QUEEN'S BENCH
DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
Claim No.HT-05-310 | ||
MIDLAND EXPRESSWAY LIMITED | Claimant | |
- and - | ||
CARILLION CONSTRUCTION LIMITED | ||
ALFRED McALPINE CONSTRUCTION LIMITED | ||
BALFOUR BEATTY GROUP LIMITED | ||
AMEC CAPITAL PROJECTS LIMITED | ||
JOHN E PRICE | Defendants | |
(No.2) |
____________________
Clifford’s Inn, Fetter Lane, London, EC4A 1LD Telephone:
020 7269 0370
____________________
Counsel for the First, Second, Third and Fourth Defendants:
MR D
STREATFEILD-JAMES QC and MS N JEFFORD
___________________
Crown Copyright ©
'Equivalent project relief means a benefit or relief under the concession agreement to which the employer is or becomes entitled from time to time, pursuant to or under the concession agreement (or would have become so entitled but for a default or omission of the employer under the concession agreement, save to the extent that the same was caused or contributed to by the contractor) to the extent that it is equivalent to a benefit or relief claimed by the contractor under this contract in respect of the same circumstances.'
'Project relevant event means any of the following:
(a) Any act of prevention or breach of contract by the Secretary of State in respect of its obligations under the concession agreement
(b) Any department's change
(c) Any other event under the concession agreement whereby the employer is or becomes entitled to compensation, reimbursement, indemnification or other payment by the Secretary of State under the concession agreement.'
7.2 'The employer shall use all reasonable endeavours to pursue under the concession agreement such rights and remedies as may relate to the works or the contractor's other risks and obligations hereunder...'7.4 'Subject to clause 7.2 (Enforcement of Rights under Concession Agreement), 7.4.1 pending the determination, agreement or resolution of any equivalent project relief under the concession agreement, the contractor shall take no steps to enforce any right, benefit, or relief under this contract to the extent that such right, benefit, or relief relates to the same circumstances as those to which the project-relevant event to which that equivalent project relief relates.'
7.4.2 'Following the determination, agreement or resolution of the equivalent project relief under the concession agreement, the contractor shall be conclusively deemed to have waived any rights, benefit, or relief under or in connection with this contract in respect of the project relevant event that gave rise to the entitlement to equivalent project relief in excess of those arising from such determination, agreement, or resolution. Accordingly, the contractor shall not take steps under the disputes resolution procedure, or otherwise, with the objective that the project relevant event should be resolved under this contract in any different manner from that under the concession agreement, and the contractor hereby waives any right to do so.'
7.5 'Save as provided in this clause (7), the employer shall have no liability to the contractor in respect of any project relevant events'.
7.6 'To the extent of any inconsistency between the provisions of clause (7) and any other provisions of this contract, the provisions of clause (7) (Contractor's Rights) shall take priority.'
"a) The contractor shall identify in any application for an interim payment certificate as a separate item the amounts claimed in respect of such department's change, and, to the extent appropriate, provide vouchers evidencing such amounts. The contractor shall also provide to the employer relevant documentation evidencing the costs referred to in Clause 39.6 (Value of Changes)."
"b) The department's change shall be valued by the employer, applying the relevant principles contained in Clause 39.6 (Valuation of Changes).
39.4.5 Subject to any rights which the contractor may have under Clause Seven (Contractor's Rights) in respect of a project relevant event, the employer shall bear no risk or liabilities whatsoever arising from a department's change, and accordingly, the employer shall have no liability to make payment in connection with or arising from a department's change, other than as either agreed pursuant to Clause 39.4.3 above, or in accordance with Clause 39.4.4, or Clause 39.4.6.
39.4.6 The employer may withdraw the request for a department's change at any time prior to the issue of a department's change certificate countersigned by the department's agent, but in the case of a withdrawal after a request pursuant to Clause 39.4.2 above, the contractor shall be entitled to be paid its reasonable costs incurred in the preparation of the design and estimates."
8.2. Within five days of receipt by the contractor of copies of the notice served under the Concession Agreement and the employer's notice referred to in paragraph eight, then, unless the contractor in his bona fide opinion disagrees that the issues in such reference are or are potentially relevant to the rights and obligations of, or issues between, the employer and the contractor under or relating to this contract, the contractor shall by notice served on the Secretary of State, the employer and the adjudicator, become a party to such reference and agree to have all relevant rights, obligations and issues under or relating to this contract determined at the same time as the dispute."
