Queen's Bench Division
Technology and Construction Court
1 Fetter Lane London |
||
B e f o r e :
____________________
ALSTOM SIGNALLING LIMITED (trading as Alstom Transport Information Solutions) |
Claimant |
|
and |
||
JARVIS FACILITIES LIMITED |
Defendant |
|
(No 1) |
____________________
Mr Martin Bowdery QC appeared for the Defendant instructed by Eversheds
____________________
Crown Copyright ©
INTRODUCTION
INTRODUCTION
Putting our commercial issues to one side, I wish to thank you for a successful commissioning. The Railtrack objective, to run Railtrack services 06:00 hours on 28 January 2002 was achieved on time. A great deal of hard work was put in by all your staff to achieve this. You successfully overcame the many problems that faced us. We still have some work to sort out post commissioning, such as speed proving, but hopefully this will not impact the project too much.
Please accept my personal thanks, and thanks on behalf of the whole project team.
We look forward to true completion of the scheme, with Metro passenger services commencing 31 March 2002. The main commissioning success is a major step to achieving this.
(TB 8/1345 - my emphasis)
It is the still unresolved "commercial issues" which were the subject of an Adjudication (see paragraphs 12(4), 12(5) and 13 below) and which now come before the Court for decision.
[Pausing at this point, it is convenient to note that the documents show a fairly loose or imprecise usage of the terms "cost" and "price" and I shall adopt the convention of referring to "cost/price" to try to make the position clear.]
The "base tender cost/price" did not include a "management fee". The "management fee" was designed to cover production overheads, non-production overheads and profit. A base "management fee" was a separate figure calculated from the "base tender cost/price".
62.2.1 The total of the Schedule of Prices in Schedule 3.4 excluding Management Fee shall be the basis of the Target Price. The Schedule of Prices shall be priced at nett cost exclusive of any allowance for risk. The individual prices within the Schedule of Prices may be used Post Contract for monitoring comparison of work activity progress against expenditure.
62.2.2 The Tenderer [Alstom] shall provide a priced risk log identifying what he considers to be the risks inherent in his tender and indicating most likely, optimistic and pessimistic costs.
62.2.3 At Post Tender Stage but prior to award a joint QRA workshop will be held with Railtrack and the Contractor [again, Alstom] to establish the agreed Risk Log for the Contract. This will be reviewed by the Employer's Representative and the Contractor and upon their agreement the 50% probability addition of risk [the so-called P50 figure] generated will form the Agreed Target Price.
62.2.4 The 80% probability addition of risk [the so-called P80 figure] generated by the QRA will form the Agreed Gross Maximum Price.
62.2.5 The Risk Analysis as detailed in 62.2.3 and 62.2.4 will be produced with the aid of Primavera P3 Montecarlo Simulation Software in order to produce cost probability graphs with P50/P80 figures.
(TB 3/222 - Railtrack's emphasis and my clarifications)
Although the tender documents sent out by Railtrack had envisaged that the "management fee" would be a fixed amount "payable outwith the incentivisation mechanism" (see Clause 61.1 at TB 3/218), in post tender negotiations the parties agreed to vary this (see paragraph 5 of the "Agreement of Outstanding Tender Issues" dated 13th December 1999 at TB 3/206). The logic which underlay this agreement was explained by Mr Irvine in his internal note – Railtrack and Alstom agreed that a full pro-rata increase should be made to the base "management fee" up to the level of the "Agreed Target Cost/Price" and that a further limited pro-rata increase should be made to the overheads elements only up to the level of the "Agreed Gross Maximum Cost/Price" (ie. Alstom's profit was to be capped at the "Agreed Target Cost/Price" level).
62.3.1.1 Variations to the Works (Clause 17) provided that such Variation shall be a specific alteration made by [Railtrack] to the type and/or extent of [Alstom's] Services and/or to the Plant and shall not in any way be on account of any change in or development of the design or the Specification or of the method of carrying out the Works made by [Alstom]. It is intended that Scope Creep be included as a risk item and therefore form part of [Alstom's] Agreed Target Cost. Approval by [Railtrack] of any proposals by [Alstom] shall not constitute a Variation.
62.3.1.2 Any additional expense reasonably incurred, or loss reasonably suffered by [Alstom] as a result of any breach of Contract by [Railtrack], pursuant to sub-clause 14.4 of the Conditions of Contract. (Any monies paid to any Sub-Contractor arising out of the negligence, default, lack of skill and care or breach of Contract by [Alstom], his servant or agents or Sub-Contractors shall not adjust the Agreed Target Price, nor shall they be paid).
62.3.1.3 Any statutory or other obligations as defined in Sub-Clause 6.2 of the Conditions of Contract except that any such extra costs shall only adjust the Agreed Target Price to the extent that they were neither included nor capable of being included in the Agreed Target Price.
62.3.1.4 Matters outside [Alstom's] control including force majeure but shall exclude exceptionally adverse weather conditions which shall be included as an [Alstom] risk item.
The benchmark by reference to which "pain" or "gain" was to be assessed was the properly adjusted "Target Cost/Price". The "Contract Price" which Alstom was to be paid was "the final figure after adjustment for the incentivisation mechanism…" (see Clause 61.1 at TB 3/218). The "Contract Price" which would be payable was to depend on the relationship between the adjusted "Target Cost/Price" and the "Final Actual Cost/Price". If the "Final Actual Cost/Price" was to come in below the adjusted "Target Cost/Price" there would be a "gain" to be shared; if the "Final Actual Cost/Price" were to come in above the adjusted "Target Cost/Price" there would be "pain" to be shared.
5. Alliancing
With regard to the Gain/Pain position as tendered, and subsequently under review, Alstom accept Railtrack principles other than unlimited pain share on the Gross Maximum Price ["GMP"[
The Parties are in agreement to develop the principles of the pain limitation in accordance with the following for the Sunderland Metro Work:-
Adjustment has been made to the P80 Risk level to establish a revised GMP in the value of £12,867,674. A cap on the Contractors 100% pain over the GMP has been agreed at a value of £14,117,674 after which Railtrack will reimburse the Contractor at net cost exclusive of any overhead or profit contribution.
This shall be with a Base Tender value of £11,003,114, with a Target Price of £12,367,674.
The above is intended to, and has been designed, to reflect a maximum loss position to Altsom where all Alstom profit and non production overhead has been eroded.
For the avoidance of doubt, should the Leamside Works be introduced then……
It is agreed that proposed [Key Performance Indicators] KPI's shall be developed on the Railtrack principles as tabled at post tender meetings and subject to Alliance review, synergy and acceptance with the Alliance Partners. At this stage Alstom accept the principles as detailed in the tender documents in respect of the operation and distribution on the KPI Fund.
(TB 3/205 and 206 – my emphasis)
The wording used is consistent with Alstom and Railtrack having agreed to develop the pain sharing provisions and recording the final agreement which had been reached between them. It is on this reading, which accords with the original version of Mr Irvine's internal note (see TB 5/358 and 359), that Alstom's case against Jarvis is premised. However, the wording is also consistent with Alstom and Railtrack having agreed in principle to develop the pain sharing provisions in the manner described without the matter being finally settled at this time. A number of later documents appear to be rather more consistent with Alstom and Railtrack regarding both pain sharing and gain sharing as matters which were the subject of ongoing negotiations (see paragraphs 24, 30 and 31 below). If that was so, at some later time Alstom appears to have accepted that the Main Contract contained a finalised pain sharing term in the terms of paragraph 5, or in terms that were substantially the same as paragraph 5. However, assuming (as Alstom allege) that final agreement on gain sharing and on limited pain sharing was reached on or before 13th December 1999, and in the terms recorded in paragraph 5, the agreed incentive scheme can be summarised as follows:
(1) the agreed (adjustable) "Target Cost/Price" was £12,367,674;
(2) if the "Final Cost/Price" came in below the adjusted "Target Cost/Price", the "gain" was to be shared between Railtrack, Alstom and the Alliance;
(3) if the "Final Cost/Price" came in at a figure up to £500,000 above the adjusted "Target Cost/Price" (i.e. between £12,367,674 and £12,867,674 on the basis of the unadjusted initial figures) this first band of "pain" was to be shared equally between Alstom and Railtrack;
(4) if the "Final Cost/Price" came in at a figure up to £1,250,000 above the adjusted "Target Cost/Price" plus £500,000 (i.e. between £12,867,674 and £14,117,674 on the basis of the unadjusted initial figures) Alstom would bear the whole of this second band of "pain"; and
(5) if the "Final Cost/Price" came in above the adjusted "Target Cost/Price" plus £1,750,000, Alstom would be reimbursed the excess "cost/price" at net cost exclusive of any overhead or profit contribution.
Given that the same principles were to be used in adjusting both the "Agreed Target Cost/Price" and the "Agreed Maximum Cost/Price" (see paragraph 4 above) it would seem probable that the difference between these two figures would remain constant whether the "cost/price" increased or decreased. In the event of increase, Alstom could expect to see proportionate increases in overheads recovery and profit but there is no suggestion that the pain cap was to be subject to a corresponding adjustment. On Alstom's case, it seems that there was agreement that the maximum "pain" which Alstom might be expected to bear was £1,500,000.
19. (1) the parties agreed that the Subcontract Price would be calculated in accordance with the rules contained in Schedule E [of the Issue 3 documents];
(2) Schedule E clause 3.1 provided that one of the rules for calculating the price was the application of the Alliance Pain/Gain mechanism;
(3) Also by Clause 3.1 the principles of the Pain/Gain Mechanism were to be based on the details contained in Schedule B, Annex B1 [of the Issue 3 documents] – these included that the percentage to be borne (or enjoyed) by Jarvis of any pain or gain would be in the same ratio as the sub-contract value bore to the main contract value;
(4) the Railtrack/ALSTOM contract provided the mechanism for determining the amount of the pain or gain to which that percentage would be applied.
20. Alternatively, insofar as any element [of the sub-contract "pain/gain mechanism] yet remained to be agreed, it was agreed by Jarvis' acceptance of ALSTOM's letter of 31st January 2002 as set out at paragraph 10(1) and 10(2) [of the Particulars of Claim – and as to which, see paragraph 44 below].
(TB 1/13 and 14 – with my parenthetic clarifications)
In the alternative, Alstom contends at paragraph 21 of the Particulars of Claim –
…… if (contrary to ALSTOM's case, but as has been contended by Jarvis) any element of the pain/gain mechanism remained to be agreed, this Court has full power to determine what the amount of any pain to be borne or gain to be enjoyed by Jarvis should be, applying the principle set out in Schedule B Annex B1 and the provisions of Schedule E [of the Issue 3 documents].
(TB 1/14)
with the Court's power deriving from Clause 45.3 of the Special Conditions of the Sub-Contract (see TB 4/297 – the clause itself is set out at paragraph 54 below.)
In addition to responding by disputing each of Alstom's submissions, Jarvis advances a positive case of its own. Jarvis also contends that a sub-contract was agreed in the terms of the Issue 3 documents. However, Jarvis disputes the inclusion of the pain/gain sharing term pleaded by Alstom – or the inclusion of any pain/gain sharing term. Jarvis accepts that the "pain/gain" issue was raised and considered during the course of intermittent and protracted sub-contract negotiations, between 1999 and 2002 but, it submits, the wording of Annex E5 which formed part of Schedule E to the Issue 3 documents contains a clear statement of the then current understanding of the parties -
1.0 The Pain/Gain share shall use the basic definitions and principles described within the ITT – Section A, Binding 1, dated July 1999, Clause 61 Schedule of amendments to the Special Conditions and General Conditions.
Details of the Pain/Gain Mechanism are to be reviewed and agreed in accordance with Action number 5 from the meeting dated 23rd August 2001. Once agreed by both parties the details shall be added to the Subcontract Agreement as an amendment.
(TB 4/655 – my emphasis)
and, it further submits, that no agreement on a mutually acceptable "pain/gain" sharing mechanism was reached at any time thereafter. In answer to the second limb of Alstom's primary case viz. that the Court has full power to determine the amount of pain to be borne or gain to be enjoyed by Jarvis, at paragraph 31 of the Defence it is said –
…… it is denied that it is necessary, reasonable or appropriate for the Court to determine what should have been agreed but was not agreed regarding any pain/gain agreement as alleged or at all.
(TB 1/91)
22. …. The sub-contract did not contain a complete or workable statement as to the sub-contract price which was and is an essential and necessary term of the sub-contract. In the premises the sub-contract is unenforceable.
23. By reason of the foregoing, Jarvis's entitlement to be paid is upon a Quantum Meruit. Alstom will contend that the reasonable price to be paid to Jarvis for their work would take into account an appropriate percentage of any pain… suffered… by Alstom under the [main contract] … .
In support of the allegation that Jarvis' entitlement is to payment upon a Quantum Meruit, Alstom relies on the following –
"(1) the fact that from September 1999 onwards Jarvis at all times agreed to the principle that it would participate in the pain/gain share agreement;
(2) the facts and matters set out at paragraph 5 to 8 [of the Particulars of Claim];
(3) the provisions of the [Issue 3 documents]…"
Under the heading "the Tendering Agreement", at paragraphs 5 and 6 of the Particulars of Claim, Alstom referred to certain clauses of a Tendering Agreement dated 24th September 1999. The clauses referred to were –
Clause 2.1:
"The parties agree to co-operate in the preparation and submission of the Tender and in the event of the award of a Contract to ALSTOM on terms accepted by each of the Parties in writing to perform the said Contract.
The Tender shall be binding on the Parties and shall be complete for the purposes of the Project."
("Tender" was defined by Clause 1(h) as "the tender to be submitted by ALSTOM to the Purchaser for the Project".)
Clause 5.1:
"Each Party shall be responsible for preparing the content of the Tender for its Scope of Work and for ensuring that its Scope of Work is complete in all respects for the purposes of the Tender.
The parties shall provide each other promptly with all information and assistance reasonably required for the purposes of the preparation submission and negotiation of the Tender."
Clause 6.1:
"The Parties shall discuss and agree limitations of liability and risk-sharing arrangements between themselves in respect of the performance of the Tender prior to the submission of the Tender."
