QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
In The Matter Of The Arbitration Act 1996
And In The Matter of An Arbitration
____________________
(1) B.R. Cantrell(2) E.P. Cantrell | Claimants | - and - |
Wright & Fuller Limited | Respondent |
____________________
Mr Darryl Royce appeared for the respondent instructed by Jackaman Smith & Mulley, Oak House, Northgate Street, Ipswich, Suffolk, IP1 3BX, DX: 3229 Ipswich, Suffolk, IP1 3BX (Ref: PBS/CJC/1W669-1) appeared for the respondent.
Date of Hearing: 6 June and 4 July 2003
____________________
Crown Copyright ©
SUBJECT MATTER
Validity of Final Certificate issued outside time limits provided for by contract, clauses 30.8 and 30.9 of the JCT Standard Form of Contract, 1980 edition, construction of conclusive evidence clauses and the Final Certificate, application of Penwith District Council v VP Developments Ltd.
DECISION
The appeal is allowed, the certificate was not the Final Certificate in form, substance or intent.
This judgment was made in writing and was handed down by the court. For the purposes of paragraph 5.12 of 52PD-19 (Practice Direction - Appeals), this written judgment is to be taken as replacing an official recording and approved transcript of the judgment.
INDEX
Section | Subject Matter | Paragraph |
1. | Introduction | 1-9 |
2. | Background Facts Submissions of Parties, | 10-30 |
3. | Award and Questions of Law being Appealed | 31-78 |
3.1 | Dispute | 31-32 |
3.2 | Issues in the Arbitration | 33-34 |
3.3 | Submission of Parties - Issues 1 and 2 in the Arbitration | 35-41 |
3.3.1 | Claimants' Submissions in the Arbitration | 35-38 |
3.3.2 | Respondent's Submissions in the Arbitration | 39 |
3.3.3 | Submissions as to the Form of the Certificate | 40-41 |
3.4 | Scope of the Award | 42-49 |
3.5 | Award | 50-52 |
3.6 | Claimants' Grounds of Appeal | 53-59 |
3.7 | Respondent's Rely | 60-62 |
3.8 | Questions of Law for Determination in the Appeal | 63-78 |
3.8.1 | Difficulties Confronting the Court in Hearing the Appeal | 63 |
3.8.2 | Questions of Law | 64-68 |
3.8.3 | Respondent's Objections | 69-73 |
3.8.4 | Conclusion - Question of Law Arising on the Appeal | 74-78 |
4. | Contract Conditions | 79-94 |
4.1 | Introduction | 79-82 |
4.2 | Form, Substance and Intent of a Valid Final Certificate | 83-93 |
4.3 | Relevant Conditions - JCT 80 | 94 |
5. | JCT Final Certificate - General Considerations | 95-132 |
5.1 | Introduction | 95-96 |
5.2 | Role of Architect or Certifier | 97-100 |
5.3 | Time Limits | 101-117 |
5.4 | Agreement and Acquiescence in Delaying Issue of Certificates | 118-123 |
5.5 | Implication Associated with Late Issue of Certificates | 124-129 |
5.6 | Conditions Precedent to Issue of Certificates | 130-132 |
6. | Meaning and Effect of Clause 30.8 | 133-162 |
6.1 | Introduction | 133 |
6.2 | Clause 30.8 in its Contractual Context | 134-138 |
6.3 | What Conditions Precedent are Imposed by Clause 30.8 | 139-157 |
6.3.1 | Introduction | 139 |
6.3.2 | Certificate of Making Good Defects | 140-143 |
6.3.3 | Clause 30.6.1.2 Documentation | 144-146 |
6.3.4 | Adjustment of Contract Sum | 147-148 |
6.3.5 | Clause 30.7 - Nominated Sub-Contractors | 149-153 |
6.3.6 | Clauses 24.1 and 25.3 - Delayed Completion and Extension of Time | 154-156 |
6.3.7. | Condition Precedent and Implied Term | 157 |
7. | Questions of Law to be Decided in this Appeal | 163-203 |
7.1 | Introduction | 163 |
7.2 | Erroneous Approach of Parties | 164-172 |
7.2.1 | Introduction | 164-165 |
7.2.2 | Form | 166-167 |
7.2.3 | Substance | 168-170 |
7.2.4 | Intent | 171-172 |
7.3 | Question 1 - Where the Arbitrator's Answers to Issues 1 and 2 Correct in Law? | 173-197 |
7.3.1 | Arbitrator's Reasoning - Substance | 173-178 |
7.3.2 | Arbitrator's Errors - Substance | 179-186 |
7.3.3 | Corrected Reasoning - Substance | 187-188 |
7.3.4 | Arbitrator's Reasoning - Form | 189-190 |
7.3.5 | Arbitrator's Errors - Form | 191-194 |
7.3.6 | Corrected Reasoning - Form | 195 |
7.3.7 | Arbitrator's Errors - Intent | 196-197 |
7.4 | Question 1 - Conclusion | 198 |
7.5 | Question 2 - What is the Correct Answer to Issues 1 and 2? | 199-203 |
JUDGMENT
1. INTRODUCTION
"1. Whether or not the certificate issued by the architect on 29 March 1999 was validly issued in accordance with clause 30.8 of the contract conditions.
2. Whether or not the certificate issued by the architect on 29 March 1999 is the final certificate for the purpose of clause 30.9 of the contract conditions."
The parties had also agreed that five further issues should be decided relating to the effect of the Final Certificate, if it be one, on various aspects of the claimants' claims and defences. However, during the hearing of the preliminary issues, the parties agreed what the relevant effects of the Final Certificate would be if the arbitrator found that the certificate in question was the Final Certificate and a consent award was made in relation to those further issues.
2. BACKGROUND FACTS
"We have been issuing instructions under contract clauses .3.2.2 and 13.2.4 which empowers us to do this but this does not mean that we have agreed any costs or liability or payment, merely that the variations and alterations have occurred factually."
"Agree to your final account as attached. Please could you or Ray Harris [of Hollins, the Architect] advise when the final certificate will be issued."
The document referred to had been the subject of discussions involving the two quantity surveyors and its contents had agreed at a meeting held between the Architect Mr Ray Harris and the two directors of the respondent responsible for this contract, Mr M and Mr N Fuller and the two quantity surveyors on 2 March 1999.