11.3: "Where the employer gives a notice to the contractor in accordance with paragraph 11.2., 11.3.1: the employer shall if he has not already done so, promptly refer the project relevant event for resolution or determination (as the case may be) under the concession agreement in accordance with the provisions of schedule 15 thereof. 11.3.2: unless the Secretary of State shall have served notice in accordance with paragraph 7.1.2 the contractor shall serve notice in accordance with paragraph 8.2. 11.3.3: The contractor shall not take any steps to enforce any of its rights under this contract which may prejudice or be inconsistent with the operation of paragraph 8. 11.4: to the extent of any inconsistency between the provisions of paragraph 11 of this appendix 6 and any other provisions of this appendix 6 or of this contract the provisions of paragraph 11 of this appendix 6 shall prevail."
Part 3 - The Facts.
"Notice of intention to refer a construction dispute to adjudication (tigers tails). We hereby give notice of an intention to refer the following construction dispute to adjudication namely CAMBBA's entitlement to an interim payment in respect of department's change 11 dated 14 July 2002 as more particularly set out below … 5. CAMBBA have submitted 'sufficient particulars to enable the employer to determine the amount due' in respect of department's change 11. In particular CAMBBA refer to their application for payment/claim submission dated 12 May 2004. 6. CAMBBA have disputed that MEL had properly certified their entitlement to payment for department's change 11. 7. Accordingly CAMBBA now seek the resolution of the construction dispute by adjudication pursuant to clause 53 of the contract. 8. CAMBBA therefore seek a decision from the adjudicator for a declaration that, 1, MEL pay CAMBBA the price adjustment they are entitled to resulting from department's change 11 in the further sum of £9,795,814 plus VAT or such other sum as the adjudicator shall think fit and, 2, interest on any such sum pursuant to the adjudicator's inherent power or as damages and/or 3, any payment certificates which have included an assessment/payment of costs for department's change 11 be opened up and revised to reflect the adjudicator's decision as to the value of the department's change 11 that should have been certified earlier and/or 4, such other relief as the adjudicator thinks fit."
"We refer to your letter of 11 October to our clients Midland Expressway Limited (MEL) enclosing a notice of intention to refer a construction dispute (tiger tails) to adjudication. As referred to in clause 7.1.1 of appendix 6 of the contract a copy of your client's notice has been sent to the department's agent in accordance with the provisions of paragraph 7.1 of schedule 8 of the second supplemental agreement to the concession agreement. We wait to hear whether the Secretary of State wishes to become a party to your client's reference. Should he wish to do so then as you are aware the Secretary of State will give notice to our respective clients within the next seven days. In the event that the Secretary of State does not wish to become a party and as your clients are claiming payment in respect of a department's change, then in accordance with the provisions of clause 7.2 our clients will use their reasonable endeavours and seek to enforce your clients' rights under the concession agreement by immediately initiating the dispute resolution procedure under the concession agreement."
"I have sought advice from the Highways Agency to determine if the Secretary of State under clause 7.1.2 of the concession agreement wishes to be party to this matter. I have now been advised that they do not. However at this stage I would reiterate again that in our opinion under the concession agreement the site is defined as 'the land, spaces, waterway, roads and any surface required for the project facilities an indication of the general area of which is provisionally identified in the drawings' and as such any work required outside of the provisional indication does not of itself necessitate a department change. If under your contract with CAMBBA there is a defined site boundary, giving rise to different contractual implications, then this is a matter for yourselves to determine. I await the outcome of the adjudication in due course."
"I regret that I am obliged to take this action but as you are aware the contractor (CAMBBA) claim that they are entitled to more money than has currently been certified and has recently instigated an adjudication under the provisions of the construction contract. Pursuant to clause 7.2 of the construction contract MEL are obliged to use all reasonable endeavours to pursue under the concession agreement such rights and remedies as may relate to the works for the contractor's benefit. I would be pleased to hear from you as to when you are available to meet in accordance with the provisions of paragraph 1.1 of the procedure in order to see whether we are able to resolve the dispute."
