QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137, Fetter Lane, London, EC4A 1HD |
||
B e f o r e :
____________________
MOWLEM PLC (TRADING AS MOWLEM MARINE) |
Claimant |
|
- and - |
||
STENA LINE PORTS LIMITED |
Defendant |
____________________
Vivian Ramsay Q.C. and Piers Stansfield (instructed by Eversheds LLP for the Defendant)
____________________
Crown Copyright ©
H.H. Judge Richard Seymour Q. C. :
Introduction
The Amended Particulars of Claim and the Defence and Counterclaim
"Declaration as to valuation of the marine works carried out at Holyhead by the Claimant on behalf of the Defendant."
"Stena's further acceptance of works after the 18th July 2003 and/or once the value of the Works being carried out exceeded the value of £10 million and/or Stena's further request after these events that the said works be carried through to completion."
"4. Each of the said Letters of Intent took effect as a contractual offer from Stena which Mowlem accepted by carrying out the Works outlined in that letter. Accordingly, the said letters took effect as a series of simple "if" contracts whereby Mowlem agreed to carry out the Works and Stena agreed to pay a reasonable sum for those works up to the sum set out in the respective Letters of Intent.
5. The last Letter of Intent, sent on the 4th July 2003, expressly committed Stena to pay for the Works only up to the 18th July 2003 and/or for Works up to the value of £10 million. It was an implied term of the contract created by Mowlem's acceptance of that Letter, however, that if Stena permitted Mowlem to carry out the Works beyond that date and/or so that they exceeded that value, then Stena would pay a reasonable sum for those works.
6. Further or alternatively:
(a) Mowlem's actions in attempting to carry out the Works beyond 4th 18th July 2003 and/or to the extent that the value of the said works exceeded £10 million amounted to an offer to carry out the said works for a reasonable price which Stena accepted in permitting the said works to be done and/or accepting and making use of the said works; or alternatively;
(b) Mowlem having carried out works beyond the 4th 18th July 2003 and/or the value of £10 million and Stena having accepted and made use of the said Works, Mowlem is entitled to be paid a reasonable sum for those works as a Quantum Meruit;
(c) in any event, Mowlem having carried out works for the benefit of Stena and Stena having accepted and made use of the said Works, Mowlem is entitled to be paid a reasonable sum for those works as a Quantum Meruit."
"Mowlem are now entitled to and claim a declaration that it is entitled to be paid a reasonable sum for the works carried out by it on Stena's behalf in relation to the Holyhead Marine Terminal."
The prayer in the Amended Particulars of Claim sought only a declaration in exactly those terms.
"The said claim is made on the following several bases:
(a) that the relationship is governed by a series of contracts arising from the said letters of intent to the effect that such a reasonable sum will be paid;
alternatively;
(b) that the relationship is governed by the said series of contracts in relation to works up to the 18th July 2003 and/or the value of £10 million and by a further simple contract thereafter arising from Mowlem offering and Stena agreeing that Mowlem would carry on the works to completion; alternatively
(c) that the relationship is governed by the said series of contracts in relation to works up to the 18th July 2003 and/or the value of £10 million with Mowlem being entitled to be paid on a quantum meruit basis for any further work carried out for Stena;
(d) that the relationship is governed by the said series of contracts in relation to works up to the 18th July 2003 and/or the value of £10 million with Mowlem being entitled to be paid on a quantum meruit basis for any further work carried out for Stena; [sic (d) as incorporated in paragraph 9 was in fact in identical terms to (c) ]
(e) in any event, Mowlem having carried out Works for the benefit of Stena and Stena having accepted and made use of the said Works, Mowlem is entitled to be paid a reasonable sum for those works as a Quantum Meruit."
"On behalf of Stena Line Ports Limited we confirm that it is their intention to award to you the above Contract, subject to this being confirmed by execution of a written contract in due course.
In the meantime, pending finalisation and agreement of a number of outstanding issues this letter of intent authorises you to proceed with the following works:
1. Secure and mobilise marine plant.
2. Secure and mobilise drilling equipment.
This letter of intent is valid until rescinded, at any time, by written notice (which shall have immediate effect) by Stena Line Ports Ltd., or a Contract is executed. You will be paid in accordance with the provisions in the Tender Documents during this period such reasonable amounts as can be substantiated in respect of your costs for orders placed or work done, subject to the maximum amount given below.
