising in respect of this agreement or any of the provisions herein
contained or anything arising hereout to be referred to arbitration". He said:
"The answer to the question whether a dispute falls within an
arbitration clause in a contract must depend on (a) what is the
dispute and (b) what disputes the arbitration clause covers. To
take (b) first, the language of the arbitration clause in this
agreement is as broad as can well be imagined. It embraces any dispute
between the parties "in respect of" the agreement, or in respect of any
provision in the agreement, or in respect of anything arising out of it.
If the parties are at one on the point that they did enter into a binding
agreement in terms which are not in dispute, and the difference that has
arisen between them is as to their respective rights under the admitted
agreement in the events that have happened for example, whether the
agreement has been broken by either of them, or as to the damage resulting
from such breach, or whether the breach by one of them goes to the root of
the contract and entitles the other party to claim to be discharged from
further performance, or whether events supervening since the agreement was
made have brought the contract to an end so that neither party is required
to perform further - in all such cases it seems to me that the difference
is within such an arbitration clause as this."
- . Mr Hargreaves also refers to HE Daniel v
Carmel Exporters [1953] 2 QB 243 in which the relevant clause was "any
dispute arising out of the contract" and in the judgment it is stated:
"I propose, however, to decide this case on broader grounds,
which I can state shortly. The parties have agreed to submit all their
disputes to arbitration. The words "any dispute arising out of the
contract ..." cover every dispute except a dispute whether there was ever
a contract at all, because if there was no contract, there was no
arbitration clause.
He also refers to Government of Gibraltar v Kenney [1956]
2 QB at 410, in which Sellers J said this:
"In my view, this arbitration clause is very wide. It covers
"any dispute or difference" which arises or occurs between the parties "in
relation to any thing or matter arising out of or under this agreement."
The distinction between matters "arising out of" and "under" the agreement
is referred to in most of the speeches in Heyman v. Darwins Ltd in
the House of Lords and it is quite clear that "arising out of" is very
much wider than "under" the agreement. This clause very widely
incorporates a difference or dispute in relation to "any thing or matter
arising out of" as well as "under" the agreement, and, in my view,
everything which is claimed in this arbitration can be said to be a
dispute or difference in relation to any thing "arising out of" the
agreement."
- . In relation to the words "in connection with",
Mr Hargreaves refers to Ashville Investments v Elmer [1989] 1 QB 488 at
496A and page 503. At page 496A, May LJ said this:
"With these points made, unless precedent requires me to
decide otherwise, I have no doubt that disputes between the parties based
upon alleged mistake at the time this contract was entered into, and upon
an alleged misrepresentation or negligent mis-statement, are ones "arising
in connection" with that contract and thus within the scope of the
arbitration clause in this case."
At page 503, Balcombe LJ added his comments, and he said
this:
"Disputes as to the construction of the contract, or as to
matters arising under the contract, are covered by the opening words of
the clause. So disputes as to matters arising in connection with the
contract must be taken to refer to disputes other than about questions of
construction, or as to matters arising under the
contract."
- . If the side agreements were separate agreements,
Mr Hargreaves submits that they would still come within the adjudication
clause. He referred me to four cases. The first was Faghirzadeh v Rudolph
Wolff [1977] 1 Lloyds Rep 630. That was a case decided by Mocatta J and
the relevant clause in an agreement of 10 May 1973, provided that "any dispute
arising out of this contract" should be settled by the rules and regulations
of the London Metal Exchange. There were negotiations in respect of that
contract and at page 634, the judgment sets out the relevant passages from the
arbitrator's findings of fact.
"During the said negotiations in Tehran between 7 June 1973
and 13 June 1973, a verbal agreement was reached between Mr Shamoon as
agent of the Respondent of the one part, and the Claimant of the other
part. The agreement provided:-
(a) That the Claimant should permit the Respondent to sell
the said 7,200 metric tons of reinforcing bars to another purchaser on
terms corresponding to Special Clause
6.
(b) That the Respondent should be relieved of the obligation
to ship the said bars to the Claimant.
(c) That the Claimant should be relieved of the obligation
to amend the said defective letters of
credit.
