QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Clark Smith Partnership Limited |
Claimant |
|
- and - |
||
Leyton Football Club |
Defendant |
____________________
Graham Platford (instructed by Richard West Freeman Christofi) for the Defendant
Hearing dates: 24, 25, 26 October 2005
____________________
Crown Copyright ©
Mr. Recorder Colin Reese QC. Sitting as a Recorder in the TCC :
2.1 TAS is a director of the Claimant, he was the Club's initial contact within the Claimant and he became the director responsible for the project. TAS assigned Mr R Cooper ("RS") to the project. Until he left the Claimant in early 2002, RS was involved (in conjunction with TAS) in day to day liaison and correspondence with the Club. RS' rτle was then taken by Mr Chris Turtle ("CT").
2.2 CS is one of the directors of the Club and at all material times he was the Chairman of the Club. The other Club director who was involved over the first 12 months (approximately) of the project, was Mr Philip Foster ("PF").
2.3 TAS was the Claimant's only factual witness. I accept the written and oral evidence which he gave. In this judgment I have not found it necessary to deal with the details of each of the areas of additional work described in the lettered sub-paragraphs of paragraph 16 of the Amended Particulars of Claim. However, for the avoidance of doubt, I record that, in respect of each, I accept the evidence given by TAS concerning the request for such work to be undertaken and content of the work which the Claimant carried out. Where his evidence conflicted with the evidence given by CS, I consider TAS had the more accurate recollection and , as will be apparent from my findings, I prefer his evidence.
2.4 CS was the Club's principal factual witness. Whilst I accept much of his written and oral evidence, as will be apparent from my findings, in certain respects I do not think CS had a particularly accurate recollection of events which had occurred. To give an example surprisingly, in view of the contrary indications in the apparently clear contemporary record, at paragraphs 14 and 15 of this first witness statement (C/337) CS stated that TAS orally quoted a fixed fee of £32,000 plus VAT and that he handed over a down payment of £5,000 to TAS at their very first meeting at the Club's ground. The error was repeated/reinforced at paragraph 8 of this second witness statement (C/373c). When cross examined CS accepted that what he had said was in error. He said he had made an error on dates for which he apologised, adding "It's four years ago". Three other features of CS' evidence are worthy of comment at this point. First, I accept his evidence that although he had been actually engaged as a dwellinghouse developer for many years, in May 2001 he was not familiar with the detail of with the JCT Forms of Contract or the ACE Conditions of Agreement. Secondly, in my judgment, insofar as CS gave evidence that he considered the Claimant was engaged to be the Club's "contract manager" or "my project manager" or that "they were in charge of completing the job" and/or when he said (or implied by what be said) that the Claimant has agreed a fixed fee of £32,000 plus VAT irrespective of the method of procurement which was to be used, those were not views which a reasonable/experienced businessman could hold if he had read the contemporary correspondence. Thirdly, I simply do not accept CS' suggestion that the Claimant's payment applications No 3 dated 19th February 2002 (I/1099), No 4 dated 29th October 2002 (I/1101) and/or No 5 dated 5th March 2003 (I/1107) were not seen by him and/or that they were processed and paid in error by members of his staff. In my judgment, CS saw each and every one of the Claimant's applications for payment and none was paid unless and until he authorised it. As he himself said at paragraph 64 of his first witness statement, save when he was in hospital, " in reality, the Club tended to rely on me authorising payments". Unfortunately, CS had to spend some in hospital in the first half of 2004 but, so far as this case is concerned the relevant period is February 2002 to May 2003.
2.5 The Club's other factual witnesses were PF and Mr Steven Benton ("SB"), a self-employed bricklayer who had been employed by the Club on the redevelopment project in 2002/2003. So far as SB's evidence is concerned, I readily accept all that he said which directly concerned the works for which he was responsible (i.e. up to and including paragraph 16 of his witness statement C/357-360) was accurate. I am less convinced that his description of conversations with CS and/or with the Claimant's CT is sufficiently full or adequately contextualised to be taken at face value but, assuming that part of the evidence could be accepted, I do not consider it could assist the Club in any way. The limitations or constraints on the matters that the Club might advance in its defence as a result of the Order made on 5th April 2005 preclude any weight being given to this evidence in the present context (see further at paragraph 35 below). If, at some future date, the stay on the Counterclaim is lifted, it may be that some or all of this evidence would then become relevant.
2.6 RF's evidence concerning the discussions with the Claimant in 2001 added little to the matters which CS covered rather more fully. He had resigned well before a dispute concerning the Claimant's fees entitlement began to develop and, as he himself had said at paragraph 26 of his witness statement, "[CS] tended to be the person running things anyway ." (C/355). His detailed recollection when preparing his witness statement contained the same obvious errors concerning the first quotation and the initial payment as CS' first witness statement (C/351). As I have already said, the errors were obvious when the contemporary documents were examined and, when asked about this, RF readily admitted that his stated recollection was wrong.
Thank you for your time and courtesy at our meeting on site on Wednesday 16th May 2001 during which we discussed proposals for the above redevelopment.