In the event that this letter of intent is rescinded and the Contract is not awarded to you, Stena Line Ports Ltd's total obligations to yourselves and any other parties will be limited to a maximum of £400,000.00.
We confirm that Stena Line Ports Ltd's commitment to expenditure up to a maximum of £400,000.00 will enable you to proceed with the marine works in accordance with your programme, until 15th November 2002.
This letter is not intended to bind Stena Line Ports Ltd. to enter into the Contract with you nor does it constitute an offer that it will do so. This letter represents only the current intentions of Stena Line Ports Ltd."
"On behalf of Stena Line Ports Limited we confirm that it is their intention to award to you the above Contract, subject to this being confirmed by execution of a written contract in due course.
In the meantime, pending finalisation and agreement of a number of outstanding issues, this Letter of Intent supersedes the Letter of Intent issued on 20 June 2003 and authorises you to proceed with the following works:
1. Secure and mobilise marine plant.
2. Secure and mobilise drilling equipment.
3. Supply and delivery of reclamation material.
4. Proceed in accordance with the Contract both for on and off site works.
This Letter of Intent is valid until rescinded, at any time, by written notice (which shall have immediate effect) by Stena Line Ports Ltd, or a Contract is executed. You will be paid in accordance with the provisions in the Tender Documents during this period such reasonable amounts as can be substantiated in respect of your costs for orders placed or work done, subject to the maximum amount given below.
In the event that this letter of intent is rescinded and the Contract is not awarded to you, Stena Line Ports Ltd's total obligations to yourselves and any other parties will be limited to a maximum of £10,000,000.00.
We confirm that Stena Line Ports Ltd's commitment to expenditure up to a maximum of £10,000,000.00 will enable you to proceed with the Works in accordance with your programme, until 18 July 2003.
This letter is not intended to bind Stena Line Ports Ltd to enter into the Contract with you nor does it constitute an offer that it will do so. This letter represents only the current intentions of Stena Line Ports Ltd.
Again, the extension of this letter of intent is entirely without prejudice to our position and Stena's that a contract already exists, so an extension is unnecessary.
Please confirm your acceptance of the terms set out in this letter by return."
"30. Each letter of intent took effect as a contractual offer from Stena which Mowlem accepted by entering the site and/or carrying out the works referred to in the letter. Since each such letter superseded the previous letter, the contractual relationship between the parties is now governed by the terms of the final letter of intent, dated 4 July 2003.
31. Stena contends that the proper interpretation of the letter dated 4 July 2003 is that:
31.1 Mowlem is entitled to be paid such reasonable amounts as it is able to substantiate in respect of its costs for orders placed or work done;
31.2 Mowlem's entitlement to be paid for all works carried out is subject to a maximum of £10,000,000;
31.3 The procedure to be used for payment was to be as described in the tender documents;
31.4 Mowlem was not prohibited from carrying out works after 18 July 2003. Insofar as Mowlem chose to carry out works after 18 July 2003, those works would be subject to the terms of the letter of intent. In particular, they would be subject to the limit of £10,000,000."
"38. As to paragraph 9 of the Particulars of Claim:
38.1 It is admitted that a series of contracts were created by the letters of intent. Each such letter superseded the previous letter.
38.2 The parties' relationship is therefore now governed by the final letter of intent, dated 4 July 2003. This letter, in common with all of the previous letters, provides that Mowlem is entitled to be paid in accordance with the provisions of the tender documents such reasonable amounts as can be substantiated in respect of its costs for orders placed or work done, subject to a maximum.
38.3 In the final letter of intent the maximum is stated to be £10,000,000, and this therefore represents a cap on Stena's liability.
38.4 Mowlem is not entitled to be paid on a quantum meruit, since there is a contract between the parties."
"1. Mouchel's letter dated 4 July 2003 amounted to a contractual offer made on Stena's behalf which Mowlem accepted by entering the site and/or carrying out works thereafter.