"It is my duty, under the terms of the Contract, to identify all the variations, which we have done, copies of which you have had, and prepare a final account statement, in which we have been aided by Messrs Hyams and Partners [the quantity surveyor appointed by the Architect]. I now report to you that this figure is £548,799 25.
Under Clause 30.7 I enclose a Certificate which authorises payments to nominated subcontractors, when fair proof of payment from [the respondent] has been received we will issue the final certificate.
I enclose copies of the final account documentation from Hyams for your information."
Enclosed was the final account document discussed and agreed at the meeting held on 2 March 1999 and the Certificate which was dated 10 March 1999 and was in the sum of £25,194.09.
Architects and Surveyors
Planning Consultants
Certificate for Payment
Job No 95173 Certificate No B536/95173/12
Issue date 29 March 1999
Employer | Contract sum | 494,682.22 |
Less contingencies | (10,000.00) | |
B R & E P Cantrell Foxearth Lodge Nursing Home Little Green Saxtead |
Add variations | 50,509.62 |
50,509.62 | 548,799.25 | |
548,799.25 | Less items paid by client: | |
Lift | (12,115.00) | |
Nurse station | (2,160.00) | |
Lift | (6,939.81) | |
----------------------------------- | ------------------------------------- | -------------- |
Site address | TOTAL | £527,584.44 |
------------------------------------- | -------------- | |
New EMI Unit (Phase 1) Foxearth Lodge Nursing Home |
||
Gross amount due | 527,584.44 | |
Less retention | Nil | |
------------------------------------- | -------------- | |
Net amount due | 527,584.44 | |
Less previously certified | 477,074.82 | |
----------------------------------- | ------------------------------------- | -------------- |
Contractor | ||
Wright and Fuller Ltd Strawberry Field Main Road, Willisham Ipswich IP8 4SP |
||
Payment now due | 50,509.62 | |
50,509.62 | VAT@17½ per cent | — |
— | ------------------------------------- | 50,509.62 |
We certify that the sum of Fifty thousand five hundred and nine pounds 62p due to the above Contractor as a final payment for works completed and under the terms of the Contract payment is due within 14 days of issue above.
Signed:
for Hollins Architects and Surveyors
4A Market Hill Framlingham Suffolk IP13 93A
CR Tanner FRICS
RAE Alexander Dipl Arch (Oxford) RIBA
Consultant Architect
SP Reid
Planning Consultant"
"Dear Mr Cantrell
New EMI Unit - Phase 1
I now write to enclose the final certificate as per the contract sum, variations and omissions I believe this now discharges our obligations under the contract.
I would respectfully remind you that you would be advised to check that the sub-contractors have been paid their due amounts before you make any final settlement.
Yours sincerely
C R Tanner"
"By copy of this letter to Warrington Martin [the respondent's quantity surveyor] we set out above [the claimants'] position and look forward to receiving reimbursement from the Contractor in the form of a cheque for £22,737.75 payable to 'Foxearth Lodge Nursing Home' within the next 14 days of the date of this letter failing which we shall take such further action as is deemed necessary."
The Architect did not reply to this letter.
3. THE SUBMISSIONS OF THE PARTIES, AWARD AND QUESTIONS OF LAW BEING APPEALED
3.1. Dispute
1. The Architect had failed to issue any instruction to make good defects despite the existence of defects that had appeared in the Defects Liability Period. Moreover, the suggested Adjusted Contract Sum did not, as it should have done, take account of the necessary abatement for these defects that remained unremedied at the end of the Defects Liability Period.
2. The suggested Adjusted Contract Sum also, wrongly, included in its make up the value of suggested variations which were not variations at all or which had not been authorised by the claimants or instructed in accordance with the requirements of the Conditions.
3. These omissions as to defects and the inclusions as to unauthorised variations rendered the certificate invalid as the Final Certificate or showed that the substance and intent of the certificate was as a final Interim Certificate and not as the Final Certificate since the adjustment process had not been completed before it had been issued. It was a necessary precondition to the issue of a valid Final Certificate that the adjustment process had first been completed.
4. The suggested Adjusted Contract Sum should have had been capable of having deducted from it liquidated damages but the necessary certificates and decisions concerned with the Completion Date and the deduction of liquidated damages required of the Architect under clauses 24.1 and 25.3.2 had not been issued. Their issue were conditions precedent to the issue of the Final Certificate so that their non-issue rendered the certificate invalid as the Final Certificate.
5. Further necessary preconditions to the issue of the Final Certificate, being the issue of a Certificate of Making Good Defects, the issue of the documents required by clause 30.6.1.2.2 and the Interim Certificate concerned with the final adjusted contract sums to be certified in favour of the two Nominated Sub-Contractors that was required by clause 30.7, had not been fulfilled.
6. The Architect could not unilaterally ignore the contractual time limits relating to the issue of the Final Certificate and then, without consulting the claimants, belatedly issue a valid Final Certificate. The certificate that was issued was, in consequence, incapable of being the Final Certificate.
7. Such express or implied agreement as the claimants had given for the "Final Certificate to be Issued out of time" would appear to have been subject to a condition that the Architect would not issue the Final Certificate until he had first notified the claimants of the proposed adjustments to the Contract Sum and had then consulted with them about these proposed adjustments. These consultations had not been held by the time the purported Final Certificate had been issued and, in consequence, the certificate was invalid as the Final Certificate. This implied agreement arose following the claimants' acceptance of the advice conveyed to them by the Architect's letter dated 14 October 1998 in which he had stated that it would be premature for the claimants to consider arbitrating against the respondent at that stage and that they should await, and by implication first discuss with him, the list of variations once these had been addressed in the Final Account.
8. The Architect had relied exclusively, when deciding upon the adjustments to be made to the Contract Sum, on the valuation advice of Mr Richard Mays of Hyams, being the quantity surveyor that he had appointed privately but who had not been appointed as Quantity Surveyor under the contract and whose involvement in the adjustment process had not been ratified or approved by the claimants so that the certificate did not certify the opinion of the Architect and was in consequence invalid.