As a result of these discussion we understand that you have full Planning Consent, a copy of which was provided to us for the demolition of the existing premises know as the Morris Minor Centre and the new build construction of a two storey development providing Restaurant, Banqueting Club and Bar facilities .
In consideration of the above you are now desirous of commencing the works, undertaking demolition of the existing buildings using your direct labour and procurement of the new building to a shell finish by traditional contractual means through a main contractor. To assist in realising the above you wish to appoint a professional consultancy to deliver various services, the least of which being design calculations and drawings for submission and approval by the Local authorities Building Control Department.
In connection with this we express our keen interest and list below matters for your consideration in delivering the project together with a range of services and associated fees.
I understand from our discussions yesterday that all internal fitting out works, finishes, internal walling and services will be undertaken by your good selves and with this in mind we offer the following:-
1. To obtain Building Regulation Approval
Take a brief, provide structural design calculations for foundations, ground floor, first floor, primary structural frame and roof, provision of below ground drainage design drawings and details, assisting with the discharge of planning conditions, arranging for trial pits, inspecting same and providing advice and assistance with soil sampling and analysis by others, obtaining information from statutory authorities in respect of gas, water, electricity and telephone, providing information on same, liaising with Local Authority as necessary, providing attendance at meetings as required, liaising with Planning Supervisor and Party Wall Surveyor as necessary, providing information as water, electricity and telephone, providing information on same, liaising with Local Authority as necessary, providing attendance at meetings as required, liaising with Planning Supervisor and Party Wall Surveyor as necessary, providing information as required to Acoustic Consultant, assisting with appointment of same and providing advice on the services of others required.
In addition we have allowed for developing the internal arrangement of accommodation in conjunction with your good selves.
Our fees for providing the above service will be £13,5000 exclusive of VAT but inclusive of all normal foreseeable expenses and disbursement.
2. Tender Action
In addition to the above we are willing to provide the following optional service in assisting you with the tendering process of structural steel work and the main contract. This service will include:-
To provide tender documentation in respect of structural steelwork, external cladding, the provision of specification for steelwork, cladding and general building works, providing form of contract, provision of tender analysis report and recommendations.
Our further fee for the provision of this service would be £6,000.00 exclusive of VAT but again inclusive of normal foreseeable expenses and disbursements.
3. Site Works
In addition to the above we can provide a construction phase service, administer the contract on your behalf and generally assist you during the construction process. For this aspect of the works we propose the following service:-
To provide intermittent site visits, provide attendance at and chair site meetings, provide minutes of same, liaise with client, contractor, local authority and checking consultant as necessary, provide stage reports and snagging lists at completion of structural steel work and completion of shell, provide monthly valuations and issue certificates as necessary, assist in obtaining, contractor warranties, and provide general advice as required.
For such a service we would expect our fees to be in the sum of approximately £12,5000.00 exclusive of VAT. It is however difficult to assess such costs since our workload will be determined by the performance of the contractor. Nevertheless we would offer the above price or alternatively could charge for this aspect of the works on a time expended basis should you so wish.
In addition to the above the services of others will be required which we list as follows:-
1. Party Wall Surveyor
The works involve demolition and construction within 3mtrs of the party wall and as such there is a statuary requirement for a Party Wall Award. To progress, it will be necessary for you to appoint a Party Wall Surveyor and we would suggest [Mr C Hookham] ..
2. Planning Supervisor
In accordance with the Construction Design and Management Regulations 1994 you are required to appoint a Planning Supervisor to manage safety issues. As with the Party Wall Surveyor this is a legal liability. Again we would suggest Mr C Hookham ..
In consideration of the above two services we have taken the liberty to speak directly to Mr Hookham on your behalf and he has offer the following:
1. Party Wall Surveyor
On the information that we have been able to provide Mr Hookham has estimated his fees to be approximately £1,500.00 exclusive of VAT. This figure will however require confirmation subject to a site visit.
In respect of Planning Supervisory Services Mr Hookham has advised the following:
a. For pre-tender Health & Safety plan and filing of F10 £1,000.00 exclusive of VAT. b. For construction stage Health & Safety file, checking of Designer and Contractor Competence and the full discharge of Planning Supervisory Services a further £1,500.00 again exclusive of VAT.
Whilst your Architect has produced planning drawings we understand that theses have not been based upon a comprehensive site survey. We would therefore strongly suggest that prior to the commencement of construction phase drawings a detailed site survey is undertaken and the information provided in digital format, ACAD compatible. For such a service may suggest [Laser Surveys] ..
In order to minimise the cost of the new below ground drainage installation it would, if possible, prove advantageous to use the existing sewer connection.
Whilst on site yesterday we noted a number of manholes to be present and would suggest that a drainage survey would be a worthwhile investment. Any reputable drain repair company can provide such a service.
We note that condition 5 of the Planning Approval requires that an Acoustic Study is prepared by a reputable firm of Acoustic Consultants. In respect of this may we suggest you contact and appoint the following [the Equus Partnership] ..
