QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137, Fetter Lane, London, EC4A 1HD | ||
B e f o r e :
____________________
CHAMBERLAIN CARPENTRY & JOINERY LTD. | Claimant | |
- and - | ||
ALFRED McALPINE CONSTRUCTION LIMITED | Defendant |
____________________
James Cross (instructed by Davies Arnold Cooper for the Defendant)
____________________
Crown Copyright ©
H.H. Judge Richard Seymour Q. C. :
Introduction
“The Sub-Contract Conditions set out contained or referred to under the Domestic Sub-Contract DOM/2 Articles of Agreement/1981 Edt. (including amendment(s) 1 to 8 (1998 Reprint) as recommended for use where the Main Contract is the J.C.T. Standard Form “With Contractor’s Design” (1981) as published by the Building Employers Confederation and approved by them and the Federation of Associations of Specialists and Sub-Contractors and the Committee of Associations of Specialist Engineering Contractors, shall apply to this Sub-Contract as completed by the Schedule hereto as if fully set out hereunder and shall be fully incorporated herein, and the Sub-Contractor hereby acknowledges that he fully appreciates and understands the terms of the said Sub-Contract with the following additions and/or revisions and notwithstanding that the said Sub-Contract Conditions are not set out in full, the said Sub-Contract Conditions shall nonetheless apply.”
In this judgment I shall refer to the Alfred McAlpine Special Projects Adjudication Rules (June 2000 Edition) as “the Rules”.“Either Party shall be entitled to refer any dispute or difference (other than a matter as to which a decision is provided by this sub-contract to be final and conclusive) to adjudication in accordance with the Housing Grants, Construction and Regeneration Act 1996 and any such adjudication shall be undertaken in accordance with the Alfred McAlpine Special Projects Adjudication Rules (June 2000 Edition).”
“2. (1) Any party to a construction contract as defined by the Act [that is, Housing Grants, Construction and Regeneration Act 1996] (“the referring party”) may give written notice (the “notice of adjudication”) of his intention to refer any dispute arising under the contract to adjudication…
(3) The notice of adjudication shall set out and provide:
(a) the nature and a description of the dispute, details and relevant copies of the contract documents under which it arises (and of any related contract) and of the parties involved,
(b) details of where and when the dispute has arisen, and
(c) the nature and details of the redress which is sought, and
(d) the names and addresses of the parties to the contract (including the addresses which the parties have specified for the purpose of the giving notices)
(e) copies of a core set of relevant correspondence, instructions and other project material upon which the claim is based…
9. (1) The adjudicator may, if requested by McAlpine, adjudicate at the same time on one or more disputes under the same contract.
21. The adjudicator shall decide only the matters in dispute as identified in the notice of adjudication….
22. The decision of the adjudicator shall reflect the legal entitlements of the parties.
25. Subject to paragraph 21(b):
(1) In his decision, the adjudicator may, if he thinks fit, order any of the parties to comply peremptorily or otherwise with his decision or any part of it.
(2) The decision of the adjudicator shall be binding on the parties and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration), or by agreement of the parties..
26. (1) The referring party shall be responsible for all of the costs of the parties incurred in the adjudication (including those of the adjudicator) on a full indemnity basis, save in circumstances where the referring party is McAlpine in which case the parties shall bear their own costs and expenses incurred in the adjudication and the parties shall be jointly and severally responsible for the adjudicator’s fees and expenses, including those of any legal or technical adviser appointed under paragraph 14(g).”
“Notwithstanding previous discussions between ourselves, no agreement has been reached as to the value of our works on site.
Accordingly as at today’s date a dispute arising under the Sub-Contract exists between Chamberlain Carpentry and Joinery Ltd. and Alfred McAlpine Construction Ltd. as to the following matters, all of which are detailed in an enclosed referral notice.
a) The wrongful deduction of amounts included for acceleration of the works.
b) The wrongful deduction of amounts included for Preliminaries.
c) The wrongful deduction of amounts for cost of Agency labour.
d) The wrongful deduction of the alleged duplication of measured works.
e) The non-payment of amounts for Prolongation of the Works on site.
f) The rates for measured works to the following items
1) Doors
2) Security Worm bolts
3) Lever handles
4) Pod architraves
g) Quantity of plastic architrave.
h) The ascertainment of fair and reasonable costs incurred by the Responding Party reference Clause 26.1 of the AMSP Adjudication Rules.
i) In view of items a) – g) included above, the release of monies incorrectly withheld by Alfred McAlpine Special Projects.
For the avoidance of doubt the above matters constitute “The Dispute” arising under the Sub-Contract and which we intend to refer to Adjudication.
Given your continuing failure to reinstate amounts wrongfully deducted, we have no alternative but to refer this matter to Adjudication and the redress which we seek is as follows:-
1) The Adjudicator’s decision as to the amount owing and due to us of the amounts wrongfully withheld.
2) An order by the Adjudicator that his decision as to 1) above, be complied with peremptorily, i.e. forthwith, by Alfred McAlpine Construction Ltd.
In accordance with the Conditions of Sub-Contract we have applied to the Institution of Civil Engineers for the appointment of an Adjudicator and a copy of the Referral Notice is included with this notice of Adjudication.”
The matters in issue
“Even if one accepts that the dispute could be fairly characterised as a dispute as to what amounts were due and owing to the Claimant under the Sub-Contract, sub-paragraph h) is nothing to do with any dispute as to sums due and owing under the Sub-Contract.”