And at paragraphs 7 and 8 of the Particulars of Claim, Alstom alleged that –
"7 By reason of their involvement in the preparation of the tender, Jarvis were aware that and agreed that
(1) the tender to Railtrack would include a "Pain/Gain Share" provision;
(2) by the terms of the Pain/Gain Share provision it was provided
(a) that in principle ALSTOM would be paid upon a cost reimbursable basis;
(b) but that this entitlement to be paid upon a cost reimbursable basis was subject to the following (among other) provisions:
(i) that a Target Cost was agreed (subject to certain provisions to revise that cost in certain circumstances);
(ii) that if the cost of the project fell below the Target Cost then ALSTOM would be entitled to share in the "gain" by receiving 50% of any shortfall in cost;
(iii) that if the cost of the project exceeded the Target Cost then ALSTOM would bear 50% of the "pain" of the first £500,000 of excess cost over the Target Cost; of the next £1,250,000 of excess cost, ALSTOM would bear the whole of the "pain"; and Railtrack would bear the whole of any "pain" over and above an excess of £1,750,000;
(3) that it was at all times the expectation that Jarvis would be the sub-contractor to ALSTOM responsible for the installation works and some elements of design on the project;
(4) that the tender was prepared jointly on the basis that ALSTOM and Jarvis would be "in alliance" with the understanding that ALSTOM/Jarvis sub-contract would provide for ALSTOM and Jarvis to share any "gain" enjoyed or "pain" suffered by ALSTOM under the Railtrack/ALSTOM contract.
8. As Jarvis knew, ALSTOM entered into their contract with Railtrack on the basis of the expectations and understanding set out at sub-paragraphs 7(3) and 7(4) above."
In response to this secondary case, Jarvis takes issue with the submission that the pain/gain provision was an essential part of the sub-contract. Jarvis contends that the unsigned sub-contract could work, and that it did in fact work, without it. However, if the Court were to reject that submission and to hold that the "pain/gain" provision was fundamental or central to the formation of any sub-contract between itself and Alstom, Jarvis maintains the positive case advanced in answer to Alstom's primary case (viz. that no agreement was reached on any pain/gain provision) and submits that, in such circumstances, no sub-contract was concluded. The result of that, in Jarvis' submission, is that it (Jarvis) is entitled to be paid a reasonable price for the work and services which it carried out at Alstom's request. When the amount of that reasonable price comes to be calculated, Jarvis submits that no account should be taken of "any failure by Alstom to comply with their main contract targets allegedly agreed with Railtrack" (see paragraph 34 of the Defence).
3.2 The Parties hereby agree that [the provisional sum of £12.75m] represents the Final Guaranteed Maximum Subcontract Price payable by [Railtrack] to [Alstom] in respect of the Jarvis subcontract works.
3.3 The Parties hereby agree that in the event that the Agreed Final Subcontract Price (as between [Alstom] and Jarvis) is in an amount less than the provisional Subcontract Price the amount of difference shall be a gain shared in equal proportions between [Alstom] and [Railtrack]
3.4 The Parties hereby agree that in the event that the Agreed Final Subcontract Price (as between [Alstom] and Jarvis) is in an amount in excess of the provisional Subcontract Price the excess shall be borne solely by [Alstom]
3.5 [Alstom] shall obtain [Railtrack's] prior written consent to the amount of the proposed Agreed Final Subcontract Price.
(see TB 8/1513)
The deduction of the two elements of agreed "pain", which together total £1,500,000, can be seen in the calculation which was shown as Schedule 1 to Appendix 1 of the Contract Amendment Agreement -
Final Guaranteed Maximum Price ("GMP") | £21,118,000.00 |
LESS 50% of P80 | (£250,000.00) |
Final GMP payable | £20,868,000.00 |
ADD sum of difference between Agreed | |
Final Actual Cost and Cap on Liability | |
(£23,860,000.00 - £21,118,000.00) | £ 2,742,000.00 |
LESS Cap amount | (£1,250,000.00) |
£22,360,000.00 | |
ADD Fixed Fee | £ 2,573,000.00 |
ADD Fee on PMIs (balance) | £ 1,817,000.00 |
Contract Price | £26,750,000.00 |
(Adjustable in accordance with paragraph 3 herein) | |
(see TB 8/1514 - my emphasis) |
The method or methods used to arrive at the agreed revised "Final Guaranteed Maximum Cost/Price" of £21,118,000 and the Agreed "Final Actual Cost/Price" of £23,860,000 is/are not transparent (but, in passing, I note two points – first, the agreement does not bind and cannot adversely affect Jarvis' legal rights/obligations; secondly, in the agreement it was said that Railtrack and Alstom agreed that the "Guaranteed Maximum Final Cost/Price" was deemed to be calculated in accordance with the particular conditions [of the main contract]" – see Clause 1.1 – TB8/1512). No revised "Target Cost/Price" was shown in the Contract Amendment Agreement but, when calculating its claim against Jarvis, Alstom appeared to have simply maintained the £500,000 differential and fixed on £20,618,000 as the appropriately adjusted figure.
THE DEVELOPMENT OF THE DISPUTES – ADJUDICATION – THE PRESENT PROCEEDINGS
It was always the intent of both parties to operate on a partnering basis incorporating gain/pain arrangements and to back to back these to the head contract.
The Alstom/Railtrack pain/gain sharing was first described to Jarvis by ALSTOM in December 1999. It has not changed since then, save that the Alliance gain share has now moved to a 50/50 share with Railtrack for each contractor. Pain share was always specific to ALSTOM and did not involve the Alliance Performance.
At a meeting in April 2000 ALSTOM and Jarvis agreed in principle to the pain/gain concept above, but with the parameters reduced in scale by a % which describes the relative size of the Jarvis/ALSTOM base costs (at the time this stood at 37%, which is quoted in the meeting notes). Today that ratio is ~50%, reflecting the relative growth of Jarvis scope. Later correspondence between Peter Middleton and myself revisited the same ground.
Without finalising this pain/gain mechanism, the concept of a JARVIS target cost and variation is meaningless. An obvious way forward on this issue, which is jointly agreed to be outstanding, is to ratify the original concept of sharing the proceeds of Alstom's pain/gain mechanism with RT. The benefit of this would be to negate the current situation of double negotiation and to allow us to concentrate both of our efforts on the single issue of increasing ALSTOM's target cost.
At this late stage I cannot see any alternative way of concluding the contract between us but if you have any other suggestions please advise them. I would like to convene a meeting within the next two weeks to finalise this and any other outstanding issue.
(TB 8/1339 and 1340 – my emphasis)
I shall have to return to this letter, which Jarvis apparently received on 6th February 2002, when I come to consider Alstom's primary case but, for now, I simply note it as the first in the series of documents where the parties set out their respective positions and which lead up to the Adjudication and then to these proceedings.
Resolutions of the Contract
Alstom considered that the signing of the Contract was fundamental as far as they were concerned the parties had acted on the Contract and it should therefore be signed. Jarvis agreed that both parties had acted on the Contract however there was clear evidence that there were two outstanding items these being the Pain/Gain mechanism and the resolution of certain Nexus materials.
It was Alstom's view that a 50/50 Pain/Gain mechanism was in place and that this had been implied on the basis of a Partnership arrangement between Alstom and Railtrack and step down between Alstom and Jarvis. Jarvis did not accept this and considered that the Pain/Gain mechanism was still to be agreed this had been clearly spelt out in the document to date. Jarvis did not accept that there was any Partnership Agreement implied or otherwise. In support of this Jarvis referred to the fact that there had been originally an alliance agreement of which they are a part.
It was Jarvis view that Alstom considered them as sub-contractors, the documentation stressed this and indeed they had been excluded from any negotiations with Railtrack in many instances at the specific insistence of Railtrack.
Jarvis considered that the Pain/Gain mechanism was always an area which had never been agreed. Mr Robson had always expressed concerns over the non-agreement of the Contract. Since his connection with the Company almost one year ago, however the only matters outstanding had been the Pain/Gain mechanism which had not agreed on the simple basis that neither Alstom nor Jarvis could agree to a clear mechanism to which a Pain/Gain Agreement could be achieved.
Jarvis considered that they would still consider a Pain/Gain mechanism to which Alstom responded that the "ball was now in Jarvis' court".
Jarvis considered that as nothing was agreed there was now no way that Alstom could either imply or impose a Pain/Gain mechanism and this would have to be to the mutual agreement of both parties.
Jarvis assessed that they would continue to increase the target cost and at which time they would be pleased to operate a Pain/Gain mechanism.
Jarvis confirmed that current target was in the region of 12.25 million which was currently 2 million pounds above the current target leaving Jarvis exposed to the tune of 2 million pounds.
(TB 8/1361 and 1362 – my emphasis)
The various different manuscript notes of or relating to the meeting are consistent in showing that Jarvis positively indicated a willingness to agree to a particular pain/gain mechanism. The mechanism proposed was a comparatively simple one, namely 50:50 gain/pain sharing up to 10% of the Target Cost with Jarvis' Management Fee limited by reference to the Target Cost (see TB 8/1364, 1366 and 1368). It is clear from two of the entries that the individual who put forward that offer on behalf of Jarvis was Mr Robson (see TB 8/1366 and 1368). It was not expressly stated in the Notes themselves that the "Target Cost" which was being referred to was Jarvis' final "Target Cost/Price" but that is, in my judgment, the fair inference to be drawn. It also seems clear from the second page of one of the Alstom notes that, after considering Jarvis' offer, at that time Alstom did not wish to accept it (see TB 8/1365).
Further correspondence/discussions followed, the detail of which I do not need to describe beyond noting –
(1) that after a meeting on 12th April 2002, Jarvis sent a first Adjudication Notice to Alstom on 15th April 2002 (see TB 8/1418 to 1425). At paragraph 2 of the Notice, Jarvis contended that it had "… commenced work pursuant to a contract agreed [with Alstom]";
(2) although an adjudicator (Mr Peter Chapman) was identified and the parties agreed that any future disputes would be referred to him, the first adjudication did not proceed to a decision (see TB 8/1480). Alstom and Jarvis endeavoured to reduce the differences between them but, by the end of August 2002, matters were once again coming to a head. Jarvis considered that the value of its works was under-certified to the extent of £1,618,253.95 (see letters of 27th August 2002 and 29th August 2002 at TB 8/1430 and 1433 to 1444). In the response to Jarvis' letter of 27th August 2002, Alstom (Mr Fossey, its Commercial Director) wrote on 28th August 2002 stating (inter alia) –
"… We both agree that the working contract is not the ITP [instructions to proceed] but the unsigned contract. This contract has no limit of liability, Jarvis will be reimbursed its costs, providing, of course, they are substantiated in accordance with the requirements of the contract…
As you are aware, the pain/gain arrangements of the subcontract are sharing Alstom's head contract pain/gain. Although we have had some movement in the Target Cost recently, the formula still produces the maximum pain of £1.5m with a proportionate share falling to Jarvis…"
(TB 8/1431 and 1432 – my emphasis)
In the letter of 29th August 2002, Jarvis (Mr Robson, its Divisional Director) dealt with each of the disputed figures, arguing its case with some particularity. This was a lengthy letter but the only part of which needs to be specifically noted is the section under the headings "General, Target Cost" which appear on its tenth and eleventh pages –
Prior to completion of the Works we repeatedly requested an update of the target cost. The following letters are a small extract of the correspondence on this subject.
Our letter dated 20 December 2001 reference 81362/ALSTOM/sj/L/1135 gave a forecast of our target cost in the sum of £12,528,140.00 and requested an urgent update. Our letter dated 8 February 2002 reference 81362/Alstom/sj/L/1180 again requested an increase in the target cost to take account of variations at that time.
In recent months we have been concentrating on providing justification and substantiation of our costs on this project. This emphasis was at your behest following our previous emphasis on providing substantiation for increasing the target cost. We acted on your assurance that we would be paid actual costs…..
Since then we have been forced to resort to formal methods to obtain payment of monies expended on this Contract. We gave formal notice of suspension on 11 February 2002 following your failure to honour the valuation certificate. This was then followed by a Notice of Adjudication on 15 April 2002 which again was as a result of your wrongful set off.
We are of the opinion that taking account of variations executed since our letter dated 8 February 2002; the target cost will now be greater that the costs expended to date.
We will therefore be re-concentrating our efforts on substantiating the amended target cost figure and will be submitting our update in the very near future. We will then be pleased to enter further negotiations regarding a pain/gain mechanism, which, as you are aware was one of the items left in abeyance in our Contract Documents.
(TB 8/1442 and 1443 – my emphasis)
A few days later Mr Robson replied to Mr Fossey's letter of 28th August 2002. In his response of 2nd September 2002, Mr Robson stated (inter alia) –
…… I do not accept that we have agreed to share with you the maximum pain of £1.5m within Alstom's contract, quite the opposite, since at least August 2001, I have refused to agree to such an arrangement. Will this be your next excuse not to pay us?......
I am currently considering all the options open to me included once again serving notice of adjudication…
(TB 8/1445 and 1446)
(3) Alstom issued a Payment Certificate No. 30 dated 19th September 2002. Jarvis disputed the amounts certified in a letter dated 27th September 2002 which included the following passage under the heading "Target Cost" –
We note from your letter dated 28 August 2002, that the unsigned Contract forms the Contract between Jarvis and Alstom. This document left the question of any pain gain mechanism to be agreed between the parties.
We also note from your letter that the "Contract has no limit of liability" and that "Jarvis will be paid its costs" provided that these are in accordance with the Contract.
In such circumstances the existence of a revised Target cost it may be argued as irrelevant in the absence of an agreed pain gain mechanism. We believe that the target cost is relevant in that in demonstrates that Jarvis actual costs are reasonable.
We enclose for your attention a copy of our letter dated 2 April 2002, again which received no meaningful response from yourselves. In this letter we confirmed our assessment of the projected Target Cost was £13,255,872.00.
This sum is considerably in excess of our current application in the sum of £12,840,423.00 currently claimed in our Application 31. This excludes additional works carried out since April 2002 for which we have received no formal instructions from yourselves.