Should you wish to appoint us in accordance with the above we would suggest that our appointment is in accordance with the ACE Conditions of Contract agreement (A1). We trust that we have understood your requirements correctly and have responded accordingly. If, however, further clarification is required please do not hesitate to contact us by phone.
In the meantime thank you once again for the courtesy extended yesterday and we look forward to hearing from you further.
We refer to our meeting this morning in connection with the above redevelopment and write in confirmation that you wish to appoint us in accordance with the services itemised as 1 to 3 in our letter dated 18th May 2001.
In order to regularise the situation, we enclose a further copy of our letter dated 18th May 2001 which we have amended to show your name correctly, which we would be pleased if you could countersign and return to us as confirmation of our agreement.
We have this afternoon contacted Mr Hookham in respect of the Planning Supervisor and Party Wall Supervisor commission and have asked that he contact you direct. In addition, we have also made further contact with Paul Gray of The Equus Partnership who should similarly contact you directly.
We will contact Messrs Laser Surveys and instructed them on your behalf to undertake a full survey of the site and again we will suggest that they contact you directly to make appropriate arrangements ..
Whilst writing we also confirm and thank you for the cheque this morning in the sum of £5,000 paid to us on account in respect of the proposed works and enclose for your retention our invoice in respect of this.
Thank you for this commission and we look forward to working with you on this project.
Further to our previous meeting and the recent discussions with regards to finding an acceptable solution to progress with the project, we have listed below the various elements of the works to be considered.Piling
Ground Works
Drainage
Precast Ground Floor Slab
Structural Steelwork, Floor Slabs, Staircases and Fire Protection
Roof
External Cladding and Glazing
External Brick/Block Walls
We understand, with the exception of Items 5, 6 and 7, the above elements could be carried out individually by Subcontractors of your choice. With regards to items 5, 6 and 7, we will enquire with the original Tenderers as to their willingness to carry out these items only and obtain prices for such works.
Further to the above, you will require the services of the following:
1. A Site/Project Manager to supervise and co-ordinate the Subcontractors. The Project Manager will possibly be responsible for setting out otherwise.
2. Setting Out Contractor such as Laser Surveys. The Setting out will be required for each separate element of works.
3. Clark Smith Partnership to provide a service to aid the Subcontractors. The extent of this service will depend on the competence of the Subcontractors.
We look forward to meeting with you to discuss the above and suggest you obtain quotations for the elements of works you are able to provide in order to ensure this method of proceeding with the project is financially viable.
This letter was discussed at a meeting on 8th November 2001. The minutes, which RC prepared, included:
1.1 [TAS] discussed contents of letter with regards to a solution to progress with project. In particular the requirements for the services of a Project manager and Setting Our Contractor, should the project be broken down into "individual trades".
1.2 With the agreement of [the Club, the Claimant] will enquire with Clive Hartley to assess his willingness to carry out the role of Project manager and to ascertain the level of service to be provided together with anticipated fees.
1.3 The Club, understood the requirements for a Setting Out Contractor and request [the Claimant] discuss this item with Laser Surveys.
..
2.4 Structural Steelwork [The Claimant advises] the preferred solution is to package together the steelwork with the upper floor slabs and the external envelope. [The Claimant has] discussed with Faircloth Ltd (preferred tenderer) and [is] awaiting a fee proposal for these items.
[The Claimant expresses] concern with the increased risks associated with procuring these elements individually.
[The Claimant is] to obtain quotations for Steelwork Contractor to provide Steel frame only.
Those minutes were forwarded to the Club on 12th November 2001 (H/621 623).
11. A meeting was held on the 8th November 2001 between [the Club] and [The Claimant] and the package procurement further discussed. [The Club] confirmed that they would commission the ground works including the ground floor slab themselves. It was also confirmed that external brick and block walling would also be procured directly by [the Club].
.
The question of [the Claimant's] services was discussed between the parties; it was agreed that it was impossible for the [the Claimant] to provide fixed fees for services of an unknown scope and duration and that [the Claimant] would continue to provide services to [the Club] which would be charged a the company's usual hourly charging rates.
The pleaded confirmations concerning the ground works, the ground floor slab and the external wallings are evidenced by items 2.2, 2.3 and 2.5 of the minutes (H622 623). However, the minutes do not record the agreement which was pleaded in the final sentence of that paragraph.
12. By reason of the matters aforesaid and the [Club's] decision to break the works down into various packages, the contract between the Claimant and the [Club] was varied by express agreement. The Claimant was to continue to provide services to the [Club] for which it was to be paid at its usual hourly charging rates. In the alternative the contact between the parties was determined by the Claimant under Clause 5.2 [of the ACE conditions] or terminated by the Claimant's (sic) breach of contract or frustrated because the contract became impossible to perform as originally intended by reason of the [Club's] decision. The Claimant is entitled to be paid a reasonable sum for the work carried out under Clause 6.5 [of the ACE conditions] or by virtue of the term pleaded at paragraph 6 above or on a quantum merit for work carried out at the [Club's] request and for the [Club's] benefit.