2. the contract made on the terms of Mouchel's letter dated 4 July 2003 superseded that made under their previous letter dated 20 June 2003, so that the relationship between the parties is now governed by the terms of the said letter dated 4 July 2003;
3. Mowlem's entitlement to payment for works carried out is subject to a maximum of £10,000,000."
The issues in this action
"THE FIRST ISSUE THAT MAY ARISE: WHETHER OR NOT MOWLEM IS ENTITLED TO BE PAID A REASONABLE SUM FOR THE WORKS WHICH INCLUDES PROVISION FOR OVERHEADS AND PROFIT
10. This issue arises because of the restrictive definition of "costs" which, Mowlem understands, Stena wishes to argue should be adopted. In particular, Stena wishes to contend that the phrase "such reasonable amounts as can be substantiated in respect of Mowlem's costs for orders placed or work done" should be interpreted very differently from the traditional view of "a reasonable amount or sum" in that it should exclude any recovery for overheads or profit.
11. If that is not Stena's position, and if it is accepted that Mowlem are entitled to be paid their costs inclusive of overheads and reasonable profit, this point does not arise."
Further facts relevant to the submissions of the parties
"61. By site instruction 120, dated 4th July 2003, Stena, through Mouchel, instructed Mowlem to modify the Bankseat. Further details of this modification to the Bankseat were provided by Mouchel by a memorandum dated 9th July 2003.
62. By site instruction 121 dated 10th July 2003, Mowlem, through Mouchel, were instructed to modify the capstan.
68. By site instruction 122 dated 15th August 2003, Mowlem, through Mouchel, were instructed to modify the Dolphin handrailing. By memorandum dated 19th August 2003 Mowlem, through Mouchel, were instructed to carry out remedial works to the Dolphins."
"I am disappointed that we do not seem able to agree a proper limit for the letter of intent.
In order to try and bridge this impasse I propose that you authorise expenditure to a limit of £10,700,000 (Ten Million Seven Hundred Thousand Pounds) to completion and give us a further letter of intent to cover this sum and period.
The above sum has been calculated as set out in Appendix A attached and as you will note it excludes the sum for the rock issue, which is being put to conciliation.
It goes without saying that all costs incurred would be subject to verification.
I look forward to your response, by return, hopefully to put this particular issue behind us while we try to resolve the other matters on this contract."
The reference to "the rock issue" was to a claim which Mowlem had made in respect of encountering during the course of carrying out the Works a vertical or steep sloping batter in rock along the alignment of certain monopiles.
"We confirm that the value of the Letter of Intent to which we are currently working is sufficient to cover the cost of carrying out the remaining work on site, the rock issue being a separate matter, which is being resolved by conciliation, as previously agreed by both parties.
We will however need the existing Letter of Intent to be extended to Friday, 1st August 2003."
"In order that there is no misunderstanding as to Stena's position, it is correct that your clause 12 claim on the "rock issue" is being referred to conciliation as agreed. It is Stena's position that a contract for the whole of the Works exists and Mowlem's entitlements to payment are in accordance with that contract. Without prejudice to that, the amount of £10 million in the letter of intent of 4 July is the limit, which applies to all works done pursuant to the letters of intent."
"We consider that the latest Letter of Intent was issued in response to our letter to Mouchel dated 3 July. It is upon this basis that we have continued on site. It is only on this basis that we can continue, as the costs on the project to carry out the works required by yourselves including the rock issue will exceed £10 million."
"We confirm that the value of the Letter of Intent to which we are currently working is insufficient to cover the cost of carrying out the remaining work on site and that this would need to be extended to £10,150,000 to cover the additional instructions recently received, the rock issue being a separate matter, which is being resolved by conciliation, as previously agreed by both parties.
We confirm that the new letter will need to be extended to Friday, 1st August 2003."
It does not appear that there was any response to that letter. Certainly there was no further letter of intent, but Mowlem continued with its work.
"We have made our position quite clear on a number of occasions. We believe a contract exists for the whole of the Works. The letter of intent to which you refer was issued without prejudice to that position and to mitigate our potential loss against your continued threats to cease work.