These figures can come as no surprise to you as the Target Cost was regularly updated and sent to you for comment. To date we have received no comment from you with regard to the numerous updates sent to you since the commencement of this project.
and the letter concluded with the following statement –
… We consider that you have not administered this Contract correctly. We have no confidence that decisions made by you will be made in a fair and reasonable manner and believe that your decisions should be reviewed by an independent third party. You should take this letter as Notice that we will be proceeding to Adjudication.
(TB 8/1455 and 1456)
In response to this letter Alstom gave notification that, in the future it would "… be applying the pain/gain formula to interim payments made to Jarvis…" (see letter dated 30th September 2002 at TB 8/1457 to 1458).
(4) on 31st October 2002, Eversheds (acting on behalf of Jarvis) sent a second Notice of Adjudication to Alstom (see TB 8/1463 to 1479 and see also 1480 to 1492 for the notification to Mr Chapman and the Railtrack Adjudication Rules). In this second Notice of Adjudication, Jarvis dealt with the sub-contract in the following way-
…5 Following a two stage tender process Jarvis commenced work in about January 2000 pursuant to a contract agreed by the parties based upon the documents set out below ("the Contract"). Although the Contract is unsigned, Alstom agreed in a letter of 28 August 2002 that the working and operative contract is the unsigned contract.
6. The Contract consists of the following documents:
6.1 The Subcontract Agreement
6.2 The General Conditions of Subcontract published in 1997 by the Institution of Chemical Engineers, which may be modified or supplemented by any Subcontract's Special Conditions in Schedule B
6.3 The Subcontract Specification…..
6.4 The following Schedules:
Schedule A: Main Contract particulars (which may include Special Conditions)
Schedule B: Subcontract Special Conditions (if any) applicable to the Subcontract
Schedule C: Description of Subcontract Works
Schedule D: Site facilities, materials, services and other things to be supplied by the Contractor. Access to Site.
Schedule E: Price Rates and Charges.
Schedule F: Terms of payment
Schedule G: Times for completion
Schedule H: Documentation for approval
Schedule I: Take-over procedures
Schedule J: Performance tests and procedures
Schedule K: Liquidated damages:
(i) lateness in completion;
(ii) shortfalls an performance
Schedule L: Final documentation and manuals
Schedule M: Quality assurance system
Schedule N: Limitations on Sub-Subcontracting
7. By Clause 45.1 of the Contract, as amended, any party to the Contract can refer a dispute or difference (other than a matter as to which a decision is provided by the Contract to be final and conclusive) to adjudication in accordance with the Housing Grants, Construction and Regeneration Act 1996 and any adjudication shall be undertaken in accordance with the Railtrack PLC Adjudication Rules (March 1998 Edition v.1) ('the Railtrack Application Rules' a copy of which is supplied with this Notice)……
(TB 8/1465 and 1466)
(5) Alstom issued a Payment Certificate No. 31 dated 1st November 2002 which showed a deduction of £750,000 against the side heading "Jarvis Pain/Gain Share" and it also showed an additional contra-charge in the sum of £81,000. The certificate indicated on its face an overpayment to Jarvis of £733,245.53 (see TB 8/1494). The legitimacy of these deductions was challenged by Jarvis in its letter of 5th November 2002 (see TB 8/1497 and 1498).
It is beyond doubt – and not in contention – that the notion of a pain/ gain share was in the contemplation of the parties at the time when Alstom and Jarvis embarked upon discussions that finally resulted in the Contract being. For a 'notion' to become a contractual term upon which significant liabilities may rely, a degree of certainty as to the operation and extent that I do not find present in the Contract as formed between the parties. To my mind, the parties were still negotiating the precise terms of the pain/gain arrangements at the time the Contract was formed and these negotiations were never concluded – I suspect because it became evident to the parties that in reality it would at best be a pain/pain arrangement.
At the second hearing, I was taken to numerous documents by Counsel from which I was to be asked to determine when the Sub-Contract was formed. As the Editors of Chitty Ed 28 point out, the exact time of the formation of a contract that is the subject of progressive negotiations is often difficult to determine. However, in this case, I am relatively confident in finding that the document sent to Jarvis and dated 30th August 2001 was the final agreement between the parties governing their commercial relationships in connection with the Sunderland Metro Project. The date of this document, i.e. 30th August 2001, is in my opinion, the date when sufficient certainty did exist as to the terms and conditions to which the parties were obliged to comply. All essential terms were expressed with sufficient clarity. I consider Mr Bowdery's equating of a pain/gain mechanism to a 'bonus' payment or a LAD provision to be compelling and I find that such a matter is a non-essential term and not fatal to the Contract formation if it is missing from the agreement. The document issue was instigated by Alstom on or around the 30th August 2001 and constitutes the Alstom offer. Jarvis accepted this offer by its continued performance of the Contract.
The Contract document, which the parties agreed was a complete statement of the contractual rights and liabilities of the parties (Subcontract Agreement recital B), when read objectively and plainly, does not indicate that there was agreement as to the precise terms of any pain/gain sharing agreement between the parties. The words expressed in Schedule E5 were no more than an agreement to agree and, as such, are of no contractual consequence. The deletion of certain words from the original text of Schedule E5 is telling as to what the parties had agreed was not their common intent. The argument that the deletion was merely because the contract value proportions had changed from since 1999 did not sway my opinion as it would have been the simplest of amendments to change the ratio from 37% to a greater figure had this really been the intent of the parties. No additional words would have been required.
As for the ITP's, I do not consider detailed analysis of their status is necessary. Put simply, they were no more than interim and discrete agreements that limited Jarvis' expenditure pending the next ITP and the finalisation of the Contract proper and at that finalisation all ITP's ceased to have any significance.
I am not persuaded by the argument for implied term as put forward by Alstom. For a term to be implied it has to fulfil a number of rules as set out in the judgment of the Privy Council in BP Refinery (Westernport) Pty Ltd v. Shire of Hastings [1978] 52 ALJR 2. I find that these pre-conditions do not all exist in the present case, for example, I do not believe the implied term argued for is 'so obvious that it goes without saying'.
Consequently, in my judgment there was no pain/gain agreement contained within the Contract upon which Alstom could rely upon to deduct sums from the Jarvis Applications.
Having reached this decision, I need not concern myself further about the validity or invalidity of Certificate 31 and the timing of its issue.
(TB 11/1124 to 1125 – my emphasis)
As Mr ter Haar QC (who appears for Alstom) acknowledged, that although these proceedings are not formally appeal from Mr Chapman's decision, they are "in effect an appeal in reality" (see Transcript, Day 1, page 5, line 3). Whilst Mr ter Haar submitted that Mr Chapman had reached wrong conclusions for wrong reasons, Mr Bowdery QC (who appears for Jarvis and whose submissions Mr Chapman appears to have accepted) submitted that the Court would find it "difficult to improve upon the analysis provided by [Mr] Chapman".
(1) Mr Robson explained that shortly after he joined Jarvis he was briefed about the project. He was advised that draft sub-contract documents had been received under cover of Alstom's Mr Blakemore's letter 14th December 2000 (see paragraph 27 below). The difference of view between Alstom and Jarvis concerning the type of pain/gain mechanism to be included as part of the proposed sub-contract was explained to him and, in particular, the Jarvis position was explained to him in the way that he summarised it at paragraph 17 of his witness statement –
…… the Jarvis position on the incorporation of pain/gain into the sub-contract agreement was very clear to me:
- Jarvis had agreed in principle on a pain/gain mechanism;
- Jarvis had not accepted Alstom's proposals on how this mechanism was to operate or be implemented; and
- Any proposed pain/gain mechanism should be inextricably linked to the value of Jarvis' work.
(TB 1/228)
As a result of the briefing(s) he received, Mr Robson understood that although the Sub-Contract Agreement had not been signed, Alstom and Jarvis were:
"working to the unsigned Sub-Contract [with] for example, the applications for payment and certificates… being issued in accordance with the unsigned sub-contract".
(see paragraph 22 at TB 1/229)
(2) Mr Robson attended a meeting on 20th March 2001, the object of which was to review the then outstanding sub-contract matters and to provide an agreed programme to conclude the sub-contract. A document entitled "Notes/Action from meeting…" was prepared by Alstom and circulated on 22nd March 2001 (see TB 7/768 to 771 – see the citation at paragraph 30 below). An updated version of the document was prepared by Alstom and circulated on 30th April 2001 (see TB 7/818 to 823 – also cited at paragraph 30 below). At paragraph 28 of his witness statement, Mr Robson said of the meeting on 20th March 2001 –
I recall that at the meeting on 20 March 2001 Alstom was specifically asked to explain the arrangement as regards the pain/gain mechanism that was in place between Alstom and Railtrack, and Alstom's proposal as to how a pain/gain mechanism should operate as between Alstom and Jarvis. They were not able to do so. This is why the notes of the meeting….. indicate that further information on this issue was required from Alstom ……..
(TB 1/230)
and, after referring to the Notes of that meeting and the notes of a Railtrack/Alstom meeting which took place on 28th March 2001 (again cited at paragraph 30 below), he said at paragraph 32 of his witness statement –
Alstom were uncertain about the arrangement they had with Railtrack, and therefore were not able to put any proposals to Jarvis [during the period March through June 2001].
(TB 1/231)
(3) Dealing with the position following the publication of Mr Chapman's adjudication decision, Mr Robson stated at paragraph 56 of his witness statement, that Alstom had not made any deduction for "pain" but a substantial sum remained in dispute. Jarvis had made application for further sums but these had not been certified by Alstom (see TB 1/237).
(4) Mr Robson explained the very simple pain/gain mechanism which Jarvis proposed in the course of discussions with Alstom viz. 50:50 on pain and gain measured against the "Target Cost/Price" and he put this into the overall context of the ongoing discussions between Railtrack and Alstom (see Transcript, Day 2, page 83 to 90 and 130). Mr ter Haar attacked the accuracy of this part of Mr Robson's evidence but, subject to the one caveat which I mention below, I accept what he said. In this regard, two particular points should be noted. First, on two occasions Mr Robson referred to his having written a letter to Mr Irvine (see page 84, lines 19 to 23 and page 90, lines 3 to 9). No bundle reference was give for this letter during his evidence (or later), and I am not aware of seeing it at any time. It is possible that such a letter was written or it is possible that Mr Robson was mistaken in his recollection that Jarvis put forward its suggested pain/gain mechanism in a letter. That brings me to the second point, subject to an apparent inconsistency between earlier and later answers as to whether Jarvis had proposed unlimited or limit pain sharing, the substance of Mr Robson's evidence concerning the pain/gain mechanism suggested in discussions with Alstom is amply supported by the various (Alstom) manuscript notes of the meeting on 19th February 2002 to which I have already referred (see paragraph 12 above). In those circumstances, in my judgment, it matters little if he was mistaken in thinking that this had been specifically addressed in a letter – the fact is, it was addressed in the way that Mr Robson said - albeit, he did not give details of the proposed pain cap – merely saying that "pain would be capped at a certain level" (see page 90, line 8).
(5) Mr Robson explained that Jarvis was always confident that it could earn "gain" against "[its] own target costs" and that "right up until the Summer of 2001 Alstom [was] trying to convince [Jarvis] that [it was] into a gain situation" (see Transcript, Day 2, page 110).
(6) Mr Robson accepted that the suggestion made by Alstom, in the latter part of 2001, to abandon any "pain/gain" provision in the Sub-Contract was contingent on an agreement being reached with Railtrack to remove pain/gain from the main contract (see Transcript, Day 2, pages 137 to 140).
(7) Mr Robson accepted, as any commercial man in the industry would be bound to recognise, that:
"there is a world of difference commercially... between a pure cost reimbursable contract without any form of target cost or pain/gain arrangement, and a cost reimbursable contract which has an incentivisation mechanism built into it."
However, he did not accept that this was a case where there had been a fully reimbursable contract (see Transcript, Day 2, pages 141 and 142).
THE FACTS
THE FACTS
We write with reference to your telephone conversation with our Mr Mick Martin earlier today.
We hereby agree in principle to develop and negotiate with yourselves the works contemplated on a partnering basis, which will incorporate a mechanism for "pain/gain" share arrangement.
This will be achieved by establishing cost rates for services provided to which a fee for overheads and profit will be applied.
(TB 4/330 – my emphasis)
and by a letter dated 23rd September 1999 Jarvis' Operations Director Rail Projects (Mr Murdoch) wrote to Alstom's Mr Blakemore in these terms –
Following on from our meeting of Tuesday 21st September 1999, we have addressed those actions presented to us, and respond as follows:-
1) As requested, we have reviewed our rates in respect of plant, transport, portakabins, etc. This further investigation has only confirmed our comments at the meeting, that the rates are competitive, and are consistent with those negotiated with Railtrack, and as currently applied against the Level Crossing Partnership Contract, which is operated on an "auditable" open book basis. We are therefore unable to offer any reductions against these elements of our price.
2) I have discussed at length with our Commercial Director, your proposal for Jarvis to accept a subcontract, incorporating a pain/gain share payment structure. The proposal being that the Jarvis share of any pain or gain would be a product of the Jarvis subcontract price, expressed as percentage of the main contract price, which currently stands at approximately 40%.
I can confirm that we would be prepared to accept this proposal in principle, subject to agreeing a mutually acceptable mechanism for its administration and application.
I trust that we have interpreted your requirements correctly, however, should you require any further information or clarification, please do not hesitate to contact me.
(TB 4/331 – my emphasis)
We are writing in response to your request for Signalling and Telecommunications works at the above project. This letter and the documents herein form the basis of or offer to yourselves:-
Section 1 - Tender Agreement.
Section 2 - Itemised breakdown of our scope of works including material supply lists for telecomm and level crossings that are included within our offer.
Section 3 - The completed Contract Price Analysis for Pelaw to South Hylton and for Pelaw to Leamside. The prices within the CPA and our preliminaries build up are inclusive of 14.5% management fee and a further 0.75% to cover insurance's.
Section 4 - The completed Jarvis risk register, costed at optimistic, most likely and pessimistic.