[The term pleaded at paragraph 6 of the Amended Particulars for Claim (to which reference was made in the second of the three alternative ways in which the entitlement was claimed) was that any variation of the services required from the Claimant and/or any additional services would be paid for by the Club "on the basis of time based fees at a reasonable hourly rate." This was pleaded as an express or alternatively an implied term by virtue of Clause 6.4 and Appendix II of the ACE Conditions and/or an implied term arising from Section 15 of the supply of Goods and Services Act 1982.]
17.1 In my judgment, because there was no agreed fixed fee and no agreed rates on the basis of which "time based fees" could be calculated for such additional services as might be requested and provided, it must follow that the Claimant's legal entitlement was to claim a reasonable remuneration for such additional services as it did in fact provide at the Club's request. I do not accept the Claimant's submission that the change made to the method of procurement was so significant that it altered the entire scope of the work which the Claimant carried out thereafter. To my mind, manifestly that was not so. But, how should the reasonable remuneration for those additional services which were required and provided be calculated ? Very probably, the Claimant would put forward a claim on a conventional time-charging basis viz. hours properly and reasonably spent charged out at rates appropriate for the salary and overhead cost of the employees involved plus disbursements but, in the absence of agreement on the rates it was to be entitled to charge, there was no established right to claim on this basis. The Club would be able to challenge the reasonableness of the Claimant's proposed charges, suggesting, if it thought fit, alternative rates or even an alterative basis of charging for some or all of the additional works.
17.2 I wish to make it clear that I have not overlooked CS' evidence that he is not a person who is in the habit of writing blank cheques for people and/or that if there had been any suggestion that the amount to be paid to the Claimant was changing from the lump sum stated in the letter of 18th May 2001 he would have "wanted to know exactly what amounts were being talked about". I accept unreservedly CS' statement that he is not in the habit of writing blank cheques but that is not something which he agreed to do. I do not accept that he did insist upon knowing exactly what were the charges which the Claimant would be making for what was, at that time, an uncertain workscope. In my judgment, CS is an experienced and successful property developer, well used to negotiating accounts which are presented to him so as to ensure that value for money is obtained. In November 2001, I believe CS accepted what TAS said and that he was confident he would be able to resolve matters satisfactorily with TAS in due course; and, if the major counterclaim issues had not arisen, I think it very likely that would indeed have happened.
Further to our previous meeting with have received a revised quotation of £220,000.00 to carry out the following items of work
1. Structural Steelwork and metal decking to Floor Slabs.
2. Roof, Gutters and RWP's.
3. External Cladding and Glazing.
The outstanding items to be considered will be:
1. Piling
2. Ground Works
3. Drainage
4. Precast Ground Floor Slab
5. Staircases
6. Lift
7. Fire Protection to structure
8. Concrete to First Floor and Plantroom Slabs
As previously discussed, there will also be a requirement for the services of the following:
1. A Site/Project Manager to supervise and co-ordinate the Subcontractors. The Project Manager will possibly be responsible for setting out otherwise.
2. Setting Out Contractor such as laser Surveys. The Setting out will be required for each separate element of works.
3. Clark Smith Partnership to provide a service to aid the Subcontractors. The extent of this service will depend on the competence of the Subcontractors.
We look forward to meeting with you to discuss the above.
Assuming the attached is acceptable, we require instruction from [the Club] to arrange to meet with the [prospective tenderers] and yourselves to set up the required contracts and commence the works.
The Club's written response to that letter came from CS on 18th December 2001 (H/666) when he said:
Re: your letter sent on 13.12.01
I would like to confirm that the estimate sent is fine and if you could go ahead to arrange a meeting to discuss the next stage.
If you could also check out the things that we spoke about on the phone and I look forward to hearing from you.
3.0 The Contract
3.1 The contract will be "Standard form without quantities, plus contractor's designed portion."
Threecie will act as principle (sic) contractor during the ground works and hand-over principle (sic) contractor responsibilities to Faircloth on commencement of the above ground works.
.
3.4 Site Facilities : All facilities including toilets, temporary power and office will be provided by [the Club].
4.0 Site possession/start date
[The Club] will demolish existing structure and have site cleared for the commencement of works by Threecie on 21st January 2002.
..
6.0 Below Ground Works
In addition to above, Threecie to provide proposed programme of works.
..
8.0 Project Management
8.1 It was agreed that Project Management/Site Supervision for integration of packages would not be necessary.
9.0 Monies
9.1 It was agreed with all parties [the Claimant] will inspect works and issue valuation certificates fortnightly. Upon issue of these certificates [the Club] should pay contractors within 14 days.
As discussed yesterday, [the Club] are required to place an order direct with Tarmac Topfloor for the supply, deliver and installation of the precast concrete ground floor planks. In writing to them, please refer to the previous correspondence, copies of which are attached.
I am sure Tarmac Topfloor will require information from [ the Claimant]. Therefore, I suggest you advise them that we are managing the project on your behalf and they are to contact us direct.
I trust the above is in order. However, should you require further assistance with the above, please do not hesitate to contact us.
