QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
YOUNG & Anor | Appellants | |
- and - | ||
BEMSTONE LTD | ||
(t/a Bemstone Homes) | Respondent |
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
MR. SCOTT ALLEN appeared on behalf of the Respondent.
____________________
Crown Copyright ©
JUDGE WILCOX:
"When we moved into number 8 it was in good decorative condition with no visible signs of cracking or structural damage. When we moved into the property, excavation work had commenced next door at number 6. Over the next two months, excavation work continued and piling works commenced. The piling works caused severe disruption to my family and me. I spent much of my time at home with the children and had to endure the daily disruption caused by the piling works. The piling works themselves involved prolonged periods of incessant banging and thudding. These caused severe vibrations making the house literally shake. At one stage the vibrations were so severe they caused picture frames to fall from the walls and caused the kitchen window to crack. I was extremely worried about the structural safety of the property at this time, as there was audible groaning and cracking noises coming from the walls of the house. Approximately two weeks after the piling works commenced at number 6 cracks began to appear in the walls of number 8 and gradually became markedly more severe. What started as very minor cracks quickly increased in size with new cracks also developing throughout the house. I recall that some of the worst affected rooms were the upstairs bedrooms, nearest to the number 6 side of the building. This was especially concerning for me as these were my children's rooms and I was concerned that piling works would cause the external wall to collapse. The disruption continued and the damage to number 8 continued to worsen with the cracks in the walls becoming progressively worse and new cracks beginning to emerge. By May the piling works next door had finished and the disturbance caused by the works lessened. However, the cracks in the property continued to become worse and in fact the cracks in the bedrooms nearest to number 6 became so severe that I moved my children into different rooms, which meant one of my children having to share a bedroom with me."
She and her children moved out because of the condition of the house. I accept that evidence.
"The property internally is in good decorative condition. There was no evidence of structural movement at ground floor level."
There was some evidence, however, of some damage having occurred between the date of Mr. May's earlier inspections, culminating in that in December 1999 and 30th January 2001. It is recorded in the schedule, it coincides, in my judgment, with the occurrence of the level reduction in the site at number 6 and the commencement of piling works.
"There is cause for concern as to the quality of the piles below the depth of casing. I note that the ingress of grout beyond the bored perimeter restricted the use of casing to a full design depth."
"I have two major concerns with the work carried out to date. Both relate to the vast variation in the height above ground of the piles. There would be approximately 700mm difference in the heights. My understanding is that all piles will have to be trimmed to within 30mm or 40mm of each other. Bearing in mind that the site is almost level, I can see no reason for the variations."
Then, significantly:
"I can only suggest sloppy workmanship and expect your company to bring them back to a reasonable uniformity. The other major concern is the length of steel reinforcement projecting for connecting to the capping beam. I would say there are at least 10 piles on the site adjacent to number 8 Salter where the steel will need extending. I believe there are approximately 13 piles left to install. I expect to see these at a uniform level with adequate steel projecting."
"Now we have exposed most of the piling to the final excavation depth, I have had to time to reflect on the overall quality of the job."
He goes on in the course of that letter to make significant comments as to the quality of the workmanship, the variability of it, and the spacing of it. He concludes:
"I would say that all of the above problems relate to the very sloppy workmanship and I would estimate our additional costs to rectify this situation will be in the region of £12,000 to £15,000."
"Case piles were being installed using a 12 tonne machine working on a platform of soft sand on top of a platform of a 6m high sand dune into completely saturated non-cohesive ground."
It goes on to point out the obvious difficulties that confronted the developer, the piler, and which would have been startlingly obvious to anybody who commenced work upon this site, and would have underlined the necessity to have a very careful work plan, and to have given proper party wall notice and details of that and probable consequences to his neighbours.