Section 5 - A full and completed breakdown of Jarvis allowance for Project Management Site Establishment and Construction Plant.
Section 6 – A contract programme for the signalling works that reflects the outputs used in the production of our prices.
Section 7 – A description of the proposed methodology for performing the signalling and telecommunication work.
Section 8 – Completed Forms C and H sections of the tender evaluation data.
Section 9 – Jarvis Safety Case Information.
In acknowledging that Alstom's main contract conditions are based upon I Chem E Model form of Conditions of Contract for Process Plant, 1992 (Green Book), our subcontract tender is therefore based upon I Chem E Model form of Conditions of Subcontract, for Process Plant, Second Edition (Yellow Book).
Prior to award of contract we will need to agree mutually acceptable amendments to accommodate the details and scope of our subcontract.
However, for the avoidance of doubt, we would confirm the following:
- All design and works undertaken by Jarvis shall be on the basis of reasonable skill, care and diligence
- Jarvis shall not be liable for any indirect, consequential or un-insurable losses, howsoever arising
- Jarvis' liability in respect of liquidated and ascertained damages shall be limited to no more than 7.5% of the Jarvis contract price.
- Our current risk register is exclusive of monetary allowance relating the following contractual and commercial risks, such items are deemed included by yourselves:-
- Monies not recoverable by insurance
- Terms of Payment
- Cap on liquidated damages
- We would like further clarification on your position relating to "scope creep", for our risk register items, we have regarded all scope creep items as sub-contractor generated changes that are developed during the course of the works to deliver the project. All Employer/Client imposed changes howsoever caused shall be considered as a variation and reimbursed accordingly, (ie. cost plus the appropriate management fee).
We understand that you would like further dialogue relating to a "pain share gain share" agreement, we agree in principle with this idea based on the following understanding:-
1. Our Management fee is considered fixed against the scope of works defined in this document.
2. Any additional costs incurred against the risk register shall be reimbursed at our rates plus the appropriate management fee.
3. All scope creep or variation items shall be reimbursed at our rates plus the appropriate management fee.
4. The apportionment of risk and gain shall in principle be inextricably linked to the value of our works. This is subject to performance parameters being in place to protect each party's interests.
Our price for carrying out these works is £8,583,938.14 (Eight Million, Five Hundred and Eighty Three Thousand, Nine Hundred and Thirty Eight Pounds and Fourteen Pence) exc, VAT and exclusive of risk register costs (see section 4).
Whilst writing we would also like to confirm that a further 2.5% discount would be offered off both our Overhead Line Price and our Signalling Price if we were successful in securing both packages with Alstom.
We do hope we have interpreted your requirements correctly, in the meantime if you require any further information, please do not hesitate to contract the writer.
(TB 4/332 to 334 – my emphasis)
To my mind, a difference between Mr Middleton's views on the pain/gain issue as they were expressed in the formal tender and Mr Murdoch's views in his letter dated 23rd September 1999 is obvious. I do not accept Mr ter Haar's submission that the two letters can be read consistently on the basis that it is inherently unlikely that Mr Middleton would put forward something different from that which his superior had proposed on the previous day. In my judgment, that is exactly what he did and it was he, not Mr Murdoch, who played a prominent role in the negotiations which took place over the months and years which followed.
… that in an alliance, the pain/gain models will provide sufficient stimulus for timely completion and any onerous additional safe guards will only result in additional costs.
(TB 2/200)
It should, perhaps, also be noted that the Risk Register which Jarvis had submitted, as Section 4 of its tender, was subsumed into the overall Alstom Risk Register. It was the April 2001 revision of this overall main contract Risk Register which, in due course, was included in the Issue 3 documents (see Annex E4, TB 4/643 ff).
A meeting was fixed for 6th October 1999 to review tender progress and to consider (inter alia) contractual matters including "how we work the pain/gain share that [Railtrack] want [including liquidated damages]" (see TB 5/61). Manuscript notes of that meeting, which appear to be Alstom's notes (see TB 5/62 to 64), record very clearly the essential difference of view on the pain/gain issue –
JARVIS – Gain/Pain – limited to works under their control (run their own A/C)
…
Alstom want pain/gain on overall project – not as per Jarvis' share
(see TB 5/63 and 64)
The formal notes which Alstom prepared and which were issued on 12th October 1999 (see TB 5/77 to 80) expressed the matter in terms which were perhaps less direct –
ALSTOM expressed the need for Jarvis to be have the same mutual objectives as ALSTOM, supported by the right contract arrangements. ALSTOM believe that the best arrangement is for Jarvis to share pain/gain/liabilities in the ratio of the contract values. Jarvis were concerned that they lacked control outside of their contract, and felt a Jarvis specific incentivisation model could be created. ALSTOM explained the likely participation through the steering group, and the difficulties that further (currently 6 models in play) cost models would create. Jarvis are to reconsider.
It was mutually agreed to explore whether there are better contract formats (currently I Chem E Yellow Book), more suited to a partnering type subcontract.
The contract negotiations are to be concluded.
(TB 5/78 and 79 – my emphasis)
Q. Actual costs of sub-contractors and affiliates will be reimbursed whether working on site or elsewhere?
A. Discussion followed as to the relationship between Alstom and Jarvis. They are partners but formally sub-contractors and have avoided putting mark ups on which would normally [be] 10 – 15% which is a big saving …….
(TB 3/187 and 188)
I have also drawn specific attention to the Agreement of Outstanding Tender Issues dated 13th December 1999 which Alstom sent to Jarvis on 17th December 1999, earlier in this Judgment. It was sent in order that it could be discussed at the next planned meeting (see TB 3/205 to 211 and TB 4/414 to 421 – the date of "17/11/99" stated on the fax cover sheet at page 414 was obviously erroneous).
ACTION 5: Gain/Pain model Jarvis – 10.01.00
Jarvis to confirm that they accept the model as advised
by Jim Musker by e-mail dated 23.12.99.
(TB 4/428)
The e-mail itself was not included in Annex B1 of the Issue 3 documents but the spreadsheet which was attached was included (see TB 5/274 and 275; TB4/436). The pain/gain model was shown on the spreadsheet under the heading "Summary" –
Leamside | Sunderland Direct | |
Alstom / RT Contract | 11,003,114 | 7,354,317 |
Alstom Man Fee | 2,572,611 | 1,464,975 |
Jarvis % | 0.347 | 0.458 |
Jarvis Risk at P50 | 472,887 | |
197,648 | ||
Jarvis Target Price | 4,460,084 | 3,623,638 |
Jarvis Risk at P80 | 173,275 | |
20,284 | ||
Jarvis GMP | 4,633,358 | 3,848,023 |
Pain Gap Leve | 5,083,455 | TBA |
On 4th January 2000 Jarvis (Mr Farmer) was addressing the matters which had been raised at the meeting on 21st December 1999. In an e-mail he asked Alstom to forward (inter alia), "Synopsis of Model Particulars for Alstom pain/gain share", ending his e-mail with an apology if anything he was requesting had already been sent (see TB 4/430). Apparently, the main matter which Mr Farmer was addressing at that time was the division of Jarvis' price between the Sunderland Direct Works and the Leamside Works (see TB 4/430 to 435). There is nothing in the documents later included in Annex B1 of the Issue 3 documents which would suggest that Jarvis did in fact positively confirm acceptance of the gain/pain model, which Mr Musker had forwarded, by 10th January 2000 or at all. In my judgment, the fair inference to be drawn is that the model was received by Jarvis; that Jarvis noted it as Alstom's current proposal; and that no comment on it was sent back to Alstom.
Jarvis have reviewed the pain/gain share model enclosed with the Alstom letter dated the 2nd February 2000. It appears to us that the model is still to be finalised.
The model appears to be very complex and therefore we have reservations with regard to the actual operation of the model. Jarvis would like for a working model demonstration to be issued using "best" and "worst" case scenarios and theoretical figures/calculations. This process should then remove any doubt as to the precise mechanism/working and implementation of the model. In addition, the model appears to only address the pain/gain share with respect to the main contractor(s) relationship with Railtrack and not sub-contractors of the main contractor(s).
We must, therefore, inform Alstom that we reserve our position on this matter and standby on our previous comments that any pain/gain share should be based purely on those parts of the project that are directly in our control.
(TB 4/480 – my emphasis)
Alstom's letter dated 2nd February 2000 was not included in Annex B1 in Issue 3 of the draft sub-contract documents. It is included in the chronological bundles (TB 5/345 to 376). The enclosed pain/gain share model was the earlier version of Mr Irvine's internal note (see TB 5/358 and 359).
- Jarvis are in agreement in principle
- Proposal: Jarvis = ALSTOM x 6
Gain/Pain Gain/Pain 17
- Based on ratio of contract values (37%) as at 28 April 2000
- Jarvis to respond by 5 May 00
(TB4/485 – my emphasis)
There is nothing in the documents later included in Annex B1 of the Issue 3 documents which would suggest that Jarvis did in fact respond to Alstom's proposal by 5th May 2000 or at all. In my judgment, the first bullet point indicates that there had been agreement in principle that the sub-contract would have a term dealing in some way with the gain/pain issue but the second bullet point is to be read disjunctively. In other words, Alstom made a specific proposal but Jarvis did not signify its agreement to that proposal. Jarvis was to go away and consider the specific proposal, responding to it within the next two days. The minutes of the meeting were not produced until 10th May 2000, some five days after the response had apparently been expected. In my judgment, the fair inference to be drawn, assuming in Alstom's favour that the minute taker had not misunderstood what was said in regard to a response, is that no response or no formal response was made by Jarvis. Furthermore, for whatever reason, at the time Alstom did not follow upon the specific proposal with Jarvis in order to extract a positive response.
Matters to be resolved prior to finalising the Contract between us.
Agreement of target cost and risk register.
Final Issue Signature of Subcontract Agreement.
Once these matters are agreed it is ALSTOM's ……….. intention that they will be contained in the Contract
(TB 4/524)
Subject: Jarvis Scope and Target Price
Jim,
David Wood has advised me that we do not have an agreed target price with [Railtrack].
I am about to use the £6,480,128.96 agreed figure with Jarvis in the subcontract and will require a requisition to support this figure in addition to the last one raised by the ITP up to the value £2.4m.
Please confirm that I can go ahead with this figure and therefore send a requisition for £6,480,128.96 stating clearly on the requisition that it replaces previous requisitions issued (please list the requisition numbers).
I propose that I suggest the following gain/pain mechanism which is based on the agreement obtained at the meeting between [Alstom] and Jarvis on the 3.5.00 in York:-
Jarvis = ALSTOM x 6
Gain / Pain Gain / Pain 17
Based on a ratio of contract values (37%) as at 28 April 2000.
Please see the attached schedule E annex E5:-
Do you agree with the above schedule. I know it has flaws in terms of our Pain Gain, however, please suggest any acceptable alternative?
(TB 6/682)
The attached Annex E5 to Schedule E of the proposed draft Sub-Contract documentation read –
Gain / Pain Mechanism
1.0 The Gain / Pain share shall use the basic definitions and principles described within the ITT – Section A, Binding 1, dated July 1999, Clause 61 Schedule of amendments to the Special Conditions and General Conditions.
2.0 The allocation of the Gain / Pain Share between the Contractor and Subcontractor shall be based on the principles agreed during the meeting dated 3rd May 2000, between the Contractor and the Subcontractor in York (see Annex B1 – Post Tender Amendments between the Contractor and the Subcontractor item 35).
Jarvis = ALSTOM x 6
Gain / Pain Gain / Pain 17
(Based on a ratio of contract values (37%) as at 28 April 2000.)
3.0 The gain shall be paid where the Agreed Final Actual Cost is less than the Agreed Final Target Price subject to 5.0 below.
4.0 Where the Agreed Final Actual Cost exceed the Agreed Final Target Price but is less than the Agreed Final Maximum Price, the excess shall be shared by the same percentages as detailed in 2.0 above.
5.0 The full amount of any gain shall be released in full providing Completion on time has been achieved (21st September 2001).
Should completion be up to one month late (1st October 2001) then any gain shall be reduced by one third.
Should completion be up to two months late (1st November 2001) then any gain shall be reduced by two thirds.
Should completion be over two months late then no gain shall be paid.
6.0 In summary, the Subcontractor shall be entitled to a share of any gain or excess in accordance with the formula set out in 2.0 above, providing the same position applies to the Contractor in the contract with the Employer.
(TB 6/684 and 685)
and, on 14th December 2000 it was Mr Blakemore who signed the letter under cover of which the draft Sub-Contract documents were sent out (TB 6/687 and 688). He referred in that letter to the "pain/gain mechanism proposal … contained in Annex E5". (my emphasis) He asked Jarvis to review and confirm its acceptance of the document by return.
You are aware that we have a number of queries on this document as outlined in the meeting in our York Office yesterday, we understand you are considering such matters and look forward to receiving your comments in due course.
In the meantime we attach a duly authorised copy of your facsimile dated 6th October 2000, which can now be included in the aforementioned Sub-Contract Agreement.
Should you have any further queries please do not hesitate in contacting the undersigned.
(TB 4/526)
The areas of debate at the meeting held in Jarvis' York office on 10th January 2001 are apparent from the e-mail which Mr Blakemore sent to Mr Middleton on 12th January 2001 (see TB 6/698 and 699). He dealt with the pain/gain issue at item 7 as follows –
7. Pain / Gain percentage on [Jarvis] S/C only – Additional wording has been inserted in Annex E5 as follows:
at the end of clause 2, insert – "The allocation shall apply to the Subcontract only between the Subcontractor and the Contractor and shall be based on the agreed final Target Cost".
(TB 6/698-9 – my emphasis)
Jarvis' "main comments" on the wording of the draft Sub-Contract documents were sent by Mr Jackson (Jarvis' site commercial manager) to Mr Blakemore on 31st January 2001 (see TB 6/718 and 719 – and see 716 for the pie charts). He dealt with the proposed "Schedule E5 Pain Gain Mechanism" by stating -
After the allocation relationship 2.0 we need to add in "The overall Alliance Pain/Gain is as detailed on the attached Pie Charts as agreed at the Alliance Board Meeting dated 11/9/00" … I have a copy of this at site, however it is in colour Barry Blakemore also has a copy dated 11/9/00. I have asked David Wood to send it to you and me.