9. The effect of these contentions was that the certificate in question was not, in form, substance or intent, the Final Certificate, albeit that the claimants did not use this rubric to describe or summarise their contentions
3.2 Issues in the Arbitration
3.3 Submissions of the Parties on Issues 1 and 2 in the Arbitration
3.3.1 Claimants' Submissions in the Arbitration
3.3.2 Respondent's Submissions in the Arbitration
3.3.3 Submissions as to the Form of the Certificate
3.4 Scope of the Award
3.5 Award
1. In agreement with, and following, Judge Lloyd's decision in the Penwith case, the issuing of the statement of adjustments was not a condition precedent to the issue of the Final Certificate. In this case, such a statement was in fact issued and the crucial questions were, therefore, whether such was needed at all and, if it was issued late, did that affect the validity of the subsequently issued Final Certificate. The arbitrator's conclusion was that that the issue and any lateness in the issue of the statement were both immaterial since its issue was not a precondition of the issue of the Final Certificate and, in any case, the time limit in clause 30.8 was directory and not mandatory.
2. In reaching his conclusion, the arbitrator particularly relied on what he regarded as the commercial absurdity of the alternative contention that the Final Certificate was not capable of being issued out of time. His argument, in summary was that:
(1) If the Final Certificate could not be issued out of time, it would mean that an unforeseen illness or accident to the Architect just before the Final Certificate was to be issued would prevent both parties obtaining the Final Certificate at all.
(2) It would make no commercial sense if the Conditions were construed in a way which precluded the issue of the Final Certificate at all if the time for its issue had passed, particularly as the Final Certificate was to the commercial advantage of both parties.
(3) The reasoning in the London Borough of Merton case was applicable. This was to the effect that the time limits for issuing the Final Certificate were not vital and that if the Final Certificate was issued late, it was still valid and conclusive in its effect.
(4) The absence of a contractual procedure to deal with what should happen if the timetable for issuing the Final Certificate slipped suggested that the strict observance of that timetable was not critical, particularly since the contract contained no clear words making that timetable critical.
3.6 Claimants' Grounds of Appeal
1. a statement of adjustments had been agreed on behalf of both parties and had been issued by the Architect on about 4 March 1999 in conformity with clause 30.6.1.2.2. At best, the document in question was a final account which had been agreed by the two quantity surveyors without their agreement or authority; and
2. The 4 March 1999 final account document was the correct starting point from which to consider whether the certificate issued on 29 March 1999 was a valid Final Certificate.
3.7 Respondent's Reply
"is this contention advanced by the claimants correct:
because the Final Certificate was not issued on or before 23 October 1998, no valid Final Certificate could have been issued on 29 March 1999?"
3.8 Questions of Law for Determination in the Appeal
3.8.1 Difficulties Confronting the Court in Hearing the Appeal
1. The parties never pleaded out their cases or agreed in advance the factual basis on which the preliminary issues should be decided.
2. The claimants, before the reference to arbitration, had advanced a case on a large number of grounds and on the widest possible basis that no Final Certificate had been issued and that the certificate that had been issued was not conclusive.
3. The parties agreed very widely worded issues for the arbitrator to decide whose wording encompassed all grounds advanced by the claimants prior to the reference to arbitration to the effect the certificate issued on 29 March 1999 was not the Final Certificate in form, substance or intent.
4. The two issues were worded in a way that meant that they were both, in reality, raising the same general issue as to whether the certificate was, in the circumstances of this case, the Final Certificate issued under clause 30.8 in form, substance and intent so as to have the conclusive effects identified in clause 30.9. This composite issue exclusively raises questions of law involving the construction of a commercial agreement and commercial documents issued under that agreement.
5. The parties addressed the arbitrator on narrower or, in the case of the respondent, much narrower grounds than those formulated and agreed to prior to the hearing as the issues to be determined. Furthermore, each party addressed the arbitrator on different bases which were not complementary.
6. The arbitrator decided the widely framed issues left for him to decide but did so by reference solely to the respondent's particularly narrow formulation of those issues which he adopted.
7. There was, at the hearing of the appeal, a dispute between the parties as to whether or not this narrowing of the issues was by the agreement of the parties or at the behest of the respondent.
8. Because leave was not required to bring an appeal from that award and because the grounds of appeal have been drafted in a diffuse manner, the questions of law arising on this appeal have not been clearly or precisely formulated but the appeal has been regularly brought before the court which must now determine it.
9. The claimants contend that the approach to the construction of the Conditions that was taken by the arbitrator was erroneous and that a different approach should be adopted. The respondent contends for the approach to construction that was adopted by the arbitrator. However, the correct meaning to be given to the relevant conditions is not precisely that decided upon by the arbitrator and contended for by the respondent nor is it that contended for by the claimants.
10. The relief sought by the grounds of appeal is widely framed and seeks the setting aside of the arbitrator's answers to both issues and also seeks that both issues should be decided by the court. Both issues raise, and only raise, questions of law so that the exercise of determining whether the arbitrator answered the issues correctly and, if incorrectly, what the correct answer should be involves and only involves an appeal as to questions of law arising out of the award.
3.8.2 Questions of Law
1. Were the arbitrator's answers to issues 1 and 2 correct in law?
2. If not, what is the correct answer to issues 1 and 2?
3.8.3 Respondent's Objections
1. Whether the Architect's failure to prepare a statement of adjustments under clause 30.6.1.2.2 within 3 months of 20 July 1998 prevented the issue of a final certificate;
2. Whether the form of the certificate, in stating that it was a final payment and that the certified sum should be paid within 14 days instead of 28 days, meant that it was not the Final Certificate. The respondent's submissions made no reference to the circumstances surrounding the issue of the certificate nor to any of the conditions save to clause 30.8.
"If there exist extenuating circumstances which make it practically impossible for the Architect to comply with major events such as [the issue of] the Final Certificate then no reasonable contractor or employer would refuse to extend a time limit, ... and if they did so refuse undoubtedly that refusal would be ignored and overruled by all arbitrators and judges in any ensuing proceedings."
