QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
JEAN LOUIS STEUERMAN | Claimant | |
- and - | ||
DAMPCOURSING LIMITED | Defendant |
____________________
Tim Lord (instructed by Watmores, solicitors) appeared for the defendant:
Dates of trial: 22,23,24 April, 2002
____________________
Crown Copyright ©
The judgment of His Honour Judge Peter Bowsher Q.C. is as follows:
INTRODUCTION
ALLEGED DEFECT
"Before commencing laying operations ensure that the substrate has falls to the drainage outlets or is laid to a +/– 5 mm tolerance to prevent ponding in depression."
"Delta MS8 and Delta MS20 are to be generally loose laid with the dimples facing the substrate in a continuous form and trimmed to suit columns and other obstructions. The sheets are to be overlapped 75 mm longitudinally at the flat selvedge and bonded together with Bitutape double-sided self-adhesive strip. End laps are formed by overlapping 200 mm interlocking the dimples and sealing between the sheets with Bitutape."
"Under normal circumstances a drainage membrane should have channels in the floor allowing the water to run through to a gully which should be lower than the internal floor area. However, we understand that due to the structural nature of the slab that forming of the channel cannot be achieved.
We must therefore consider the option of a high stud drainage membrane such as the Delta MS 20. This has a stud height of 20 mm and will easily cope with any ingress or build up within the floor area and will prevent any further "lift".
…
We would confirm that the system, when in place, is reliant on you providing a gully which will be sufficient to remove the build up of ground water.
If the system is installed as per our specification we should be pleased to provide you with a 30 year guarantee on both materials and workmanship."
(a) Failure in the overall approach to application adopted by Mr. Donaldson;
(b) Failures in detailed workmanship.
"Before commencing laying operations ensure that the substrate has falls to the drainage outlets or is laid to a +/– 5 mm tolerance to prevent ponding in depression."
He did not ensure that the substrate had falls to the drainage outlets. That was particularly important since the evidence of Mr. James was that on a floor of this size it would have been more than one could expect that a builder could lay the slab even to a tolerance of +/– 12 mm. If the alternative of +/– 5 mm was unlikely to be achieved (and it had not even been specified to the builder) it was all the more important that the required falls should be provided.
THE CONTRACT
QUANTUM
" ...where any injury is to be compensated by damages, in settling the sum of money to be given for reparation of damages you should as nearly as possible get at that sum of money which will put the party who has been injured, or who has suffered, in the same position as he would have been in if he had not sustained the wrong for which he is now getting his compensation or reparation".
"Where there is a contract to build a wall or a house, or to do repairs to it, then if the contractor does not do the work or does it badly, the employer is entitled by way of damages, to recover the reasonable cost of doing such work as is reasonable to make good the breach."
Here the claimant wanted his new basement to be free from water and damp. It would be useless unless it was dry. He was supplied with and paid for two systems that did not work, the tanking and the system provided by the defendants. So he consulted an architect, Mr. Mathew, for advice on a third system that would work. There is no suggestion that Mr. Mathew is incompetent or would give unreasonable advice. There can be no doubt that lifting the floor and replacing two failed systems with a third would be much more expensive than putting in one system that worked in the first place. To speak of a Rolls Royce system is not appropriate. The claimant was not going to swank about his damp-proofing system. All he wanted was a system that worked so that he could forget about its existence. To achieve that end he acted on competent professional advice and I find that the cost involved was, in Lord Denning's words, "the reasonable cost of doing such work as is reasonable to make good the breach." The claimant has received no benefit from the third system that he would not have received from the second system if the defendants had performed their promises.
I should add that the remedial work was considered by the experts at their meeting on 2 April, 2001. The minute of that meeting included the following:
"It was noted that remedial work had been carried out to resolve the problem of water ingress, to the specification and under the direction of James Mathew BA (Hons) B Arch RIBA. To date this work has proved effective.
Ray James agreed to provide details of this work on request."
No criticism has been made of the competence, work or advice of Mr Mathew nor of the contractors who put in the third system nor of the charges that they made. The amount of the cost of the work done has been proved by production of an invoice.
(a) There is inadequate proof of any agreement to pay;
(b) The piano should not have been put in other premises but should have been put back on the first floor of the claimant's home;
(c) The period in respect of which the claim is made is too long.
CONCLUSION