Queen's Bench Division
Technology and Construction Court
1 Fetter Lane London |
||
B e f o r e :
____________________
(1)Richard Charles Goodway (2) Carabos Ltd |
||
and |
||
Zurich Insurance Company |
____________________
Mr Andrew Davis appeared for the defendant instructed by Berrymans Lace Mawer, Salisbury House, London Wall, London EC2M 5QN, DX: (Ref: SYC/MIS/20734/5l)
Date of hearing: 17, 18 and 19 November and 17 December 2003
____________________
Crown Copyright ©
1. Introduction
2. Factual and procedural background
2.1 The Newbuild scheme
2.2 Mr Goodway and Carabos
2.3 The proceedings
2.4 The Tomlin Order
"Where [the Zurich] is of the opinion that in relation to a completed New Home ... [Carabos] has fulfilled all his obligations pursuant to these rules then ... it will provide a final certificate in respect of the New Home."
Thus, the survey was intended to satisfy the Zurich that each property had been completed in accordance with the Zurich's technical requirements which are listed in great detail in its technical literature issued as part of the Newbuild scheme.
2.5 Events following the Tomlin Order
"We therefore ask you by return of post that you will provide our client's surveyor access to the properties for the purpose of carrying out the survey."
No answer was provided to this question and, unless and until Mr Goodway provided a clear statement to both BLM or the Zurich and to Mr Needham that access for the surveys would be provided and any that the necessary facilities to enable the inspections to proceed would be made available and then made contact with Mr Needham to arrange details for that access and those facilities, the necessary inspections and surveys could not take place.
1. Mr Needham was additionally being appointed jointly by the Zurich and Carabos to conduct the final inspection and survey of the properties envisaged by the Newbuild scheme that was needed to advise whether the properties were in a condition whereby Carabos "had fulfilled its obligations pursuant to the Newbuild scheme Rules" to allow for the issue of final certificates.
2. Mr Needham was required to liaise with Mr Goodway and to arrange directly with him the carrying out of such tests and opening up and for the provision of such drawings, calculations, any prior test and inspection documentation and information from subcontractors as were needed to enable the required survey and its accompanying details of required work to be provided to both the Zurich and Carabos.
3. Mr Needham was being jointly appointed to issue a list of works considered necessary before a final certificate could be issued in sufficient detail to enable a Form 8 notice specifying them to be issued by the Zurich to Carabos under rule 29(b) of the scheme rules.
1. The report stated that the gulley connections between the roof drainage system and the combined sewer should have been but were not accessible to roding and that it was not clear that they had in fact been constructed as trapped connections. Moreover, it was not clear that the drain runs adjacent to these connections were defect free. In consequence, the report recommended that the drains should be exposed by opening up so that it could be demonstrated by photographic evidence from that opening up that there were no undetected defects in the drains in close proximity to the walls that could lead to subsidence of the foundations caused by water penetration through the defects and also that the connection had in fact been constructed in conformity with the building regulations.
2. The report recommended that a tree be removed that was located close to a retaining boundary wall of one of the properties and the damaged section of the wall rebuilt. The damage was not likely to cause early collapse of the wall but had been caused by tree root incursion which had not been adequately provided £ or and protected against in the design and construction of the wall.
"The height/size of the tree will be reduced by lopping and pruning. Cut out the damaged section of wall and provide a full depth joint with a flexible filler/sealant (minimum 25mm). Place vertical paving slab between the wall and the retained soil to project joint. This solution will be adopted but the front garden wall will be removed from the insurance policy to be provided by the Zurich. This endorsement to the policy is related to the preservation of the tree and visual amenity which should therefore not be an impediment to the sale of the properties."
2.6. The issues
1. Would the Zurich have been entitled to an order in the terms sought but for the developments that occurred during the hearing? This issue is primarily related to the inevitable costs application for its costs of this application by the Zurich and a responsive cross-application for their costs from Carabos and Mr Goodway of that application in the light of it no longer being pursued.
2. Were the Zurich in breach of the Tomlin Order by the delay in its being implemented in part and, if so, what damages may be recovered by Carabos and Mr Goodway?
3. Is the Tomlin Order to be set aside or are damages for misrepresentation inducing it to be recovered on account of misrepresentations by the Zurich addressed to Mr Goodway and Carabos prior to its being finalised which induced the settlement and, if damages are to be awarded, what damages are recoverable?
3. The application for mandatory relief
4. Was the Zurich in breach of the Tomlin Order
1. At no time did either defendant seek to put the properties on the market, to advertise them or to instruct agents to market them.
2. Throughout the period from July to September 2002, both Carabos and Mr Goodway sought to prolong with petty objections the discussions as to the terms of appointment and the identity of the surveyor. Both could have notified the Zurich at the outset of their objections and then asked the Zurich to appoint the surveyor on appropriate terms and continue the discussion about fees whilst the surveys were being arranged and carried out.
3. Both decided soon after the Tomlin Order had been made that they would seek alternative insurance cover for the properties which they successfully achieved in February 2003. Notwithstanding that, the properties were not then marketed.
4. Both failed to respond to the Zurich's invitation to undertake the proposed remedial work, to seek to show that the drains were satisfactory or to propose the alternative scheme to deal with the boundary wall once the Needham report was served on them.
5. Neither defendant had the means or the intention to provide the £20,000 deposit required before the final certificates were issued.
5. Misrepresentation
"As requested please find attached brief description of the works with sketches and budget. ... Obviously this information has had to have been provided at very short notice but we can amplify if required given more notice. Hope sufficient at this stage.
Brief budget breakdown between properties:
Orotava
Excavation and pipework replacement £23,000
Merrythought
Excavation and pipework replacement £3,000
General
Externals, paving & landscaping £10,000
Prelims, pre contract client liaison etc £,7000.
1. There is no misrepresentation alleged The best that can be suggested is that the list of documents amounted to a misrepresentation that it contained all disclosable documents when the fax and the covering breakdown were not disclosed but were in BLM's possession. However, the nature and extent of the non-disclosure is so limited that the list, as served, cannot amount to any misrepresentation as to the disclosable documentation or as to the potential weakness of the Zurich's case.
2. The fax is a privileged document since it was a communication from a witness to the Zurich's solicitor for the purpose of preparing the Zurich's case for trial.
3. The documents do not clearly show that the damages claimed were inflated, dishonestly calculated or relating to work which was not done or which did not itself relate to defects caused by Carabos and Mr Goodway.
4. There is no evidence that a payment into court was contemplated, would have been made had the documents been disclosed or that any assessment of the defendant's prospects and risks would have relied to any extent on these documents even if they had been made available to Carabos and Mr Goodway.
5. The documents, and their absence from the discovery provided in November 2001, did not induce or even influence Carabos and Mr Goodway in their thinking in agreeing to enter into the settlement reached in June 2002.
6. The future
7. Conclusion
no order as to costs on both the Zurich's application and the defendants' cross-claims.