3.8.4 Conclusion - Questions of Law Arising on the Appeal
4. CONTRACT CONDITIONS
4.1 Introduction
"18. The basic framework of this section of the 1980 JCT forms is relatively clear and reflects long-standing practice. Once the works are completed the scene is set out for the last act at the end of which the final certificate should appear. The final certificate has a dual role: it ostensibly deals only with the final accounting and as such, it is intended to arrive at the Adjusted Contract Sum; it is also deemed to express the Certifying Architect's satisfaction with the quality of the works and with their apparent compliance with the contract. The two strands are linked in as much as the certified value of the works is intended also to reflect their contractual worth for if they have been properly executed or completed what might otherwise have been their full contractual value will presumably not be certified, either because the Certifying Architect cannot conscientiously do so or because the process of arriving at an Adjusted Contract Sum requires an adjustment or abatement ... it is clear that the contract represents a consensus within the building industry that, if the JCT forms are used, there should, with certain exceptions, be finality on all matters and on all issues relating to the contractor's apparent compliance with the contract and finality should be achieved as soon as reasonably practical after practical completion so that the parties can go their separate ways. The contractor should be reasonably confident that it will not be called back to attend to further defects; both should be confident that the accounts have been settled so that the financial outturn is clear and no provision is required for contingent liabilities. The last is an objective which most employers are keen to attain. In addition the final certificate does more than repeat the contents of the Adjusted Contract Sum. It states the balance due and, as [one of the three contracts] demonstrates ... that may be in favour of the employer who may therefore have as much commercial interest in having a final certificate as the contractor. In accepting [counsel's] submission that the contract should be approached on a commercial basis and not in a clinical manner I do so with these considerations in mind."
4.2 Form, Substance and Intent of a Valid Final Certificate
"That clause required him to 'certify' in writing. While no set form of certificate is provided, unlike that under clause 21(a) and (b), it must clearly appear that the document relied upon is the physical expression of a certifying process. One should, therefore, have some regard to the factors of 'form', 'substance' and 'intent' of which Mr Justice Devlin spoke in admittedly different circumstances of Minter Trust Ltd v Traps Tractors Ltd. Or to borrow a passage in Hudson (10th edition, page 479), the document should be 'the expression in a definite form of the exercise of the ... opinion ... of the ... architect in relation to some matter provided for by the terms of the contract'. And, as Mr Garland [counsel for the employer] accepted, it must be free from the ambiguity."
Roskill LJ stated, at pages 58 - 59:
"It is important to appreciate that the architect, when acting or purporting to act under either conditions ... or indeed under any other empowering clause or condition in this contract, is exercising a power which affects the contractual rights of the parties to the contract by varying those rights in one or more ways as the parties have agreed should be the case. It is therefore of crucial importance that the exercise of power by the architect should be done clearly and unambiguously so that the parties know where they are and should not be left in doubt or indeed in dispute as to their consequent mutual rights and liabilities after the exercise or purported exercise of this power.
I respectfully agree with and adopt what was said by Mr Justice Devlin in Minster Trust Ltd v Traps Tractors Ltd. The learned judge said:
'I think that a certificate of this sort must, to satisfy the contract, be unambiguous and readily understandable. When a document is tendered under a contract, the recipient has often to make up his mind whether he is going to pay out money upon it or accept or reject goods; he has no right to clear up doubts.'"
4.3 Relevant Conditions - JCT 80 Standard Form of Building Contract
Articles 3 and 4B
These provided that the Architect should mean Hollins Architects & Surveyors and that the functions ascribed by the Conditions to the Quantity Surveyor should be exercised by Hollins Architects & Surveyors.
1. Interpretation, definitions etc.
1.2 The Articles of Agreement, the Conditions and the Appendix are to be read as a whole and the effect or operation of any article or clause in the Conditions or item in or entry in the Appendix must therefore unless otherwise specifically stated be read subject to any relevant qualification or modification in any other article or any of the clauses in the Conditions or item in or entry in the Appendix.
1.3 Unless the context otherwise requires or the Articles or Conditions or an item in or entry in the Appendix specifically otherwise provides, the following words and phrases in the Articles of Agreement, the Conditions and the Appendix shall have the meaning given below or as ascribed in the article, clause or Appendix item to which reference is made:
Final Certificate: the certificate to which clause 30.8 refers.
5. Contract Documents - other documents - issue of certificates
…
5.8 Except where otherwise specifically so provided any certificate to be issued by the Architect under the Conditions shall be issued to the Employer, and immediately upon the issue of any such certificate the Architect shall send a duplicate copy thereof to the Contractor.
…
8. Work, materials and goods
…
8.4 If any work, materials or goods are not in accordance with this Contract and the Architect, without prejudice to the generality of his powers, may:
…
8.4.2 after consultation with the Contractor (who shall immediately consult with any relevant Nominated Sub-Contractor) and with the agreement of the Employer, allow all or any of such work, materials or goods to remain and confirm them in writing to the Contractor (which shall not be construed as a Variation) and where so allowed and confirmed an appropriate deduction shall be made in the adjustment of the Contract sum;
…
14. Contract Sum
…
14.2 The Contract Sum shall not be adjusted or altered in any way whatsoever otherwise than in accordance with the express provisions of the Conditions.
15. Value added tax - supplemental provisions.
…
15.2 any reference in the Conditions to 'Contract Sum' shall be regarded as such Sum exclusive of any tax recovery by the Contractor from the Employer of [VAT].
…
17. Practical Completion and defects liability.
…
17.2 any defects, shrinkages or other faults which shall appear in the Defects Liability Period and which are due to materials or workmanship not in accordance with this Contract or to frost occurring before Practical Completion of the Works, shall be specified by the Architect in a schedule of defects which he shall deliver to the Contractor as an instruction of the Architect not later than 14 days after the expiration of the Defects Liability Period, and within a reasonable time after receipt of such schedule the defects, shrinkages and other faults therein specified shall be made good by the Contractor at no cost to the Employer unless the Architect with the consent of the Employer shall otherwise instruct; and if the Architect does otherwise instruct then an appropriate deduction in respect of any such defects, shrinkages or other faults not made good shall be made from the Contract Sum.
24. Damages for non-completion
24.1 If the Contractor fails to complete the Works by the Completion Date the Architect shall issue a certificate to that effect. …
24.2.1 Subject to the issue of any certificate under clause 24.1, the Contractor shall, as the Employer may require in writing not later than the date of the Final Certificate, pay or allow to the Employer liquidated and ascertained damages at the rate stated in the Appendix … for the period between the Completion Date and the date of Practical Completion and the Employer may deduct the same from any monies due or to become due to the Contractor under this Contract (including any balance stated as due to the Contractor in the Final Certificate) …
25. Extension of time
…
25.3.3 After the Completion Date, if this occurs before the date of Practical Completion, the Architect may, and not later than the expiry of 12 weeks after Practical Completion shall, in writing to the Contractor either
3.1 fix a Completion Date later than previously fixed ...; or
3.2 fix a Completion Date earlier than that previously fixed ...; or
3.3. confirm to the Contractor the Completion Date previously fixed
30. Certificates and payments
30.1.1 The Architect shall from time to time as provided in clause 30 issue Interim Certificates stating the amount due to the Contractor from the Employer and the Contractor shall be entitled to payment therefor within 14 days from the date of issue of each Interim Certificate.