(TB 6/719)
Further to my e-mail of 22nd January 2001, listing outstanding issues relating to the Subcontract I understand that we have addressed and agreed to the Engineering scope and responsibilities (point 3) and the words to be inserted in Schedule E., Clause 3.4 – Leamside (point 4).
We have remaining two outstanding points (The Collateral Warranty with Railtrack and the Parent Company contract Performance Guarantee and the Pain / Gain Mechanism), which I feel should be carried out in parallel with the signing of the Subcontract, both parties having a clear understanding and commitment to resolve both issues to conclusion within 30 days and the Subcontract can be varied accordingly. I can re-issue the Subcontract with a supporting letter inserted in the appropriate places.
The Collateral Warranty with Railtrack and the Parent Company Contract Performance Guarantee. This actions remains with yourselves. Please advise the position?
The pain / gain mechanism - I suggest that we have a further discussion and I shall arrange a meeting accordingly.
I will update the Subcontract to issue 2.0 and scope to issue 3, reflecting the changes agreed. I will send two fully numbered copies for you to sign under seal and return to the undersigned.
Please confirm your acceptance of the above proposal and I shall despatch copies accordingly.
(TB 7/731 and 732)
Jarvis' reply came in a lengthy letter from Mr Middleton dated 14th February 2001.
With reference to your letter dated 9th February 2001 and our telephone conversation yesterday, my comments are as follows:-
I agree that this whole process has taken up a disproportionate amount of time, however, I believe this is due to the hybrid nature of the Contract. In an effort to finalise mattes I set out below what I understand to be the current status of the outstanding matters to be agreed between us. …..
Annex E5 Pain/Gain Mechanism
You are completely aware of our position on this matter in that any pain / gain arrangement would only apply to this Sub-Contract your e-mail dated 12th January 2001 confirms this.
We must also agree a cap on any pain arising from the operation of this Sub-Contract, we understand you have achieved this within the Main Contract. Obviously the status of the Risk Register impacts upon this issue. …….
(TB 7/736 to 738 – my emphasis)
Annex E5 – Pain / Gain Mechanism
After a brief explanation ALSTOM to issue a copy of the Information on Pain / Gain together with detailed wording to support the Pie Charts.
Action David Wood
Action Jarvis to respond to the principles of Pain / Gain.
(TB 7/771)
In an undated letter which is at TB 7/777 and 778, and which appears to have been sent in late March or early April 2001, Mr Middleton wrote to Mr Blakemore stating that he was awaiting pain/gain mechanism proposals. On 28th March 2001 Alstom had a commercial meeting with Railtrack. The minutes of this meeting were forwarded to Mr Robson of Jarvis. So far as the "pain/gain" issue was concerned, the minutes record that it was not discussed because it was "being addressed in other forums" (see TB 7/784).
On 5th April 2001, Alstom's Mr Wood e-mailed Mr Blakemore saying –
Action 8 Annex E5 – Pain / Gain Mechanism. At this point in time the mechanism is under review / negotiation, and therefore we need some words that will allow us to agree post contract, wording similar to those in our contract with Railtrack.
(TB 7/790)
and, it was almost a month later before, on 30th April 2001, Mr Blakemore sent a collation of responses to the points which had been raised on 20th March 2001. This was done in an updated version of the earlier "notes/actions" document (see TB 7/819 to 823). In that response Alstom said –
Annex E5 – Pain / Gain Mechanism
After a brief explanation ALSTOM to issue a copy of the Information on Pain / Gain together with detailed wording to support the Pie Charts.
Action David Wood
Due to the changes in the Alliance members, a review of the mechanism is underway with Railtrack. WE suggest that words are entered into the Subcontract Agreement similar to the main contract to reflect the intention of the parties to agree a suitable pain / gain mechanism. ALSTOM shall advise the exact details as soon as available.
Action Jarvis to respond to the principles of Pain / Gain.
(TB 7/822 – my emphasis)
In a letter of 21st May 2001 Jarvis stated again that it was awaiting Alstom's "pain/gain" proposals for comment (see TB 7/841 to 843). Things had not moved forward by the end of June 2001. Discussions were held on 28th June 2001 which Mr Musker summarised in an e-mail dated 29th June 2001 in the following way –
The Jarvis objective of the discussion was to resolve issues preventing signing of the contract plus Jarvis EOT claim.
Present:- Peter Middleton, Alan Robson, Bob Thomas, Steve Jackson, Barry Blakemore, Dave Wood and myself.
- Gain/Pain sharing and Appendix A materials are the only two contractual issues unresolved. Both can be recorded as reserved matters to enable the contract to be signed.
- We explained where we were up to in receipt of our David Holmes letter and 20 PMI's.
- We explained that we are going through the AFC process and needed their input.
- Hopefully ALSTOM come out of it with gain share
- We offered Jarvis the opportunity to look at our ALSTOM overall price build up and for Jarvis to convince themselves that ALSTOM is likely to earn gain share.
- We explained that we were hoping to achieve a 50/50 gain share with Railtrack now that there is no formal Alliance gain share.
- Set a target for ALSTOM to agree 50/50 gain sharing and Jarvis to be convinced of ALSTOM likely to achieve gain share by end of July. Any later is meaningless as the "horse will be close to crossing the line", too late to participate in gambling.
- Jarvis have engaged a claims specialists (Peter Slater) for their EOT claim. We agreed to use him to help us prepare our own EOT claim.
- We discussed safety and quality
- Jarvis are still resource limited and Alan Robson took the action to look at it again.
- Overall the meeting went well, and I think that Jarvis are likely to sign up to gain and pain sharing by the end of July.
(TB 7/889 – my emphasis)
It should also be noted that during these months Alstom issued a fourth ITP dated 25th May 2001. This was said to supersede the third ITP which had been issued on 6th October 2000. The authorised expenditure was increased to £5,400,000. At paragraph 3 of this ITP it was said –
Matters to be resolved prior to finalising the Contract between us.
Final Issue Signature of Subcontract Agreement.
Outstanding items detailed on the Actions List, viz.
a) Action 5: Annex B2 – Collateral Warranty
b) Action : Schedule C; Annex C1 – Scope of Works, Clause 9
c) Action 8: Schedule E; Annex E5 – Pain/Gain Mechanism.
Once these matters are agreed it is ALSTOM's …….. intention that they will be contained in the Contract.
(TB 4/534 to 536)
This ITP was countersigned by Mr Middleton on 29th June 2001 and returned to Alstom.
Further to our meeting of the 28th June, we have the following information with regards to ALSTOM's "Gainshare" position with Railtrack.
ALSTOM are now of the opinion that no incentivisation mechanism is likely to be agreed with Railtrack and suggest that reference to this is the Subcontract is removed including any reserved matters relating to the Subcontract.
Please confirm your acceptance to this proposal.
We are preparing to issue the revised issue 2.0 of the Subcontract earlier next week for signature. Please contact the undersigned if you have any queries ……
(TB 7/899- my emphasis)
That letter obviously came as a surprise to Jarvis' Mr Middleton. He immediately telephoned to discuss it and he suggested a further meeting with Alstom (see TB 7/901). The proposed meeting was delayed because of holiday arrangements – see Mr Blackmore's letter of 13th July 2001 which concluded –
In the meantime if you could give some thought to the 'incentivisation' issue, it would be appreciated. As you will be aware ALSTOM have no firm indication from Railtrack that 'incentivisation' is still on the 'table'.
(TB 7/905)
and Mr Middleton's letter of 18th July 2001 (TB 7/935). On 30th July 2001, Jarvis (Mr Robson) wrote expressing concern at the company's perceived financial exposure (see TB 7/955 and 956).
It was agreed that the proposed agenda for Thursday's meeting, namely Target Cost Pain/Gain share is a worthless exercise. Jarvis have yet to submit their prolongation claim that is a key element of the overall assessment of their FCAC [Final Cost Anticipated Completion]. Alstom need to have a level of comfort with Jarvis' FCAC before we can progress with confidence…
The issues considered for discussion are as follows:
……
- Pain/Gain – Jarvis need to understand that Alstom will not agree to a Pain/Gain arrangement unless we have confidence with Jarvis' figures. Validation of Jarvis' prolongation claim is a precursor to progressing discussions.
- We do not declare to Jarvis our commercial position with Railtrack; whilst they may know our position they do not know our strategy.
- Current Alstom/Jarvis subcontract position:
RT24 with I Chem E Yellow Book
Pain/Gain principle in spirit but no commercial obligation to fulfil this requirement, particularly if we cannot agree a 'back to back' arrangement with Railtrack; this is the driver…
Proposed agenda:
……
- Target Cost Pain/Gain position; cannot go forward until we have confidence in Jarvis' figures – key to achieving closure with Railtrack. Pain/gain split to review once Alstom have confidence in figures. Do we want to review the current pain/gain split for the balance of the works in excess of the original contract sum?...
(TB 7/998 and 999)
Action 8 Annex E5 – Pain/Gain Mechanism remains unchanged pending the agreement to Action 4 from the meeting of the 23rd August. (I have proposed deletion of most of wording in the Subcontract with the exception of the principles of Pain/Gain in 1.0 Annex E5).
(TB 7/1043)
and it can be seen that paragraph 2 onwards of the Version 2 text of Annex E5 (which was a slightly modified version of the original proposed text which I have cited at paragraph 27 above) was transparently deleted. Paragraph 1 of the text was retained, and a new paragraph was added with the result that the effective text was that which I have set out at paragraph 7 above. When I come to deal with the contractual/construction arguments it will be necessary to consider also a number of the other terms of the Issue 3 documents (see paragraphs 48 to 50 below).
Sub-Contract Agreement remaining unsigned – Both parties have been progressing the actions raised at our meeting 23 August 2001. All issues to be addressed by Alstom from the meeting have been responded to with the exception of the extension of time. This item has and is currently being actively pursued with Railtrack to ensure a meaningful response.
(TB 8/1096)
In his turn, Mr Robson then responded in a friendly way to Mr Taylor (see TB 8/1107).
It is of considerable concern that at this late stage of the works the Contract is still not signed. Whilst there are a number of minor areas of differences between us, the main difference appears to be the basis of the Pain/Gain Mechanism included in Annexe E5 of Schedule E.
In view of the situation regarding your failure to extend the completion date it is arguable that in the absence of an agreed Pain/Gain mechanism we are entitled to be reimbursed all reasonable costs irrespective of whether or not a revised target cost has been agreed or not.
From the above it can be clearly seen that there are a number of critical issues which should be addressed at the very highest level within your Company. We would therefore suggest that following our joint meeting with Railtrack on Tuesday 16 October we should set out a clear basis upon which we may resolve our differences.
(TB 8/1117 – my emphasis)
On 12th October 2001, Mr Robson wrote to Mr Irvine expressing similar sentiments (see TB 8/1134 and 1135). This letter was followed by a telephone discussion, the substance of which was recorded in an exchange of further letters on 17th (Mr Robson) and 22nd (Mr Irvine) October 2001 (TB 8/1140 to 1144). In his letter Mr Robson said –
TARGET COSTS
You confirmed progress had been slow on your behalf increasing our target cost due to a lack of progress between yourselves and Railtrack. However, you had an assurance from Railtrack that this would be addressed immediately and in return you would address our target costs. A meeting has been arranged with your goodselves for Thursday 1st November by which time you will have substantially increased our Target Cost.
CONTRACT AGREEMENT
Due to the time that has elapsed there is little likelihood of us agreeing with you, and you agreeing with Railtrack a meaningful Pain/Gain mechanism. In the light of this, both parties need to go forward with a proposal to recover our costs plus overheads and profit, this item to be discussed at our meeting (01.11.01).
(TB 8/1140 – my emphasis)
and in reply, to those sections of Mr Robson's letter, Mr Irvine said –
Target Costs
I do not recall agreeing to "substantially increase" your Target Cost by the time we next meet – however all PMI's agreed with Railtrack that relate to Jarvis scope will result in the corresponding increase in your Target Cost, and we shall continue to address prolongation costs.
Contract Agreement
Agreed.
(TB 8/1142 – my emphasis)
We have now progressed this contract near to completion and yet our contractual position with yourselves remains incomplete 20 months into the contract. Though we have made good recent progress on PMI's, a number still remain undecided or have no financial value assigned to them.
The original intention of the contract was to have an over-arching alliance agreement involving all the original members of the project on Sunderland Direct. As you know this has never been implemented because of change in the project membership, though I think we would agree that the spirit of alliance working has prevailed. Nevertheless, we are formally still trying to agree a target cost at a point when the project is near to completion, and a similar position exists in our relationship with Jarvis. The whole basis of target cost contracting is to set goals early in the project which by joint effort can be achieved for the benefits of all. Both Jarvis and ourselves have now concluded that the time to realistically enact a target cost contract has now passed and it is no longer the appropriate vehicle for the completion of Sunderland Direct.
Alan Robson of Jarvis and myself have therefore agreed to a joint approach to yourself with the aim of establishing an emerging cost contract in place of the target cost arrangement still within the basic RT24 contract. We believe this to be the only approach which gives us a realistic contractual vehicle for the successful financial conclusion of this project…
(TB 8/1145 and 1146 – my emphasis)
The letter received an unsympathetic response from Railtrack on 31st October 2001 which included the following paragraph –
We have a contract with Alstom which is not a joint venture between yourselves and Jarvis. This contract is a partnering contract with a GMP this legal agreement is unaffected by the status of the alliance.
(TB 7/1176)
1.0 Contract
1.1 Alstom had written to Mr Solomon of Railtrack, requesting a meeting to discuss various contractual issues. This had received a negative response. In addition to this, Mr Solomon had written with regard to Alstom's claim submission and had suggested that the claim was "spurious".
1.2 In view of this Alstom confirmed that they had carried out an internal commercial review where it had been suggested that a more contractual approach was to be adopted.