(d) That, in accordance with the spirit of Special Clause 6,
the Respondent would keep the Claimant informed of market trends and
would only sell the said reinforcing bars with the Claimant's consent."
- . When he then came to consider whether the
agreement was within the terms of the contract dated 10 May 1973 or was an
entirely new contract, Mocatta J said this:
"It was pointed out by Mr Hunter that in order to understand
what the agreement was, which had been entered into as the arbitrators had
found during the negotiations in Tehran, one has to refer to the contract
of May 10. One has to refer to it in the first place to ascertain what
special cl.6 provided. Further in order to ascertain the overprice one
would again have to refer to the contract and one would similarly have to
make such reference in order to ascertain the technical description and
sizes of the reinforcing bars originally sold by the respondents…"
- . In giving judgment, Mocatta J said this:
"… the negotiations in Tehran … altered the contract of May 10
much more fundamentally than did the correspondence between the shipowners
and the India office in the last mentioned authority."
That was a reference to the case of Union & India v EB
Aaby's Rederi A/S.
"Nevertheless, as already indicated, the negotiations in
Tehran and the agreement there reached particularly the latter, are
unintelligible without referring back to the contract of May 10. In one
sense the agreement made in Tehran was a new agreement, but in another
sense it varied, though very radically, the contract of May 10. I see no
reason for concluding that the agreement made in Tehran jettisoned the
arbitration provisions contained in the contract of May 10."
- . Mr Hargreaves secondly referred me to the
decision of Mustill J in A&B v C&D [1982] 1 Lloyds Rep 166, a
case where the relevant clause provided for disputes to go to arbitration if
they arose in connection with this agreement. In that case, Mustill J said
this:
"Even if there were a third agreement, I consider that a claim
relating to a breach of it would, in the particular circumstances of this
case, be connected with both the previous agreements. The services related
to the investigation and repair of work done under the first agreement..."
- . Thirdly, Mr Hargreaves referred me to Davies
Middleton & Davies Ltd v Toyo Engineering Corporation [1997] 85 BLR
59, in which Phillips LJ (as he then was) in the Court of Appeal said in
respects of the judgment of Judge Thornton QC below:
"Thus, any dispute which is in connection with the contract is
referable to arbitration. This expression is wide enough to cover disputes
arising out of a second contract which is related to the contract
containing the arbitration clause as can be seen from the decision of
Mustill J in A and B v C and D…
It follows that a dispute arising out of a contract entered
into to provide a means of resolving disputes that had arisen under an
earlier contract are disputes which, in principle, arise in connection
with the earlier contract."
- . Finally, Mr Hargreaves referred me to El
Nasharty v J Sainsbury Plc [2004] 1 Lloyds Rep 309 where Mr Julian Flaux
QC (sitting as a Deputy High Court Judge) had to make a decision on an
arbitration clause where the provision was for disputes arsing "in relation to
this agreement" to be referred to arbitration. He said:
"However, although neither the Wolff nor the
Ashville Investments case are therefore binding because the clauses
were in different terms, I do find the reasoning of those courts as to the
width of expression such as "in relation to" and "in connection with" of
considerable assistance in construing the present clause. Clearly the use
of the phrase "in relation to" connotes a wider scope of arbitration
clause than one which is limited to disputes arising under a contract such
as whether there has been a breach of contract or not. "In relation to"
includes disputes which whilst not arising under the contract, are related
to or connected with it. In my judgment, a dispute concerning an alleged
variation to a contract is a dispute which is "in relation to" that
contract."
- . Mr Nissen points out what was stated in
Ashville v Elmer at page 495. May LJ said this at page 495A-E:
"Similarly, it is a principle of law that the scope of an
arbitrator's jurisdiction and powers in a given case depend fundamentally
upon the terms of the arbitration agreement, that is to say upon its
proper construction in all the circumstances. However, I do not think that
there is any principle of law to the effect that the meaning of certain
specific words in one arbitration clause in one contract is immutable and
that those same specific words in another arbitration clause in other
circumstances in another contract must be construed in the same way. This
is not to say that the earlier decision on a given form of words will not
be persuasive, to a degree dependent on the extent of the similarity
between the contracts and surrounding circumstances in the two cases. In
the interests of certainty and clarity a court may well think it right to
construe words in an arbitration agreement, or indeed in a particular type
of contract, in the same way as those same words have earlier been
construed in another case involving an arbitration clause by another
court. But in my opinion the subsequent court is not bound by the doctrine
of stare decisis to do so.