The stage of the Works now is such that the very substantial losses, which would have been incurred had you failed to continue with the Works previously, will not be incurred. However, it remains our position that if you do not continue and complete the Works you will be in breach of contract."
"Further to our letter ref. 0451, dated 3.7.03 we confirm that the value of the Letter of Intent is insufficient to cover the cost of carrying out the remaining work on site and that this will need to be extended to £10,400,000 to cover the additional instructions received, the rock issue being a separate matter, which is being resolved by conciliation, as previously agreed by both parties."
Submissions on behalf of Mowlem
"(i) Nonetheless, Stena did not withdraw its instruction, made in the letter of 18th July 2003, that the Works were to be continued to completion. Nor did it withdraw the allegation that if Mowlem did not complete the Works it would be in breach of contract.
(j) After the 18th July 2003 (the limit date set out in the final (4th July 2003) Letter of Intent), Mowlem continued to carry out works on behalf of Stena. Stena was fully aware of this. [A list of these works, together with details of meetings at which they were discussed is set out at Agreed Fact 65, et seq. ];
(k) Indeed, Stena (through its agent, Mouchel) issued various orders for extra work after being informed that the cost of the works as they stood would exceed £10,000,000 and after the limit date of the 18th July 2003;
18. Accordingly, the reality of this case is that Stena expressly instructed Mowlem to complete the Works in the full knowledge that that instruction involved Mowlem working beyond the final Letter of Intent limits of the 18th July 2003 and cost of £10,000,000. Because of its mistaken belief as to the contractual terms which govern those Works it even contended that Mowlem would be acting in breach of contract if it did not do so. It ordered additional and varied works during this time. It has had the full benefit of those works.
19. In spite of Stena's insistence, (or rather command backed with the threat of substantial litigation), that Mowlem not only carry out the works for Stena's commercial benefit, but continue without interruption up until completion, and in the knowledge that this would last beyond the 18th July 2003 and was at a cost far exceeding the £10m, Stena apparently seriously now contends that it may retain the benefit of Mowlem's works, costing as it well knew in excess of £10m, and only pay what it knows to be a knock-down price for those works. The irony of the contention will not be lost on the Court. Such a contention was of course only capable of being advanced by Stena after it belatedly conceded that there was no formal contract governing the Works. A more flagrantly opportunistic stance might be hard to conceive.
20. More to the point it is clearly incorrect as a matter of law. Stena are clearly obliged to pay for the works in circumstances where it used as much compulsion as it was able to muster to compel Mowlem to complete and of which it has since enjoyed the benefit. The nature of that obligation arises from the parties' conduct as follows:
(a) Whilst Stena ordered the work completed, the parties failure to agree the terms pursuant to which that would be done once the costs exceeded £10,000,000 means that Mowlem is now entitled to a reasonable sum for that work as a quantum meruit;
(b) Alternatively, the parties conduct Stena's order to complete the work notwithstanding the warnings as to the cost implications and Mowlem's conduct in doing so took effect as a further "if" contractual agreement to vary the letter of intent so as to dispense with the £10 million and date specific limit;
(c) Alternatively Stena's conduct took effect as a waiver by it of the limits placed upon the final Letter of Intent; or
(d) Alternatively, the parties conduct gives rise to an estoppel by convention and Stena is now estopped from denying that Mowlem is entitled to be paid a reasonable sum in respect of the said works and/or that the limits placed upon the final Letter of Intent are ineffective. The common assumption shared by both parties was that Mowlem would be paid a reasonable sum for the Work which it carried out at Stena's insistence. In relation to that Mowlem will rely upon Chitty on Contracts, 29th Edition, paragraphs 3-107 to 3-114 and the cases referred to therein. In particular the Claimant will rely upon the case of Amalgamated Investment & Property Co. Limited v- Texas Commerce International Bank Limited [1982] QB 84."
Submissions on behalf of Stena
"I only wish to add to this part of my judgment the footnote that, even if I had concluded that in the circumstances of the present case there was a contract between the parties and that that contract was of the kind I have described as an "if" contract, then I would still have concluded that there was no obligation under that contract on the part of BSC to continue with or complete the contract work, and therefore no obligation on their part to complete the work within a reasonable time."