30.1.3 Interim Certificates shall be issued at the Period of Interim Certificates specified in the Appendix [1 month] up to and including the end of the period during which the Certificate of Practical Completion is issued. Thereafter Interim Certificates shall be issued as and when further amounts are ascertained as payable to the Contractor from the Employer and after the expiry of the Defects Liability Period named in the Appendix ... .
30.2 The amount stated as due in an Interim Certificate, shall be the gross valuation referred to in clause 30.2 less …
any amount which may be deducted and retained by the Employer …(… "the retention") and the total amount stated as due in Interim Certificates previously issued under the Conditions.
.1 There shall be included …
.1.1 the total value of the work properly executed by the Contractor …
30.6.1.1 Not later than 6 months after Practical Completion of the Works the Contractor shall provide the Architect or, if so instructed by the Architect, the Quantity Surveyor, with all documents necessary for the purposes of the adjustment of the Contract Sum including all documents relating to the accounts of the Nominated Sub-Contractors and Nominated Suppliers.
30.6.1.2 Not later than 3 months after receipt by the Architect or by the Quantity Surveyor of the documents referred to in clause 30.6.1.1.
.2.1 Not later than 3 months after receipt by the Architect or by the Quantity Surveyor of the documents referred to in clause 30.6.1.1.
.2.2 the Quantity Surveyor shall prepare a statement of all adjustments to be made to the Contract Sum as referred to in clause 30.6.2 other than any to which clause 30.2.6.1 applies
the Architect shall forthwith send a copy of any ascertainment to which clause 30.6.1.2.1 to the Contractor and the relevant extract therefrom to each Nominated Sub-Contractor.
30.6.2 The Contract Sum shall be adjusted by:
[the adjustments, deductions and additions are here defined in detail. These include
.2.4 any amount deducted or deductible under clause 8.4.2 or 17.2 ...]
30.7 So soon as is practicable but not less than 28 days before the date of issue of the Final Certificate referred to in clause 30.8 and notwithstanding that a period of one month may not have elapsed since the issue of the previous Interim Certificate, the Architect shall issue an Interim Certificate the gross valuation for which shall include the amounts of the sub-contract sums for all Nominated Sub-Contracts as finally adjusted or ascertained under all relevant provisions of Conditions of Nominated Sub-Contract.
30.8 The Architect shall issue the Final Certificate (and inform each Nominated Sub-Contractor of the date of its issue) not later than 2 months after whichever of the following occurs last:
the end of the Defects Liability Period;
the date of the issue of the Certificate of Completion of Making Good Defects under clause 17.4;
the date on which the Architect sent a copy to the Contractor of any ascertainment to which clause 30.6.1.2.1 refers and of the statement prepared in compliance with clause 30.6.1.2.2.
The Final Certificate shall state:
30.8.1 the sum of the amounts already stated as due in Interim Certificates, and
30.8.2 the Contract Sum adjusted as necessary in accordance with clause 30.6.2
and the difference (if any) between the two sums shall (without prejudice to the rights of the Contractor in respect of any Interim Certificates which have not been paid by the Employer) be expressed in the said Certificate as a balance due to the Contractor from the Employer or to the Employer from the Contractor as the case may be, and, subject to any deductions authorised by the Conditions, the said balance shall as from the 28th day after the date of the said Certificate be a debt payable as the case may be by the Employer to the Contractor or by the Contractor to the Employer.
30.9.1 Except as provided in clauses 30.9.2 and 30.9.3 (and save in respect of fraud), the Final Certificate shall have effect in any proceedings arising out of or in connection with this Contract (whether by arbitration under article 5 or otherwise) as
.1.1 conclusive evidence that where and to the extent that any of the particular qualities of any materials or goods or any particular standard of an item of workmanship was described expressly ... to be for the approval of the Architect, but such Certificate shall not be conclusive evidence that such or any other materials or goods or workmanship comply or complies with any other requirement or term of this Contract, and
.1.2 conclusive evidence that any necessary effect has been given to all the terms of this Contract which require that an amount is to be added to or deducted from the Contract Sum or an adjustment is to be made of the Contract Sum save where there has been any accidental inclusion or exclusion of any work, materials, goods, or figure in any computation or any arithmetical error in any computation, in which event the Final Certificate shall have effect as conclusive evidence as to all other computations, and
.1.3 conclusive evidence that all and only such extensions of time, if any, as are due under clause 25 have been given, and
.1.4 conclusive evidence that the reimbursement of direct loss and/or expense, if any, to the Contractor pursuant to clause 26.1 is in final settlement of all and every claims which the Contractor has or may have arising out of the occurrence of any of the matters referred to in clause 26.2 whether such claim be for breach of contract duty of care, statutory duty or otherwise.
30.9.2 if any arbitration or other proceedings shall have been commenced by either party before the Final Certificate has been issued the Final Certificate shall have effect as conclusive evidence as provided in clause 30.9.1 after either
.2.1 such proceedings have been concluded, whereupon the Final Certificate shall be subject to the terms of any award or judgment or settlement of such proceedings, or
.2.2 a period of 12 months during which neither party has taken any further step in such proceedings, whereupon the Final Certificate shall be subject to any terms agreed in partial settlement,
whichever shall be the earlier.
30.9.3 if any arbitration or other proceedings have been commenced by either party within 28 days after the Final Certificate has been issued, the Final Certificate shall have effect as conclusive evidence as provided for in clause 30.9.1 save only in respect of all matters to which those proceedings relate.
…
Nominated Sub-Contractors
…
35.13.3 Before the issue of each interim Certificate (other than the first Interim Certificate) and of the Final Certificate the Contractor shall provide the Architect with reasonable proof of discharge by the Contractor pursuant to clause 35.13.2.
…
35.13.5.1 If the Contractor fails to provide reasonable proof under clause 35.13.3, the Architect shall issue a certificate to that effect stating the amount in respect of which the Contractor has failed to provide such proof, and the Architect shall issue a copy of the certificate to the Nominated Sub-Contractor concerned.
