QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
EQ PROJECTS LTD | Claimant | |
- and - | ||
JAVID ALAVI | ||
(T/A MERC LONDON) | Defendant |
____________________
MR. PAUL LETMAN (instructed by Saunders, Solicitors) appeared on behalf of the Defendant.
___________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
Crown Copyright ©
JUDGE PETER COULSON QC:
A: INTRODUCTION
(a) Section B below, which sets out an outline of the facts (paras.4-23);
(b) Section C below, which makes some general observations as to the evidence (paras.24-34);
(c) Section D below, which deals with the original Contract and provides answers to issues 1, 2, 3 and 11 (paras.35-76);
(d) Section E below, which deals with the Supplemental Agreement and the claim for quantum meruit and provides answers to issues 4, 5, 6, 7, 8 and 9 (paras.77-137 below);
(e) Section F below, which deals with the defects and provides answers to issues 12, 13, 14 and 15 (paras.138-167);
(f) Section G below, which deals with the alleged compromise of April 2004 and provides an answer to issue 10 below (paras.168-171);
(g) Section H below, which sets out my conclusions (paras.172-179).
B: AN OUTLINE OF THE FACTS
"We think you for appointing EQ Projects Limited as your main contractor for this shopfitting project for the agreed sum of £236,119.
Please find here our payment terms as agreed by both parties:
- 25 per cent with order – £59,029.75 plus VAT due 4th August 2003
- 25 per cent when start on site – £59,029.75 plus VAT due 15th September 2003
- 25 per cent on completion of work – £59,029.75 plus VAT due 27th October 2003
- 25 per cent 30 days after completion, less 10 per cent retention – £35,417.85 plus VAT due 1st December 2003
- 10 per cent retention (£23,611.90 plus VAT) to be held for 90 days
We trust these terms are acceptable and look forward to receiving your order confirmation."
C: GENERAL OBSERVATIONS ON THE EVIDENCE
C1 – The Absence of Documents
C2 – The Oral Evidence
C3 – Unsatisfactory Features of the Evidence
D: THE ORIGINAL CONTRACT
D1 – The Essentials of the Contract
D2 – Did the Contract Workscope Include the Air Extraction System (Issue 1)?
D3 – What was the Preprint in the Pre-Contract Negotiations (Issue 2)?
D4 – Who was Paul Storey Representing (Issue 3)?
D5 – Misrepresentation/Breach of Contract (Issue 11)
(a) The Defendant's Case
(b) The Documents
(c) The Meeting on 17th July
"Q The £200,000/£36,000 split was not discussed?
A. It was brought up in conversation. We did not necessarily sit down to discuss it. It was brought up by way of a reply. The Defendant asked if any further sums were due to Preprint. We said, no, it was all in the figures. It was mentioned.
Q That was just the overall price?
A. It was not specifically said: £200,000 and £36,000.
Q It was not said?
A. Not in those terms, no."
This seems to me to be a clear statement that the true split was not explained or revealed to the Defendant at the meeting, even indirectly.
(d) Findings of Fact
(e) Conclusions
D6 – Sums due under the Original Contract
E: THE SUPPLEMENTAL AGREEMENT/QUANTUM MERUIT
E1 – The Pleaded Claim
"9 Whilst the Claimant was undertaking works under the initial contract it became clear that additional work over and above those agreed in the initial contract would be necessary in order for the works to meet the Landlord's specifications. Without such works the original contract could not be complied with. The extent of the works and the necessity therefore were explained to the Defendant at a site meeting on 14th October 2003.
10 The Defendant agreed at the meeting that the Claimant should undertake the works and that following satisfactory completion of the works the Defendant would pay to the Claimant the costs of such works upon receipt of an invoice.
11 The Claimant, in accordance with the agreement of the Defendant, undertook the additional works. The meeting and the agreement of the Defendant is evidenced by an email from the Claimant to the Defendant dated 16th October 2003 which is annexed hereto."