That observation was obiter because in fact Robert Goff J held that no contract at all had been concluded. However, Mr. Ramsay and Mr. Stansfield submitted that it was a correct statement of the law. What it meant, submitted Mr. Ramsay orally, was that the correct course for Mowlem to follow in the event that it considered that the limit of £10 million imposed by the letter dated 4 July 2003 was too low in the light of work carried out, was to stop work, or at least to threaten to do so. Mr. Gray accepted that such threats had been made by Mowlem from time to time during the course of the execution of the Works. Stena's case, as set out at paragraph 46.2 of the written opening of Mr. Ramsay and Mr. Stansfield, was that Mowlem's entitlement in the circumstances as they in fact turned out was simply to be paid in accordance with the terms of the letter dated 4 July 2003.
"such reasonable amounts as can be substantiated in respect of your costs for orders placed or work done,"
up to a maximum of £10 million. Mr. Ramsay emphasised that the proper construction of the words which I have just quoted was not before the Court in this action. What in effect I did have to decide, according to Mr. Ramsay, was simply whether the limit of £10 million applied and, if so, to what. The actual evaluation of the sums to which Mowlem was entitled in respect of the execution of the Works was for another occasion.
"We confirm that Stena Line Ports Ltd's commitment to expenditure up to a maximum of £10,000,000.00 will enable you to proceed with the Works in accordance with your programme, until 18 July 2003."
was simply a statement of the anticipation of Mouchel as to how much work the limit of £10 million would cover, and not in any sense a temporal inhibition on the application of that financial limit. Mr. Ramsay disputed the analysis of Mr. Gray that the date 18 July 2003 was that to which the expression "during this period" in the third paragraph of the letter dated 4 July 2003 referred. Mr. Ramsay asserted that that expression, in the second sentence of the paragraph, simply referred back to the period identified in the first sentence of that paragraph as the period of the validity of the letter of intent, namely until it was rescinded or a contract was executed.
"As regards quantum meruit where there are two parties who are under contract quantum meruit must be a new contract, and in order to have a new contract you must get rid of the old contract."
That passage was referred to and applied by the Court of Appeal in Gilbert & Partners v. Knight [1968] 2 All ER 248. Lest those authorities might be thought to have been tainted in their references to the necessity for a new contract, if there was to be an entitlement to payment on a quantum meruit basis, by the former theory of the justification for a quantum meruit being an implied contract, Mr. Ramsay drew to my attention a decision of the Court of Appeal of New South Wales, Trimis v. Mina (2000) 2 TCLR 346. There were a number of issues in that case. The only substantive judgment was that of Mason P. In paragraph 54 of the judgment, at pages 357 and 358 of the report, Mason P said, so far as is presently material, this:-
"The starting point is a fundamental one in relation to restitutionary claims, especially claims for work done or goods supplied. No action can be brought for restitution while an inconsistent contractual promise subsists between the parties in relation to the subject-matter of the claim. This is not a remnant of the now discarded implied contract theory of restitution. The proposition is not based on the inability to imply a contract, but on the fact that the benefit provided by the plaintiff to the defendant was rendered in the performance of a valid legal duty. Restitution respects the sanctity of the transaction, and the subsisting contractual regime chosen by the parties as the framework for settling disputes. This ensures that the law does not countenance two conflicting sets of legal obligations subsisting concurrently. As Deane J explained in the context of the quantum meruit claim in Pavey & Matthews (at 256), if there is a valid and enforceable agreement governing the claimant's right to payment, there is "neither occasion nor legal justification for the law to superimpose or impute an obligation or promise to pay a reasonable remuneration." "
Mr. Gray did not contest that the statement of principle contained in that passage accurately represented the law of England and Wales, as well as the law of New South Wales. I do not think that he contested the applicability of the principle to the present case. At all events, I am satisfied that the law as stated by Mason P does accurately represent the law of England and Wales and that the principle so stated is applicable in the present case.