By 4th March 2002 no order had been placed (see Progress Report 4th March 2002 H/699). On 5th March 2002 TAS sent a fax to CS informing him that this presented a programming problem because of the long delivery period involved. The fax continued:
An option would be construct an insitu slab. I have spoken to Clive Hartley [of Threecie] about this and he has provided a budget price of £20k. This is £4000 more than the pre-cast but will keep the job going and on programme.
Clive will require an instruction ASAP if we require insitu. Please call me ASAP to discuss.
At paragraph 32 of this first Witness Statement (C/99) TAS stated that CS called him, said he wanted the insitu slab and asked that the Claimant design it. At paragraphs 33 to 35 of the Witness Statement , he described the work involved (C/99 100).
(i) instead of the works being carried out by one main contractor the works were carried out in various individual sub-contract packages or by the Club itself employing direct labour;
(ii) the Club did not appoint a project manager or site supervisor until about April 2003 despite the Claimant's advice that it should do so;
(iii) there were delays to the project due to the Club ordering materials and instructing consultants late; and
(iv) the Club required advice and assistance from the Claimant in respect of some aspects of the internal fit-out works and the building services installation which were not part of the original contract.
Particulars of these alleged additional services were given in lettered sub-paragraphs (a) to (w) inclusive. Given the extent of agreement which the expert witnesses were able to reach, I do not need to set these out in full and make individual findings in respect of each of them but, in case it were to become relevant in relation to any appeal, I have already recorded my acceptance of the factual evidence given by TAS in relation to each of the additional services. I will have to deal with "the acoustics issue" in more detail later but, at this point, it is sufficient to note the following. As well as mentioning the further work allegedly involved as a result of the change in the method of procurement (the sub-paragraphs (a), (b) and (w)) and in designing an insitu concrete floor slab (see sub-paragraph (e)), to which I have already referred, the Claimant identified a number of design changes which the Club was said to have made (see sub-paragraphs (e), (i), (j), (k) and (s) to (v) and see also paragraph 18 of the Amended Particulars of Claim) and a number of instructions to become involved with the building services and internal fit out works (see sub-paragraphs (f), (h), (m), (n) and (o) to (r)). The Claimant also alleged that additional work was required in relation to the obtaining of local authority grant monies (something of which it had had no knowledge in May 2001 - see sub-paragraph (b)), in relation to the existing flood light towers (see sub-paragraph (d)) and in dealing with acoustic issues as was required by the terms of the planning consent (see sub-paragraph (g) and also see paragraph 17 of the Amended Particulars of Claim).
Having received the letter from Waltham Forest Council Environmental Health yesterday we have now confirmed the roof, cladding and window specifications to both David Faircloth and Lightfoot Windows.
Accordingly therefore we have finally completed the specification and detailing of the external envelope. You should by now have received revised coloured elevational drawings which reflect our agreements of last week and these drawings have been copied to both Planning Officer and Building Control. Having reached this stage it is timely for us to submit a 4th Application for Payment and in compiling this I have had occasion to research our costs. Not unsurprisingly due to the additional work that we have undertaken in liaising with the Local Authority, Equus Partnership and Lightfoot Windows and in producing stair drawings, alternative layouts and coloured elevations we have significantly overspent our quoted fees. With your agreement I would propose to postpone discussions concerning additional fees until the project is more substantially complete. I have enclosed our Request for Payment for the agreed construction stage activities.
I trust this meets with your approval although should you wish to discuss this matter further please do not hesitate to contact me by telephone.
There was no written response to that letter. As had been the case in February 2002, the Club expressed no written dissent or surprise at its contents. The sum claimed was paid promptly and in full. The receipt was dated 14th November 2002 (I/1100).
I refer to your brief discussion with [CT] yesterday and our discussion this morning.
As you are aware we have undertaken considerably more work than was originally envisaged, not only in the design and drawing of additional on site works but in liaison, site visits and meetings. As such our fee expenditure has risen alarmingly and I will collate additional costs and services and will write to you again shortly with such details. I would then hope that we can meet to discuss our current situation of a sizeable overspend and agree a mutually acceptable remuneration.
In the meantime however, and in accordance with our discussions this morning, we enclose our Request for Payment for an "on account" sum which will help to redress the situation pending a full costing exercise.
Your prompt attention to the enclosed would be much appreciated.
So far as the discussions referred to in the letter were concerned, in his evidence CS stated that he recalled discussions with CT who had told him "there were too many hours on the job" but, he said, he was not clear whether CT had been referring to additional hours. CS accepted he had seen this letter and agreed that he had not written in response to dispute what had been said. In my judgment, the letter fairly reflected the discussions. What was discussed was the considerable amount of extra work which the Claimant was contending it had undertaken; CS had acknowledged the Claimant's concerns and agreed that a further payment application could be submitted in the sum of £12,500; and, CS had accepted that the Claimant would be collating its "additional costs" which would be submitted as the basis for a discussion at which, so it was hoped, a mutually acceptable remuneration would be agreed. Insofar as the case pleaded by the Claimant at paragraph 21 of the Amended Particulars of Claim (A/11) goes further than those findings, it has not been made out.