1.3 Alstom confirmed that in view of the large number of changes on the project and the fact that they considered time was at large. The contract had reverted to cost reimbursable contract.
1.4 This position had been tentatively broached with Mr Solomon who had rejected this argument and had confirmed that in his view the original contract was still in existence. Alstom confirmed that the basis of their contractual approach was as follows:
- The pain/gain mechanism, which formed the basis of their original offer, was no longer in operation.
- As there was no longer an Alliance board, the original mechanism which operated the pain/gain recovery was no longer available.
- Without a pain/gain clause in operation, Alstom's legal people had suggested that the contract had now moved on to a cost reimbursable contract.
- There was still a variation process where extras to the contract were required to be separately identified. However, variations were no longer able to be sanctioned by the Alliance board. This resulted in the final decision being made by Faithful & Gould, which was causing major problems.
1.5 Jarvis queries this on the basis that if the contract moved to cost reimbursable, what then would happen with the management fee – Cost could be interpreted as net cost – the fee and profit recovery may well be at risk if this method was considered. Alstom agreed to let Jarvis have a look at their legal opinion.
1.6 There was a general query over whether or not the employer could seek credit on a cost reimbursable contract. Jarvis confirmed that there did appear to be grounds where the client would not be required to pay for defects etc.
1.7 Jarvis confirmed that their own costing system was transparent and in the event that the contract moved towards this method of recovery, they were confident that all their costs could be substantiated.
1.8 Despite the attractiveness of this method of recovery of both Jarvis and Alstom, it was however unlikely that Railtrack would agree to this, especially under the current "political" climate.
1.9 Alstom considered that the strength of their argument was that their contract was with the Alliance board. In reality the Alliance board had never been formed and had in fact, never met.
(TB 8/1199 and 1200 – my emphasis)
Mr Robson wrote to Mr Irvine on 5th November 2001 to confirm various of the matters raised at the meeting on 1st November 2001. In that letter he dealt with the issue of "contractual arrangements" in these terms –
Both parties are still of the opinion that it would be inappropriate to have a contract at this late stage with a pain/gain mechanism. Although there is reluctance on behalf of Railtrack to deal jointly with Alstom and Jarvis it was agreed that we still feel this is the best way forward and we should pursue this through our own individual contacts within Railtrack.
(TB 8/1179)
Mr Robson wrote to Mr Irvine on 27th November 2001 (see TB 8/1214 and 1215) to confirm various of the matters raised at the meeting on 22nd November 2001. In that letter he dealt with the issue of "contractual agreement" very shortly, by recording that it had been agreed that he would "meet with John Meacock/Robin Gisby" [I believe these gentlemen were Jarvis' Railtrack contacts]. It seems that, at the meeting Alstom had stated that its legal department was "reviewing the contract to advise whether contractually [it could] proceed on the contract under a fully reimbursable philosophy" and that Alstom had said it would inform Jarvis of the advice given by 30th November 2001 (see TB 8/1221).
Alstom Certificate No |
Total Certified £ |
Date |
ITP Date and Value |
17 January 2000 £200,000 |
|||
86,199 | |||
2 | 259,848 | 12 June 2000 | 08 June 2000 £700,000 |
3 | 393,353 | 30 June 2000 | |
4 | 455,002 | 31 August 2000 | |
5 | 555,095 | 5 October 2000 | 6 October 2000 £2,400,000 |
6 | 865,702 | 7 November 2000 | |
7 | 983,560 | 22 November 2002 | |
8 | 1,210,637 | 22 November 2002 | |
9 | 1,482,048 | 12 January 2001 | |
10 | 2,218,836 | 12 January 2001 | |
11 | 2,625,610 | 19 February 2001 | |
12 | 3,301,706 | 29 February 2001 | |
13 | 4,196,602 | 18 April 2001 | |
14 | 4,904,604 | 11 May 2001 | 25 May 2001 £5,400,000 |
15 | 5,411,933 | 20 June 2001 | |
16 | 6,069,509 | 31 July 2001 | |
17 | 6,740,338 | 30 August 2001 | 28 August 2001 £8,651,232 |
18 | 7,317,907 | 18 September 2001 | |
19 | 8,270,988 | 8 October 2001 | |
20 | 9,291,822 | 14 November 2001 | 9 November 2001 £9,500,000 |
21 | 9,625,466 | 14 December 2001 | 13 December 2001 £10,250,000 |
22 | 10,716,277 | 05 January 2002 | |
23 | 10,823,095 | 22 February 2002 | |
24 | 10,731,353 | 8 March 2002 | |
25 | 10,776,195 | 25 March 2002 | |
26 | 11,445,556 | 3 May 2002 | |
27 | 11,476,601 | ||
28 | 11,349,974 | ||
29 | 11,439,988 | 19 August 2002 | |
30 | 11,607,166 | 19 September 2002 | |
31 | 11,634,631 | 1 November 2002 |
THE SUB-CONTRACT
(1) By a letter dated 31st January 2002 [cited at paragraph 11 above] ALSTOM offered to contract upon the terms of the unsigned Sub-Contract [the Issue 3 documents] subject to incorporation of a pain/gain mechanism referred to herein.
(2) The offer contained in the letter dated 31st January 2002 was accepted by Jarvis by the service by them on 15th April 2002 of a Notice of Adjudication [see paragraph 12(1) above] relying upon the terms of the unsigned Sub-Contract;
(3) Alternatively, the offer was accepted by Jarvis by the service by them of a second Notice of Adjudication dated 31st October 2002 [cited at paragraph 12(4) above];
(4) Alternatively at least after the date of the letter of 28th August 2002 [see paragraph 12(2) above], both parties have acted upon the basis that they are bound by the terms of the unsigned sub-contract and both parties are now estopped from denying that they are so bound.
(TB 1/9)
Jarvis' case, which is at paragraphs 12, 13 and 14 of the Defence, can perhaps not unfairly be said to be a variant of the alternative described by Alstom at (4) above. What Jarvis said at paragraph 12 was -
Following a two-stage tender process Jarvis commenced work in about January 2000 pursuant to a contract agreed by the parties based upon the documents set out below ("the Contract"). Although the Contract is unsigned, Alstom agreed in a letter of 28 August 2002 that the working and operative contract is the unsigned contract.
What followed at paragraphs 13 and 14 made it clear that Jarvis was referring to the Issue 3 documents which it did not receive until the end of August 2001 (see again paragraph 34 above). Accordingly, as Mr ter Haar rightly observed in the course of argument, Jarvis did not in fact commence work in January 2000 "pursuant to …" those documents. However, although paragraph 12 was not expressed as clearly as it might have been, I think that, when read in context, the pleader's intention to allege agreement to retrospectively operating terms may be discerned.
THE PRIMARY CASES
B. The Subcontract as hereinbefore defined constitutes a complete statement of the contractual rights and liabilities of [Alstom and Jarvis] in relation to the Subcontract Works and no negotiations between them nor any document agreed or signed by them prior to the date of the Subcontract in relation to the Subcontract Works shall hereafter be of any contractual effect
C. Both [Alstom and Jarvis] agree that they shall not be entitled to enforce or otherwise rely on any contractual term or condition which is not contained or incorporated expressly in this Subcontract. …..
D. [Alstom and Jarvis] hereby agree that any pre-contractual representations or warranties, whether made orally or in writing, shall be of no legal effect whatsoever, with the result that neither party shall be entitled to found any claims to damages in reliance thereon.
(TB 3/6 and 7)
So far as payment was concerned, Clause 39.1 of the General Conditions provided –
39.1 [Alstom] shall pay [Jarvis] for the Subcontract Works and the total of the sums payable shall constitute the Subcontract Price. The sums payable shall be calculated in accordance with the provisions of Schedule E (Prices, rates and charges) and paid in accordance with the provisions of Schedule F (Terms of payment).
(TB 3/40)
In Schedule E the Sub-Contract Price was to be "… determined by the application of the rules in this Schedule" and "… as set out in Annex E3 – "Target Cost Summary" (see Clauses 1.1 and 1.2 at TB 4/554). At Clause 3.1 of Schedule E it was provided –
3.1 [Jarvis] has agreed to participate in the Alliance Pain / Gain mechanism. The principles are based on details contained in the Post Tender Amendments in Schedule B – Subcontract Special Conditions, Annex B1 – Post Tender Amendments between [Alstom] and [Jarvis].
The percentages of the pain / gain mechanism are set out in Annex E5-Pain / Gain Mechanism.
(TB 4/555)
Turning to the Annexures themselves, included within Annex E3 was a detailed "Target Cost Reconciliation" which showed a "Revised Target Cost as at 13th September 2000" in the sum of £6,840,128 (see TB 4/623 to 638). It would seem that significant increases in the scope of the Sub-Contract works had occurred over the year that had elapsed since Jarvis' original tender had been submitted and further development had been anticipated when that document was prepared. Included within Annexure E4 was a copy of the Main Contract Risk Register in the revised form in which it had been agreed between Railtrack and Alstom in March 2001 (see TB 4/645 to 652). Annex E5 dealt with the pain/gain mechanism itself – in terms which I have already set out (see TB 4/655 and 656 and see paragraph 7 above). It did not, in fact, contain "percentages" as Clause 3.1 envisaged it would.
On behalf of Alstom, Mr ter Haar drew attention to Annex B1 to Schedule B and to various parts of Schedule E, including, in particular, Clause 3.1 and Annex E5. On behalf of Jarvis, Mr Bowdery concentrated his attention on the second paragraph of Annex E5.
(1) Unequivocal agreement in principle to the incorporation of a "pain/gain" share term;
(2) Jarvis being informed of the development of the main contract "pain/gain" scheme between October 1999 and December 1999 and Jarvis being informed of the later discussions between Railtrack and the Alliance members which seem to have focussed much more on "gain" than "pain". If Mr Irvine's updated internal note is correct (TB 7/1048 to 1050 and see paragraph 2 above), these discussions may have resulted in an amendment to the gain sharing provisions but pain sharing provisions either remained unchanged or, if they had not been regarded as finally agreed in December 1999, they were firmed up as being the agreement;
(3) Specific proposals were made by Alstom for the "pain/gain" share term which it considered should be included in the Sub-Contract but, there was no acceptance by Jarvis of those specific proposals. Within the scheduled documents Jarvis' reservations were most clearly expressed in the attachment to the e-mail of 27th April 2000 (see paragraph 22 above). Mr ter Haar put great emphasis on the terms of the minute of the meeting held shortly thereafter on 3rd May 2000 when Alstom repeated the proposals which had previously been made. However, there is nothing in the scheduled documents which shows Jarvis' subsequent agreement to those previously rejected and then repeated proposals. I reject the suggestion that the exchanges concerning the "Alliance Gain Share and Charter" (see paragraph 24 above) were Jarvis' positive response to those repeated proposals; and, I note that the ITPs that were issued in 2001, including the fifth ITP issued on 28th August 2001, state that the pain/gain mechanism was an outstanding item that needed to be resolved (see paragraphs 23, 30 and 33 above).
1.0 The Pain/Gain share shall use the basic definitions and principles described within the ITT – Section A, Binding 1, dated July 1999, Clause 61 Schedule of amendments to the Special Conditions and General Conditions.
Details of the Pain/Gain Mechanism are to be reviewed and agreed in accordance with Action number 5 from the meeting dated 23rd August 2001. Once agreed by both parties the details will be added to the Subcontract Agreement as an amendment.
2.0 The allocation of the Pain/Gain share between the Contractor and Subcontractor shall be based on the principles agreed during the meeting dated 3rd May 2000, between the Contractor and the Subcontractor in York (see Annex B1 Post Tender Amendments between the Contractor and the Subcontractor).
Jarvis = ALSTOM x 6
Pain/Gain Pain/Gain 17
(Based on a ration of contract values (37%) as at 28 April 2000).
3.0 The gain shall be paid where the Agreed Final Actual Cost is less than the Agreed Final Target Price subject to 5.0 below.
4.0 Where the Agreed Final Actual Cost exceed the Agreed Final Target Price but is less than the Agreed Final Maximum Price, the excess shall be shared by the same percentages as detailed in 2.0 above.
5.0 If the Final Target Price is exceeded then the Subcontractor shall be paid "proven" net cost only.
6.0 The full amount of any gain shall be released in full providing completion on time has been achieved (1st September 2001).
Should completion be up to one month late (1st October 2001) then gain shall be reduced by one third.
Should completion be up to two months late (1st November 2001) then the gain shall be reduced by two thirds.
Should completion be over two months later then no gain shall be paid.
6.1 The above completion dates are based on the agreed programme and shall be subject to any extensions granted hereto, or any such entitlement to an extension whereby an overall delay has occurred not caused by the Subcontractor. The completion dates shall be changed to reflect such amendments agreed between the Contractor and pro rata accordingly.
(TB 4/655 and 656)
So far as Schedule E is concerned, three points are to be noted. First, it records that Jarvis had agreed "to participate in the Alliance pain/gain mechanism…" but when the two operative passages of Annex E5 are read together, it is clear that the method of participation had yet to be agreed. Secondly, the wording of both Clause 3.1 and Clause 1 of Annex E5 was inelegant. Clause 1 sensibly referred to definitions at Clause 61 of the Particular Conditions of the Main Contract (see TB 3/215 to 221) but there were no relevant principles to be found in Clause 61 – arguably they were to be found in Clause 62 and in the development of the tender proposals which was recorded in paragraph 5 of the Agreement dated 13th December 1999 (see paragraphs 4 and 5 above). Clause 3.1 was worded in a way that can fairly be said to be either premature or inaccurate – the drafstman assumed detailed agreements would be found at Annex B1 and Annex E5 when, in fact, such agreements had yet to be made. Thirdly, reference was made in the second paragraph of Annex E5 to the notes of the meeting of 23rd August 2001 to identify the time when the parties had reached the agreement to review/agree/and later add in the Pain/Gain mechanism. The notes of the meeting were not included in Annex B1 (or elsewhere in the Issue 3 documents). There were no documents post-dating the meeting which contained an agreement on the pain/gain mechanism; the only document post-dating the meeting included in Annex B1 which addressed the issue was the fifth ITP which included an express statement that "pain/gain" remained outstanding (see TB 4/537 to 540 – and see paragraph 33 above).
