QUEENS BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
Birmingham Civil Justice Centre 33 Bull Street Birmingham B4 6DS | ||
B e f o r e :
____________________
BALDWINS INDUSTRIAL SERVICES PLC | Claimant | |
- and - | ||
BARR LIMITED | Defendant |
____________________
Mr Simon Hargreaves (instructed by Masons) for the Defendant
____________________
Crown Copyright ©
104(1): In this part a "construction contract" means an agreement with a person for any of the following -
the carrying out of construction operations;
arranging for the carrying out of construction operations by others, whether under sub-contract to him or otherwise;
providing his own labour, or the labour of others, for the carrying out of construction operations.
105(1): In this part "construction operations" means, subject as follows, operations of any of the following descriptions -
construction, alteration, repair, maintenance, extension, demolition or dismantling of buildings, or structures forming, or to form, part of the land (whether permanent or not);
…
(e) Operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this subsection, including site clearance, earth-moving, excavation, tunnelling and boring, laying of foundations, erection, maintenance or dismantling of scaffolding, site restoration, landscaping and the provision of roadways and other access works;
105(2): The following operations are not construction operations within the meaning of this part -
…
(b) Manufacture or delivery to site of -
(i) building or engineering components or equipment,
(ii) materials, plant or machinery."
(i)The delivery to site of building equipment; and/or
(ii) The delivery to site of engineering equipment; and/or
(iii) The delivery to site of plant; and/or
(iv) The delivery to site of machinery
and in none of these cases did the contract provide for the installation of that equipment, plant or machinery. The contract was for delivery of plant or machinery to site without provision for installation and thus falls within the exception in section 105(2)(d)(ii). Baldwins' case is that the supply of a mobile crane plus labour cannot, on a true construction, fall within any of the excepted categories described within Section 105(2). This contract was not a contract for mere delivery to site of plant. Accordingly, it is not caught by the exception in that section.
"[The owners say] that, giving the words their ordinary meaning, no one would say that the person who had hired out the crane was undertaking a building operation but that they would naturally, if asked, say that the builder was undertaking the building operation…The argument on behalf of the plaintiff, on the other hand, is that to determine whether or not a person is undertaking an operation one looks at the actual work being carried on at the time of the accident, and if it appears that a contractor and/or employer is, through a workman of his, actively engaged in a building operation, he is undertaking it for the purposes of regulation 3…In my view, the plaintiff's construction is to be preferred. In this case the owners of the plant knew that they were providing it so that it could take part in a building operation. As a company they could only take part in that building operation through their employees."
In his judgment in that case, Dillon LJ made a clear distinction between a plant hire firm which hires out a machine with a driver and one which is hired without an operator.
Stay of Execution
There are special circumstances because Baldwins are now in administrative receivership. In addition to the fact of the appointment of Administrative Receivers, Barr rely on information gleaned from the financial press which suggests that their financial position is poor.
On the merits, there is a realistic prospect that Barr would succeed before a court or arbitrator.
(i) the CPA conditions were not incorporated
(ii) there was no contract between the parties at all,
(iii) the CPA Model Conditions were not incorporated
(iv) there was a second contract but not on the CPA conditions or the first contract was substantially varied and the CPA conditions did not apply to the variation
(v) Barr would establish that the driver's actions caused the damage to the crane or that Baldwins failed to supply a competent driver.
(vi) Baldwins will not be able to establish causation as they failed to provide any evidence as to the condition of the crane prior to the accident
(vii) Quantum will not be established: no "meaningful" evidence as to the nature of the damage to the crane was produced to the adjudicator. The adjudicator made no enquiry into the facts.
(viii) Baldwins will not be able to show that they took steps to mitigate their loss.
(i) pay into court, within seven days from the date of judgment, the principal sum which the adjudicator decided Barr should pay to Baldwins; and
(ii) undertake to commence arbitral or court proceedings within one month from the date of judgment in respect of matters the subject of the adjudicator's decision; and
(iii) do so commence proceedings; and
(iv) within seven days from the date of judgment lodge at court a formal application for a stay, service to be taken as having been effected
failing which the money be paid out to Baldwins.