"5. Pursuant to clause 39.7 of the contract CAMBBA are 'entitled to have included in any interim payment certified by the employer pursuant to clause 38 such amount in respect of any department's change as the employer may consider due' Clause 39.6 sets out MEL's obligation to value the price adjustment as defined in the contract required in respect of the department's change. 6. MEL wrote to CAMBBA on 10 June 2004 … confirming that they were 'obliged to formally value any claimed department change. We now propose to do so.' To date MEL have not valued the department's change. Instead, MEL seem to be operating a 'pay when paid' approach and have paid CAMBBA £1.5 million for department's change 11 being the sum they themselves have been paid by their employer, the Secretary of State. 7. No detailed valuation seems to have been carried out by the department's agent and only an arbitrary and unallocated sum of £1.5 million has been paid in two tranches, £800,000 prior to CAMBBA's detailed claim of 12 May 2004 and £700,000 on 16 September 2005 (exclusive of VAT). 10. CAMBBA know of no issue that prevents MEL valuing their claim. They are aware that MEL and the DA are debating whether under the concession agreement the scope of work of the southern tie in required by department change 11 was required of MEL in any event. MEL have the benefit of Jacobs Babtie's report showing what they believed should have been constructed but for department change 11. They therefore have all the information they need to value the southern tie in works caused by department change 11. The fact that they cannot persuade their employer of what the southern tie in would have required but for department change 11 is a matter for them and their employer. On an interim basis CAMBBA's entitlement to payment is clear. Clause 39.7 refers. Whether or not MEL pursue their entitlement under the concession agreement is a matter for them. In the event that it is established that MEL are not entitled to payment from their employer for any monies they may have paid to CAMBBA on an interim basis for the department change, then such overpayment will have to be repaid pursuant to the final certificate as envisaged by clause 38.5.2 of the contract or corrected in a later interim certificate pursuant to clause 38.4.3. The present position of MEL waiting for their employer to value and pay for the work is not what the contract requires of MEL."
Part 4 - The Present Proceedings.
"1. A declaration that on a true interpretation of the design and construction contract executed as a deed between the claimant and the 1st, 2nd, 3rd and 4th defendants on 27 September 2000 those defendants are not entitled to proceed as claimants in the adjudication begun by the notice of intention to refer a construction dispute to adjudication dated 11 October 2005. 2. A declaration that the 5th defendant has no jurisdiction as adjudicator in the above adjudication. 3. An order restraining the 1st, 2nd, 3rd and 4th defendants whether by themselves or by their directors, officers, employees or agents or otherwise howsoever forthwith from proceeding as claimants in the above adjudication. 4. An order restraining the 1st, 2nd, 3rd and 4th defendants from beginning any further adjudication as claimants in respect of the same subject matter as that of the above adjudication. 5. An order restraining the 5th defendant forthwith from proceeding as adjudicator in the above adjudication."
"A construction dispute means a difference or dispute of whatever nature between the employer and the contractor arising out of or in connection with this contract …"
(1) The definition of "construction dispute" is broad and compendious. Subparagraphs (a) and (b) which are tacked onto that definition do not cut down its breadth.
(2) The concession agreement and D&C contract together establish an elaborate machinery whereby (a) the department changes may be valued under the concession agreement, and (b) the sums found to be due may be passed down the line to CAMBBA. However, that procedure has exceptions as set out in clause 39.4.4 and in the last two lines of clause 39.4.5.
(3) In the present case CAMBBA rely upon clause 39.4.4 and, accordingly, contend that their claim for payment falls outside the scope of clause 39.4.5. Mr Streatfeild-James has explained why CAMBBA assert their entitlement under clause 39.4.4 against the employer, but I need not delve into that explanation for present purposes. CAMBBA may be right in their claim against MEL under clause 39.4.4. CAMBBA may be wrong in that regard. But whether CAMBBA are right or wrong, the fact remains that CAMBBA are making a disputed claim against MEL qua Employer. That disputed claim falls squarely within the definition of "construction dispute."
(4) CAMBBA further contend that if and insofar as any provisions of the D&C contract prevent CAMBBA from pursuing their present claim or receiving payment until the mechanisms under the concession agreement have been operated, and/or MEL have received further payment from the department, those provisions fall foul of sections 108 and 113 of the 1996 Act. Accordingly, CAMBBA are entitled to press on with their present claim for payment despite those provisions. In my view these assertions made by CAMBBA (albeit in response to MEL's current stance) themselves give rise to a separate construction dispute between MEL and CAMBBA. Whether CAMBBA are right or wrong in these assertions, they clearly give rise to a dispute "in connection with this contract".