….
(2) Even if the parties have reached agreement on all the terms of the proposed contract, nevertheless they may intend that the contract shall not become binding until some further condition has been fulfilled. That is the ordinary 'subject to contract' case.
(3) Alternatively, they may intend that the contract shall not become binding until some further term or terms have been agreed; see Love and Stewart v. Instone, where the parties failed to agree the intended strike clause, and Hussey v. Horne-Payne, where Lord Selborne said, at p.323:
'…The observation has often been made, that a contract established by letters may sometimes bind parties who, when they wrote those letters, did not imagine they were finally settling the terms of the agreement by which they were to be bound; and it appears to me that no such contract ought to be held established, even by letters which would otherwise be sufficient for the purpose, if it is clear, upon the facts, that there were other conditions of the intended contract, beyond and besides those expressed in the letters, which were still in a state of negotiation only, and without the settlement of which the parties had no idea of concluding any agreement. (Lloyd L.J.'s emphasis).
"(4) Conversely, the parties may intend to be bound forthwith even though there are further terms still to be agreed or some further formality to be fulfilled (see Love and Stewart v. Instone per Lord Loreburn at p.476).
(5) If the parties fail to reach agreement on such further terms, the existing contract is not invalidated unless the failure to reach agreement on such further terms renders the contract as a whole unworkable or void for uncertainty.
(6) It is sometimes said that the parties must agree on the essential terms and that it is only matters of detail which can be left over. This may be misleading, since the word 'essential' in that context is ambiguous. If by 'essential' one means a term without which the contract cannot be enforced then the statement is true; the law cannot enforce an incomplete contract. If by 'essential' one means a term which the parties have agreed to be essential for the formation of a binding contract, then the statement is tautologous. If by 'essential' one means only a term which the Court regards as important as opposed to a term which the Court regards as less important or a matter of detail, the statement is untrue. It is for the parties to decide whether they wish to be bound and, if so, by what terms, whether important or unimportant. It is the parties who are, in the memorable phrase coined by the Judge: "the masters of their contractual fate". Of course more important the term is, the less likely it is that the parties will have left it for future decision. But there is no legal obstacle which stands in the way of the parties agreeing to be bound now while deferring important matters to be agreed later. It happens every day when the parties enter into so-called 'heads of agreement'…"
([1987] 2 Lloyds Rep at page 619)
Mr Bowdery relied particularly on the second, fifth and sixth of Lloyd LJ's principles, submitting that they were relevant to the facts and circumstances of this case. In his submission, the parties' enthusiasm for a pain/gain share arrangement ebbed and flowed as the project developed and it could not be said that a pain/gain arrangement was an essential requirement for either party. As he summed it up - the unsigned sub-contract could work and did work without a pain/gain agreement; it did so during the lengthy negotiations; and, during the latter part of 2001 both parties had contemplated moving forward without any pain/gain term forming part of their agreement. He suggested that in such circumstances, far from being fundamental, a pain/gain agreement should be considered an "inappropriate embellishment to this sub-contract". And, he submitted that when what the parties had left to be agreed was an appropriate pain/gain mechanism, it was unnecessary, unreasonable and beyond the Court's powers to intervene by determining and imposing a pain/gain mechanism. In this context, he relied upon the observation of Lord Ackner in Walford v Miles [1992] 2 AC 128. That was a case where Plaintiffs had agreed, "subject to contract" to purchase a company and the premises from which it traded. The Defendants decided to break off negotiations. The Plaintiffs alleged that, so long as the Defendants continued to desire to sell the business/property, they were legally bound to continue to negotiate with them in good faith. The House of Lords disagreed. The only speech was that of Lord Ackner who dealt with the general principles in this way -
"The reason why an agreement to negotiate, like an agreement to agree, is unenforceable, is simply because it lacks the necessary certainty. The same does not apply to an agreement to use best endeavours. This uncertainty is demonstrated in the instant case by the provision which it is said has to be implied in the agreement for the determination of the negotiations. How can a court be expected to decide whether, subjectively, a proper reason existed for the termination of negotiations? The answer suggested depends upon whether the negotiations have been determined "in good faith". However the concept of a duty to carry on negotiations in good faith is inherently repugnant to the adversarial position of the parties when involved in negotiations. Each party to the negotiations is entitled to pursue his (or her) own interest, so long as he avoids making misrepresentations. To advance that interest he must be entitled, if he thinks it appropriate, to threaten to withdraw from further negotiations or to withdraw in fact, in the hope that the opposite party may seek to reopen the negotiations by offering him improved terms. Mr. Naughton, of course, accepts that the agreement upon which he relies does not contain a duty to complete the negotiations. But that still leaves the vital question – how is a vendor ever to know that he is entitled to withdraw from further negotiations? How is the court to police such an "agreement?" A duty to negotiate in good faith is as unworkable in practice as it is inherently inconsistent with the position of a negotiating party. It is here that the uncertainty lies. In my judgment, while negotiations are in existence either party is entitled to withdraw from those negotiations, at any time and for any reason. There can be thus no obligation to continue to negotiate until there is a "proper reason" to withdraw. Accordingly a bare agreement to negotiate has no legal content."
[1992] 2 AC at page 138
So far as material, Clause 45 of the Special Conditions provided –
45.1 Any party of this Subcontract can refer a dispute or difference (other than matter as to which a decision is provided by the Subcontract to be final and conclusive) to adjudication in accordance with the Housing Grants Construction and Regeneration Act 1996…..
45.3 Subject to the above any dispute or difference which arises between the parties shall be referred to the High Court of England and Wales for resolution as business of the Technology and Construction Court ["TCC"].
(TB 4/297 – my emphasis and my addition of the abbreviation)
This was the clause that gave the Court that power and it should be exercised by "applying the principles set out in Schedule B Annex B1 and the provisions of Schedule E" (see paragraph 53 of his written submissions).
Mr ter Haar submitted that because the sub-contract had been performed, this case was properly analogous with F&G Sykes (Wessex) Limited v. Fine Fare Limited [1967] Lloyds Rep 53. In that case the Court had declined to hold that the parties' failure to reach agreement on an important matter – the numbers of fowl to be supplied after the end of the first year of a long term supply contract – had the result that there was no binding contract after the end of the first year. The contract contained an arbitration clause which provided in very wide terms for references to be made in respect of any "differences" which might arise. As Lord Denning MR succinctly summed the matter up –
The provision that figures were to "be agreed" does not nullify the contract. It can be made certain by reasonable figures being ascertained by an arbitrator.
[1967] 1 Lloyds Rep at page 58
and, as Danckwerts LJ put it (after he had read the arbitration clause) –
The word "differences" seems to me to be particularly apt for a case where the parties have not agreed: Viscount Dunedin said, in the case which was quoted to us of May and Butcher, Ltd. v. The King[1934] 2 KB 17n: "… a failure to agree… is a very different thing from a dispute." But it seems to me that the word "difference" is particularly apt to describe that situation… the [terms] of this arbitration clause… seem to me to be sufficiently wide to cover a difference of the kind which has arisen in this case. The arbitrator has jurisdiction to decide the matter referred to him as to what is a reasonable amount for the defendants to have given notice of and which the suppliers should be in a position to supply…
[1967] 1 Lloyds Rep at page 60.
… at such price not being less than [£12,000] as may be agreed upon by two valuers one to be nominated by the lessor and the other by the lessee and in default of such agreement by an umpire appointed by the… valuers
The tenant gave the required notices and nominated its valuer. The landlords refused to nominate a valuer with the result that the price fixing machinery could not operate. The majority of the House of Lords overruled earlier Court of Appeal authorities which precluded the Courts' stepping in where the parties had agreed on a particular price fixing machinery. The majority held that, in essence, the option contracts provided for the tenant to purchase the reversion at an objectively fair and reasonable price; that the machinery for fixing that price was a subsidiary and non-essential term of the contract; and, that on the breakdown of the agreed machinery for establishing the price, the Court could undertake the necessary inquiries. Lord Fraser of Tullybelton explained this matter in this way –
I recognise that the logic of the reasoning which had led to the courts' refusing to substitute their own machinery for the machinery which has been agreed upon the parties. But the result to which it leads is so remote from that which parties normally intend and expect, and is so inconvenient in practice, that there may in my opinion be some defect in the reasoning. I think the defect lies in construing the provisions for the mode of ascertaining the value as an essential part of the agreement. That may have been perfectly true early in the 19th century, when the valuer's profession and the rules of valuation were less well established that they are now. But at the present day, these provisions are only subsidiary to the main purposes of the agreement which is for sale and purchase of the property at a fair or reasonable value. In the ordinary case parties do not make any substantial distinction between an agreement to sell at a fair value, without specifying the mode of ascertaining the value, and an agreement to sell at a value to be ascertained by valuers appointed in the way provided in these leases. The true distinction is between those cases where the mode of ascertaining the price is an essential term of the contract, and those cases where the mode of ascertainment, though indicated in the contract, is subsidiary and non-essential: see Fry of Specific Performance, 6th ed. (1921), pp. 167, 169, paragraphs 360, 364. The present case falls, in my opinion, into the latter category. Accordingly when the option was exercised there was constituted a complete contract for sale, and the clause should be construed as meaning that the price was to be a fair price…
([1983] AC at page 483E-G)
"… What other reasons could there be for making such elaborate provisions, emphasising its long term nature? At the present day, in cases where the parties have agreed on an arbitration or valuation clause in wide enough terms, the Courts accord full weight to their manifest intention to create continuing legal relations. Arguments invoking alleged uncertainty, or alleged inadequacy in the machinery available to the Courts for making contractual rights effective, exert minimal attraction…
…..
In accordance with the approach adopted in those cases, their Lordships have no doubt that here, by the agreement, the parties undertook implied primary obligations to make reasonable endeavours to agree on the terms of supply beyond the initial five-year period and, failing agreement and upon proper notice, to do everything reasonably necessary to procure the appointment of an arbitrator. Further, it is implicit in a commercial agreement of this kind that the terms of the new price structure are to be fair and reasonable as between the parties. That is the criterion or standard by which the arbitrator is to be guided. If there are cases where the true meaning of the contract is that the arbitrator is to aim, not at objectively fair and reasonable terms, but merely at some result which appeals to him subjectively, they must be rare indeed and the present is certainly not one of them. The statements of basic intention in the recitals and in Cl. 9.1, together with the detailed pricing provisions for the first five years, supplement the ordinary implication of a fair and reasonable test. They lay down broad guidelines as to the object to be achieved; and how the system has worked during the first five years is likely to provide the arbitrator with much help in determining what is fair and reasonable for later periods.
([1989] 1 Lloyds Rep at page 210 – my emphasis)
"… [the provision] contains what are clearly intended to be words of obligation: "Owners shall be indemnified"; "such increase to be calculated". This is not tentative: it is a liability which is capable of calculation. If the legal effectiveness of this provision is to be attacked it must be because, in truth, the liability is not capable of calculation or assessment and therefore is too vague or too uncertain to be the subject of a legally enforceable obligation…
…..
However,… I do not consider it right to categorise the provision as merely an agreement to agree. The words of a contract are used objectively to state the intention of the parties to the contract. They may do so skilfully or clumsily, but the function of the Court is to extract from the words used their objective intention. The words of this paragraph do not disclose an intention merely to require an agreement. The words "to be mutually agreed" are directory or mechanical and do not represent the substance of the provision…"
(see [1988] 2 Lloyds Rep at page 111)
and, in dismissing the appeal, Bingham LJ (as he then was) said –
"… I ask this question: Does the provision in issue in this case relate to an essential term of agreement or to the existence of any contract at all, or does it relate to a subsidiary and non-essential question of how a contractual liability to make payment according to a specified objective standard is to be quantified ? I consider that this provision falls plainly in the second category.
The substantial provision in sub-cl. (4) is that the –
… Owners shall be indemnified by way of increase of hire, such increase to be calculated…
The procedure for calculation is in my judgment a matter of machinery, and I conclude that there was here a binding obligation to which effect can be given as a matter of contract."
([1988] 2 Lloyds Rep at page 115)
He also accepted the owners' secondary submission, based on the Sykes case, that any defect in the provisions was cured by the arbitration clause which enabled any lack of agreement to be overcome (see again, page 115 of the report).
"69. In my judgment the following principles relevant to the present case can be deduced from these authorities, but this is intended to be in no way an exhaustive list:
Each case must be decided on its own facts and on the construction of its own agreement. Subject to that:
Where no contract exists, the use of an expression such as "to be agreed" in relation to an essential term is likely to prevent any contract coming into existence, on the ground of uncertainty. This may be summed up by the principle that "you cannot agree to agree".
Similarly, where no contract exists, the absence of agreement on essential terms of the agreement may prevent any contract coming into existence, again on the ground of uncertainty.
However, particularly in commercial dealings between parties who are familiar with the trade in question, and particularly where the parties have acted in the belief that they had a binding contract, the Courts are willing to imply terms, where that is possible, to enable the contract to be carried out.
Where a contract has once come into existence, even the expression "to be agreed" in relation to future executory obligations is not necessarily fatal to its continued existence.
Particularly in the case of contracts for future performance over a period, where the parties may desire or need to leave matters to be adjusted in the working out of their contract, the Courts will assist the parties to do so, so as to preserve rather than destroy bargains, on the basis that what can be made certain is itself certain. Certum est quod certum reddi potest.
This is particularly the case where one party has either already had the advantage of some performance which reflects the parties' agreement on a long term relationship, or has had to make an investment premised on that agreement.
For these purposes an express stipulation for a reasonable or fair measure or price will be a sufficient criterion for the Courts to act on. But even in the absence of express language the Courts are prepared to imply an obligation in terms of what is reasonable.
Such implications are reflected but not exhausted by the statutory provision for the implication of a reasonable price now to be found in s. 8(2) of the Sale of Goods Act, 1979 (and, in the case of services in s. 15(1) of the Supply of Goods and Services Act, 1982).