Whilst I can fully understand your frustrations concerning poorly executed remedial works to the cladding and your frustrations with the Cladding Contractor generally I cannot accept your allegation that we are not committed to this project. Equally I cannot accept, and am offended at your suggestion that we have not acted honourably.
It is a point of fact that there has been many difficulties with the project, not least of which with the cladding and window sub contracts. As your representative we have, at all times, acted diligently and have expended enormous amounts of time and effort on your behalf, way beyond that which we can reasonably ask for reimbursement. Our Mr Turtle has been working on this project since last February, and for considerable periods of time virtually full time on your project. Please be assured that any frustrations that you feel are equally felt here and that us without considering our sizable financial loss.
Throughout our involvement, we have constantly phoned and faxed the cladding and window sub contractors on your behalf, in an effort to achieve completion of their works to a satisfactory standard. Indeed when we last spoke you acknowledged the efforts that we were making on your behalf.
Notwithstanding the problems to date, the priority must still remain to complete the envelope of the building. This is not best served by removing the Contractors from site, although I can certainly understand your motives. .
Despite the fact that our commission with your goodselves is in respect of steelwork, cladding and windows we have undertaken considerably more than this on your behalf. Indeed with the internal works we have to date been instrumental in pushing this forward and liaising and negotiating with the other consultants on your behalf. Bearing in mind however that the other consultants now involved should be more than capable of delivering the fit out and your obvious dissatisfaction with us it may prove beneficial to all if we cease to be involved. Rest assured however, that we have not and will not shirk our current responsibilities and commitment to you to deliver a completed shell to your satisfaction.
After this exchange of correspondence the works continued and the sum which the Claimant had requested in the fifth application for payment was paid towards the end of May 2003. When paid, it was paid in full. The receipt was dated 28th May 2003 (I/1106).
We last wrote to your regarding fees on the 5th March 2003.
As outlined in this letter, and [as] has been explained many times during our discussions, we have expended considerable sums on your behalf due to the extent of additional works undertaken and liaison we have undertaken with various contractors and consultants. Now that we are virtually complete on the project, I have been able to take stock of our financial situation and write to report this to you.
Our job costing amounts to £101,000.00 which for the sake of simplicity I have assumed to be £100,000.00. As I have previously explained to you, we did incur significant additional costs during the change over period when Roy Cooper unexpectedly left us and the project was handed over the Chris Turtle. Obviously we will not expect you to bear these costs since these were generated purely in house. I have made a rough assessment of the likely magnitude of costs involved and conclude that this amounts to something in the region of £8,000.00. Bearing in mind, however, the likely inaccuracy in this and giving you the benefit of the doubt, I am willing to accept that our costs involved in this handing over period amount to £10,000.00. Effectively, therefore, I am accepting that our productive costs are £90,000.00. So far to date we have invoiced £55,186.21 which again I have rounded down to £55,000.00 for the sake of simplicity. We are therefore currently facing a short fall of £35,000.
We also accept that some of this overspend was due to circumstances beyond both our and your control being generally associated with poor performance by others for example the Cladding Contractor, but it is a point of fact that we expended enormous amounts of time and energy in resolving these problems on your behalf. You may recall, however, that during our discussions we advised that it would not be our intention to seek full recovery of the extra fees incurred in this fashion and we fully intend to honour this commitment.
On the basis of the foregoing therefore, we propose to base our fees on the total amount of productive costs less our profit i.e. 80% of £90,000.00 which equates to a total fee due of £72,000.00. On the basis that we consider this is more than fair and reasonable, we enclose our Request for Payment in the sum of £17,000.00 plus VAT being the final amount due.
We trust you agree that we are being extremely fair over this matter , however, should you wish to discuss this issue in further detail, please do not hesitate to contract me by telephone.
I write to acknowledge receipt of your letter dated 4th August 2003 regarding your calculation of fees.
I would confirm it is my intention that you receive all legitimate fees due. However, in light of the protracted period experienced in reaching this point and the apparent complicated contractual procedures, in the first instance it is proposed that that a full analysis of this project be undertaken.
In my judgment, the text of this letter is significant. CS did not contend that it had mistakenly made an overpayment in relation to a £32,000 net fixed price contract. The references to the Claimant receiving "all legitimate fees due" and to the need for a "full analysis" of the project are consistent with the Club accepting that the Claimant had undertaken more work than the originally agreed price had covered and with the need to establish what would be a fair and proper amount for the Club to pay for that work.
1. The [Club] do have permission to withdraw paragraphs 20 to 24 of the Amended Defence on the basis that it undertakes not to pursue those matters at a later stage.
2. The [Club] be granted relief from the sanction of the Order of 4 March 2005 as varied by the Order of 18 March 2005 on the condition that:
a. paragraphs 20 to 24 of the Amended Defence and Counterclaim are withdrawn as set out in paragraph 1 above. ..
c. the Counterclaim be stayed in the form it is in and it is to be pursued only with the leave of this Court and if properly perfected and re-pleaded.
3. The Amended Defence and Counterclaim did stand struck out for failure to comply with the Order of 4 March 2005 as varied by the Order of 18 March 2005 until the relief set out in paragraph 2 above was granted.