35.5.2 Provided that the Architect has issued the certificate under clause 35.13.5.1, ... the amount of any future payment otherwise due to the Contractor under this Contract shall be reduced by any amounts due to Nominated Sub-Contractors which the Contractor has failed to discharge ... and the Employer shall himself pay the same to the Nominated Sub-Contractor concerned. …
Early Final Payment of Nominated Sub-Contractors
35.17 … at any time after the day named in the certificate of Practical Completion of the Sub-Contract Works [which shall forthwith be issued when practical completion of the works executed by a Nominated Sub-Contractor is achieved] the Architect may, and on the expiry of 12 months from the aforesaid day shall, issue an Interim Certificate the gross valuation for which shall include the amount of the relevant sub-contract sum or ascertained final sub-contract sum as finally adjusted or ascertained under the relevant provisions of ... Conditions of Nominated Sub-Contract
Settlement of disputes - Arbitration
41.4 Subject to the provisions of clauses 30.9 … the Arbitrator shall, without prejudice to the generality of his powers, have power to rectify this Contract, to direct such measurements and/or valuations as may in his opinion be desirable in order to determine the rights of the parties and to ascertain and award any sum which ought to have been the subject of or included in any certificate and to open up, review and revise any certificate, opinion, decision, (...) requirement or notice and to determine all matters in dispute which shall be submitted to him in the same manner as if no such certificate, opinion, decision, requirement or notice had been given. 5. Clause 30.8 of The Conditions
5. JCT FINAL CERTIFICATE - GENERAL CONSIDERATIONS
5.1 Introduction
5.2 Role of the Architect or Certifier
"33. The third 'undoubted breach' [found by the arbitrator to have been committed by the Architect during the certifying and issuing of the Final Certificate] occurred because the final certificate was dated 9 February 1993 but was not sent to [the contractor] until 16 February 1993. Condition 5.8 of the JCT form states:
'Except where otherwise specifically so provided any certificate to be issued by the Architect under the Conditions shall be issued to the Employer, and immediately upon the issue of any such certificate the Architect shall send a duplicate copy thereof to the Contractor.'
Mr Blackburn [counsel for the Employer] argued that a certificate is not issued until it is sent …
34. … in my judgment the final certificate was not issued until 16 February 1993 when it was sent …
35. The events which the arbitrator decided were 'undoubted breaches' were not therefore defaults in complying with the terms of the contract. Even if any of them had been an instance of non-compliance with the terms of the contract Mr Blackburn submitted that they could not be breaches of contract by [the Employer]. He referred to Panamena Europea Navigacion v Leyland (1943) 76 Lloyd's Rep 113 (CA) and [1947] AC 428 (HL) as applied by Macfarlan J in Perini Corporation v Commonwealth of Australia [1969] 2 NSWR 350. In the former case in the Court of Appeal Scott LJ said (at page 124):
'It seems to me that if the shipowners had known that [the certifying officer under the ship repairing contract] was departing from his proper function under the contract, it would have been their duty to stop him and tell him what the function was for which the contract provided. In those circumstances I think the court ought to imply an undertaking by the owners that in the event of its becoming known to them that their surveyor was departing from the function which both parties had agreed he was to perform, they would call him to book, and tell him what his real function was.'
Goddard LJ agreed with Scott LJ and in dismissing the appeal the House of Lords endorsed in general terms the judgment of Goddard LJ. In Perini, Macfarlan J had to consider the position of a certifier, the Director of Works, who was employed by the Commonwealth. He followed Panamena and held (at page 515) that there was 'an obligation to require the Director to act in accordance with his mandate if the defendant is aware that he is proposing to act beyond it'.
36. In my judgment these decisions are correct. [The Architect], although employed by [the Employer], was given authority by the parties to the contract to form and express the opinions and to issue the certificates as and when required by its terms. He was not the agent of [the Employer] in so acting so that [the Employer] was liable to> [the Contractor] for what he did or did not do in his capacity as certifier. On the other hand [the Employer] was the party who could control him if he failed to do what the contract required. Since the contract is not commercially workable unless the certifier does what is required of him, [the Architect] as part of the ordinary implied obligation of co-operation, was under a duty to call [the Architect) to book (to use Scott LJ's phrase) if it knew that he was not acting in accordance with the contract. Both Scott LJ and Macfarlan J make it clear that the duty does not arise until the Employer is aware of the need to remind the certifier of his obligations. I am also of that opinion for the same reasons. a mere failure by the certifier to act in accordance with the contractual time table is not a failure on the part of the employer to discharge an implied obligation positively to co-operate and cannot be a breach of contract by the party whose employee is the certifier. On the facts set out in the award [the Employer] could not therefore have been in breach of contract. In arriving at this conclusion I bear in mind the argument that the existence of an arbitration clause which confers on the arbitrator wide powers to open up etc means that a failure to issue a final certificate can be put right and thus there is no need for an implied obligation of the kind found in Panamena and Perini since he necessity there arose as there was no such arbitration clause. It is not however necessary to express any view about such an argument."
5.3 Time Limits
"29. I cannot accept that the contract terms, properly construed, prohibit the provision and receipt of further information, documentation or details about direct loss and expense after the six month period following practical completion Such a stringent time-bar would in my view require to be expressed in clear and unambiguous language which I have been unable to find in the contract terms. On the contrary, the wording of [the clause in question] suggests that [the sub- contractor) are correct in their contention that the statutory [sic - the learned judge clearly meant contractual] provisions simply provide a time table to which the parties are expected to adhere."
5.4. Agreement or Acquiescence in Delaying Issue of Certificate
"And it is said that this certificate was issued very much out of time. It should have been issued, according to the terms of the contract, I think I am right in saying, within six months of the end of the defects liability period. It matters not. It should have been issued some years before it actually was.
According to the terms of the contract - I forbear from reading them; they appear in the papers and in the judgment of the learned judge - the certificate should have been issued earlier, and it was the duty of the architect to issue it. But on the facts of the case what happened was this: the contractors called for the certificate, the [employer] asked the architect not to issue it, there was still some electrical work to be done, and it was not until May 1973 that the [employer] agreed on the advice of the architect, that the certificate could be issued. In the correspondence between the [employer] and the architect relating to this matter they speak of the issue of the final certificate; and into the covering letter enclosing the certificate with which we are concerned the [architect] say to the contractors 'We are enclosing the final certificate'.