The presence of an arbitration clause may assist the Courts to hold a contract to be sufficiently certain or to be capable of being rendered so, presumably as indicating a commercial and contractual mechanism, which can be operated with the assistance of experts in the field, by which the parties, in the absence of agreement, may resolve their dispute."
([2001] 2 Lloyds Rep at pages 89/90 – my emphasis)
When he turned to consider the facts of the case itself, he said –
73. In my judgement, the 1993 contract should be viewed as a contract for a fixed period of 10 years and a term should be implied that in the absence of agreement reasonable fees should be determined for the period after 1994……
(v) The contract does not expressly state that the fee after the end of 1994 is "to be agreed". It is simply silent as to what is to happen in that period. Therefore, this case is simply not presented with the difficulties which arise, in the face of "to be agreed" language, where it is uncertain whether there is any contract at all. It cannot be said as was said in May and Butcher v. The King, that the statutory implication of a reasonable price, or an implication that the fee should be such reasonable fee as the arbitrator may decide, is excluded by express agreement that the parties were to agree the figure.
(vi) There is no evidence that the resolution of a reasonable fee would cause any difficulty at all. On the contrary, the evidence is the other way… In the absence of evidence to the contrary, I would infer that it was perfectly possible to derive from the agreements of price and price increases over the years objective criteria for working out a reasonable fee. Thus, although it is true to say that the contract itself contained no mechanism or guidance (other than the arbitration clause) as to how a reasonable fee would be derived. I do not consider that the contract should fail on that ground. Contractually derived criteria or guidance may be of assistance in finding an implied term for a reasonable price: but the authorities indicate that the Courts are well prepared to make the implication even in their absence.
(vii) I do not consider that the additional issues as to the length of any period of price revision or as to quantity discounts, raise any different problems. In practice agreement was made for one or two years. I see no difficulty in an arbitral tribunal or Court finding that that was a reasonable period for which to fix the fee. The discount for throughput above a certain figure is simply another factor of price. Again, it gave the parties no difficulty over the years.
(viii) The presence of an arbitration clause was not relied on as a particularly strong point by Mr Howard. But I do not think that it is without its effect. It is a contractual mechanism for resolving "any dispute… which cannot be amicably resolved". It involves the parties' autonomous choice of their tribunal. It seems to me to be apposite to deal with a lacuna which, in common with other contracts which have to provide for future events, commercial practicalities lead parties to leave unresolved at the time of contract…"
([2001] 2 Lloyds Rep at pages 91/92)
The Issue 3 documents contained an unequivocal agreement to participate in pain/gain sharing to an extent and in a manner which had yet to be agreed. In my judgment, the commercial cases to which Mr ter Haar referred and which I have specifically cited above indicate the principles which are to be applied in a case such as this. Once parties have contracted, the commercial considerations which need to be weighed are quite different from those which fall to be considered when negotiations are broken off before a transaction is agreed or before performance of a project is commenced. When the very different factual contexts of Walford v. Miles and the Queensland Electricity cases are taken into account the observations of Lord Ackner and the observations of Sir Robin Cooke can both be accepted.
In this case by Clause 45.3 of the Special Conditions of the Sub-Contract, the parties expressly gave the TCC power, in terms more usually found in an arbitration clause, to determine any "differences" as well as any "disputes" which might arise (see paragraph 54 above for the text). In this regard, I respectfully adopt the final paragraph observations which are to be found in paragraph 69 and the further observations in paragraph 73(viii) of Rix LJ's judgment in Mamidoil. These observations are, I think, equally applicable where the parties have chosen a Court as their preferred final arbiter.
In my judgment, it is the reasoning of Sir Robin Cooke and not that of Lord Ackner that should apply in this case viz. when agreeing to be bound by the Issue 3 documents, Alstom and Jarvis undertook implied primary obligations to make reasonable endeavours to agree on the pain/gain provisions by which Jarvis would participate in some way in the Main Contract pain or gain. Neither party could thwart the agreement by refusing to negotiate in good faith and/or by refusing to allow an Adjudicator or a TCC Judge to resolve the matter. It is implicit in the agreement that the standard by which the Adjudicator or TCC Judge is to be guided is fairness and reasonableness as between the parties. If each party has negotiated in good faith but neither has been persuaded to accept the other's view and there has been no compromise, the Adjudicator or Judge is the person who is entrusted to decide what would be a fair and reasonable mechanism which should apply. If one party refuses to negotiate, the other has an effective remedy because the Adjudicator or Judge can be invited to consider the facts/matters/arguments which it wishes to put forward, together with whatever facts/matters/arguments the previously reluctant party may elect to bring forward at that stage, before deciding what would be a fair and reasonable mechanism which should apply. Quite obviously, in performing such a task, the Adjudicator or Judge may have to choose between a number of possible solutions, each of which could be said to be fair and reasonable but, that is something which he (or she) has been specifically empowered to do by the parties. It was the parties themselves who decided to contract on the terms of the Issue 3 documents, rather than refraining from contracting unless and until they had reached agreement on the particular outstanding issue(s)
In the course of his submissions, Mr Bowdery placed great weight on the various statements made by Alstom on and after 28th June 2001, all of which I have included in my summary of the facts at paragraphs 30 to 38 above. However, when each of those statements is considered in the overall context they do nothing to undermine the point made in the previous paragraph. Furthermore, the commercial realities were readily acknowledged by Mr Robson during the course of his cross-examination – see Transcript, Day 2, pages 137 to 140 to which I have referred at paragraph 14(6) above.
63. Whilst, as I have said, agreement in principle existed from the outset, it is equally true to say that practically from the outset – see manuscript notes and typed minutes of the meeting of 6th October 1999 to which I have referred at paragraph 19 above - there were different views as to the manner in which effect was to be given to it. Was it to be dealt with in the manner Alstom favoured viz. a direct proportion of whatever "gain" Alstom might achieve or whatever "loss" Alstom might suffer being passed on ? Or, was it to be dealt with in the manner Jarvis favoured viz. a formula based on and referable to the sub-contract value which would, so Jarvis thought, give it greater control over its own destiny ? If I approach the matter by asking myself the rhetorical question posed by Bingham LJ in the Didymi (rather than concentrating on the Advice of the Privy Council in Queensland Electricity as I did at paragraph 61 above), my answer to that question is this –
the provision(s) in issue in this case relate to subsidiary/non-essential questions; the procedure for calculation of the gain or pain is a matter of machinery. If the Courts (or an arbitrator) can determine the reasonable numbers of fowl which a supermarket chain could require and which the suppliers should be able to supply (Sykes), new base prices and new price variation provisions for coal to be supplied to an electricity generator (Queensland Electricity), an equitable increase in a charter-party hire rate in the light of variation in speed and/or fuel consumption (the Didymi) and appropriately revised handling fees for crude oil movement (Mamidoil), I can see nothing to prevent the Court considering and resolving the difference or differences between these parties concerning the precise mechanism by which, in some meaningful way, Jarvis should participate in the scheme of gain sharing or pain sharing which was agreed as part of the Main Contract. In my judgment, as I have already said at paragraph 61 above, in a case such as this, agreement in principle carried with it an implication that the terms of participation should be fair and reasonable as between the parties; and, that constitutes a sufficiently objective basis upon which an Adjudicator or TCC Judge can act.
In any event, Alstom's suggestion that the level of Jarvis' participation should be linked to the final account figures, rather than the tender figures, does not seem to me to be particularly fair or reasonable. Alstom and Railtrack fixed the maximum main contract "pain" by reference to the tender figures. There was no suggestion that the figure itself should be adjusted upwards or downwards depending on the levels of the adjusted "Target Cost/Price" and "Gross Maximum Cost/Price" when compared with the "Final Cost/Price". The cost/price levels at which "pain" might begin to be felt were variable but the potential maximum amount of pain to be suffered was not. Accordingly, if (contrary to my views) it were to be held that Jarvis' participation in pain sharing should be calculated as a simple proportion of whatever pain Railtrack became entitled to inflict, and which Railtrack did inflict under the terms of the Main Contract, the fair and reasonable proportion to be passed on should be 6/17. This was the proportion Alstom proposed in May 2000 and again in December 2000. This would place Jarvis at risk of being required to contribute (a) £88,235.29 towards the £250,000 which Alstom stood at risk of having to pay if the "Final Cost/Price" came in at £500,000 above the adjusted "Target Cost/Price" and (b) a further £441,176.47 towards the £1,250,000 which Alstom stood at risk of having to pay if the "Final Cost/ Price" came in at the pain cap level (i.e. £1,250,000 above the adjusted "Target Cost/Price" plus £500,000). The total of these two pain component figures is £529,411.76. Before passing away from this aspect of the case, it is convenient to mention that Alstom did not involve Jarvis in the negotiations and the commercial compromise it made. Accordingly, as I have already indicated at paragraph 9 above, in my judgment, neither what was said in the course of the negotiations between Railtrack and Alstom that lead up to the "Contract Amendment Agreement" of May 2003 nor the Agreement itself can bind or in any way adversely affect Jarvis.
(1) to decide now upon the fair and reasonable mechanism by which, in my judgment, Jarvis should participate in the Main Contract pain (or gain) sharing; or
(2) to invite the parties to consider/reconsider their respective positions in the light of the indications which I have now given and the fact that I have rejected major parts of each of their pleaded cases.
I do not think it would be appropriate for me to proceed on basis (1) without first inviting the parties to address me in relation to (2) above. In my view, the parties should be afforded the opportunity to agree upon a mechanism which each of them would consider fair and reasonable. In the alternative, if no agreement is reached, either or both parties should have the opportunity to make further (brief) submissions, before I determine the difference for them. If agreement is not reached, once I have heard and considered any further submissions that either party wishes to make (and the other's response thereto), I would expect to issue a short addendum to the judgment determining the outstanding difference for them.
THE SECONDARY CASES
If, contrary to my to my conclusion, it were to be held that the Sub-Contract is unenforceable for the reason stated at paragraph 22 of the Particulars of Claim then, save in the two respects which I mention below, the facts alleged by Alstom in support of the allegation that Jarvis' entitlement was to payment on a Quantum Meruit, are made out. At paragraph 7(2)(b)(ii) of the Particulars of Claim the original Main Contract "gain" term is not correctly described – see paragraph 5 above for the term which was then proposed/agreed. Paragraphs 7(4) and 8 of the Particulars of Claim contain an incomplete statement of the parties' understanding over the period that Alstom's tender was being negotiated with Railtrack and when the contract was made between Alstom and Railtrack. The pleader fails to acknowledge the important fact that the basic difference concerning the method by which Jarvis should participate in pain/gain sharing, was already identified - see paragraphs 17 to 22 above for a fuller statement of the facts. When Alstom contracted with Railtrack it may have hoped that, in due course, Jarvis would come to accept pain/gain participation in the terms it had proposed but, there was no such "understanding" with Jarvis upon which Alstom could reasonably be said to have "relied". In my judgment, Alstom's claim that the Quantum Meruit calculation should take into account its preferred "pain/gain" mechanism because it contracted with Railtrack at a time when it was relying upon an understanding with Jarvis that Jarvis would participate in pain/gain sharing in that way, fails on the facts.
I do not accept that a quantum meruit basis of remuneration would recognise and take into account pain/gain participation in the manner or to the extent that Mr ter Haar submitted it should. However, I do not accept Mr Bowdery's submission that no account at all could ever be had to the overall financial result which Alstom achieved under the Main Contract with Railtrack. In my judgment, when computing the amount that should reasonably be paid, the rates/prices upon which the parties themselves had agreed, would be the obvious and only starting point. Notice should be taken that those rates were intended to be established as sub-contract rates/prices in a sub-contract which would provide for the sub-contractor's participation in pain/gain sharing. In my judgment, the law of restitution is possessed of flexible principles which permit the Courts to achieve substantial justice in any given case. In this case, I can see no reason why factual and/or expert evidence would not be admissible to address the following issues if either or both were raised. If Jarvis were to seek remuneration on an effectively risk free basis, it might be thought that adjustments should be made to some or all of the rates/prices to make appropriate allowance for the fact that the original rates/prices had taken into account the possibility of gain and the risk of pain. Alternatively, it might be thought that some appropriate adjustment should be made to the total "final cost/price" calculated on the basis of the original rates/prices to reflect any financial gain or detriment to Alstom arising from the manner in which Jarvis had performed the works. Assuming, as Alstom alleges it has suffered the maximum Main Contract pain, arguably the value of Jarvis' work to Alstom might be less than it would have been if no pain had been suffered. On the other hand, if Alstom had been in receipt of some significant gain, it would seem to me equally arguable that the value of Jarvis' work would be greater. The facts would need to be investigated in detail to see the part which Jarvis had played in the overall works and the extent to which its performance had impacted on the overall performance (see generally the observations of Slade and Bingham LJJ in Crown House Engineering v. AMEC Projects Limited (1989) 48 BLR 37 at pages 54 and 57 to 58).
CONCLUSION
A declaration that the Sub-Contract between the Claimants and the Defendants contained an agreement to share "pain and gain" as contended in paragraphs 19 or 20 or 21 above alternatively that the price to be paid to the Defendants for the work done by them is to be calculated taking into account a share by the Defendants of the "pain" suffered by the Claimants under the contract between the Claimants and Railtrack PLC."
(TB 1/17)
In view of my findings, a modified declaration will be appropriate – the parties are invited to consider the form of the declaration they would wish to see in view of my conclusions that –
(1) at some time in 2002, Alstom and Jarvis concluded a Sub-Contract in the terms of the Issue 3 documents;
(2) by Clause 45.3 of the Special Conditions of the Sub-Contract, Alstom and Jarvis agreed that any "differences" which might arise should be finally resolved by the Court;
(3) whilst Jarvis unequivocally agreed that the Sub-Contract should include a mechanism by which it would participate in "pain/gain sharing", no agreement has been reached between Alstom and Jarvis as to that said mechanism;
(4) Alstom was and is entitled to invite the Court to determine this outstanding difference but the Court considers it appropriate to invite further submissions from the parties before making its determination.
11th May 2004
COLIN REESE Q.C.
(Recorder – sitting as a Deputy Judge of the Technology and Construction Court)