There was no appeal against that Order and it must follow that the matters which the Club may advance in its defence to the Claimant's claims are now strictly limited or constrained by the terms of paragraphs 1 and 2c of that Order. At paragraph 20 of the Amended Defence (A/25) the Club had pleaded that the Claimant owed contractual/ tortious duties to exercise reasonable skill and care; at paragraph 21 (A/24-26) the Club had pleaded that the Claimant ought to have done certain things; at paragraph 22 (A/26-29) various alleged breaches of duty were identified; and then at paragraphs 23 and 24 (A/29) it was said "In consequence of those breaches of duty, the Claimant carried out more work and incurred more expenditure than would have been reasonably necessary but for those breaches" and "furthermore, the [Club] is entitled to set off against the claim such sums as may be found due to it under the Counterclaim hereafter set out."
The reasonable fees for the project would be:
1. The fee originally agreed for the works as proposed.
2. Additional works as a result of the variation in the form of tender & contract and as set out in paragraph 16 [of the Amended Particulars of Claim]
Item 1 is priced at £32,000.
Item 2 could be assessed in two ways. Either by the analysis of time records and apportionment into normal and additional services which has been carried out by [Mr Carter] in his report, or, by assessment of each item which might be needed to undertake the additional services. This second alternative has not been carried out by either expert.
Mr Carter and Mr Kendall did not discuss two matters which Mr Carter had considered in his report because they did not fall within the ambit of Mr Kendall's instructions. These matters were whether the time expended by the Claimant on the redevelopment project was reasonable and what would be a reasonable fee for the whole of the Claimant's work on the redevelopment project if the claim was to be assessed on a pure time basis. Mr Carter and Mr Kendall noted that what might conveniently be called "notification issues" viz. to what extent did the Claimant notify the Club that it was undertaking work outside the terms agreed in May/June 2001 and what effect should any shortcomings on the Claimant's part in this regard have on its claim for additional fees, were matters falling outside their expertise.
16(c): The change from suspended concrete planks to an in-situ reinforced slab
(16(f): The internal stairs was the work carried out by the Claimant after November 2001 additional work ?
16(n): The appointment of the Building Services Consultant (or M&E Contractor)
16(u): The link with the existing Clubhouse
16(g) and 17: The acoustic issue - did the Claimant fail to instruct Equus to provide acoustic advice as required, with the result that additional works were required ? If so, can the Club rely on this failure in the light of the Order dated 7th April 2005 ?
"All of the above quotations relate to work that has been instructed and as you know, [the Club] has already paid the invoices listed."
It was suggested to TAS that RC had meant what he had written and that the letter had (incorrectly) conveyed to the Club the fact that Equus had been instructed. TAS disagreed, and so do I. Equus had sent its quotation to the Club on 18th September 2001 (H/607-610) but no instruction was given by the Club to Equus at that time. By February 2002, CS may have been aware that Equus had come to site at the Claimant's request in October 2001 and undertaken an environmental noise survey (see H/1087b-1087c for Equus later account to Alan Bright Associates) but, he was also aware that notwithstanding the Claimant's advice (summarised by TAS in his evidence), the Club had deliberately not yet instructed Equus. Matters came to a head in August 2002. At that time, CS and TAS exchanged angry words when CS (wrongly) suggested that it was the Claimant who was at fault before, as a matter of fact he ensured the necessary instruction was (belatedly) given to Equus.
45.1 In his report, Mr Kendall stated that he had been instructed to give his opinion "as to the extent to which the services which [the Claimant] provided lay inside or outside the terms of the contract [it] had agreed with [the Club], and the reasonable price for any work which [the Claimant] undertook which lay outside the terms of the contract". In his oral evidence he said that the Claimant's records had not allowed him to determine the time spent on additional services and, accordingly, he had not been able to calculate what would be an appropriate level of remuneration for them. So far as the Claimant's time records were concerned, Mr Kendall confirmed that he did not suggest that the personnel involved has not worked the hours shown for the project.
45.2 In his report, Mr Kendall emphasised the particular requirements of the ACE Conditions A1 concerning the notification and recording of additional works and/or of disruption to the Engineer's works. He drew attention to the "importance" of the Engineer's monitoring progress on a project so that, if the client was to request a variation, the Engineer could promptly comply with his contractual obligation to notify the client that additional fees were likely to become due. He also drew attention to the "necessity" for the Engineer to keep records of time spent on work made necessary by variations or disruptions, and to keep those records separate from the records of work done in order to perform previously agreed obligations. He was critical of the parties' failure to agree rates for time based fees at the outset; critical of the Claimant's adoption of hourly rates rounded to the nearest £5 (albeit he agreed with Mr Carter that the rates charged were reasonable in accordance with industry standards at the time) and critical of the Claimant's job cost records. The main conclusions which he reached can be seen from paragraphs 34 and 37 of his report (D/390 and 396). They were:
34. In my opinion, LFC [the Club] was entitled to expect the CSP [the Claimant] would undertake all the duties offered in their letter of 18/5/2001 for the fixed price fees quoted, and LFC was entitled to believe they were free to exercise their commercial preferences, for example in changing from the intention of using a main contractor to acting as the main contractor themselves and in procuring the building shell using several sub-contractors, without being concerned that this involved CSP in additional work as they believed the fixed-price fees quoted would cover CSP's entire service. In my opinion, CSP encouraged LFC in this belief by (i) quoting fixed-price fees initially for what appeared to be the entire service, and (ii) by failing to advise LFC when LFC's actions would make them liable for time-charge fees under Conditions A1. In my opinion, CSP did not appear to have wished to 'rock the boat' by putting forward a claim for time-charge fees each time they were entitled to do so. In my opinion, CSP appear to have taken comfort from their believe that under the Conditions A1 they would be entitled to reimbursement for any additional work they undertook for LFC. Undoubtedly LFC did require CSP to undertake extra work because of variations or disruption, but I have seen no documentary evidence that CSP at any time advised LFC that additional fees would become due as a result, as required by the ACE Conditions, nor that CSP at any time estimated the amount of such fees.