"68. First, this new contention is contrary to the Agreed Statement of Facts which records that the parties agree that their relationship is governed by the letters of intent (Agreed Facts, paragraph 41).
69. In any event, although the order to complete the works is not identified, it appears to be Mowlem's case that the instruction was contained in Stena's letter dated 18 July 2003.
70. It is quite impossible to construe that letter as a further letter of intent giving rise to an "if" contract. The letter does not contain any request that Mowlem carry out further works, nor any statement that any further works carried out by Mowlem would be paid for in addition to the sums which could be claimed under final letter of intent."
Conclusions
"such reasonable amounts as can be substantiated in respect of your costs for orders placed or work done, subject to the maximum amount given below [namely £10 million]."
I have heard no argument as to the proper construction of the first two lines of the passage which I have just set out and I express no view as to what elements fall, or do not fall, to be taken into account in evaluating the sum to which Mowlem is in fact entitled. I am satisfied that the letter dated 4 July 2003 did not have effect only until 18 July 2003 or only in relation to work done before that date or only in relation to work instructed before that date. The reference to the date had, as it seems to me, only the significance for which Mr. Ramsay contended. I accept the submission of Mr. Ramsay that the period during which the obligation to make payment to which I have referred endured was until the letter dated 4 July 2003 was rescinded or a contract was executed. Grammatically that is what the letter said, and it would make no commercial sense to have a financial limit on Stena's obligations to make payment which could be avoided by the simple expedient of continuing to carry out work after 18 July 2003. It would be even more bizarre commercially if the financial limitation on Stena's obligations could be avoided simply by Mowlem exceeding that limit. I reject the argument that the term set out in paragraph 5 of the Amended Particulars of Claim was to be implied into the contract incorporating the letter dated 4 July 2003. There was, as it seems to me, no justification in law for any such implication. I do not accept that Stena conducted itself on the material before me in such a way as to lead Mowlem to believe that it would not seek to rely upon the terms of the letter dated 4 July 2003. I reject the submission of Mr. Gray that by not in terms restating in his letter dated 18 July 2003 the position on "the rock issue" set out in his letter dated 7 July 2003 Mr. Parry led Mowlem to believe that Stena had altered its position on that question and had accepted the position of Mowlem. In the letter dated 18 July 2003, as it seems to me, Mr. Parry did say that Stena's position had been made quite clear on a number of occasions in relation to the matter raised in Mr. Jones's letter dated 10 July 2003, to which the letter dated 18 July 2003 was a response. While Mr. Parry went on to repeat the assertion that there was a contract between the parties which governed the whole of the Works and contended that Mowlem would be in breach of that contract if it did not complete the whole of the Works, no reasonable interpretation of those contentions is that Stena was accepting the position of Mowlem in relation to "the rock issue". Equally, in my judgment, those contentions did not amount to any request or instruction or order or command to Mowlem to complete the Works. They were simply a statement of Stena's position as to Mowlem's existing obligations. I do not see how that statement could possibly be interpreted as some sort of offer to pay additional sums for work. I accept the submission of Mr. Ramsay that there is no evidence of any waiver on the part of Stena of its right to rely on the terms of the letter dated 4 July 2003. I also accept his submission that the terms of Mr. Ford's letters dated, respectively, 17 July 2003 and 1 August 2003 demonstrate that Mowlem did not believe at the time that Stena would not seek to rely on the letter dated 4 July 2003. While those letters did inform Stena that Mowlem was anticipating that the cost of the Works would exceed £10 million, even apart from "the rock issue", the fact that in each letter a further letter of intent was sought demonstrates, in my view, that Mowlem well understood at the time the significance of the terms of the letter dated 4 July 2003 and that Stena would seek to rely upon those terms. I reject the submission of Mr. Gray that there was a common assumption between Stena and Mowlem that would prevent Stena from denying that Mowlem is entitled to be paid a reasonable sum in respect of the Works or that the financial limitation in the letter dated 4 July 2003 is ineffective. I accept the submissions of Mr. Ramsay that there is no evidence of any such common assumption and that the existence of any such assumption would be contrary to the agreed statement of facts put before me.