(1) Clause 7.4 must be construed narrowly and in a manner which is compatible with the 1996 Act.(2) Clause 7.4 of the contract is contrary to s. 108 of the 1996 Act. Accordingly the contractual provisions for adjudication fall away and the Scheme for Construction Contracts is substituted. This scheme confers a right upon the contractor to go to adjudication at any time.
(1) On some occasions the assessment made by the DA under clause 8 of the concession agreement, albeit in good faith, may be too low.(2) On those occasions MEL can secure that the sum which is properly due is evaluated and paid to MEL by operating the dispute resolution procedure in schedule 15 to the concession agreement. The schedule 15 procedures will, by one means or another, result in a correction to the original evaluation under clause 8.6. The corrected evaluation may result from a meeting under paragraph 1 or from adjudication under paragraphs 2-8 or from litigation under paragraph 9.
(3) The effect of clause 39.6.2 is two-fold: (a) CAMBBA cannot be paid any money in respect of the department change until MEL has established its entitlement to be paid under clause 8 of the concession agreement. (b) If the original evaluation under clause 8 is in error, CAMBBA cannot be paid the correct sum due until the dispute resolution procedure under the concession agreement has been operated.
(4) The practical consequence of clause 39.6.2 is that CAMBBA will not be paid for department's changes unless and until MEL has received a corresponding sum from the department. This is so even in cases where CAMBBA has established or could establish an entitlement to payment or additional payment under the dispute resolution procedures of the D&C contract. This state of affairs is precisely what s. 113 of the 1996 Act is legislating against.
(5) Clause 39.6.2 uses the phrase "the amounts …to which the employer is entitled to be paid" rather than "the amounts which the employer is paid." In my view, this particular choice of language cannot save the clause. Contracting parties cannot escape the operation of s. 113 by the use of circumlocution.
(6) If I am wrong in the previous sub-paragraph, then I consider that clause 39.6.2 must be read in conjunction with clause 7.1.3. Save in those rare cases where the employer certifies that it has funds available, clause 7.1.3 in conjunction with clause 39.6.2 constitute express and ineluctable "pay when paid" provisions.
(1) MEL has not served any written notice under paragraph 11.2 of appendix 6.(2) Paragraph 11.3.3 of appendix 6 conflicts with s. 108 2(a) of the 1996 Act. Therefore either that paragraph must be narrowly construed or, alternatively, the Scheme for Construction Contracts applies and displaces the adjudication provisions set out in appendix 6.
(1) Paragraph 11.3.3 must be narrowly construed so as not to deprive CAMBBA of their entitlement to adjudication at any time.(2) Paragraph 11.3.3 of appendix 6 is contrary to s. 108. Accordingly, the contractual provisions for adjudication fall away and the Scheme for Construction Contracts is substituted. This confers an immediate right on the contractor to proceed to adjudication at any time.
(1) There is a construction dispute between CAMBBA and MEL. Appendix 6 to the D&C contract permits CAMBBA to take that dispute to adjudication now. The Secretary of State had a contractual right to join in the adjudication, but he chose not to exercise that right. Therefore the adjudication will go ahead without him. The adjudicator has jurisdiction to decide that dispute on the interim basis which is inherent in all the adjudications and which is spelt out in paragraph 9 of appendix 6.(2) There is a dispute between CAMBBA and MEL arising under the D&C contract. It is common ground that this is a "construction contract" within the meaning of the 1996 Act. Accordingly, CAMBBA have a statutory right to refer that dispute to adjudication and the adjudicator has jurisdiction to deal with that dispute. The D&C contract does not and cannot cut down: (a) CAMBBA's statutory right to refer the dispute to adjudication or (b) the adjudicator's power to deal with the dispute.
(3) It is the duty of this court to uphold and support the adjudication system, and to give effect to the intention of Parliament as expressed in the 1996 Act.
(4) The various arguments advanced by MEL in this litigation are, at least in part, available to be put forward as defences in the adjudication. However, those arguments cannot be used to stop the adjudication going ahead at all.
(5) Paragraph 9.5 of appendix 6 prohibits MEL from claiming relief of the kind set out in the Claim Form. That paragraph requires that the adjudication should be completed before there is litigation to challenge the adjudication.
Part 9. Conclusion.