QUEEN'S BENCH
DIVISION
TECHNOLOGY & CONSTRUCTION COURT
Strand, London. | ||
B e f o r e :
____________________
McALPINE PPS PIPELINE SYSTEMS JOINT VENTURE | ||
-v- | ||
TRANSCO PLC |
____________________
MR SIMON
HARGREAVES appeared on behalf of the defendant.
____________________
Crown Copyright ©
12th May 2004
JUDGE TOULMIN CMG, QC:
The facts
- 'the actual cost of the work already done',
- 'the forecast/actual cost of the work not yet done' and
- 'the resulting fee'".
"We advise that we will prepare a submission in due course once most of the compensation events are finalised ..."If for whatever reason the period of payments exceeds one month, then it necessarily follows that there will have been additional financing costs incurred which have not so far been reimbursed.
"Alternatively, it could be stated that if there has been what equates to delayed payment of a reasonable amount due at a particular time, then the justification of an interest charge has occurred".
"11.1 The responding party's failure to certify the amount due to the referring party by the assessment date (clause 51.4 of the contract) and/or"11.2 The amount which is stated to be due in a certified payment, being corrected in a later certificate (clause 51.3 of the contract)".
"11. The dispute between the parties concerns the referring party's claim for interest as a result of"11.1 the responding party's failure to certify the amount due to the referring party by the assessment date (clause 51.4 of the contract) and/or
"11.2, the amount which is stated to be due in a certified payment being corrected at a later certificate (clause 51.3 of the contract)".
The law
"(a) act impartially in carrying out his duties and shall do so in accordance with any relevant terms of the contract and shall reach his decision in accordance with the applicable law in relation to the contract".
(2) There was a real risk that the adjudicator was biased (see Glencott Development v. Barrett [2001] BLR 207.(3) The adjudicator had no jurisdiction to reach the decision because he did not reach a decision that was responsive to the issues referred in the adjudication or decided matters that were not referred (see e.g. Ballast plc v. the Burrell Company [2001] BLR 529 and C & B Scene Concept Design v. Isobars [2002] 82 CLR 154 and, in particular, paragraphs 29 and 30 of the judgment of Sir Murray Stuart-Smith at page 161).
(4) There was no dispute on which the adjudicator could reach a decision because a dispute can only arise where the subject matter of the dispute has been brought to the attention of the other party and the other party has had a proper opportunity to consider it (see Fastrack v. Morrison [2000] BLR 168).
(5) Notwithstanding the relatively free hand that the adjudicator has in directing the procedure, the adjudicator acted unfairly and to the significant prejudice of the defendant in failing to give the parties an equal opportunity to present their case with the result that one party was prejudiced. This problem can occur where one party adds new claims, arguments or evidence to which the other party is not given an adequate opportunity to respond before the adjudicator reaches his decision (see e.g. Discain Project Services v. Opek Prime Development Ltd. [2000] BLR 402).
What constitutes the dispute?
Conclusion