E2 – The Evidence of the Meeting on 14th October 2003
"Q Mr. Barrand wanted to pull people off site. That was not acceptable to Mr. Alavi?
A. Correct …
Q It was not reasonable to expect the Defendant to pay the additional costs?
A. Mr. Barrand wanted to leave. He could not do the works in a proper way. Mr. Alavi would not allow him to do that.
Q Mr. Alavi was entitled to do that?
A. He did say, 'I'll make the bastards pay'.
Q There was no agreement that Mr. Alavi would meet the bill? A. No. We expected him to get the costs from the landlord.
Q Mr. Alavi did not agree?
A. There were no figures. He did say he wanted Mr. Barrand to stay on site."
"Q There was no agreement to meet your addition costs, was there? A. Not on the face of the meeting. He did not sanction the extra costs at that meeting but he wanted to keep us on site.
Q Why did you say he agreed to meet the costs?
A. He agreed it with Storey …
Q So it is all based on implication which you say was an agreement?
A. I take it on board that it was agreed with Paul Storey …
Q After that, nothing further was said about extra work?
A. Not by myself."
"Q He would not have appreciated that you were looking to him to pay these costs?
A. Probably not, no."
Mr. Weatherill Q.C. argued that this clear answer was contrary to the other evidence and should be disregarded. For the reasons I have already given I consider that this evidence was, in fact, entirely consistent with both the evidence of Mr. Storey and the earlier evidence of Mr. Barrand. It confirms my finding that there was no agreement as alleged on the part of the Defendant.
E3 – The Reasons for the Claims for Additional Works
(a) the fitting of new shop fronts to the Property;
(b) the movement of the fire exit from one wall of the basement of the Property to another;
(c) the works in the service yard outside the Property.
(a) The New Shop Fronts
(b) The Fire Exit
(c) The Service Yard
"Q This was a matter of EQ's contractual risk?
A. Yes, I accept that."
(d) Withholding of Information
(e) Conclusions
E4 – The Individual Claims
(a) Introduction
(b) The Air Conditioning
(c) Fire Alarm System and Intruder Alarm System
(d) The Prolongation Claim
(a) the contract period was six weeks with a completion date of 24th October 2003;
(b) the Claimant was entitled to take his men off site in the middle of this period because of the ongoing landlord's works;
(c) the Defendant did not agree to the Claimant taking his men off site;
(d) accordingly the men stayed on site and the works were completed two weeks late, on 5th November 2003;
(e) thus the Defendant is liable to the Claimant for the cost consequences of that two week delay.
(e) Re-Tiling
E5 – Answers to Issues 4-9
F: THE COUNTERCLAIM FOR DEFECTS
F1 – The Air Extraction System
(a) the Claimant had no obligation to strip out the existing air extraction system;
(b) the Claimant had no obligation to install a new air extraction system.
On the basis of those findings, the majority of this item of counterclaim falls away.
F2 – Tiling
"My tile contractor can and will rectify this problem quite easily. It is a repair and does not warrant a new floor as suggested."
He was certainly right about that. He confirmed in cross-examination that at that time he was prepared to carry out the necessary remedial work and that today he stood by that offer. Even in re-examination he said, "We would have accepted the floor tiles but this was not solely our fault."
F3 – Display Units/Paintwork
F4 – Counter Top
F5 – Leaking Air Conditioning Unit
F6 – Staff Toilet
F7 – Summary of Counterclaim Items
(a) F1 – Air Extraction System £6,110.00
(b) F2 – Tiling £822.50
(c) F4 – Counter Top £235.00
(d) F5 – Leaking Air Conditioning Unit £822.50
(e) F6 – Staff Toilet £470.00
_________
Total £8,460.00
_________
F8 – Answers to Issues 12-15
G: THE COMPROMISE OF APRIL 2004
H: CONCLUSIONS