“12. The Adjudicator’s decision requires the Defendant to pay sums arising out of the Claimant’s application for payment NO2001986 dated 3 August 2001(“Valuation 5”).
13. The Claimant’s Notice of Adjudication does not seek relief in respect of Valuation 5 and there is no correlation between the items listed (a) to (i) in the Notice of Adjudication and Valuation 5…
Mr. Cross elaborated upon those points in his written submissions as follows:-15. The Claimant did not refer any dispute as to its entitlement to payment to adjudication, in its Notice of Adjudication or in its Referral Notice.”
“4.1 There are 2 aspects to this which are referred to in the Witness Statement of David Weare. The first is that the Notice of Adjudication failed to identify the dispute; the second is that the Notice of Adjudication did not refer a claim for payment to adjudication.
4.2 The second aspect will not be further pursued at the hearing. It can be noted that it was not a point taken before the Adjudicator either.
4.3 So far as the first aspect is concerned, the starting point is that the Adjudicator’s jurisdiction is not derived from the further documents which come into existence following the notice of adjudication: KNS Industrial Services v Sindall [2000] CILL 1652….
In his oral submissions Mr. Cross explained that the point which he was seeking to advance was really that the letter dated 11 January 2002 did not identify with sufficient precision any dispute fit to be determined. In other words, nothing was referred to Mr. Mouzer for adjudication, so he had no jurisdiction to decide anything.4.6 The short point is that it should not have been left to the Adjudicator to try to make sense of the Notice of Adjudication and to address the issues raised in the Notice of Adjudication by reference only to Application/Valuation No. 5. The Notice of Adjudication should have defined the dispute and made the ambit of the dispute clear.”
(i) did the letter indicate with sufficient clarity to comply with the requirements of Rule 2(3) of the Rules a dispute fit to be determined by adjudication?
(ii) if so, what was the dispute or what were the disputes which were the subject of the letter?
The proper approach to construction of the letter dated 11 January 2002
Mr. Pilling invited me to approach the case before me in what he submitted was the manner indicated by H.H. Judge Thornton Q.C. in the passage which I have set out. I think that Mr. Pilling came close to submitting that what H.H. Judge Thornton had said amounted to a “dispute” in the context of adjudication was whatever the referring party chose to identify in a notice of adjudication.“It is to be noted that the HGCRA refers to a “dispute” and not to “disputes”. Thus, at any one time, a referring party must refer a single dispute, albeit that the Scheme allows the disputing parties to agree, thereafter, to extend the reference to cover “more than one dispute under the same contract” and “related disputes under different contracts”. During the course of a construction contract, many claims, heads of claim, issues, contentions and causes of action will arise. Many of these will be, collectively or individually, disputed. When a dispute arises, it may cover one, several or many of one, some or all of these matters. At any particular moment in time, it will be a question of fact what is in dispute. Thus, the “dispute” which may be referred to adjudication is all or part of whatever is in dispute at the moment that the referring party first intimates an adjudication reference. In other words, the “dispute” is whatever claims, heads of claim, issues, contentions or causes of action that are then in dispute which the referring party has chosen to crystallise into an adjudication reference.”
“There is in my view, some force in Mr. Currie’s criticism of His Honour Judge Thornton’s analysis in Fastrack Contractors Ltd of what constitutes a dispute. If everything currently in dispute between the parties forms a single dispute, paragraph 8(1) is severely restricted in scope or perhaps even deprived of content.”
“The principles may be summarised as follows.
(1) Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract.
(2) The background was famously referred to by Lord Wilberforce as the “matrix of fact”, but this phrase is, if anything, an understated description of what the background may include. Subject to the requirement that it should have been reasonably available to the parties and to the exception to be mentioned next, it includes absolutely anything which would have affected the way in which the language of the document would have been understood by a reasonable man.
(3) The law excludes from the admissible background the previous negotiations of the parties and their declarations of subjective intent. They are admissible only in an action for rectification. The law makes this distinction for reasons of practical policy and, in this respect only, legal interpretation differs from the way we would interpret utterances in ordinary life. The boundaries of this exception are in some respects unclear. But this is not the occasion on which to explore them.
(4) The meaning which a document (or any other utterance) would convey to a reasonable man is not the same thing as the meaning of its words. The meaning of words is a matter of dictionaries and grammars: the meaning of the document is what the parties using those words against the relevant background would reasonably have been understood to mean. The background may not merely enable the reasonable man to choose between the possible meanings of words which are ambiguous but even (as occasionally happens in ordinary life) to conclude that the parties must, for whatever reason, have used the wrong words or syntax: see Mannai Investments Co. Ltd. v. Eagle Star Life Assurance Co. Ltd. [1997] AC 749.
(5) The “rule” that words should be given their “natural and ordinary meaning” reflects the common sense proposition that we do not easily accept that people have made linguistic mistakes, particularly in formal documents. On the other hand, if one would nevertheless conclude from the background that something must have gone wrong with the language, the law does not require judges to attribute to the parties an intention which they plainly could not have had. Lord Diplock made this point more vigorously when he said in Antaios Compania Naviera SA v. Salen Rederierna AB [1985] AC 191,201:
“if detailed semantic and syntactical analysis of words in a commercial contract is going to lead to a conclusion that flouts business commonsense, it must be made to yield to business commonsense.”
Consideration and conclusion