If I were wrong, then in any event it must be necessary to
compare the surrounding circumstances in each case to ensure that those in
the latter case did not require one to construe albeit the same words
differently when used in the different context.
However, before turning to the authorities upon which counsel
for Ashville particularly relied, there are in my opinion some further
important considerations to bear in mind. First, it is trite law that the
answer to the question whether a particular dispute falls within an
agreement to arbitrate depends primarily upon the proper construction of
that agreement."
- . Mr Nissen therefore submits that the language of
the various clauses in the cases cited by Mr Hargreaves, provide little
assistance as they are particularly sensitive to the words used and the
particular facts of those cases.
- . Whilst Mr Nissen is undoubtedly right and I must
approach this case on the basis of the particular words of the clause and the
facts of this case, the authorities are helpful in illustrating in a
persuasive way, the breadth of particular wording.
- . In this case it is evident that the phrase
"under" the contract is less broad than "arising out of or in connection with"
the contract, and this is clear from what Balcombe LJ said in Ashville v
Elmer. In the present case, the background to the side agreements was that
certain issues arose between the parties as to the performance of the
underlying contract. The side agreements therefore introduced a bonus system
and a system of relief of liquidated damages with a view to obtaining as early
completion as possible.
- . Unlike Shepherd Construction v Mecright,
this was not a case of a full and final settlement agreement. Whilst I accept
that the terms relied on did not in express language, refer to particular
clauses in the Contract as being varied, I consider that the introduction of a
bonus system and the waiver of liquidated damages did vary the Contract.
Whilst the parties did not expressly add a clause to the contract to provide
for bonus, the bonus payment evidently had the effect of adding a provision
which led to additional payment and changed or varied the payment required
under the Contract. In addition, the waiver of liquidated damages did not
expressly refer to the original obligation in clause 24.1 of the contract, nor
to the dates nor to the rates of liquidated damages in appendix 1. However,
the side agreements were changing or varying the entitlement under the
Contract.
- . In addition, I bear in mind that it is quite
common in the construction industry for parties to enter into side or
supplemental agreements which add to or vary the terms when matters arise
during the course of the contract. Those agreements frequently do not have
their own provisions for dispute resolution, including adjudication. If the
officious bystander had asked such parties what dispute resolution methods
applied, I consider that they would invariably assume that those in the
underlying contract would apply. The idea that different or no provisions
applied to such additional changed obligations would, in my judgment, be an
impossible situation and make adjudication unworkable for such projects.
- . In this case, I consider that the side
agreements fell into this category of agreement. It was necessary to have
regard to the underlying Contract, in particular to see what liquidated
damages had been waived. As a result, because, in my judgment, the side
agreements were variations to the contract, I consider that the disputes under
those side agreements would be properly categorised as disputes under the
contract.
- . The phrases "out of or in connection with" are
wider than "under" the contract. They cover matters which arise out of the
performance of the contract and in connection with that performance. The side
agreements and the disputes under them arose out of the performance of the
contract or in connection with them. Therefore, even, if contrary to my view,
the side agreements were separate obligations without sufficient connection to
amount to variations of the contract, then disputes under those side
agreements would, in my judgment, arise out of or in connection with the
contract.
- . I therefore find that the dispute under the side
agreements which gave rise to the sums determined in the decision of the
adjudicator, were disputes under the contract, but in any event, would have
been disputes arising out of or in connection with the contract.
- . For those reasons, I find that the
jurisdictional challenges in the Part 8 proceedings do not succeed. Subject to
any further submissions, Brown are therefore entitled to judgment in the sums
determined as due to them from Crosby in the adjudicator's decision of 26
October 2005.
BAILII: Copyright Policy |
Disclaimers |
Privacy Policy |
Feedback | Donate
to BAILII
URL:
http://www.bailii.org/ew/cases/EWHC/TCC/2005/3503.html