I take the view that the [employer], in an action brought by them against a main contractor, could not have been heard to say that this document was not a final certificate. It goes against all commonsense. In my view it goes against the rules of law, too. They would have been estopped from so contending, in my view. The fact that the words 'Final certificate' did not appear upon it seems to me to be wholly irrelevant in the present circumstances. They appeared so strongly in the covering letter that the two must be read together."
"17. Clearly a certifier or other decision-maker must have the necessary contractual authority to act for otherwise the certificate or decision will be invalid. If the person has gone outside the limits of the decision-making authority conferred by the contract, ie the person does not have the power or jurisdiction to make the decision or to issue the certificate, the certificate or decision will be unenforceable and will be liable to be set aside. The parties may of course agree to accept the act and in effect to ratify it and, by waiver or otherwise, accept the certificate or decision as valid so that it is not always useful to describe it as a 'nullity'."
However, if further time elapses once the agreed extended period has passed, the certificate will usually still be capable of being issued, depending on the terms of the contract, but the power to certify must be exercised reasonably as opposed to being exercised in strict accordance with the express or implied, agreement, ratification or waiver of the parties.
5.5 Implication Associated With Late Issue of Certificates
5.6 Conditions Precedent to Issue of Certificates
6. MEANING AND EFFECT OF CLAUSE 30.8
6.1 Introduction
"The Architect shall issue the Final Certificate (and inform each Nominated Sub-Contractor of the date of its issue) not later than 2 months after whichever of the following occurs last:
the end of the Defects Liability Period;
the date of the issue of the Certificate of Completion of Making Good Defects under clause 17.4;
the date on which the Architect sent a copy to the Contractor of any ascertainment to which clause 30.6.2.1 refers and of the statement prepared in compliance with clause 30.6.1.2.2."
6.2. Clause 30.8 in its Contractual Context
"18. ... The final certificate has a dual role: it ostensibly deal only with the final accounting and, as such, it is intended to arrive at the Adjusted Contract Sums it is also deemed to express the Architect's satisfaction with the quality of the works and with their apparent compliance with the contract. The two strands are linked in as much as the certified value of the works is intended also to reflect their contractual worth for if they have been properly executed or completed what might otherwise have been their full contractual value will presumably not be certified, either because the Architect cannot conscientiously do so or because the process of arriving at an AFS requires an adjustment or abatement …".
6.3 What Conditions Precedent are Imposed by Clause 30.8?
6.3.1 Introduction
6.3.2 Certificate of Making Good Defects
6.3.3 Clause 30.6.1.2 Documentation
"24. In my judgment the provision of a copy of the ascertainment, and of a statement, of the AFS is not a condition precedent to the issue of the final certificate so that a failure to provide them before the final certificate does not affect the Architect's authority to issue a final certificate."
In summary, Judge Lloyd reached this conclusion because the Architect retains authority to finally adjust the Contract Sum and to issue a Final Certificate even if no service of these documents has occurred. The requirement for service is purely to inform the Contractor what ascertainment has been undertaken, but it is not an essential step in the adjustment process since the contract allows the Final Certificate to be issued within moments of the service of the documents given that no minimum period of time must elapse between their service and the subsequent issue of the Final Certificate.
6.3.4 Adjustment of the Contract Sum
"21. The timing of the final certificate may be affected by the operation of clause 17. This contains two provisions whereby, as an alternative to the remedy granted by clause 4.1.2 for non-compliance with an instruction, if the contractor does not make good a defect or if an instruction is issued dispensing with the need to do so, a deduction may be made from the contract sum, for which provision is made in the calculation of the Adjusted Contract Sum by clause 30.6.2.4. The amount otherwise payable to the contractor is thus to be abated. The amount of the deduction or abatement may be the cost or estimated cost to the employer of having the defect put right by others (where an assessment by way of diminution in value is not appropriate). However the cost will probably not be known until after the remedial work has been done ... Whatever the state of the completion of the Adjusted Contract Sum it is therefore probable that its final calculation may be deferred. Even if a statement of the AFS were sent to the contractor before the end of the DLP or the issue of the certificate of making good defects it would still be the duty of the Architect and the Quantity Surveyor to make a deduction and make a further adjustment to the AFS should the need arise under clause 17."
6.3.5 Clause 30.7 - Nominated Sub-Contractors' Adjusted Contract Sums
"23. Furthermore, clause 30.7 may be satisfied much earlier Mr Blackburn [counsel for the Employer] adopted in argument the illustration of a piling sub-contractor whose work and its measurement and valuation will almost invariably be finished and completed well before practical completion so in such an instance effect would be given to clause 30.7 by an interim certificate issued much earlier than 28 days prior to the issue of the Final Certificate. In any event the purposes of clause 30.7 are those given by Mr Blackburn (and accepted by Mr Stimpson [counsel for the Contractor]), namely to enable the Contractor and Nominated Sub-Contractors to have advance notice of what was going to be certified so that, if necessary, steps can be taken to avoid the effect of the Final Certificate and to establish multi-party arbitration and to enable the employer to pay a sub-contractor direct and to recover the amount from the balance of the Final Certificate (where there was a sufficient sum available). It is not a condition precedent to the issue of the Final Certificate."
6.3.6 Clauses 24 1 and 25 3 - Delayed Completion and Extensions of Time
6.3.7 Condition Precedent and Implied Term
6.4 Time for Issue of Final Certificate
6.5 Challenging the Validity of the Final Certificate
7. QUESTIONS OF LAW TO BE DECIDED ON THIS APPEAL
7.1 Introduction
7.2 Erroneous Approach of the Parties
7.2.1 Introduction
7.2.2 Form
7.2.3 Substance
7.2.4 Intent
7.3 Question 1 - Were the Arbitrator's Answers to Issues 1 and 2 Correct in Law?
7.3.1 Arbitrator's Reasoning - Substance
"2.06 ... the [claimants] submits that the Certificate for Making Good Defects and/or the Architect's statement under clause 306.1.2.2 are conditions precedent to the issue of a Final Certificate, which have not yet been met. (In fact more correctly, it is the Quantity Surveyor who is referred to, in the Contract, .not the Architect, although Hollins is referred to, in the Contract, as Architect and Surveyors and under Article 4B are to undertake the function of Quantity Surveyors, the error is probably irrelevant)."
7.3.2 Arbitrator's Errors - Substance
"empowers us to do this but does not mean that we have agreed any costs or liability for payment, merely that the variations and alterations have occurred factually."