..
37. The majority of the additional fees claimed by CSP relate to items which were variations to the work for which they originally proposed fees. The ACE Conditions make provision for such work to be reimbursed, probably at hourly time-charge rates, but the ACE Conditions also require the consultant to advise the client when such charges are to be incurred. In my experience, almost every client then requires an estimate of the size of the additional cost. From my examination of the project documentation I can find no evidence that CSP informed LFC when additional fees were to be incurred, nor did they provide an estimate of cost. Furthermore, CSP do not appear to have kept records identifying which costs were attributable to which items and it would seem to be impossible to separate the costs incurred in performing previously agreed obligations from the costs incurred in undertaking variations and copying with disruption.
Interest
.. entitled to interest upon the sum claimed pursuant to the Late Payment of Commercial Debts (Interest) Act 1998 at the rate of 12.5% per annum on the sum of £19,975 from 19 August 2003 to 5 December 2003, and on the sum of £43,288.75 from 6 December 2003 to date, alternatively pursuant to section 35A of the Supreme Court Act 1981 on such sum and such period and at such rate as the Court sees fit.
52.1 In my Judgment, this is not a case where it would be appropriate to contemplate ordering interest under the 1998 Act. Had the Claimant maintained and sued upon the offer which was made in August 2003 to limit its fees claim to the sum then requested, then arguably, the position might have been different. However, it did not do so, and instead it brought an action in which it claimed to be entitled to recover an amount calculated by reference to its charge out rates for all of the hours booked to the project (less only the allowance, which it thought appropriate, to cover the handover from RC to CT). That claim succeeded in part and, in my judgement, interest should awarded under the 1981 Act. Over what period ? At what rate(s) ? In my view, the Club was entitled to a reasonable time to consider the fees claim made in August 2003 and then the further fees claim made in November 2003. A reasonable time had elapsed by 12th January 2004 and simple interest should be allowed from that date up to the date of judgment. The appropriate commercial rate to allow over that period is 6½% per annum on the net sum of £24,231,79. It would not be appropriate to award any interest on the VAT. The parties have agreed the amount of the interest awarded, in the sum of £2,986.15.
52.2 The Claimant made a CPR, Part 36 offer in June 2005. At the trial the Club was held liable for more than that offer and, accordingly the provisions of CPR, Part 36 Rule 21 have been brought into play. By virtue of Rule 36.21(4) the Court is required to make an enhanced interest order under Rule 36.21(2) for some or all of the period starting 21 days after the offer was made, "unless it considers it unjust to do so". In the circumstances of this case, I do not consider it could possibly be said to be unjust to made such an order. As to the rate of interest which should apply over that period, in my judgment, the justice of the case is met if the rate awarded on the net sum is increased from 6½% to 8% per annum (viz the Judgment Rate). On that basis, the parties have agreed the amount of the enhanced interest in the sum of £147.38.
Costs
53.2 In the context of costs, the Claimant's CPR, Part 36 Offer made in June 2005 (to which I have already referred in paragraph 52.2 above) which has brought Part 36 Rule 21 into play, is equally significant. In the circumstances of this case, I do not consider it could possibly be said to be unjust to order the Club to pay the Claimant indemnity costs for the whole of the period starting 21 days after that offer was made. Accordingly, pursuant to Rule 36.21(3)(a) and Rule 36.21(4) that Order is made.
53.3 Turning to Rule 36.21(3)(b) which empowers the Court to order interest on those costs at a rate not exceeding 10% above base rate, in my view it would be unjust to order the payment of any enhanced interest on costs prior to the date(s) of actual payment. I was informed that all the Claimant's costs were being met by its Insurers. No details of payment made for work carried out over the last few months was provided and, in the absence of such information, in the circumstances of this case, I declined to make any Order pursuant to Rule 36.21(3)(b) and Rule 36.21(4).
53.4 No costs information was put forward when the case was listed for judgment. No application was made for any interim costs payment. Detailed assessment of the Claimant's costs is required.
Permission to Appeal
COLIN REESE QC
14th December 2005