Clause 4.3.2.2 provides that oral instructions (which would ordinarily not entitle the respondent to extra payment) might be confirmed and then take effect as written instructions requiring a variation if these were confirmed in writing at any time prior to the issue of the Final Certificate. Clause 13.2.4 provides that the Architect might sanction in writing any variation made by the respondent otherwise than pursuant to an instruction of the Architect.
7.3.3 Corrected Reasoning - Substance
1. Since Practical Completion had occurred after the Completion Date, it was a condition precedent to the issue of the Final Certificate that the certificates required by clauses 24.1 and 25.3 had first been issued.[6]
2. Since the value of variations required of the two Nominated Sub-Contractors were only first included in an Interim Certificate issued on 10 March 1999, clause 30.7 required that no Final Certificate could be issued until at least 7 April. 1999, being at least 28 days, after that certificate had been issued. Compliance with clause 30.7 where the relevant adjusted contact sums had not been certified earlier, was a condition precedent to the issue of the Final Certificate.[7]
3. Since no decision had been taken as to the potential operation of clauses 4.3.2.2 and 13.2.4 and as to the adjustments to the Contract Sum on account of the operation of clauses 8.4 and 17.2, the process of the adjustment of the Contract Sum under clause 30.6.2 had not been completed. This completion of the adjustment process had to be achieved prior to the issue of the Final Certificate.[8]
4. The delay in issuing the Final Certificate had only been agreed to, or acquiesced in by, the claimants on the basis that they would consider with the Architect after the Final Account had been produced what if any adjustment to the Contract Sum should be made for variations and whether it was necessary to resort to arbitration against the respondent. Equally, it would not have been reasonable for the Architect to issue the Final Certificate until he had communicated to the claimants the reasons why he had included any disputed variation in his adjustment and had not included a deduction for any item of defective work and had given the claimant a reasonable period to consider and discuss these decisions. The period of 17 days between the submission of the Final Account to the claimants on 10 March 1999 and the issue of the disputed certificate on 29 March 1999 complied with neither the terms on which the claimants had agreed to the extension of the date for the issue of the Final Certificate nor with the requirement of reasonableness.[9]
7.3.4 Arbitrator's Reasoning - Form
7.3.5 Arbitrator's Errors - Form
1. The certificate was in form identical to the immediately preceding interim certificate and the words "final payment" on its face were equally consistent with it being either the final interim certificate or the Final Certificate.
2. Clause 30.8 required the Final Certificate to state "the Contract Sum adjusted as necessary in accordance with clause 30.6.2". The sum certified did not state that it was the product of the completed adjustment process required by clause 30.6.2.
3. The sum certified, which is described as "Total", was a total of the Contract sum and variations less contingencies and sums previously paid direct by the claimants, That sum may, but need not necessarily, have been the Adjusted Contract Sum. It might equally have been calculated in the different way that the total certified in interim certificates had been calculated since those sums were also described as being "Total" in the interim certificates issued by the Architect.[12]
4. The requirement that the certificate was to be paid within 14 days clearly indicated, in context, that the certificate was an Interim Certificate. This stated requirement on the face of the certificate added weight to the conclusion that it was, in form, an interim and not the Final Certificate.
5. The covering letter referred to the certificate as "the final certificate" whereas the conditions carefully define the certificate as being the "Final Certificate" using capital letters. This could have been a deliberate choice by the Architect to use lower case so as to indicate that the certificate was to be the last certificate to be issued but was not to be the Final Certificate issued under clause 30.8.
6. The covering letter also referred to the certificate as being "as per the contract sum, variations and omissions". This wording would appear to differentiate the certificate from one certifying the "Adjusted Contract Sum" and to suggest that the sum did not take account of certain matters such as defective work and the operation of clause 4.3.2.2.
7. The covering letter also suggested that Mr Cantrell should check that all nominated sub-contractors have been paid in full before "you make any final settlement". It was for the Architect to certify any non-payment to nominated sub-contractors so that a direct payment could be made by the claimants to those sub-contractors and so that those direct payments could then be deducted from the Adjusted Contract Sum. The Conditions did not allow any such deduction from the Adjusted Contract Sum unless that procedure had been operated. The language of the letter therefore suggests that the Architect was envisaging a less formal procedure and that the certificate was not the Final Certificate.
8. The covering letter uses the words "before you make any final settlement". This suggests that the sum certified was intended to be one about which the parties would be having further discussions, something which would not be contemplated if the certificate indeed certified the Adjusted Contract Sum when the claimants would not be making a final settlement of the sum certified but a final payment of it.
9. The Architect suggested this in sending the final certificate: "I believe this now discharges our obligations under the contract". Had the certificate been the Final Certificate, rather than the last certificate he proposed to issue without it having final and conclusive effect, it would have been more natural for the Architect to have positively asserted: "This Final Certificate now discharges our obligations under the contract".
10. The factual background that I have already summarised[13] all pointed to the certificate as not being the Final Certificate. There remained too much unfinished business concerning variations, defects, liquidated damages and VAT to make it a realistic possibility that the document was indeed the Final Certificate issued under clause 30.8 with intended conclusivity as provided for by clause 30.9.
7.3.6 Corrected Reasoning - Form
7.3.7 Arbitrator's Errors - Intent
7.4 Question 1 - Conclusion
7.5 Question 2 - What is the Correct Answer to Issues 1 and 2?
HH Judge Thornton QC
Technology and Construction Court
July 2003
Note 1 See paragraph 82 below. [Back] Note 2 See paragraphs 85 - 93 below.
[Back] Note 3 See paragraph 132 below. [Back] Note 4 See paragraphs 101 - 117 above for my reasoning. [Back] Note 5 …See paragraphs 144 - 146 above for my reasoning. [Back] Note 6 See paragraphs 130 - 139 and 154 - 156 above. [Back] Note 7 See paragraphs 149 - 153 above. [Back] Note 8 See paragraphs 140 - 143 and 184 - 196 above. [Back] Note 9 See paragraphs 124 - 132 above for a discussion about agreed extensions of the period and reasonableness. [Back] Note 10 See paragraph 106 above for the relevant extract from the judgment. [Back] Note 11 Waller LJ started in a brief third judgment that: “In my opinion the certificate given on 4 May 1973 was a valid certificate and accepted as such by all concerned” (page 47). [Back] Note 12 See paragraph 83 above. [Back] Note 13 See paragraphs 10 - 30, 168 - 170 and 183 - 186 above. [Back]